Detailed Estimate : Abstract of Cost
2 Soling:
i Flatbrick Soling: Providing and laying, dry brick
soling in floor with first class chimney made bricks
complete to specified level including sand filling on Cu.m 835.41 944.95 789,421.97
joints.
13 Flooring Works
A Screeding works: Providing and laying, 75 mm
thick screeding with 1:2:4 concrete mix on proper
slope after scraping, cleaning and watering (which
in some case may require air blast or water blast
method ) the old surface, including 3mm thick
cement punning work as per drawing, specification Sq.m 1157.12 1204.61 1,393,874.35
and instruction of engineer-in-charge, all
complete.Rate shall be inclusive of all the
preparation works for the job to be done and
preparing sample for obtaining approval for the
screeding work.
14 Painting Works
i Painting works : Providing and applying, inside
and outside painting work on wall and ceiling of
approved color including necesary primer to give
uniform color after rendering surface clean as per
specifications, drawings, and instruction of the
engineer-in-charge, all complete.
a Two coat of acrylic emulsion paint with primer coat
Sq.m 2764.64 165.10 456,442.63
b Two coat of external paint with primer coat Sq.m 836.07 354.96 296,769.63
ii Enamel Paint: Providing and applying, inside and
outside painting with approved color and paints
with two coats of primer to give uniform color after
Sq.m 283.22 286.33 81,093.24
rendering surface clean with sandpapering as per
drawing, specifications and instruction of the
engineer-in-charge, all complete.
15 Metal Works
i Structural steel: Supplying, fabricating and
erecting in position structural steel works in
columns, beams, portals, runners, roof structural
elements, trusses, purlins, bracings, platforms,
decking, railings, ladders, stairs, hangers etc. as per
design, drawings, specifications and instruction of
Kg 14125.04 200.00 2,825,007.20
engineer-in-charge..
Rate to include consumables such as bolts, nuts,
washers, surface preparation as per specifications,
painting with one coat of red oxide and 2 or more
coats of enamel paint one at shop level and one
after erection and alignment.
Government of Nepal
Ministry of Physical Infrastructure Development
Preparation of Master Plan for Developing Pokhariya as a Satellite City(Town Hall)
Province No.2 Janakpur, Dhanusha
Detailed Estimate : Summary of Quantities
2 Soling
Flat Brick Soling Cu.m 835.41 944.95 496.17 339.24
3 PCC
1:3:6 Manual Mix Cu.m 113.96 9861.94 49.62 64.34
7 Brickwork
230 mm thickness in 1:6 (Cement : Sand ) Cu.m 366.67 17514.63 70.10 296.58
110 mm thickness in 1:4 (Cement : Sand ) Cu.m 59.57 16013.93 59.57
8 Plaster
Internal Plaster Sq.m 3596.53 383.99 2245.73 1350.79
External Plaster Sq.m 818.55 454.80 138.32 680.22
9 Paint
Internal Emulsion Sq.m 2764.64 165.10 1413.85 1350.79
External Weather Guard Sq.m 836.07 354.96 155.84 680.22
Enamel Sq.m 283.22 286.33 283.22
11 Finishing
Screeding 75mm Sq.m 1157.12 1204.61 496.17 660.95
12 Metal Works
Truss Kg 14125.04 10668.60 14125.04
13 Roofing
UPVC roofing Sq.m 10.50 2145.69 10.50
Ridge R.m 1.00 3191.94 1.00
Government of Nepal
Ministry of Physical Infrastructure Development
Preparation of Master Plan for Developing Pokhariya as a Satellite City(Town Hall)
Province No.2 Janakpur, Dhanusha
Detailed Estimate
2 Soling
i Flatbrick Soling: Providing and laying, dry brick soling in floor with first class chimney made bricks complete
to specified level including sand filling on joints.
Along grid (A-D)/(1-5) Sq.m 1 21.470 23.110 496.17
3 Plain Cement Concrete : Providing and laying of plain cement concrete as leveling course for foundation,
basement and all locations depth, including lead from batching site to site of work, placing in position
mechanical compaction, finishing, curing (if necessary), consolidation, finishing, curing etc.
i Nominal mix (1:3:6)
Below raft
Along grid (A-D)/(1-5) Cu.m 1 21.470 23.110 0.100 49.62
Total 49.62 Cu.m
B Column
Column Cu.m 40 0.450 0.450 2.350 19.04
Sub Total 19.04 Cu.m
C Beam
Main Beams
Along grid A/(1-5) Cu.m 2 21.110 0.300 0.325 4.12
Along grid B/(1-5) Cu.m 2 23.550 0.300 0.325 4.59
Along grid C/(1-5) Cu.m 2 23.550 0.300 0.325 4.59
Along grid D/(1-5) Cu.m 2 21.110 0.300 0.325 4.12
Detailed Estimate
D Slab
Along grid (A-B)/(1-5) Cu.m 2 22.150 6.340 0.125 35.11
Along grid (B-C)/(1-5) Cu.m 2 24.250 6.560 0.125 39.77
Along grid (C-D)/(1-5) Cu.m 2 22.150 6.340 0.125 35.11
E Staircase Nos 1
Waist slab Cu.m 1 5.510 1.650 0.125 1.136
Steps Cu.m 17 1.500 0.300 0.125 0.956 Triangular
Portion
Landing Cu.m 1 1.100 1.850 0.125 0.254
Sub Total 2.35 Cu.m
5 Rebar
i Steel Reinforcement: Reinforcement for RCC work including supplying, delivering and storing of various
diameters as required at site of work transportation, unloading at site, straightening, cutting, bending, placing in
position at any level, binding in position of steel reinforcements Fe-550D including cost of binding wire,
labour, scaffolding, transportation to & from stores etc complete all.
Raft Foundation M.T 2.00% of Concrete Volume 248.086 38.949
Column M.T 4.00% of Concrete Volume 19.035 5.977
Beam M.T 3.00% of Concrete Volume 36.401 8.572
Slab M.T 1.30% of Concrete Volume 109.986 11.224
Staircase M.T 1.30% of Concrete Volume 2.347 0.240
Band M.T 1.30% of Concrete Volume 22.979 2.345
Total 67.307 M.T
Detailed Estimate
A Raft Foundation
C Slab
Along grid (A-B)/(1-5) Sq.m 2 22.150 6.340 280.86
Along grid (B-C)/(1-5) Sq.m 2 24.250 6.560 318.16
Along grid (C-D)/(1-5) Sq.m 2 22.150 6.340 280.86
D Staircase Nos 1
Waist slab Sq.m 1 5.510 1.650 9.092
Sides Sq.m 2 11.020 0.150 3.306
Steps Sq.m 17 0.300 0.150 0.765 Triangular
Portion
Steps front Sq.m 1 1.500 0.125 0.188
Landing Sq.m 1 1.100 1.850 2.035
Sides Sq.m 1 5.900 0.125 0.738
Sub Total 16.12 Sq.m
Detailed Estimate
7 Brick Works: Providing brick work in cement mortar in walls, chambers etc. in thickness mentioned below at
all heights, places and position above plinth including raking out joints, curing, scaffolding etc.
i 110 mm thick wall
Internal wall
Along grid 2'/(A-D) Cu.m 2 4.150 0.150 2.550 3.17
Along grid 3'/(A-D) Cu.m 2 32.298 0.150 2.550 24.71
Along grid D'/(1-5) Cu.m 2 13.670 0.150 2.550 10.46
Along grid C/(1-5) Cu.m 2 7.670 0.150 2.550 5.87
Along grid B/(1-5) Cu.m 2 7.670 0.150 2.550 5.87
Along grid B'/(1-5) Cu.m 2 12.410 0.150 2.550 9.49
8 Plaster works: Providing and applying plaster works in cement sand mortar for all surfaces of brick / block /
RCC walls and finishing the same (smooth or broom) in correct line, level & plumb, making of edges, corners,
sill, jambs, soffits, grooves etc.with all necessary surface preparation, scaffolding, hacking of concrete surface to
receive plaster, watering, curing, cleaning etc.
I 12.5 mm thick in 1:4 (cement : sand ) mortar
A Walls
External wall (Interior)
Along grid A/(1-5) Sq.m 2 20.350 2.100 85.47
Along grid D/(1-5) Sq.m 2 20.350 2.100 85.47
Along grid 1/(A-D) Sq.m 2 17.670 2.100 74.21
Along grid 6/(A-D) Sq.m 4 16.280 2.100 136.75
Detailed Estimate
D Slab
Along grid (A-B)/(1-5) Sq.m 2 22.150 6.340 280.86
Along grid (B-C)/(1-5) Sq.m 2 24.250 6.560 318.16
Along grid (C-D)/(1-5) Sq.m 2 22.150 6.340 280.86
E Staircase Nos 1
Waist slab Sq.m 1 5.510 1.650 9.092
Sides Sq.m 2 11.020 0.150 3.306
Steps Sq.m 17 0.300 0.150 0.765 Triangular
Portion
Steps front Sq.m 1 1.500 0.125 0.188
Landing Sq.m 1 1.100 1.850 2.035
Sides Sq.m 1 5.900 0.125 0.738
9 Painting works
i Painting works : Providing and applying, inside and outside painting work on wall and ceiling of approved
color including necesary primer to give uniform color after rendering surface clean.
a Two coat of acrylic emulsion paint with primer coat
A Walls
External wall (Interior)
Along grid A/(1-5) Sq.m 2 20.350 2.550 103.79
Along grid D/(1-5) Sq.m 2 20.350 2.550 103.79
Along grid 1/(A-D) Sq.m 2 17.670 2.550 90.12
Along grid 6/(A-D) Sq.m 4 16.280 2.550 166.06
Detailed Estimate
B Beam
Main Beams
Along grid A/(1-5) Sq.m 2 22.150 0.450 19.94
Along grid D/(1-5) Sq.m 4 22.150 0.450 39.87
Along grid 1/(A-D) Sq.m 4 22.150 0.450 39.87
C Slab
Along grid (A-B)/(1-5) Sq.m 2 22.150 0.125 5.54
Along grid (B-C)/(1-5) Sq.m 2 24.250 0.125 6.06
Along grid (C-D)/(1-5) Sq.m 2 22.150 0.125 5.54
Staircase Nos 1
Waist slab Sq.m 1 5.510 1.650 9.09
Sides Sq.m 2 11.020 0.150 3.31
Steps Sq.m 17 0.300 0.150 0.77
Steps front Sq.m 1 1.500 0.125 0.19
Landing Sq.m 1 1.100 1.850 2.04
Sides Sq.m 1 5.900 0.125 0.74
Total 1413.85 Sq.m
Detailed Estimate
Government of Nepal
Ministry of Physical Infrastructure Development
Preparation of Master Plan for Developing Pokhariya as a Satellite City(Town Hall)
Province No.2 Janakpur, Dhanusha
Detailed Estimate
b Earthwork in Filling: Earth work in filling in foundation, floor etc. shall be done with good excavated soil in
the floor with proper ramming in 20cm layers ,after sprinkling water and consolidating to 15 cm layer.
Filling trenches Cu.m 60% of excavation 234.927 140.956
Filling upto plinth Cu.m 1 34.750 19.020 0.300 198.284
ii Beam
Along X-axis
Along Grid A/6-11 Sq.m 1 27.750 0.530 14.708
Along Grid B/6-11 Sq.m 1 29.550 0.530 15.662
Along Grid C/6-11 Sq.m 1 29.550 0.530 15.662
Along Grid D/6-11 Sq.m 1 27.750 0.530 14.708
Along Y-axis
Along Grid 6/A-D Sq.m 1 17.670 0.530 9.365
Along Grid 7/A-D Sq.m 1 18.570 0.530 9.842
Along Grid 8/A-D Sq.m 1 18.570 0.530 9.842
Along Grid 9/A-D Sq.m 1 18.570 0.530 9.842
Along Grid 10/A-D Sq.m 1 18.570 0.530 9.842
Along Grid 11/A-D Sq.m 1 17.670 0.530 9.365
Detailed Estimate
3 Plain Cement Concrete : Providing and laying of plain cement concrete as leveling course for foundation,
basement and all locations depth, including lead from batching site to site of work, placing in position
mechanical compaction, finishing, curing (if necessary), consolidation, finishing, curing etc.
a. Nominal mix (1:3:6)
i. Foundation Cu.m 16 1.800 1.800 0.075 3.888
ii. Beam
Along X-axis
Along Grid A/6-11 Cu.m 1 27.750 0.530 0.075 1.103
Along Grid B/6-11 Cu.m 1 29.550 0.530 0.075 1.175
Along Grid C/6-11 Cu.m 1 29.550 0.530 0.075 1.175
Along Grid D/6-11 Cu.m 1 27.750 0.530 0.075 1.103
Along Y-axis
Along Grid 6/A-D Cu.m 1 17.670 0.530 0.075 0.702
Along Grid 7/A-D Cu.m 1 18.570 0.530 0.075 0.738
Along Grid 8/A-D Cu.m 1 18.570 0.530 0.075 0.738
Along Grid 9/A-D Cu.m 1 18.570 0.530 0.075 0.738
Along Grid 10/A-D Cu.m 1 18.570 0.530 0.075 0.738
Along Grid 11/A-D Cu.m 1 17.670 0.530 0.075 0.702
Detailed Estimate
Internal
Along X-Axis Cu.m 2 25.720 0.230 0.100 1.183
Along Y-Axis Cu.m 2 15.770 0.230 0.100 0.725
Deduction
Opening Cu.m 5 1.000 0.230 0.100 (0.115)
5 Reinforcement Works for RCC work including supplying, delivering and storing of various diameters as
required at site of work transportation, unloading at site, straightening, cutting, bending, placing in position at
any level, binding in position of steel reinforcements Fe-550D including cost of binding wire, labour,
transportation to & from stores etc complete all as per specifications, drawings and as per instruction of
a. For foundation M.T 1.3% of conc vol 12.564 1.282
b. For foundation and plinth M.T 3.0% of conc vol 36.099 8.501
c. beam
For RCC band M.T 1.3% of conc vol 6.740 0.688
c. Seating slab and steps M.T 1.3% of conc vol 57.096 5.827
Total 16.298 M.T
7 Formwork : Providing & Fixing form work with approved quality laminated ply wood of required thickness
and smooth surface for foundation, columns, beams, slabs staircases, etc. for all heights and at all locations
including chamfers, splays, keys, wedges, metal props, rails, bracings, brackets, cutting holes if specified for
pipes etc. providing and applying approved form oil on all surfaces of formwork.
a. Footing Sq.m 16 6.000 0.200 19.200
b. Foundation beam
Along X-axis
Along Grid A/6-11 Sq.m 2 27.750 0.350 19.425
Along Grid B/6-11 Sq.m 2 29.550 0.350 20.685
Along Grid C/6-11 Sq.m 2 29.550 0.350 20.685
Along Grid D/6-11 Sq.m 2 27.750 0.350 19.425
Along Y-axis
Along Grid 6/A-D Sq.m 2 17.670 0.350 12.369
Along Grid 7/A-D Sq.m 2 18.570 0.350 12.999
Along Grid 8/A-D Sq.m 2 18.570 0.350 12.999
Along Grid 9/A-D Sq.m 2 18.570 0.350 12.999
Along Grid 10/A-D Sq.m 2 18.570 0.350 12.999
Along Grid 11/A-D Sq.m 2 17.670 0.350 12.369
Detailed Estimate
Internal
Along X-Axis Sq.m 4 25.720 0.100 10.288
Along Y-Axis Sq.m 4 15.770 0.100 6.308
Deduction
Opening Sq.m 10 1.000 0.100 (1.000)
6 Brick work : Providing brick work in cement mortar in walls, chambers etc. in thickness mentioned below at all
heights, places and position above plinth including raking out joints, curing, scaffolding etc.
a. 230 mm thickness in 1:6 (Cement : Sand ) mortar. (Class A Brick)
External
i. Foundation level
Along X-axis
Along Grid A/6-11 Cu.m 1 27.750 0.230 1.115 7.116
Along Grid B/6-11 Cu.m 1 29.550 0.230 1.115 7.578
Along Grid C/6-11 Cu.m 1 29.550 0.230 1.115 7.578
Along Grid D/6-11 Cu.m 1 27.750 0.230 1.115 7.116
Along Y-axis
Along Grid 6/A-D Cu.m 1 17.670 0.230 1.115 4.531
Along Grid 7/A-D Cu.m 1 18.570 0.230 1.115 4.762
Along Grid 8/A-D Cu.m 1 18.570 0.230 1.115 4.762
Along Grid 9/A-D Cu.m 1 18.570 0.230 1.115 4.762
Along Grid 10/A-D Cu.m 1 18.570 0.230 1.115 4.762
Along Grid 11/A-D Cu.m 1 17.670 0.230 1.115 4.531
ii. External
Along X-axis
Along Grid A/6-11 Cu.m 1 27.750 0.230 7.770 49.592
Along Grid D/6-11 Cu.m 1 27.750 0.230 7.770 49.592
Along Y-axis
Along Grid 11/A-D Cu.m 1 17.670 0.230 7.770 31.578
Deduction
Opening Cu.m 1 1.000 0.230 2.100 (0.483)
Detailed Estimate
8 Plaster works: Providing and applying plaster works in cement sand mortar for all surfaces of brick / block /
RCC walls and finishing the same (smooth or broom) in correct line, level & plumb, making of edges, corners,
sill, jambs, soffits, grooves etc.with all necessary surface preparation, scaffolding, hacking of concrete surface to
receive plaster, watering, curing, cleaning etc.
a. 20 mm thick in 1:6 (cement : sand ) mortar
i. External
Along Grid A/6-11 Sq.m 1 27.750 7.770 215.618
Along Grid D/6-11 Sq.m 1 27.750 7.770 215.618
Along Y-axis
Along Grid 11/A-D Sq.m 1 17.670 7.770 137.296
Deduction
Opening Sq.m 1 1.000 2.100 (1.050)
ii. Steps
Vertical Sq.m 3 1.650 0.300 1.485
Horizontal Sq.m 3 0.900 0.750 2.025
ii Internal
Along X-Axis Sq.m 1 25.720 7.770 199.844
Along Y-Axis Sq.m 1 15.770 7.770 122.533
Deduction
Opening Sq.m 4 1.000 2.100 (4.200)
Detailed Estimate
9 Floor Finishing
a. Screeding works: Providing and laying, 75 mm thick screeding with 1:2:4 concrete mix on proper slope after
scraping, cleaning and watering (which in some case may require air blast or water blast method ) the old
surface all complete.
Floor Sq.m 1 34.750 19.020 660.945
Total 660.945 Sq.m
10 Painting works : Providing and applying, inside and outside painting work on wall and ceiling of approved
color including necesary primer to give uniform color after rendering surface clean.
a. Two coat of acrylic emulsion paint with primer coat
i External
Along Grid A/6-11 Sq.m 1 27.750 7.770 215.618
Along Grid D/6-11 Sq.m 1 27.750 7.770 215.618
Along Y-axis
Along Grid 11/A-D Sq.m 1 17.670 7.770 137.296
Deduction
Opening Sq.m 1 1.000 2.100 (1.050)
ii Internal
Along X-Axis Sq.m 1 25.720 7.770 199.844
Along Y-Axis Sq.m 1 15.770 7.770 122.533
Deduction
Opening Sq.m 4 1.000 2.100 (4.200)
ii. Steps
Vertical Sq.m 3 1.650 0.300 1.485
Horizontal Sq.m 3 0.900 0.750 2.025
Detailed Estimate
11 Metal works :
a. Truss : Supplying, fabricating and erecting in position structural steel works in columns, beams, portals,
runners, roof structural elements, trusses, purlins, bracings, platforms, decking, railings, ladders, stairs, hangers
etc.
i. Inclined Chord (ISNB 100) Kg 1 16.473 12.200Kg/m 200.971
ii. Vertical Chord (ISNB 100) Kg 1 10.920 12.200Kg/m 133.224
iii. Bottom Chord (ISNB 125) Kg 1 18.000 15.900Kg/m 286.200
iv. Top Chord (ISNB 100) Kg 1 20.900 12.200Kg/m 254.980
v. Purlin(ISNB 100) Kg 16 33.000 12.200Kg/m 6441.600
vi. Column (ISMC 200) Kg 16 7.770 22.300Kg/m 2772.336
vii. Connection Kg 40% of Metal works 10089.311 4035.725
Total 14125.036 Kg
ii Ridge: Providing and laying ridge cover UPVC PMMA(3mm Thick ) regular with fittings all complete.
R.m 1 1.000 1.000
Total 1.000 R.m