Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

CoQ MMCD

Download as pdf or txt
Download as pdf or txt
You are on page 1of 227
At a glance
Powered by AI
The document provides supplementary specifications for construction projects in the City of Coquitlam, British Columbia.

The document supplements the Master Municipal Construction Documents (MMCD) specifications.

The document covers specifications for various divisions of construction work including earthworks, road and site improvements, and landscaping.

 

 
Supplemenntary Specifiications 
er Municipal Constructio
Maste on Documen nts 
 
 
 
 
 
 
 
 
 
 
 
 
  MAR
RCH 22016
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
The City of Coquitlam “Supplementary Specifications”” are suppleemental specifications to
o the 
 
Masterr  Municipall  Constructiion  Documment  –  200 9  Edition  (Platinum  B
Book)  and  take 
 
precedeence over th
he MMCD Sp pecificationss. 
 
 
 
 

File #: 11-5330
0-01/000/2015-1 Doc
D #: 2105578.v4A
A
Left Blank Intentionally 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  TABLE OF CONTENTS  PAGE i 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  SPECIFICATION INDEX   
SUPPLEMENTARY SPECIFICATIONS    2016 

TABLE OF CONTENTS 
PAGE 
SPECIFICATION INDEX 
CONCORDANCE INDEX 
 
DIVISION 01 – GENERAL REQUIREMENTS  1 
MMCD SECTION 01 33 01S   PROJECT RECORD DOCUMENTS ................................................................................ 1 
MMCD SECTION 01 55 00S  TRAFFIC CONTROL, VEHICLE ACCESS AND PARKING ....................................................... 2 
MMCD SECTION 01 57 01S  ENVIRONMENTAL PROTECTION ................................................................................ 3 
DIVISION 03 – CONCRETE  6 
MMCD SECTION 03 30 20S  CONCRETE WALKS, CURBS AND GUTTER ..................................................................... 6 
DIVISION 26 – ELECTRICAL  7 
MMCD SECTION 26 56 01S  ROADWAY LIGHTING ............................................................................................. 8 
DIVISION 31 – EARTHWORKS  15 
MMCD SECTION 31 05 17S  AGGREGATES AND GRANULAR MATERIALS ................................................................. 16 
MMCD SECTION 31 11 41S  SHRUB AND TREE PRESERVATION ............................................................................. 18 
MMCD SECTION 31 23 01S  EXCAVATING, TRENCHING AND BACKFILLING............................................................... 19 
MMCD SECTION 31 23 17S  ROCK REMOVAL .................................................................................................. 20 
MMCD SECTION 31 24 13S  ROADWAY EXCAVATION, EMBANKMENT AND COMPACTION ........................................... 21 
DIVISION 32 – ROAD AND SITE IMPROVEMENTS  22 
MMCD SECTION 32 11 16.1S  GRANULAR SUBBASE ............................................................................................ 22 
MMCD SECTION 32 11 23S  GRANULAR BASE ................................................................................................. 23 
MMCD SECTION 32 12 13.1S  ASPHALT TACK COAT ............................................................................................ 24 
MMCD SECTION 32 12 16S  HOT MIX ASPHALT CONCRETE PAVING ..................................................................... 25 
MMCD SECTION 32 12 17S  SUPERPAVE HOT MIX ASPHALT CONCRETE PAVING ...................................................... 27 
MMCD SECTION 32 14 01S  UNIT PAVING ..................................................................................................... 29 
MMCD SECTION 32 17 23S  PAINTED PAVEMENT MARKINGS ............................................................................. 32 
MMCD SECTION 32 31 13S  CHAIN LINK FENCES AND GATES .............................................................................. 34 
MMCD SECTION 32 91 21S  TOPSOIL AND FINISH GRADING ................................................................................ 41 
MMCD SECTION 32 92 19S  HYDRAULIC SEEDING ............................................................................................ 51 
MMCD SECTION 32 92 20S  SEEDING ............................................................................................................ 58 
MMCD SECTION 32 92 23S  SODDING ........................................................................................................... 64 
MMCD SECTION 32 93 01S  PLANTING OF TREES, SHRUBS AND GROUND COVERS .................................................... 71 
MMCD SECTION 33 01 30.1S  CCTV INSPECTION OF PIPELINES .............................................................................. 86 
MMCD SECTION 33 11 01S  WATERWORKS .................................................................................................... 88 
MMCD SECTION 33 30 01S  SANITARY SEWERS ............................................................................................... 95 
MMCD SECTION 33 34 01S  SEWAGE FORCE MAINS ......................................................................................... 97 
MMCD SECTION 33 40 01S  STORM SEWERS .................................................................................................. 98 
MMCD SECTION 33 42 13S  PIPE CULVERTS.................................................................................................. 100 
MMCD SECTION 33 44 01S  MANHOLES AND CATCHBASINS ............................................................................. 101 
DIVISION 34 – TRANSPORTATION  103 
MMCD SECTION 34 41 13S  TRAFFIC SIGNALS ............................................................................................... 104 
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  TABLE OF CONTENTS  PAGE ii 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  CONCORDANCE INDEX   
SUPPLEMENTARY SPECIFICATIONS    2016 

This concordance relates the 2016 Supplementary Specification numbers to the 2003 Supplementary Specification 
numbers for reference.  
 
Section Information 
Division  Reference
Title 
2009 2000
     
SUPPLEMENTARY SPECIFICATIONS 
     
01  GENERAL REQUIREMENTS  01 33 01S 01721 Project Record Documents 
    01 55 00S 01570 Traffic Control, Vehicle Access and Parking
    01 57 01S 01561 Environmental Protection 
     
03  CONCRETE  03 30 20S 02523 Concrete Walks, Curbs and Gutters 
     
26  ELECTRICAL  26 56 01S Roadway Lighting
     
31  EARTHWORKS  31 05 17S 02226 Aggregates and Granular Materials 
    31 11 41S 02104 Shrub and Tree Preservation 
    31 23 01S 02223 Excavating, Trenching and Backfilling  
    31 23 17S Rock Removal
    31 24 13S 02224 Roadway Excavation, Embankment and Compaction
     
32  ROADS AND SITE  32 11 16.1S 02234  Granular Subbase 
IMPROVEMENTS 
    32 11 23S 02233 Granular Base
    32 12 13.1S 02547 Asphalt Tack Coat
    32 12 16S 02512 Hot‐Mix Asphalt Concrete Paving 
    32 12 17S Superpave Hot Mix Asphalt Concrete Paving
    32 14 01S 02515 Unit Paving
    32 17 23S 02580 Painted Pavement Marking 
    32 31 13S 02831 Chain Fences ad Gates 
    32 91 21S 02921 Topsoil and Finish Grading 
    32 92 19S 02934  Hydraulic Seeding
    32 92 20S 02933 Seeding
    32 92 23S 02938 Sodding
    32 93 01S 02950 Planting of Trees, Shrubs and Ground Covers
     
33  UTILITIES   33 01 30.1S CCTV Inspection of Pipelines 
    33 11 01S 02666 Waterworks 
    33 30 01S 02731 Sanitary Sewers
    33 34 01S 02732 Sewage Force Mains
    33 40 01S 02721 Storm Sewers
    33 42 13S 02723 Pipe Culverts
    33 44 01S 02725 Manholes and Catchbasins 
     
34  TRANSPORTATION  34 41 13S Traffic Signals
 
   

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
SUPPLEMENTARY SPECIFICATIONS  
DIVISION 01 – GENERAL REQUIREMENTS 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 1  MMCD SECTION 01 33 01S 
ENGINEERING AND PUBLIC WORKSDEPARTMENT    SS PAGE 1  
SUPPLEMENTARY SPECIFICATIONS  Project Record Documents  2016 
 
 
MMCD Section 01 33 01S   Project Record Documents 
 
1.0 GENERAL     
 
1.3   Submission  Delete  1.3.2  and  Submit  one  copy  of  accurate  project  record 
replace  with  the  documents  in  final  form  prior  to  applying  for 
following  Substantial  Performance  including  all  video  and 
material testing reports.  Substantial Performance will 
not  be  issued  until  record  documents  have  been 
submitted and accepted by the Contract Administrator 
and the City. 
     
   
 
 
 
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 1  MMCD SECTION 01 55 00S 
ENGINEERING AND PUBLIC WORKSDEPARTMENT  GENERAL REQUIREMENTS  SS PAGE 2  
SUPPLEMENTARY SPECIFICATIONS  Traffic Control, Vehicle Access and Parking  2016 
 
 
MMCD Section 01 55 00S  Traffic Control, Vehicle Access and Parking 
 
1.0 GENERAL  Add 1.0.6  The  Contractor  is  responsible  for  all  temporary  traffic 
    control  on  the  streets  required  for  completion  of  the 
work.  The  Contractor  will  be  responsible  to  provide  a 
Traffic  Management  Plan  (TMP)  for  approval  (5)  five 
working  days  prior  to  any  lane  closures  taking  place. 
TMP  is  to  be  prepared  by  a  professional  certifified  by 
the American Traffic Safety Services Association. 
 
The  TMP  shall  outline  the  approach  to  traffic 
management,  show  recognition  and  minimization  of 
risks indicates signing locations, identify Traffic Control 
Persons  (TCP)  stations,  show  lane  shifting  and 
proposed closures. 
 
  Add 1.0.7  A  Road  and  Sidewalk  Closure  Permit  is  required  from 
Coquitlam  for  all  work  affecting  pedestrian  and  traffic 
flow  related  to  construction.    A  permit  is  required  for 
each specific construction interference with pedestrian 
and traffic flow.  The road and sidewalk closure permit 
form can be obtained for use from the City’s website at 
http://www.coquitlam.ca.  The Contractor must follow 
the approved TMP.  Any changes to this TMP must be 
submitted to City’s Traffic Operations for approval. 
 
1.4  Traffic Control  Add   The  Contractor,  as  required  by  the  Contract 
1.4.9.3.1  Administrator  and  the  City,  is  to  supply  Construction 
Zone information signs (stationary), refer to MMCD 01 
58 01 for the required identification signage. 
 
The  Contractor  is  responsible  for  the  removal  of  the 
signs at the completion of the work. 
 
  Delete 1.4.10.1.3  When  workmen  or  equipment  are  employed  over 
and replace with  travelled  way  over  brow  of  hills,  around  sharp  curves 
the following  or at other locations where oncoming traffic would not 
otherwise have adequate warning.  
 
 
 
 
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 1  MMCD SECTION 01 57 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  GENERAL REQUIREMENTS  SS PAGE 3  
SUPPLEMENTARY SPECIFICATIONS  Environmental Protection  2016 
 
MMCD Section 01 57 01S  Environmental Protection 
 
1.0 GENERAL     
 
1.0.3  Erosion and  Add 1.03  The  Erosion  and  Sediment  Control  (ESC)  Supervisor  is 
Sediment Control  the  Qualified  Professional  who  is  experienced  in 
Supervisor  implementing ESC Plans and who is responsible for the 
  inspection  and  monitoring  of  ESC  Facilities  to  ensure 
these are installed and maintained in accordance with 
the  ESC  Plan,  and  if  necessary,  are  modified  during 
construction  to  ensure  compliance  with  the  Stream 
and Drainage System Protection Bylaw No. 4403, 2013. 
1.2  Temporary  Delete 1.2.1 and  Properly  drain  all  portions  of  the  site.  Protect  the  site 
Erosion and  replace with the  and  the  watercourses  to  which  it  drains,  directly  or 
Sediment  following  indirectly,  against  erosion  and  siltation  in  accordance 
Controls  with  a  Sediment  Control  Plan  under  the  City  of 
Coquitlam  Stream  and  Drainage  System  Protection 
Bylaw No. 4403, 2013 during construction and until the 
maintenance  period  is  completed.  Ensure  no  silt, 
gravel,  debris  or  other  deleterious  substance  resulting 
from  construction  activity  discharges  into  existing 
drainage systems or watercourses or onto highways or 
adjacent property. The Contractor is responsible for all 
damage  that  may  be  caused  by  water  backing  up  or 
flowing  over,  through,  from  or  along  any  part  of  the 
work or otherwise resulting from his operations. 
Keep  existing  culverts,  drains,  ditches  and 
watercourses  affected  by  the  work  clear  of  excavated 
material at all times. When it is necessary to remove or 
alter  any  existing  drainage  structure,  provide  suitable 
alternative  measures  for  handling  the  drainage. 
Adequately  support  culverts  and  drainpipes  across 
trenches  to  prevent  displacement  and  interference 
with  the  proper  flow  of  water  due  to  trench 
settlement. 
Sweep streets, and clean catch basins, manhole sumps, 
detention  tanks,  and  maintain  siltation  controls  as 
often as the Contract Administrator and the City deems 
necessary. 
Follow  all  Federal  and  Provincial  regulations  and 
guidelines  respecting  protection  of  fish,  fish  habitat, 
and watercourses. 
Follow  all  Federal  and  Provincial  regulations  and 
guidelines  respecting  protection  of  fish,  fish  habitat, 
and watercourses. 
 
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 1  MMCD SECTION 01 57 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  GENERAL REQUIREMENTS  SS PAGE 4  
SUPPLEMENTARY SPECIFICATIONS  Environmental Protection  2016 
 
  Delete 1.2.2.2 and  Do  not  operate  construction  equipment  in 
replace with the  watercourses. 
following 
 
1.4  Environmental  Add 1.4.3.5   Immediately  contain  and  clean  up  any  leaks  and  spills 
Protection  of prohibited materials at the Place of Work. 
  Add 1.4.3.6  Ensure that a well‐stocked spill kit is on‐site at all times 
and  that  the  Contractor’s  employees  are  familiar  with 
appropriate spill response techniques. 
  Add 1.4.3.7  Immediately notify the Contract Administrator and the 
City  of  any  leaks  or  spills  of  prohibited  materials  that 
occur at the Place of Work. 
  Add 1.4.3.8  Ensure that any fuel stored on‐site is located at least 15 
metres from the nearest stream, and is placed within a 
bermed  and  lined  area,  in  order  to  prevent  leaks  or 
spills into the environment. 
  Add 1.4.3.9  Ensure  that  no  equipment  fueling  or  servicing  is 
conducted within 15 metres of a stream. 
1.9   Archaeological /  Add 1.9   Immediately  cease  work  and  inform  the  Contract 
Historical  Administrator  and  the  City,  if  any  archaeological  or 
Resources  historical  resources  are  encountered  during 
construction.  Leave  these  resources  in  place  and  do 
not disturb them in any way. 
 
 
 
   

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


   
SUPPLEMENTARY SPECIFICATIONS  
DIVISION 03 – CONCRETE 
CITY OF COQUITLAM  DIVISION 3  MMCD SECTION 03 30 20S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  CONCRETE  SS PAGE 6  
SUPPLEMENTARY SPECIFICATIONS  Concrete Walks, Curbs and Gutter  2016 
 
MMCD Section 03 30 20S  Concrete Walks, Curbs and Gutter 
 
2.0 PRODUCTS     
 
2.1  Materials  Delete 2.1.5.1 and  Hand‐formed and hand‐placed concrete:  
replace with the 
Slump:  80 mm 
following 
Air entrainment: 5 to 8%. 
 
Maximum aggregate size:  20 mm. 
Miminum cement content:  335 kg/m3. 
Minimum 28 day compressive strength:  32 MPa. 
  Add 2.1.7  Tactile warning surface tile shall be replaceable cast‐in‐
  place  style.  Truncated  domes  shall  be  in  square  grid 
pattern  with  a  5  mm  nominal  raised  height,  base 
diameter  of  23  mm  and  top  diameter  of  11.5  mm. 
Dome spacing range shall be between 40 mm – 60 mm.
Color  of  the  panel  shall  be  Federal  Yellow  (Y)  per  US 
Federal Standard 595B Table IV, Color No. 335. 
Minimum  size  of  the  panel  shall  be  600  mm  by 
1200 mm. 
3.0 EXECUTION     

3.5  Concrete  Delete 3.5.9 and  The  Contractor  is  responsible  for  adjusting  all  utility 
Placement  replace with the  manhole  frames  and  valve  boxes,  belonging  to 
following  Coquitlam  and/or  other  agencies  that  are  affected  by 
  the  road  works.  All  adjustments  to  utilities  must  be 
  completed to the satisfaction of the utility owner. Riser 
rings will not be accepted. 
The Contractor should note that certain utility owners 
may  decide  to  complete  their  own  adjustments.  The 
Contractor  will  be  required  to  cooperate  with  any 
utility company providing their own adjustments. 
The  Contractor  shall  be  responsible  to  contact  the 
appropriate  utility  company  within  a  minimum  of 
seventy  two  (72)  hours  of  the  work.  No  adjustment 
shall  be  made  without  the  written  approval  of  the 
utility  company.  All  manholes  must  be  vertically 
adjusted a minimum of twenty four (24) hours prior to 
concrete placement. 
 
3.9  Expansion Joints  Delete 3.9.1 and  Form transverse expansion joints at both ends of curb 
replace with the  returns  and  at  maximum  spacing  of  9.0 m  for 
following  sidewalks,  30.0 m  of  curb  and  gutter,  at  each  end  of 
driveway  crossing,  at  tangent  point  of  circular  work, 
and on either side of catch basins. 
 

 
 
   
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
SUPPLEMENTARY SPECIFICATIONS  
DIVISION 26 – ELECTRICAL 
   
CITY OF COQUITLAM  DIVISION 26  MMCD SECTION 26 56 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ELECTRICAL  SS PAGE 8  
SUPPLEMENTARY SPECIFICATIONS  Roadway Lighting  2016 
 
MMCD Section 26 56 01S  Roadway Lighting 
 
1.0 GENERAL     
 
1.3  Shop Drawings  Delete 1.3.4 and  Shop  drawings  for  pole  structures,  where  required,  to 
replace with the  be  sealed  by  a  Professional  Engineer  registered  in 
following  British Columbia. 
 
1.4  Electrical Energy  Add 1.4.4  The  Electrical  Contractor  shall  process  a  letter  of 
Supply  application  to  the  City  of  Coquitlam  for  the  Utility 
Company and attain all required permits.  
 
1.5  Contractor  Add 1.5.3  All on‐site traffic signal installations shall be under the 
Qualifications    responsibility of a primary journeyman electrician with 
IMSA Level 1 Roadway Lighting Certification and have a 
minimum  of  three  (3)  years  experience  maintaining 
and  installing  street  lighting  systems.  This  primary 
journeyman  electrician  is  expected  to  be  on  the  work 
site  and  report  work  progress  to  City  of  Coquitlam’s 
Traffic Operations staff, in addition to reporting to the 
Contract Administrator. 
 
1.6  Permits and  Add 1.6.4  Contractor shall provide the BC Safety Electrical Permit, 
Tests    and  arrange  all  inspections  with  the  City.  The 
  inspection  entails,  but  not  limited  to,  Coquitlam’s 
Street  Lighting  Inspection  Report,  which  can  be 
obtained from Coquitlam’s Traffic Operations staff.  
 
  Add 1.6.5  Contractor to obtain approval of all buried portions of 
  the  installation  from  the  City  Inspector  before  any 
backfill is commenced.  
 
1.8  Record Drawings  Add 1.8.2  Final payment(s) will be withheld until record drawings 
  are received.  
 
2.0 PRODUCTS     

2.1  General   Delete 2.1.2 and  All  products  supplied  to  be  new,  in  accordance  with 
replace with the  Contract  Documents.  All  products  are  to  meet 
following  Canadian Electrical Code requirements and be certified 
  by  either  CSA,  UL©,  or  Intertek  Testing  Systems 
(Warnock  Hersey)  and  be  supplied  with  the  certifier’s 
label. 
 
  Delete 2.1.3 and  All  products  shall  be  in  accordance  with  the  City  of 
replace with the  Coquitlam’s  List  of  Approved  Materials  and  Products 
following  List.  Any  products  not  listed  with  in  the  Approved  List 
shall default to the current BCMOTI specification. 
 
CITY OF COQUITLAM  DIVISION 26  MMCD SECTION 26 56 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ELECTRICAL  SS PAGE 9  
SUPPLEMENTARY SPECIFICATIONS  Roadway Lighting  2016 
 
  Delete 2.1.5 and  Equipment models listed within the City of Coquitlam’s 
replace with the  List  of  Approved  Materials  and  Products  shall  be 
following  confirmed  with  the  City  immediately  prior  to  their 
  order  to  ensure  that  they  are  current.  Cut‐sheets, 
equipment  make,  model  and  serial  number  list  to  be 
provided to the City by the Contractor. 

2.2  Conduit  Add 2.2.1.3  All exposed metallic surfaces to be hot dip galvanized.  

2.3  Trench marker  Add 2.3.2  Detectable  (Magnetic)  marker  tape  shall  be  used  in 
Tape   all  trenches  containing  interconnection 
(communications) conduit.  
 
2.6  Concrete Bases   Add 2.6.2  Maximum of four (4) conduits shall enter the base of a 
  luminaire pole, however more than four (4) may enter 
a service base. 
2.8  Conductors and  Add 2.8.5  .1 Minimum  conductor  size  to  be  as  follows,  unless 
Cables     specified otherwise on Contract Drawing: 
.1 No 6 AWG for feeder conductors in conduit. 
.2 No 8 AWG for bond conductors in conduit. 
.3 No 12 AWG for luminaire conductors in poles. 
 
2.9  Conductor Tags   Delete 2.9 and  Refer to the City of Coquitlam’s List of Approved 
replace with the  Materials and Products. 
following   
 
2.11  Fuses and Fuse  Delete 2.11 and  Refer to the City of Coquitlam’s List of Approved 
Holders  replace with the  Materials and Products. 
following   
 
2.13  Receptacles  Add 2.13.3  Receptacles  shall  have  a  spring  loaded  cast  aluminum 
  covers. 
 
  Add 2.13.4  Refer  to  the  City  of  Coquitlam’s  List  of  Approved 
Materials and Products. 
 
2.14  Luminaires  Add 2.14.6  Refer to the City of Coquitlam’s List of Approved 
  Materials and Products. 
 
2.19  Service Panels   Add 2.19.1  Type 40A 120/240V, 60A 120/240V roadway lighting 
    and 100A 120/240V combination roadway lighting / 
traffic signal, per Contract Drawing to include items 
listed within the 2009 MMCD Section 34 41 13 ‐ Traffic 
Signals ‐ 2.11.2 
 
  Add 2.19.2  Refer to the City of Coquitlam’s List of Approved 
Materials and Products. 
 
CITY OF COQUITLAM  DIVISION 26  MMCD SECTION 26 56 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ELECTRICAL  SS PAGE 10  
SUPPLEMENTARY SPECIFICATIONS  Roadway Lighting  2016 
 
2.20  Wire Anti‐Theft  Add 2.20.1  Handhole access shall utilize security covers with 
Devices     reinforced backing bars. 

3.0 EXECUTION     

3.1  General   Add 3.1.5  During the installation of the lighting system, maintain 


  the existing system as noted on the Contract Drawing. 
  If  temporary  or  permanent  relocations  of  related 
lighting equipment are required, such equipment shall 
be  reinstated  as  required  under  the  Contract 
Documents  or  as  directed  by  the  Contract 
Administrator. 
 
3.3  Concrete Bases  Add 3.3.7  Concrete  service  bases  detailed  on  Standard  Detail 
  Drawings  CE1.3  and  CE1.4,  Type  C1  and  C3  service 
bases  shall  have  five  (5)  conduits.  See  Coquitlam 
Standard Detail Drawing SS‐E7.3. 
 
  Add 3.3.8  All  concrete  bases  shall  be  pre‐cast  concrete  only, 
  unless  noted  on  Contract  Drawing  or  directed  by  the 
Contract Administrator.  
 
3.4  Junction Boxes  Delete 3.4.1 and  Install  junction  boxes  as  shown  on  Standard  Detail 
and Vaults   replace with the  Drawings  E2.2  to  E2.4.  Install  vaults  as  shown  on 
following  Coquitlam Standard Detail Drawing SS‐E2.5. 
   
  Add 3.4.5  Bell  end  fittings  shall  be  installed  in  all  conduits 
  entering junction boxes or vaults. 
 
  Add 3.4.6  All junction boxes shall be provided with RPVC bars to 
  support  electrical  connections  and  fuse  holders.  The 
RPVC bars shall be attached into the junction box side 
walls  with  the  electrical  connections/fuse  holders  tie‐
wrapped in place and installed in the up‐right position.  
 
  Add 3.4.7  Junction  boxes  requiring  3  or  more  sections  must  be 
  approved by the City of Coquitlam’s Traffic Operations 
staff. 
 
3.5  Underground  Delete 3.5.2 and  Minimum  cover  over  conduits  to  be  600 mm  in 
Conduit   replace with the  boulevard areas and 900 mm in roadway areas. 
following   

  Delete 3.5.3 and  Place  trench  marker  tape  300 mm  above  installed 


replace with the  conduit in trench. Trench marker tape not required for 
following  conduits installed via trenchless technology. 
   
  Delete 3.5.5 and  Empty conduits shall have a No. 8 HB Yellow/Green Mk 
replace with the  pull string and capped at both ends. 
following   
CITY OF COQUITLAM  DIVISION 26  MMCD SECTION 26 56 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ELECTRICAL  SS PAGE 11  
SUPPLEMENTARY SPECIFICATIONS  Roadway Lighting  2016 
 
  Add 3.5.6  Conduit run shall contain no more than the equivalent 
  of 4 – 90 degree bends. 
 
  Add 3.5.7  Conduits shall be blown out with compressed air, from 
  both  ends  if  necessary,  then  swabbed  out  to  remove 
stones, dirt, water and other material which may have 
entered during installation. 
 
  Add 3.5.8   All conduits entering poles and cabinets shall be sealed 
  with “Duct Seal”. 
 
  Add 3.5.9  Conduit  depth  of  bury  to  be  recorded  when  a 
  trenchless technology method is used.  
 
  Add 3.5.10  Conduit  shall  not  be  bent  in  the  field.  Only  factory 
  bends will be accepted.  
 
3.7  Electrical  Delete 3.7.2 and  Mount  electrical  service  panels  in  service  base  or  on 
replace with the  poles as shown on Standard Detail Drawings E7.2, E7.6 
following  to E7.9, as well as Coquitlam Standard Detail Drawings 
SS‐E7.3 to SS‐E7.5. 
 
3.8  Wiring   Delete 3.8.3 and  Make  conductor  splices  in  handholes.  See  Standard 
replace with the  Detail Drawing E7.11 for splice details. 
following   
 
  Delete 3.8.6 and  Wire  each  luminaire  and  receptacle  separately  from 
replace with the  the base of pole.  
following   
 
  Delete 3.8.7 and  Neatly  arrange  and  bundle  wiring  in  junction  boxes, 
replace with the  pole  handholes  and  service  panels.  Conductor 
following  connections  in  all  access  points  to  be  installed  in  the 
  up‐right position, allowing for easy access  
 
  Delete 3.8.11 and  Bond all luminaires and receptacles with No. 12 RW90 
replace with the  green conductor, and steel junction box lids with No. 8 
following  RW90 green conductor. 
 
3.9  Pole Mounted  Delete 3.9.1 and  Pole mounted receptacles to be installed as detailed on 
Receptacle   replace with the  the  Contract  Drawing  and  Coquitlam  Standard  Detail 
following  Drawings SS‐E7.19 to SS‐E7.23.  
   
3.10  Luminaires and  Add 3.10.4  NEMA  wattage  label  shall  be  visible  at  the  bottom  of 
Photocells   the luminaire on all fixtures. 
 
3.11  Grounding &  Add 3.11.5  Ground plates and grounding conductors are to have a 
Bonding     minimum  of  5  meters  clearance  between  them  and 
other utility grounding. 
CITY OF COQUITLAM  DIVISION 26  MMCD SECTION 26 56 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ELECTRICAL  SS PAGE 12  
SUPPLEMENTARY SPECIFICATIONS  Roadway Lighting  2016 
 
  Add 3.11.6  Remove  all  paint  around  bonding  studs  on  inside  of 
  pole to expose the galvanized or metal surface prior to 
bonding equipment. 
3.13  Pole Finish  Delete 3.13 and  .1 Prior  to  producing  a  powder  finish  product  the 
Application   replace with the  supplier  must  provide  a  Certificate  of  Compliance 
following  indicating  that  they  have  met  or  exceeded  the 
  following  specifications.  The  supplier  will  name 
their  independent  testing  agency  and  this 
information  will  be  submitted  to  the  City  for  their 
files. 
.2 The application process will be as follows: 
.1 The pole or product will be hot dip galvanized. 
.2 Powder will only be applied after the product is 
completely  fabricated.  No  welding  or  bending 
will take place after the powder is applied. 
.3 The pole or product will be thoroughly cleaned 
by brush blasting in accordance with SSPC‐SP7. 
The  brush  blast  will  maintain  a  minimum 
profile of 0.5 mils. If brush blasting is done off 
site  then  the  product  will  be  covered  and 
shielded  from  any  dirt  or  moisture  during  its 
return  to  the  powder  applicators  facility. 
Where  poles  or  products  are  not  kept  clean 
and dry or have any signs of flash rust they will 
be returned for further brush blasting. 
.4 Once  at  the  applicators  facility  the  pole  or 
product  will  be  thoroughly  cleaned  and  dried 
with an air gun. All hand marks or grease spots 
will be cleaned with a mild solvent. 
.5 After brush blasting the entire pole or product 
will be pre‐baked in an oven at 220 degrees C 
for at least 30 minutes to 1 hour, depending on 
steel  thickness.  The  pre‐baking  must  be  done 
to prevent out‐gassing during the curing cycle. 
.6 The  base  powder  coat  will  then  be  applied 
electrostatically  while  the  pole  or  product  is 
cooling  from  the  220  degrees  C  pre‐bake 
period to allow the powder to melt and fuse to 
the  surface.  The  base  coat  will  be  a  minimum 
of 3 mils in thickness. 
.7 After  base  coat  is  applied  and  set  the  topcoat 
will be applied to a thickness of 3 to 5 mils. The 
pole  or  product  will  be  returned  to  the  oven 
and  heated  to  190  to  220  degrees  C 
(temperature  will  not  exceed  pre‐bake)  for  a 
minimum  of  25  minutes,  depending  on  steel 
thickness.  Thicker  product  material  may 
CITY OF COQUITLAM  DIVISION 26  MMCD SECTION 26 56 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ELECTRICAL  SS PAGE 13  
SUPPLEMENTARY SPECIFICATIONS  Roadway Lighting  2016 
 
require  longer  bake  cycles  to  fully  cure.  Upon 
removal of the pole or product from the oven 
it will be left to rest until the pole or product is 
cool enough to the touch. 
.8 Once  the  topcoat  has  cured  and  the  poles  or 
product  cooled,  they  will  then  be  individually 
wrapped  (min  4”  overlapping  method)  with 
1/8”  foam  wrap  over  the  entire  pole  or 
product.  The  poles  or  product  will  be  bundled 
together  and  separated  with  suitable  wood 
dunnage  to  avoid  contact  between  the  poles, 
product  or  other  bundles.  All  bundles 
themselves  will  be  fully  wrapped  with  foam 
and  with  stretch‐wrap  as  noted  above.  The 
poles or products will be handled and shipped 
with  great  care  to  prevent  damage;  damaged 
product  will  be  cause  for  rejection  of  the 
item(s). 
.3 Testing process will be as follows: 
.1 Each  run  of  product  in  an  oven  will  have  at 
least one sample tested for: 
.2 Adhesion  –  The  finished  powder  surface  will 
have  minimum  pull‐off  strength  exceeding 
1000  PSI  as  tested  in  accordance  with 
ASTM D4541. 
.3 Quality  –  The  finished  powder  surface  will  be 
free  from  any  holidays  (skips  or  misses)  as 
tested  in  accordance  with  ASTM  D4541.  The 
product will also be free from wrinkles, orange 
peel,  cracking,  pinholes,  fish  eyes,  blisters,  etc 
by visual inspection. 
.4 Color  –  The  color  will  be  verified  to  be  within 
3 DE of specialized color. 
.5 An  independent  firm  such  as  CanSpec  Testing 
who are qualified to test powder finish will do 
the testing at the supplier’s expense. The result 
of  tests  must  accompany  the  Certificate  of 
Compliance  and  will  be  made  available  to  the 
City  or  their  representative  upon  request.  A 
supplier  who  fails  to  test  product  as  noted 
above will have their product rejected until the 
testing  is  completed  and  the  product  deemed 
acceptable by the testing agency.  
.6 Where  the  tested  product  fails  on  a  given 
production run then a minimum of 30 % of the 
entire production run will be tested. If no other 
failures  are  found  then  the  individual  failed 
CITY OF COQUITLAM  DIVISION 26  MMCD SECTION 26 56 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ELECTRICAL  SS PAGE 14  
SUPPLEMENTARY SPECIFICATIONS  Roadway Lighting  2016 
 
product  will  be  stripped,  reapplied  and  re‐
tested  until  it  passes.  If  any  of  the  30%  of 
product  tested  fails  then  the  entire  order  will 
be  stripped,  reapplied  and  retested  until  it 
passes. 
.4 Field  repairs  will  be  undertaken  as  required  to  fix 
any  scratches  or  imperfections  in  the  final  finish. 
Field repairs will be done as follows: 
.1 Feather the damaged area with sandpaper. 
.2 Clean area with solvent. 
.3 Let dry. 
.4 Neatly  brush  on  an  application  of  Aliphatic 
Urethane Acrylic Semi‐Gloss High Build applied 
at  2‐4  mils  DFT  over  the  entire  sanded  and 
damaged area. The ambient conditions will be 
dry  and  over  10  degrees  C  when  the  paint  is 
applied. 
.5 The pole supplier will warranty the integrity of 
the  surface  for  a  minimum  of  1  year  from  the 
date  of  installation.  The  warranty  will  include 
all  labour  and  materials  required  to  provide 
replacement  product  if  required.  The  powder 
finish  will  be  the  responsibility  of  the  pole 
supplier.  The  warranty  will  apply  to  fading, 
blistering, cracking or chipping of the surface. 
 
     
 

 
SUPPLEMENTARY SPECIFICATIONS  
DIVISION 31 – EARTHWORKS 
CITY OF COQUITLAM  DIVISION 31  MMCD SECTION 31 05 17S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  EARTHWORKS  SS PAGE 16  
SUPPLEMENTARY SPECIFICATIONS  Aggregates and Granular Materials  2016 
 
MMCD Section 31 05 17S  Aggregates and Granular Materials 
 
2.0 PRODUCTS   

2.3  Pit Run Gravel  Add to 2.3.2  The use of recycled concrete shall be approved by the 


Contract Administrator and the City prior to use. 
  Add 2.3.3  Asphalt  millings  free  from  contaminated  and  other 
  extraneous  material,  conforming  to  the  specified 
gradations  may  be  used  as  pit  run  gravel.    The  use  of 
asphalt  millings  shall  be  approved  by  the  Contract 
Administrator and the City prior to use. 
2.7  Granular Pipe  Add to 2.7.1  All  recycled  or  other  extraneous  materials  shall  be 
Bedding and    approved by Contract Administrator and the City prior 
Surround  to use. 
Material 

2.10  Granular Base  Delete 2.10.2   


 
  Add 2.10.3  All 25 mm minus granular base is to conform to the 
following gradation specifications for Collector / Arterial 
Roads: 
 
Sieve Designation (mm)  Percent Passing (%) 
25  100 
19  80‐100 
12.5  75‐90 
9.5  50‐85 
4.75  35‐70 
2.36  25‐50 
1.18  15‐35 
0.30  5‐20 
0.075  0‐5 
 
   
  Add 2.10.4  The intention of the Gradation Chart is to identify the 
desired mix of size of aggregate in the granular base. The 
Target Percentage Passing is the middle of the shown 
Range.  
Tests that show sieve values of Percent Passing that are 
consistently low or consistently high in two (2) or more 
consecuitive tests will be considered to be non‐
conforming. 
 
CITY OF COQUITLAM  DIVISION 31  MMCD SECTION 31 05 17S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  EARTHWORKS  SS PAGE 17  
SUPPLEMENTARY SPECIFICATIONS  Aggregates and Granular Materials  2016 
 
2.11  Recycled  Delete 2.11.1 and  Aggregates containing recycled material may be utilized 
Aggregate  replace with the  if approved by the Contract Administrator and the City.  
Material  following  In addition to meeting all other conditions of the 
specifications, recycled material should not reduce the 
quality of the construction achievable with quarried 
materials.  Recycled material shall consist only of 
aggregates, crushed portland cement concrete, or 
asphalt that is free of impurities. 

     
     
CITY OF COQUITLAM  DIVISION 31  MMCD SECTION 31 11 41S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  EARTHWORKS  SS PAGE 18  
SUPPLEMENTARY SPECIFICATIONS  Shrub and Tree Preservation  2016 
 
MMCD Section 31 11 41S  Shrub and Tree Preservation 
 
2.0  PRODUCTS     
 
2.1   Materials  Add 2.1.10  Protective  Fencing:  Posts  ‐  Pressure  treated  wood 
100 mm  dia.;  Post  to  be  1.8 m  to  2.0m  in  height  at 
2.0 m  O.C.  Snow  fence  as  per  Coquitlam  Approved 
Products  List;  Flagging  Tape  ‐  4”  Orange  glow  ‐  ‘Tree 
Retention Area’. 
 
3.0 EXECUTION     
 
3.1  Existing Trees  Add 3.1.7  The  Contractor  is  responsible  to  minimize  damage  to 
all trees which are to remain. 
 
  Add 3.1.8  The  Contractor  will  be  responsible  for  all  claims  and 
costs including the cost of examination by an Arborist, 
repair,  removal  and  replacement  of  trees,  as  required 
by  the  Arborist,  the  Contract  Administrator  and  the 
City for tree damage where proper notification was not 
received from the Contractor. Damage will be assessed 
based  on  the  International  Society  of  Arboriculture 
Guidelines. The term shall be for a period of one year 
following  the  date  of  Substantial  Performance  of  the 
Work. 
 
  Add 3.1.9  Place  protective  fencing/barricades  as  detailed  on 
Coquitlam  Standard  Detail  Drawings  COQ‐R26  and 
COQ‐R27.  Contractor  shall  maintain  fence  in  good 
condition during construction. 
 
  Add 3.1.10  When  work  is  to  be  performed  inside  fenced  areas, 
Contractor shall take care to avoid damage to existing 
vegetation.  Work  to  be  done  inside  areas  of  existing 
vegetation to be retained includes: 
.1 Removal  of  isolated  trees  as  directed  by  the 
Contract Administrator and the City. 
.2 Selective  pruning  and  tree  removal  at  edges  to 
create tidy and well‐shaped forest edge. 
.3 Placing planting soil and planting of trees. 
 
  Add 3.1.11  Do  not  park,  service  or  fuel  vehicles  within  the 
vegetation retention areas. 
 
3.4  Pruning  Add 3.4.2  Do not cut roots or branches of retained trees without 
approval of the Contract Administrator and the City. 
CITY OF COQUITLAM  DIVISION 31  MMCD SECTION 31 23 01S 
ENGINEERING DEPARTMENT  EARTHWORKS  SS PAGE 19  
SUPPLEMENTARY SPECIFICATIONS  Excavating, Trenching and Backfilling  2015 
 
MMCD Section 31 23 01S  Excavating, Trenching and Backfilling 
 
1.0 GENERAL     
 
1.8  Limitations of  1.8.1  If  circumstances  do  not  permit  complete  backfilling  of 
Open Trench  Replace last  all  trenches,  and  where  permitted  by  the  Contract 
sentence with the  Administrator and the City, adequately protect all open 
following  trenches  or  excavations  with  approved  fencing  or 
barricades and, where required, with flashing lights. 
 
2.0 PRODUCTS     
 
2.2   Use of Specified  Delete 2.2.1.2  Delete Pit Run Sand 
Materials 
 
  Delete 2.2.3.3  Delete Pit Run Sand 
 
3.0  EXECUTION     
 
3.3  Excavation  Delete 3.3.1.2 and  Connections  to  existing  waterworks  systems  are  to  be 
replace with the  made  by  the  Contractor  under  the  inspection  / 
following  supervision of the Contract Administrator and the City. 
 
3.6  Surface  Delete 3.6.2.4 and  Restore lawns with approved topsoil and sod to match 
Restoration  replace with the  existing lawn. 
following 
 
  Delete 3.6.3.1 and  Restore  surface  with  a  minimum  100 mm  of  19 mm 
replace with the  granular road base material. 
following 
 
  Delete 3.6.7.5 and  Restore  Pavement  as  detailed  on  Coquitlam  Standard 
replace with the  Detail  Drawing  COQ‐G4.  Temporary  patch  shall  be  a 
following  minimum  thickness  of  50 mm  thickness.  Permanent 
restoration  to  existing  asphalt  thickness  (minimum  of 
75 mm)  with  a  35 mm  key  where  existing  thickness 
permits.  A 50 mm  key  is  required  on  Arterial  and 
Collector Roadways.  Dry if necessary and paint clean, 
dry edge with asphalt emulsion (tack coat). 
 
 
CITY OF COQUITLAM  DIVISION 31  MMCD SECTION 31 23 17S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  EARTHWORKS  SS PAGE 20  
SUPPLEMENTARY SPECIFICATIONS  Rock Removal  2016 
 
MMCD Section 31 23 17S  Rock Removal 
 
1.0 GENERAL     
 
1.7   Seismic Survey  Delete 1.7.1 and  Contractor  will  arrange  for  assessment  of  adjacent 
and Monitoring  replace with the  buildings  and  structures  to  determine  existing 
  following  conditions  and  will  provide  building  and  structure 
  owners  with  proposed  blasting  procedures  and  copies 
of  assessment  reports  and  seismic  recording 
operations. 
 
  Delete 1.7.2 and  Cost  of  professional  seismic  survey  and  monitoring 
replace with the  reports will be paid by Contractor. 
following 
 
 
CITY OF COQUITLAM  DIVISION 31  MMCD SECTION 31 24 13S 
ENGINEERING DEPARTMENT  EARTHWORKS  SS PAGE 21  
SUPPLEMENTARY SPECIFICATIONS  Roadway Excavation, Embankment and Compaction  2015 
 
MMCD Section 31 24 13S  Roadway Excavation, Embankment and Compaction 
 
2.0 PRODUCTS     
 
2.2   Specified  Delete 2.2.1.3  Pit Run Sand 
Materials 
 
  Delete 2.2.1.4  River Sand 
 
  Delete 2.2.2   
     
SUPPLEMENTARY SPECIFICATIONS  
DIVISION 32 – ROAD AND SITE IMPROVEMENTS 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 11 16.1S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 22  
SUPPLEMENTARY SPECIFICATIONS  Granular Subbase  2016 
 
MMCD Section 32 11 16.1S  Granular Subbase 
 
2.0   PRODUCTS     
 
2.1  Specified  Delete   2.1.1.1: Select Granular Subbase 
Materials  2.1.1.2: 75 mm Pit Run Gravel 
  2.1.1.4: Pit Run Sand 
2.1.1.5: Approved Native Material 
2.1.1.7: River Sand 
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 11 23S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 23  
SUPPLEMENTARY SPECIFICATIONS  Granular Base  2016 
 
MMCD Section 32 11 23S  Granular Base 
 
2.0 PRODUCTS     
 
2.1   Granular Base  Add 2.1.1.3  25 mm  minus  crushed  gravel  conforming  to  the 
gradation  specifications  for  Collector/Arterial  Roads 
under Section 31 05 17S – 2.10.3. 
3.0 EXECUTION     
 
3.5   Proof Rolling  Delete 3.5.1 and  For proof rolling, use fully loaded single axle, to 80 KN 
replace with the  (18, 000 lb) minimum, dump truck. 
following 
 
  Add 3.5.7  Prior to paving with asphalt concrete, the base surface 
  shall be checked by the Contract Administrator and the 
City,  for  deflections  utilizing  a  Benkelman  Beam,  in 
order  to  insure  that  the  final  rebound  requirements 
can  be  obtained  with  the  asphalt  pavement.  In  the 
event  that  such  deflection  are  in  excess  of  those 
required to produce the final standards, than the base 
shall  be  adequately  strengthened  by  additional  gravel 
or  asphalt  concrete  to  insure  that  final  deflections  as 
follows are not exceeded. 
The Benkelman spring rebound value of the completed 
pavement  surface  shall  not  at  any  point  exceed 
0.75 mm  for  arterial  industrial  roads  and  lanes, 
1.15 mm  for  collector  roads,  and  1.5 mm  for  local 
roads  and  lanes  as  determined  in  the  procedures 
outlined  in  the  Transportation  Association  of  Canada 
publication “Pavement Management Guide.” 
 
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMMCD SECTION 32 12 13.1S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 24  
SUPPLEMENTARY SPECIFICATIONS  Asphalt Tack Coat  2016 
 
MMCD Section 32 12 13.1S  Asphalt Tack Coat 
 
3.0 EXECUTION     
 
3.2   Application  Add to 3.2.3  Asphalt tack coat to be applied using a truck mounted 
spray  bar  unless  otherwise  approved  by  the  Contract 
Administrator  and  the  City.    Contractor  shall 
demonstrate,  to  the  Contract  Administrator  and  the 
City,  prior  to  application  that  all  spray  nozzles  are 
operational and providing a consistent application. 
 
 
 
 
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 12 16S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 25  
SUPPLEMENTARY SPECIFICATIONS  Hot Mix Asphalt Concrete Paving  2016 
 
MMCD Section 32 12 16S  Hot Mix Asphalt Concrete Paving 
 
1.0 GENERAL     

1.1  Related Work  Add 1.1.8  Manholes and Catchbasins   Section 33 44 01 


   
1.6  Inspection and  Add 1.6.3  Test cores will be taken by the Contract Administrator 
Testing    in the areas of new paving and will include cores along 
  construction  joints  to  ensure  compliance  with  the 
required design and compaction. 
2.0 PRODUCTS   
 
2.1  Materials  Add 2.1.2.1  Usage  of  recycled  asphalt  shingles  will  not  be 
permitted. 
  Add 2.1.2.2  Usage  of  softening  agents,  rejuvenators,  or  recycling 
agents will not be permitted. 
2.2  Mix Design  Delete 2.2.2 and  Mix may contain up to a maximum of 15 % by mass of 
  replace with the  RAP for Upper Course Asphalt and 20 % by mass of RAP 
following  for Lower Course Asphalt without a special mix design.  
The  Contract  Administrator  and  the  City  may  approve 
higher  proportion  of  RAP  if  Contractor  demonstrates 
ability  to  produce  mix  meeting  requirements  of  the 
specification. 
  Delete 2.2.3.2  Marshall  Stability  at  60oC  for  both  lower  and  upper 
Marshall Stability  courses to be 10 KN min. 
and replace with 
the following 
3.0 EXECUTION   
 
3.3  Preparation  Delete 3.3.3 and  The  Contractor  is  responsible  for  adjusting  all  utility 
replace with the  manhole  frames  and  valve  boxes,  belonging  to 
following  Coquitlam  and/or  other  agencies  that  are  affected  by 
  the  road  works.  All  adjustments  to  utilities  must  be 
completed  to  the  satisfaction  of  the  utility  owner. 
Utility  adjustment  within  the  paved  surface  will  be 
considered  incidental  to  the  Work  unless  otherwise 
noted in the Contract Documents. 
The Contractor should note that certain utility owners 
may  decide  to  complete  their  own  adjustments.  The 
Contractor  will  be  required  to  cooperate  with  any 
utility company providing their own adjustments. 
The  Contractor  shall  be  responsible  to  contact  the 
appropriate  utility  company  with  in  minimum  of 
seventy  two  (72)  hours  of  the  work.  No  adjustment 
shall  be  made  without  the  written  approval  of  the 
utility company.  

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 12 16S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 26  
SUPPLEMENTARY SPECIFICATIONS  Hot Mix Asphalt Concrete Paving  2016 
 
All manholes must be vertically adjusted a minimum of 
twenty four (24) hours prior to paving.  The use of riser 
rings for adjusting manhole frames and value boxes will 
not be permitted. 
 
3.7  Joints  Delete 3.7.5 and  Construct  butt  joints  at  locations  as  shown  on  the 
replace with the  Contract  Drawing  and  as  directed  in  the  field  by  the 
following  Contract Administrator and the City.  
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 12 17 S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 27  
SUPPLEMENTARY SPECIFICATIONS  Superpave Hot Mix Asphalt Concrete Paving  2016 
 
MMCD Section 32 12 17S  Superpave Hot Mix Asphalt Concrete Paving 
 
1.0 GENERAL     
 
1.1  Related Work  Add 1.1.13  Manholes and Catchbasins   Section 33 44 01 
 
2.0 PRODUCTS   
 
2.1  Materials  Add 2.1.2 and  Reclaimed asphalt pavement (RAP): Processing quality, 
replace with the  and  use  to  requirements  of  NCHRP  report  452  and 
following  Table 1, with a RAP incorporation limit of 20 % in lower 
  course  superpave  HMA  and  15 %  in  upper  course‐
superpave HMA. 
  Add 2.1.2.1  Usage  of  recycled  asphalt  shingles  will  not  be 
  permitted. 
 
  Add 2.1.2.2  Usage  of  softening  agents,  rejuvenators,  or  recycling 
  agents will not be permitted. 
 
  Add 2.1.5  Asphalt cement: for SuperpaveTM 
Volumetric  mix  design  for  Asphalt  Cement  shall  meet 
or exceed performance grade PG 64‐22. 
The  asphalt  supplier  shall  be  required  to  submit  test 
results  conforming  with  the  PG  sepecifications.    All 
documented technical data, including softening curves 
and  the  asphalt,  must  be  supplied  to  the  Contract 
Administrator and the City. 
3.0 EXECUTION     
 
3.3  Preparation  Delete 3.3.3 and  The  Contractor  is  responsible  for  adjusting  all  utility 
replace with the  manhole  frames  and  valve  boxes,  belonging  to 
following  Coquitlam  and/or  other  agencies  that  are  affected  by 
  the  road  works.  All  adjustments  to  utilities  must  be 
completed  to  the  satisfaction  of  the  utility  owner. 
Utility  adjustment  within  the  paved  surface  will  be 
considered  incidental  to  the  Work  unless  otherwise 
noted in the Contract Documents. 
The Contractor should note that certain utility owners 
may  decide  to  complete  their  own  adjustments.  The 
Contractor  will  be  required  to  cooperate  with  any 
utility company providing their own adjustments. 
The  Contractor  shall  be  responsible  to  contact  the 
appropriate  utility  company  with  in  minimum  of 
seventy  two  (72)  hours  of  the  work.  No  adjustment 
shall  be  made  without  the  written  approval  of  the 
utility company.  
All manholes must be vertically adjusted a minimum of 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 12 17 S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 28  
SUPPLEMENTARY SPECIFICATIONS  Superpave Hot Mix Asphalt Concrete Paving  2016 
 
twenty four (24) hours prior to paving.  The use of riser 
rings for adjusting manhole frames and value boxes will 
not be permitted. 
  Add 3.3.7  A  pre‐paving  meeting  shall  be  conducted  on‐site  with 
the  paving  staff,  the  Contract  Administrator  and  the 
City  just  prior  to  paving  to  provide  instruction 
regarding  the  existing  grading  and  requirements  for 
the paving process and the end product.  
The  Contractor  must  provide  information  to  the 
Contract  Administrator  and  the  City,  for  review, 
regarding  proposed  paving  elevation  control  method, 
mat thickness control method, and rolling patterns. 
It  will  be  the  responsibility  of  the  Superintendent  to 
ensure  continuity  between  the  base  preparation  and 
the paving process. 
3.5  Placing  Add to 3.5.4.3  Minimum thickness for surface course shall not be less 
than 50 mm. 
3.6  Compaction  Delete 3.6.1 and  Roll  asphalt  continuously  to  a  density  >93 %  of  the 
replace with the  Maximum Theoretical Density of the mix.  A minimum 
following  of four (4) out of five (5) consecutive density test shall 
meet this criteria.  No individual test shall be less than 
92 %.  A Quality Control Plan (QCP) shall be submitted 
to  the  Contract  Administrator  and  the  City  prior  to 
paving  which  shall  include  full  details  of  the  paving 
equipment,  rate  of  placement,  proposed  rolling 
patterns  for  breakdown,  intermediate  and  finishing 
rollers,  in‐sin  densite  testing  during  and  after 
compaction  and  monitoring  of  temperature  of  the 
asphalt mix in the trucks. 
3.7  Joints  Delete 3.7.5 and  Construct  butt  joints  as  shown  on  Contract  Drawing 
replace with the  and  as  directed  in  the  field  by  the  Contract 
following  Administrator and the City.  
 
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 14 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 29  
SUPPLEMENTARY SPECIFICATIONS  Unit Paving  2016 
 
MMCD Section 32 14 01S  Unit Paving 
 
1.0  GENERAL     
 
1.1  Related Work  Add 1.1.7  Geosynthetics   Section 31 32 19 
 
1.3  Samples  Add 1.3.2  The  Contractor  shall  install  a  2m  x  2m  trial  area  for 
approval prior to full installation. 
 
  Add 1.3.3  The trial area shall be retained as the standard for the 
project.    Surcharge  of  the  bedding  sand  layer,  joint 
sizes, line, laying pattern(s), color(s) and texture of the 
trial panel shall be consistent throughout the job. 
 
  Add 1.3.4  The trial area may form part of the permanent surface 
if  approved  by  the  Contract  Administrator  and  the 
City.  Any trial area that is not part of the final product 
shall  be  removed  and  properly  disposed  of  at  the 
contractor’s expense. 
 
1.7  Inspection and  Add 1.7.2  Contractor shall provide an independent quality test to 
Testing  be  completed  during  construction.    Testing  company 
  shall  be  approved  by  the  Contract  Administrator  and 
the City. 
 
  Add 1.7.3  Geotechnical  assessment  of  subgrade  is  required  in 
order  to  assess  soil  conditions  and  design  the  road 
structural section.  Design report shall be submitted to 
the  Contract  Administartor  and  the  City  for  approval 
prior to commencing work. 
 
2.0  PRODUCTS     
 
2.1  Materials  Delete 2.1.4 and  Bedding sand shall conform to the following gradation 
replace with the  limits: 
following  Sieve Size (mm)  Percent Passing (%) 
  9.52  100 
4.75  95 – 100 
2.35  80 – 100 
1.18  50 ‐ 85 
0.60  25 ‐ 60 
0.30  10 ‐ 30 
0.15  5 – 15 
0.075  0 ‐ 10 
   
  Add 2.1.7  Concrete pavers shall conform to ASTM C939 to C982, 
specifications  for  solid  concrete  interlocking  paving 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 14 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 30  
SUPPLEMENTARY SPECIFICATIONS  Unit Paving  2016 
 
units. 
 
  Add 2.1.8  Paver  type,  size  and  colour,  shall  be  as  indicated  on 
  the  Contract  Drawing.  Paver  thickness  shall  vary.  All 
pavers  used  in  driveways  shall  be  a  minimum  80  mm 
thick. All pavers used for boulevard or sidewalk areas 
shall be a minimum 60 mm thick. 
 
  Add 2.1.9  Pigmentation of concrete pavers shall be a solid colour 
throughout the unit. 
 
  Add 2.1.10  Normal  weight  aggregate  shall  be  used  for  the 
concrete mix. 
 
  Add 2.1.11  Jointing  sand  shall  consist  of  at  least  30%  of  1  mm 
sand  particles  and  shall  otherwise  meet  the 
requirements for bedding sand. 
 
  Add 2.1.12  All concrete pavers shall be sealed. 
 
3.0  EXECUTION     
   
3.2  Granular  Add 3.2.5  Sand,  when  stock  piled  onsite,  shall  be  protected 
Subbase and  against the rain. 
Base  
3.5  Unit Paving  Delete 3.5 and  .1  Concrete pavers shall be delivered and stored on‐
replace with the  site in metal strapping or shrink wrapped PVC. 
following   
    .2  Prior  to  installation  of  concrete  pavers  all  street 
signs shall be installed. 
 
    .3  Sand  bedding  shall  have  moisture  content  not 
less  than  6%  and  not  more  than  8%  prior  to 
compaction. 
 
    .4  All  pavers  shall  be  sealed  with  a  clear  protective 
sealant after installation. 
 
    .5  Sand bedding shall be spread evenly over an area 
not  greater  than  required  to  receive  concrete 
pavers  in  one  day  and  shall  be  protected  against 
accidental pre‐compaction and rain. 
.1  This  bedding  shall  have  a  minimum 
compacted  thickness  of  20  mm  and  a 
maximum  compacted  thickness  of  40  mm, 
and  shall  be  graded  to  meet  crossfalls  in 
boulevards, sidewalks and driveways. 
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 14 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 31  
SUPPLEMENTARY SPECIFICATIONS  Unit Paving  2016 
 
    .6  Concrete  pavers  shall  be  laid  in  a  pattern  as 
indicated on the Contract Drawing. 
.1  Joints between units shall not exceed 3 mm. 
.2  Full  units  shall  be  installed  first  and  edge 
pieces fitted subsequently. 
 
    .7  Edge  restraint  shall  be  as  indicated  on  the 
Contract Drawing. 
 
    .8  Gaps  at  junctions  between  concrete  pavers  and 
edge restraints shall be filled with purpose made 
or cut edge pieces. Paver shall be cut to fit other 
conditions.  All  pavers  shall  be  cut  with  an 
approved paver guillotine or masonry cut‐off saw 
to  neatly,  and  accurately  fit  without  damaged 
edges. 
 
    .9  Pavers  shall  be  vibrated  to  their  final  level  by 
having not less than 3 passes of a vibrating plate 
compactor. 
The  compactor  shall  be  a  high  frequency,  low 
amplitude unit with plate size sufficient to cover a 
minimum 12 pavers. 
 
    .10  After  placement,  jointing  sand  shall  be  spread 
over the paver surface and vibrated to completely 
fill  all  joints.  Jointing  sand  shall  be  reinstalled 
after the first heavy rainstorm. 
 
3.6  Acceptance  Add 3.6.2  All pavers must drain freely with no ponding of water.  
 
  Add 3.6.3  Defective,  chipped  or  poorly  cut  pavers  shall  be 
replaced. 
 
  Add 3.6.4  Surfaces  shall  abut  flush  with  adjacent  materials. 
Surface  of  finished  pavement  shall  be  free  from 
depressions  exceeding  3 mm  as  measured  with  3m 
straight edge. 
 
     

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 17 23S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 32  
SUPPLEMENTARY SPECIFICATIONS  Painted Pavement Markings  2016 
 
MMCD Section 32 17 23S  Painted Pavement Markings 
 
1.0 GENERAL     
 
1.2  Scope  Delete 1.2.1 and  Pavement  Markings:  Miscellaneous  taped  temporary 
replace with the  and  permanent  pavement  paint  markings  including 
following   pedestrian  crosswalk,  merge  and  diverge  markings, 
  stop  lines,  solid  and  broken  line  road  lane  markings 
including  edge  lines  of  merge  and  diverge  markings, 
bike  symbols,  etc.  to  be  provided  as  shown  on  the 
Contract Drawing.  
 
  Add 1.2.2  All  permanent  paint  markings  shall  be  marked  with 
  thermoplastic. 
 
2.0 PRODUCTS     
 
2.1   Materials  Delete 2.1.1 and  All  permanent  paint  markings  shall  be  marked  with 
replace with the  thermoplastic  manufactured  by  Lafrentz  Road 
following  Markings. 
 
  Delete 2.1.6 and  Pavement Markings: 
replace with the 
following 
 
  Delete 2.1.7 and  Thermoplastic material 
replace with the  .1  Material composition shall be at the discretion of 
following  the  manufacturer  subject  to  the  approval  of  the 
  Contract  Administrator  and  the  City.    Each 
formulation shall be identified by a code number. 
.2  No retained water when tested by ASTM D‐570. 
.3  Specific  gravity  of  the  supplied  product  shall  be 
within  3 %  of  that  specified  for  the  selected 
formulation. 
.4  Material  shall  not  deteriorate  upon  contact  with 
deicing  chemicals,  gasoline,  diesel  fuel  or  grease 
dropped by traffic. 
.5  Material shall not break down, deteriorate, scorch 
or  discolour,  if  held  within  the  application 
temperature range specified by the manufacturer 
for  a  period  of  four  hours  and  it  must  be  able  to 
be  reheated  from  room  temperature  to  the 
application  temperature  four  (4)  times  without 
showing any of these detrimental effects. 
.6  When  applied  at  the  temperature  recommended 
by the manufacturer and at a film thickness of 2 to 
4 mm,  the  material  shall  set  solid  and  show  no 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 17 23S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 33  
SUPPLEMENTARY SPECIFICATIONS  Painted Pavement Markings  2016 
 
tracking  under  traffic  after  elapsed  times  as 
follows: 
.1  Two  (2)  minutes  at  an  air  temperature  of 
10o C,  relative  humidity  less  than  75 %,  and 
road surface temperature from 10o C to 20o C. 
.2  Five  (5)  minutes  at  an  air  temperature  of 
32o C,  relative  humidity  less  than  75 %,  and 
road surface temperature from 35o C to 50o C. 
.3  The  drying  time  under  conditions 
intermediate  between  te  two  air 
temperatures  shall  be  interpolated  using  a 
straight line model. 
.7  The  quantity,  type,  and  gradation  of  the 
component  reflecting  glass  spheres  premixed  in 
the  thermoplastic  material  shall  be  at  the 
discretion  of  the  manufacturer,  but  shall  provide 
retroreflection levels specified below. 
 
3.0  EXECUTION     
     
3.3  Application  Add to 3.3.1.3  Temporary  raised  pavement  markings  (TRPMs)  are  to 
be  provided  on  all  multi  lane  roadways  as  directed  by 
the Contract Administrator and the City. 
     
Delete 3.3.3.3 and  Thermoplastic material shall be heated in the melter to 
replace with the  a temperature of 382 °F. 
following 
 
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 31 13S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 34  
SUPPLEMENTARY SPECIFICATIONS  Chain Link Fences and Gates  2016 
 
MMCD Section 32 31 13S  Chain Link Fences and Gates 
 
1.0 GENERAL     
1.2  References  Add 1.2.2  CAN/CGSB‐138.1‐M80, Fence, Chain Link Fabric 
  Add 1.2.3  CAN/CGSB‐138.2‐M80,  Fence,  Chain  Link,  Framework, 
Zinc‐Coated, Steel. 
  Add 1.2.4  CAN/CGSB‐138.3‐M80, Fence, Chain Link Installation. 
  Add 1.2.5  CAN/CGSB‐138.4‐M82, Fence, Chain Link, Gates. 
  Add 1.2.6  CSA  G164‐M1981,  Hot  Dip  Galvanizing  of  Irregularly 
Shaped Articles. 
  Add 1.2.7  ASTM  A90‐81,  Test  Method  for  Weight  of  Coating  on 
Zinc‐Coated (Galvanized) Iron or Steel Articles. 
  Add 1.2.8  ASTM  A53‐88a,  Specification  for  Pipe,  Steel,  Black  and 
Hot‐Dipped, Zinc‐Coated Welded and Seamless. 
  Add 1.2.9  CGSB 1‐GP‐181M‐77, Coating, Zinc‐Rich, Organic, Ready 
Mixed. 
1.4  Samples  Delete 1.4.1 and  Prior  to  the  start  of  the  work,  submit  a  300 mm  long 
replace with the  powder‐coated pipe sample that will be representative 
following  of  the  quality  of  the  powder‐coating  for  all  powder‐
  coated fencing materials installed as part of the Work. 
 
1.6  Inspection and  Add 1.6.2  The surface of the posts and rails will be scratch tested 
Testing  to  ensure  the  finish  does  not  flake.    Finishes  that  flake 
when scratched will be rejected. 
1.7  Qualifications  Add 1.7.1  Execute  work  in  this  Section  only  by  a  Contractor  who 
has  adequate  equipment,  skilled  tradesmen,  and 
materials to perform the work expeditiously and to the 
contract specifications.  
2.0 PRODUCTS     
 
2.1  Materials  Delete 2.1.1 and  Fencing,  posts,  rails,  and  fabric  shall  be  constructed  as 
replace with the  shown  on  the  Contract  Drawing  and  Specifications 
following  herein. 
  Delete 2.1.3 and  Chain‐link fence fabric: to CAN/CGSB‐138.1. 
replace with the  1. All chain link fabric shall be galvanized, vinyl coated, 
following  black,  commercial  and  heavy  grade  with  50 mm 
  openings.    The  widest  rolls  of  fabric  shall  be 
employed  in  the  construction  of  the  appropriate 
fence  type  (i.e.  1200 mm  wide  rolls  for  1200 mm 
high  fencing  and  2400 mm  wide  rolls  for  2400 mm 
high fencing, etc.).   
2. Fabric  gauges,  fabric  opening  sizes,  fence  heights, 
and post spacing shall be as follows: 
.1 For passive and low activity City and Park areas 
the chain link fence shall be: 
.1 1200 mm  high  with  the  post  spacing 
3000 mm o.c. and,  

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 31 13S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 35  
SUPPLEMENTARY SPECIFICATIONS  Chain Link Fences and Gates  2016 
 
.2 Chain link fabric shall be 9 gauge (3.55 mm 
diameter)  galvanized,  vinyl  coated,  black, 
commercial grade with 50 mm openings. 
.2 For  high  activity  City  and  Park  areas  the  chain 
link fence shall be: 
.1 1200 mm  high  with  the  post  spacing 
2400 mm o.c. and, 
.2 Chain link fabric shall be 6 gauge (4.50 mm) 
galvanized, vinyl coated, black, commercial 
and heavy grade with 50 mm openings 
.3 For  the  baseball  diamond  backstop  the  chain 
link fence shall be: 
.1 4600 mm and higher with the post spacing 
2400 mm o.c and, 
.2 Chain link fabric shall be 6 gauge (4.50 mm) 
galvanized, vinyl coated, black, commercial 
and heavy grade with 38mm openings. 
.4 For the soccer playing field backstop fences the 
chain link fence shall be: 
.1 6000 mm and higher with the post spacing 
2400 mm o.c and, 
.2 Chain link fabric shall be 6 gauge (4.50 mm) 
6  gauge  galvanized,  vinyl  coated,  black, 
commercial  and  heavy  grade  with  38 mm 
openings. 
  Delete 2.1.4 and  Posts  and  rails  for  all  fencing  locations  are  to 
replace with the  CAN/CGSB‐138.2, schedule 40 galvanized steel pipe and 
following  shall  be  powder‐coated  black  steel  pipe.    No  short 
  lengths,  tubing,  conduit  or  open  seam  material  will  be 
permitted.   
.1 Post and rail sizes shall be as follows: 
.1 For  passive/active  public/non‐public  areas 
which are 1200 mm or 2400 mm and higher: 
.1 Corner  and  gate  posts  shall  be  75 mm 
nominal  outside  diameter,  standard 
continuous  weld  Schedule  40  powder‐
coated black steel pipe. 
.2 Line posts shall be 60 mm nominal outside 
diameter,  standard  continuous  weld 
Schedule  40  powder‐coated  black  steel 
pipe. 
.3 Top and bottom rails and horizontal braces 
shall  be  48 mm  nominal  outside  diameter, 
plain  ends,  continuous  lengths,  standard 
continuous  weld  Schedule  40  powder‐
coated black steel pipe. 
.2 Baseball diamond backstop which are 4600 mm 
and higher: 
.1 Corner  and  line  posts  shall  be  114 mm 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 31 13S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 36  
SUPPLEMENTARY SPECIFICATIONS  Chain Link Fences and Gates  2016 
 
nominal  outside  diameter,  standard 
continuous  weld  Schedule  40  powder‐
coated black steel pipe. 
.2 Top,  bottom,  and  horizontal  bracing  rails 
shall  be  48 mm  nominal  outside  diameter, 
plain  ends,  continuous  lengths,  standard 
continuous  weld  Schedule  40  powder‐
coated black steel pipe. 
.3 Post  extensions  for  the  overhang  shall  be 
75 mm nominal outside diameter, standard 
continuous  weld  Schedule  40  powder‐
coated  black  steel  pipe.    At  connection 
install welded 13 mm plate steel gussets as 
per  the  drawings  herein.    Overhang 
horizontal rails and bracing shall be 48 mm 
nominal  outside  diameter,  plain  ends, 
continuous  lengths,  standard  continuous 
weld  Schedule  40  powder‐coated  black 
steel pipe. 
.3 Soccer  playing  field  backstop  which  are 
6000 mm and higher: 
.1 Corner  and  line  posts  shall  be  89 mm 
nominal  outside  diameter,  standard 
continuous  weld  Schedule  40  powder‐
coated black steel pipe. 
.2 Top,  bottom,  and  horizontal  bracing  rails 
shall  be  48 mm  nominal  outside  diameter, 
plain  ends,  continuous  lengths,  standard 
continuous  weld  Schedule  40  powder‐
coated black steel pipe. 
 
  Delete 2.1.5 and  Bottom  tension  wire:  single  strand,  black  vinyl  gated 
replace with the  galvanized steel wire, 6 gauge (4.5mm Diameter). 
following 
  Delete 2.1.6 and  Tie  wire  fasteners  shall  be  single  strand,  black  vinyl 
replace with the  coated  galvanized  aluminium  or  steel  wire  conforming 
following  to requirements of fence fabric. 
  Delete 2.1.7 and  Tension  bars:  4.76  x  19 mm  minimum  galvanized  black 
replace with the  power coated steel. 
following 
  Delete 2.1.8 and  Tension bar bands: 3 x 20 mm galvanized black powder 
replace with the  coated steel or 5x20 mm minimum black powder coated 
following  aluminium.   
  Delete 2.1.9 and  Install  the  chain  link  fence  person  gates  and  vehicle 
replace with the  gates as shown on the Contract Drawing. 
following  .1 Chain Link Vehicle Gates. 
.1 The vehicle gates shall not be used as a centre 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 31 13S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 37  
SUPPLEMENTARY SPECIFICATIONS  Chain Link Fences and Gates  2016 
 
post.   The closure device  shall be operated  by 
securing the gates together when in the closed 
position.    The  closure  device  shall  be  be 
operated  independent  of  the  locking  pins.  
Closure device must accept a standard padlock.
.2 The  vehicle  gate  is  to  have  locking  pins  with 
locking  pin  aluminum  sleeves  recessed  25 mm 
into the concrete walkway to secure the gates 
in  the  open  and  closed  positions.    The  top  of 
the sleeve shall be flused with the surrounding 
concrete  surface.  The  locking  pin  rod  shall  be 
spring‐loaded  so  that  the  pin  is  always  in  the 
raised  position  unless  pushed  and  turn  locked 
into place, as per the drawings herein. 
.3 The  vehicle  gate  shall  be  to  the  full  height  of 
the  fence  and  shall  not  be  bridged  with  a  top 
rail  over  it  as  to  eliminate  any  restrictions  on 
the height of objects passing through the gate. 
.4 The vehicle gate is to operate on wheels which 
fully  support  the  weight  of  the  gate.    The 
wheels  must  be  suitable  for  use  on  concrete 
surfaces  and  must  not  mark  the  concrete 
surface. 
.5 Vehicle gates shall not have signage inserts. 
.6 All hinges shall be welded into place. 
 
.2 Chain Link Person Gates. 
.1 The person gates are to have clear openings of 
1219 mm.  
.2 The  person  gates  shall  be  used  as  a  closure 
device  to  operate  by  securing  the  gate  to  the 
gate  post  when  in  the  closed  position.    The 
closure devices shall be operated independent 
of the locking pins.  Closure device must accept 
a standard padlock. 
.3 The  person  gates  shall  have  locking  pins  with 
locking  pin  aluminum  sleeves  recessed  25 mm 
into the concrete walkway to secure the gates 
in  the  open  and  closed  positions.    The  top  of 
the  sleeve  shall  be  flushed  with  the 
surrounding concrete surface.  The locking pin 
rod  shall  be  spring‐loaded  so  that  the  pin  is 
always in the raised position unless pushed and 
turn  locked  into  place,  as  per  the  drawings 
herein. 
.4 For  soccer  playing  field  entry  gates,  the  gates 
shall  not  have  locking  pins  for  the  open 
positions.    Field  entry  gates  shall  be  able  to 
swing  180  degrees  wide  and  lock  open  by 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 31 13S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 38  
SUPPLEMENTARY SPECIFICATIONS  Chain Link Fences and Gates  2016 
 
attaching to main fence line. 
.5 The  person  gates  shall  be  to  the  full  height  of 
the  fence  and  shall  not  be  bridged  with  a  top 
rail  over  them  as  to  eliminate  any  restrictions 
on  the  height  of  objects  passing  through  the 
gate. 
.6 All hinges shall be welded into place. 
  Delete 2.1.10 and  All fastenings and fittings shall be hot dip galvanized. All 
replace with the  caps shall be powder coated black and welded in place. 
following   
2.2  Finishes  Add 2.2.4  Powdercoating: 
.1 Powdercoat  all  exposed  surfaces.    Powder  coating 
to use powdercoat paint on acid washed surfaces.  
Wash  and  coating  shall  be  completed  on  a 
conveyor system.  Dipping is not acceptable.  Finish 
must  be  baked  dry.    Colour  shall  be  black  except 
for backstop signage and signage inserts which are 
to have Owner selected custom colours. 
.2 The  powder‐coat  finish  must  not  crack  or  chip 
when scratched tested. 
  Add 2.2.5  Organic zinc rich Galvicon paint coating: to CGSB 1_GP‐
181M shall be applied to all joints, welds and damaged 
areas.    Two  coats  are  required.    Paint  to  have  a  high 
gloss finish.  Use black or a custom colour as necessary 
to match the surrounding powder‐coating. 
3.0 EXECUTION     
 
3.1   Grading  Delete 3.1 and  .1 Remove  debris  and  correct  ground  undulations 
replace with the  along  fence  line  to  obtain  smooth  uniform 
following  gradient between posts. 
.2 Accurately survey and layout the specified work as 
shown on the Contract Drawing.   
.3 The  installation  procedures  for  all  materials  must 
be  in  strict  accordance  with  the  manufacturer’s 
specifications  and  provide  for  a  long‐term 
successful installation of all materials. 
3.2   Installation of  Delete 3.2 and  .1 Erect fences along lines as shown on the Contract 
Fence  replace with the  Drawing and in accordance with CAN/CGSB‐138.3. 
following  .2 Space  straining  posts  at  equal  intervals  not 
exceeding  150  metres  if  distance  between  end  or 
corner  posts  on  straight  continuous  lengths  of 
fence  over  reasonably  smooth  grade  is  greater 
than 150 metres. 
.3 Install end posts at end of fence and at changes in 
fence  alignment.    Install  gate  posts  on  both  sides 
of gate openings. 
.4 Embed  posts  into  concrete  to  depths  indicated.  

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 31 13S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 39  
SUPPLEMENTARY SPECIFICATIONS  Chain Link Fences and Gates  2016 
 
Brace to hold posts in plumb position and true to 
alignment and elevation until concrete has set. 
.5 Do not install fence fabric or pickets until concrete 
has cured a minimum of 5 days. 
.6 Install  intermediate  rail  between  end  and  gate 
posts  and  nearest  line  post,  placed  in  centre  of 
panel  and  parallel  to  ground  surface.    Install 
intermediate  rails  on  both  sides  of  corner  and 
straining posts in similar manner. 
.7 Install and weld overhang tops and caps. 
.8 Install  rails  between  posts  and  weld  securely  to 
terminal  posts  and  secure  waterproof  caps  and 
overhang tops. 
.9 Lay  out  fence  fabric.    Stretch  tightly  to  tension 
recommended by manufacturer and fasten to end, 
corner,  gate  and  straining  posts  with  tension  bar 
secured  to  post  with  tension  bar  bands  spaced  at 
300 mm  intervals.    Knuckled  selvedge  at  bottom.  
Twisted selvedge at top. 
.10 For  sport  activity  fencing  provide  clearance 
between  bottom  of  fence  and  concrete  curb 
neither less than 15 mm nor more than 40mm.  In 
other  areas  provide  50  to  75 mm  clearance 
between the bottom of the fence and the ground.  
The clearance under all rails shall be consistent. 
.11 Secure  fabric  to  rails  and  posts  with  tie  wires  as 
follows.  Give tie wires a minimum of two twists. 
.1 At every knuckle for 50 mm opening mesh. 
.2 At  every  second  knuckle  for  38 mm  opening 
mesh. 
.3 At  every  fourth  knuckle  for  25 mm  opening 
mesh. 
3.3  Removal and Re‐ Add 3.3  .1 Cut tie wires and remove existing fabric.  Take care 
use of Usable  not to stretch or otherwise damage the fabric.  Do 
Existing Chainlink  not re‐use damage portions of existing fabric. 
Fabric  .2 Cut fabric to length and height as required.  Ensure 
cut  edges  are  properly  and  securely  tied.    Attach 
fabric as per the specifications herein. 
.3 All  surplus  fabric  shall  be  rolled  up  into  roll  sizes 
that  are  manageable  by  one  person  and  handed 
over  to  the  City  if,  requested  to  do  so.    Damaged 
fabric shall be disposed of off‐site. 
3.4  Removal and Re‐ Add 3.4  .1 Cut existing posts and rails taking care to maximize 
use of Usable  the  usable  length  of  the  existing  post  or  rail.    Do 
Existing Chainlink  not re‐use damage posts or rails. 
Posts and Rails  .2 Cut  posts  and  rails  as  required.    Prepare  surfaces 
and  powder‐coat  as  per  the  specifications  herein.  
Install  posts  and  rails  as  per  the  specifications 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 31 13S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 40  
SUPPLEMENTARY SPECIFICATIONS  Chain Link Fences and Gates  2016 
 
herein.  2400 mm post spacing can be adjusted to 
accommodate  re‐used  rails.    Ensure  that  where 
spacing  is  adjusted  it  is  consistent  and  in  one 
section of fence. 
.3 Dispose  of  damaged  or  surplus  posts,  rails,  and 
mesh off‐site. 
3.5  Touch Ups  Add 3.5  .1 Clean damaged surfaces with wire brush removing 
loose and cracked coatings.  Apply two coats of 
black high gloss organic zinc‐rich Galvicon paint to 
damaged areas, allowing the manufacturer’s 
recommended drying time between coats.  Pre‐
treat damaged surfaces according to 
manufacturers' instructions for zinc‐rich paint. 
.2 Wire brush, clean, and paint all welds with two 
coats of high gloss zinc rich Galvicon paint, 
allowing the manufacturer’s recommended drying 
time between coats.  Use paint colour that 
matches surrounding powder‐coated surfaces. 
 
3.6  Site clean‐Up  Add 3.6  Upon completion of the work remove all containers, 
surplus materials, and installation debris, etc.  Project 
area must be left in a clean and orderly condition. 
 
3.7  Maintenance  Add 3.7  Upon completion of the work, the Contractor shall 
Supplies  provide the City with maintenance materials consisting 
of the following. 
.1  Two (2) 500 ml cans of black high gloss organic 
zinc‐rich paint. 
.2  One (1) 500 ml can of high gloss organic zinc‐rich 
paint of each custom colour. 
.3  Four (4) packages of 50 tie wires. 
 
3.8  Protection  Add  3.8  .1  The Contractor is responsible for the protection of 
all new and existing facilities from damage and/or 
disfiguration from the processes of the Work and 
from vandalism.  Any damage or disfiguration must 
be repaired promptly and to the original condition 
of the facility prior to the damage. 
.2  Acceptance of the repair work is at the sole 
discretion of the Contract Administrator and the 
City.  All repairs must be completed and accepted 
prior to Total Performance of the Work being 
granted. 
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 91 21S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  Road and Site Improvements  SS PAGE 41  
SUPPLEMENTARY SPECIFICATIONS  Topsoil and Finish Grading  2016 
 
MMCD Section 32 91 21S  Topsoil and Finish Grading  

1.0   GENERAL     
 
1.0  General  Delete 1.0.1 and  .1 Section  32  91  21  refers  to  those  portions  of  the 
Requirements  replace with the  Works  that  are  unique  to  the  supply,  placement 
following  and finish grading of Growing Medium. This section 
must  be  referenced  to  and  interpreted 
simultaneously with all other sections pertinent to 
the Works described herein. 
    For the purpose of this specification, the term 
"Growing Medium" shall mean a soil produced 
offsite by homogeneous blending of mineral 
particulates, micro organisms and organic matter 
which provides suitable medium for supporting 
intended plant growth and the term “Topsoil” shall 
mean on‐site native or surface soil material which 
may be used as Growing Medium provided it meets 
standards set for imported material Growing 
Medium and can be modified to meet the 
requirements set out for specified Growing 
Medium. 
  Add 1.0.3  .3 For the purpose of this specification, the term ‘Soil‐
Testing  Laboratory’  shall  mean  an  independent 
laboratory,  recognized  by  the  landscape  nursery 
industry,  with  the  experience  and  capability  to 
conduct  the  testing  indicated  and  that  specializes 
in types of tests to be performed. 
1.5  Inspection and  Delete 1.5 and  .1  The Contractor is responsible for testing imported 
Testing  replace with the  Growing Medium and all related cost incurred.  
following  Testing shall be carried out by an approved Soil 
Testing Laboratory. 
.2  The sample analysis shall be of tests done on the 
proposed Growing Medium from samples taken at 
the supply source within a minimum of 14 days in 
advance of Growing Medium placement.  Allow 
7 days for soil testing by the laboratory for each 
sample.  The sample shall be picked up by the Soil 
Testing Laboratory from the supply source. The 
Growing Medium sample shall be a composite of at 
least three (3) samplings for the proposed source 
and shall be at least one (1) litre in volume. 
    .3  Forward a copy of all test results directly to the 
Contract Administrator and the City for review. 
The analysis shall outline the testing laboratory’s 
required amendments such as sand, organic 
matter, fertilizers and lime to achieve adequate 
growing conditions.   
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 91 21S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  Road and Site Improvements  SS PAGE 42  
SUPPLEMENTARY SPECIFICATIONS  Topsoil and Finish Grading  2016 
 
    .4  The Contractor shall not deliver any Growing 
Medium to the site until the test results have been 
reviewed and approved by the Contract 
Administrator and the City. 
    .5  All submitted soil analysis must be dated and 
include supplier name and phone number, project 
location and submitted to Contract Administrator 
and the City for approval prior to commencing 
work. Soil analysis shall include measurements of: 
.1   Percent sand, fines, silt and clay 
.2  Organic matter to 100% 
.3  pH, acidifying additive required to achieve 
noted herein 
.4  Water soluble salts 
.5  Total carbon to nitrogen ration 
.6  Total nitrogen and available levels of 
phosphorus, potassium, calcium & magnesium  
    .6  At the discretion of the Contract Administrator and 
the City submit up to two (2) additional samples, at 
intervals outlined by the  Contract Administrator 
and the City, of Growing Medium taken from 
material delivered to the site. Samples shall be 
taken form a minimum of three (3) random 
locations and mixed to create a single uniform 
sample of testing. Results of these tests shall be 
forwarded to the Contract Administrator and the 
City for review. 
    .7  The Contractor is responsible for soil analysis and 
requirements for amendments to supply Growing 
Medium as specified. Failure to satisfy these 
contractual requirements could result in the 
Contractor being required to remove unacceptable 
Growing Medium at their expense. 
    .8  Notify the Contract Administrator at least forty‐
eight (48) hours prior to Growing Medium 
placement for inspection. 
.9  Refer to General Conditions, Clause 4.12 Tests and 
Inspections. 
1.6  Product Handling  Add 1.6  .1  All materials to be handled and adequately 
protected to prevent damage.  Do not handle 
Growing Medium in an excessively wet, extremely 
dry, frozen condition or in any manner in which 
structure may be adversely affected. Growing 
Medium whose structure has been damaged by 
handling under these conditions shall be rejected 
and shall be replaced by the Contractor at their 
expense. 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 91 21S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  Road and Site Improvements  SS PAGE 43  
SUPPLEMENTARY SPECIFICATIONS  Topsoil and Finish Grading  2016 
 
.2  Stockpile materials in bulk form in paved areas or 
in pre‐approved areas of the site.  Provide 
additional protection of storage under roof or 
tarpaulins.   
.3  Take all precautions to prevent contamination of 
Growing Medium and amendments from wind 
blown soil particles, weed seeds and from insects.  
Contamination of the Growing Medium and 
amendments may result in their rejection for use. 
.4  Store fertilizer and chemical amendments in the 
manufacturer's original containers. 
.5  All Growing Medium shall be delivered to site 
premixed from a recognized Growing Medium 
source ensuring consistency throughout the mix. 
 
2.0 PRODUCTS  Delete 2.0 and   
  replace with the 
following 
 
2.1  Materials    .1  Growing Medium Preparation 
.1  Shall be prepared from Compost Material with 
Sand  and  other  Soil  Amendments  as  required 
to meet the specifications herein. 
.2  Ensure  commercial  processing  and  mixing  of 
Growing  Medium  components  are  done 
thoroughly by a mechanized screening process.  
Do  not  mix  the  components  by  hand.  Ensure 
the  resulting  product  is  a  homogeneous 
mixture  having  the  required  properties 
throughout  free  of  stones  25 mm  or  larger  in 
any  dimension,  woody  plant  parts,  toxic 
materials, foreign object and other extraneous 
materials  harmful  to  plant  growth.    Provide 
composted  soil  free  from  crabgrass,  couch 
grass,  equisetum,  convolvulus,  or  other 
noxious weeds or seed or parts thereof. 
    .2  Inorganic Soil Amendments 
.1  Sand:  Imported  pit  sand  or  river  pump  sand, 
free  of  impurities,  chemicals,  horsetails,  and 
other  noxious  weeds.  The  saturation  extract 
electrical  conductivity  of  salinity  shall  not  be 
greater than 3.0 millimhos/cm at 25 degrees C. 
Sieve Size (mm)  Percent passing (%) 
4.75  95‐100 
0.50  0‐40 
0.050  0‐5 
   
.2  Fertilizers:  Uniform  in  composition,  free 
flowing and dry, granular, pill form, or pelleted 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 91 21S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  Road and Site Improvements  SS PAGE 44  
SUPPLEMENTARY SPECIFICATIONS  Topsoil and Finish Grading  2016 
 
commercial product with 50% of total nitrogen 
(if  applicable)  derived  from  natural  organic 
material in a slowly available form delivered in 
unopened  water  proof  containers  with  the 
manufacturer's  guaranteed  N‐P‐K  analysis, 
type  and  trade  name  attached  to  each 
container.    The  planting  soil  test  results  will 
specify  a  formulation  and  application  rate  to 
achieve  the  levels  of  nitrogen,  phosphorous 
and potassium required. Fertilizer to meet the 
requirements of the Canada Fertilizer Act. 
.1  Lime: ASTM C 602, agricultural limestone
containing a minimum 80 percent calcium
carbonate equivalent and as follows:
.1 Class: Class T, with a minimum
99 percent passing through No. 8
(2.36 mm) sieve and a minimum
75 percent passing through No. 60
(0.25 mm) sieve.
.2 Provide lime in form of dolomitic
limestone. 
    .3 Perlite: Horticultural perlite, soil amendment
grade. 
    .3  Organic Soil Amendments 
.1  Compost:    Well‐composted,  stable,  and  weed‐
free  organic  matter,  pH  range  of  5.5  to  8; 
moisture  content  35  to  55  percent  by  weight; 
100  percent  passing  through  25 mm  sieve; 
soluble salt content of 5 to 10 decisiemens/m; 
not  exceeding  0.5  percent  inert  contaminants 
and  free  of  substances  toxic  to  plantings;  and 
as follows: 
.1  Organic Matter Content:  50 to 60 percent 
of  dry  weight  containing  no  cedar, 
redwood, wood or bark. 
.2  Colour:  dark brown to black in colour. 
.2  Peat:   
.1  Finely  divided  or  granular  texture,  with  a 
pH  range  of  6  to  7.5,  containing  partially 
decomposed  moss  peat,  native  peat,  or 
reed‐sedge  peat  and  having  a  water‐
absorbing  capacity  of  1100  to  2000 
percent. 
.3   Wood Residual 
.1  Content  of  wood  residuals  such  as  Fir  or 
Hemlock  sawdust  present  in  the  Growing 
Medium shall not cause the total carbon to 
total Nitrogen ration to exceed 40:1.  
.2  Cedar  or  redwood  sawdust  shall  not  be 
File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A
CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 91 21S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  Road and Site Improvements  SS PAGE 45  
SUPPLEMENTARY SPECIFICATIONS  Topsoil and Finish Grading  2016 
 
present in Growing Medium. 
.4  Manure 
.1  Well‐rotted,  unleached,  stable  or  cattle 
manure  containing  not  more  than  25 
percent  by  volume  of  straw,  sawdust,  or 
other  bedding  materials;  free  of  toxic 
substances, stones, sticks, soil, weed seed, 
and  material  harmful  to  plant  growth  and 
free  from  salt  or  other  harmful  chemicals, 
such  as  any  used  to  artificially  hasten 
decomposition. 
.2  All particles in manure to pass a 6.35 mmm 
sieve. 
.3  Salt content shall give a reading of less 
than 0.5 millimhos/cm at 25 degrees C. 
2.2  Nutrient    .1  Nutrient  requirements  shall  meet  the 
Requirements  BCSLA/BCNTA  Landscape  Standard  Growing 
Medium  requirements  for  nitrogen,  phosphorus, 
potassium,  calcium,  magnesium,  boron,  sodium 
cation exchange capacity, carbon to nitrogen ratio. 
.1  Boron: not to exceed 1.0ppm 
.2  Sodium:  Sodium  absorption  ratio(SAR)  not  to 
exceed 8.0 
.3  Total Nitrogen: to be 0.2‐0.4% by weight 
.4  Available Phosphorous: to be 50‐100 ppm 
.5  Available Potassium: to be 50‐70 ppm 
.6  Cation Exchange Capacity: to be 30 to 50 meq. 
.7  Carbon to nitrogen ratio: Maximum 40:1. 
2.3  Salinity    .1  The electrical conductivity of the liquid taken from 
the  soil  pH  evaluation  shall  not  exceed  3.0 
millimhos/cm  at 25 degrees C before additions of 
fertilizers and/or liming agents. 
2.4  Drainage Rate    .1    Percolation shall be such that mixing, handling and 
placement  to  be  done  in  such  a  manner  that  the 
minimum saturated hydraulic conductivity show on 
Table  –  ‘Growing  Medium  Properties  for  Different 
Applications’ (found herein these specifications)  is 
achieved  and  no  standing  water  is  visible  60 
minutes  after  at  least  10  minutes  of  moderate  to 
heavy rain or irrigation. 
2.5  Growing Medium    .1  Import planting medium or manufactured planting 
Source  medium from off‐site sources.  Do not obtain from 
agricultural land, bogs or marshes. 
.2  Supplier of Growing Medium shall be as per the 
Coquitlam Approved Products List. 
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 91 21S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  Road and Site Improvements  SS PAGE 46  
SUPPLEMENTARY SPECIFICATIONS  Topsoil and Finish Grading  2016 
 
2.6  Bark Mulch    .1  Mulch  backfilled  surfaces  of  planting  beds  and 
other areas indicated on drawings. 
.1  Organic  Mulch:    Apply  50 mm  average 
thickness  of  organic  mulch,  and  finish  level 
with  adjacent  Finish  Grades.    Do  not  place 
mulch against plant stems. 
.2  Supplier of Bark Mulch shall be as per the 
Coquitlam Approved Products List. 
.3  Dark  brown  in  colour  and  free  of  all  soil,  stones, 
roots  or  other  extraneous  matter,  and  free  of 
weeds, seeds and spores. 
 
2.7  Growing Medium  Properties Low Traffic Lawn  High Traffic Lawn  Planting Areas, 
Properties for  Areas,  Areas Planters 
Different  Trees and Large  Shrubs & 
Applications Shrubs  Groundcover
  Texture: 
Particle size classes by 
Percent of Dry Weight Mineral Fraction (%) 
Canadian System of Soil 
Classification 
  Gravel  
(greater than 2 mm less  0‐10  0  0 
than 75 mm) 
  Sand  
(greater than 0.05 mm  50‐70  80‐90  50‐70 
and less than 2 mm) 
  Silt  
(larger than 0.002 mm  10‐30  5‐20  10‐30 
and less than 0.5 mm) 
  Clay  
7‐20  2‐5  7‐20 
(less than 0.002 mm) 
  Organic Content
5‐10  3‐5  25‐30 
Percent of Dry Weight 
  Drainage 
Minimum saturated 
2.0  7.0  2.0 
hydraulic conductivity 
(cm/hr) in place 
  Acidity (pH) 6.0‐6.5  6.0‐6.5  5.0‐6.0 

2.8  Miscellaneous    .1  Root Barrier: 400x610 mm linear root barrier, 


Products  copolymer polypropylene, 50% recycled plastic, black 
in colour.  Supplier of Root Barrier shall be as per the 
Coquitlam Approved Products List. 
.2  Construction  Adhesive  shall  be  as  per  the  Coquitlam 
Approved Products List. 
.3  Drain Mat:  Light duty, uv stable, impermeable 
cuspated core bonded to a layer of non‐woven filter 
fabric with the following minimum properties:  
.1  Compressive Strength ‐718 kN/m2  as per ASTM 
D‐1621 
File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A
CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 91 21S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  Road and Site Improvements  SS PAGE 47  
SUPPLEMENTARY SPECIFICATIONS  Topsoil and Finish Grading  2016 
 
.2 Flow Rate – 188 l/min/Metre as per ASTM D‐4716
.3  Approximate profile thickness of 10 mm. 
.4  Supplier  of  Drain  Mat  shall  be  as  per  the 
Coquitlam Approved Products List. 
.4  Filter Fabric: Install root barriers in accordance with 
manufacturer’s reviewed installation instructions 
where indicated on reviewed drawings with vertical 
root directing ribs facing inwards towards trees or 
plants; connect panels together as required.  
1. Supplier  of  Filter  Fabric  shall  be  as  per  the 
Coquitlam Approved Products List. 
.5  Drain Rock: Shall consist of clean round stone or 
crushed rock. Acceptable material includes 19 mm 
drain rock or torpedo gravel conforming to the 
following gradations. 
Percent Passing 
Sieve Designation Coarse  Fine (Torpedo gravel)
25 mm 100
19 mm 0‐100 
9.5 mm 0‐5 100
4.75 mm 0 50‐100
2.36 mm 10‐35
1.18 mm 5‐15
0.60 mm 0‐8
0.30 mm 0‐5
0.15 mm 0‐2
 

2.9  Structural Soil    .1 Soil stabilizer shall be friable, containing a minimum of 4% 


and maximum of 6% organic matter by dry weight, free from 
stones and debris over 30 mm. Acidity (ph) shall be in the 
range 5.5‐7.5. Carbon to nitrogen ratio shall not exceed 40:1, 
and salinity shall not exceed 3.0 milliohms at 25 deg C. 
Gravel greater than 2 mm shall not exceed 10% of total 
weight. 
.2  Supplier  of  Structural  Soil  shall  be  as  per  the  Coquitlam 
Approved Products List. 
.3  Growing Medium to be a gap‐graded mixture. 
.4  Texture of Growing Media  Percentage of mixture 
Gravel: greater than 2 mm‐less than 75 mm  0% 
Sand: greater than 0.0 5mm‐less than 2 mm  max 60% 
Silt: greater than 0.002‐less than 0.0 5mm  max 35% 
Clay: less than 0.002mm   max 15% 
Clay and silt combined  max 40% 
Acidity (pH)  6.0‐7.0 
Drainage: minimum saturated hydraulic  3.0 
Conductivity (cm/hr) in place   
Salinity: saturated extract conductivity  
shall not exceed  3.0 milliohms/cm at 25 degC 
Organic content: percent of dry weight  8‐12% 

    5  Stone ballast: Clean inert stone of high angularity is 
preferred  over  washed  gravel.  Stone  dimension 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 91 21S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  Road and Site Improvements  SS PAGE 48  
SUPPLEMENTARY SPECIFICATIONS  Topsoil and Finish Grading  2016 
 
aspect ratio should be 1:1:1 with a maximum 2:1:1 
length:width:depth.  Single  size  stone,  60 mm‐
75 mm  clear  sieve  designation:  Blasted  Quarry 
Rock.  Aggregate  to  be  used  for  structural  soil  shall 
be free of any foreign elements or material. 
.6  Structural Geotextile  
Shall be installed as a structural filter layer directly 
above the compacted structural soil mixture. Do 
not install fabric until adequate compaction of the 
structural soil mixture has been confirmed. Filter 
fabric shall be selected and deigned to withstand 
wear and tear during construction without 
deterioration of its strength and filtering 
properties. 
.1  Supplier of Geotextile shall be as per the 
Coquitlam Approved Products List. 
.7  Ground dolomite limestone containing no less 
than 85% of its total weight as calcium carbonate 
and magnesium carbonate shall be used to control 
ph level. The degree of grind for the limestone 
shall allow 100% of the total weight to pass a #10 
(2 mm) sieve, 90% to pass a #18 (1 mm) sieve and 
20% to pass a #40 (0.105 mm) sieve. Spread‐easy 
fertilizer shall be used as a slow release fertilizer 
source of calcium and magnesium. 
.8  Mixing of structural soil: 
Blend as per following ratios: 
.1  5 metric tones (MT) of aggregate 
.2  1 cubic meter of growing media 
.3  2 kg soil stabilizer 
.9  Moisten mixture with fine spray of clean potable 
water while mixing to activate soil stabilizer 
product. Do not over mix. Place mixture in 300 mm 
lifts through entire area of structural soil mixture. 
Compact each lift to 95% MPD prior to placement 
of next lift. Install filter fabric such to ensure a 
minimum of 60 cm overlap of all fabric seams and 
beyond edge of structural soil. 
 
 
 
 
 
 
3.0  EXECUTION     

3.2  Preparation of  Delete 3.2.4 and  Remove debris, roots, branches, stones in excess of 


Subgrade  replace with the  50 mm diameter and other deleterious materials, soil 
File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A
CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 91 21S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  Road and Site Improvements  SS PAGE 49  
SUPPLEMENTARY SPECIFICATIONS  Topsoil and Finish Grading  2016 
 
following  contaminated with calcium chloride, toxic materials and 
petroleum products, and debris which protrudes more 
than 25 mm above the surface.  Dispose of all removed 
material off site to approved offsite disposal area at no 
additional cost to the Owner. 
  Delete 3.2.5 and  Course cultivate entire area which is to receive Growing 
replace with the  Medium to depth of 250mm.  Cross cultivate those areas 
following  where  equipment  used  for  hauling  and  spreading  has 
compacted soil. 
  Add 3.2.6  Grade  transitions  shall  be  smooth  and  even  and  shall 
blend  into  surrounding  areas  as  determined  by  the 
Contract Administrator and the City. 
  Add 3.2.7  Provide erosion‐control measures to prevent erosion or 
displacement of soils and discharge of soil‐bearing water 
runoff  or  airborne  dust  to  adjacent  properties  and 
walkways. 
3.3  Processing  Add 3.3.4  Growing Medium shall be imported and stockpiled on 
Growing Medium  site in a location approved by the Contract Administrator 
and the City. 
.1  Carry out stock piling operation such that the 
Growing Medium structure is not compromised 
through compaction, vibration or other actions.  
.2  Stock piled Growing Medium shall be protected 
from rain, drying and contaminants.  
.3  Growing Medium shall be free of subsoil, pests, 
roots, wood, construction debris, undesirable 
grasses including crabgrass or couch grass, noxious 
or weeds and weed seeds or parts thereof foreign 
objects and toxic materials. Presence of these 
contaminates shall be grounds for rejection of 
Growing Medium and replacement at no cost to the 
Owner. 
3.4  Placing Growing  Delete 3.4.2 and  Place Growing Medium to the required finished grades 
Medium  replace with the  with adequate moisture, in uniform lifts of 100 mm to 
following  150 mm compacted to 80 MPD during dry weather, over 
dry, unfrozen Sub Grade where planting is indicated free 
of any standing water. 
  Delete 3.4.5 and  Minimum depths after settlement and 80% compaction: 
replace with the  .1  Trees pits:  900 mm  
following  .2  Shrub beds:  450 mm  
.3  Ground cover areas:  300 mm  
.4  Lawn areas:  300 mm  
.5  Blvd. areas:  150 mm 

  Add 3.4.6  Increase sand content to 90% in the planting soil below lawns 
where heavy wear by pedestrians or maintenance equipment 
is anticipated.  Increase sand content in a 1.5m wide strip at 
the bottom of swales, banks or other wet areas and as 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 91 21S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  Road and Site Improvements  SS PAGE 50  
SUPPLEMENTARY SPECIFICATIONS  Topsoil and Finish Grading  2016 
 
directed by the Landscape Architect.  On steep south or west 
facing banks, reduce sand content in lawns and planting beds 
to 50 ‐ 60% for better moisture retention. 
3.5  Applying  Delete 3.5 and  .1  Addition of amendment components shall be at the 
Fertilizers  replace with the  rates indicated in the Growing Medium analysis 
following  recommendations via the following methods: 
.1  Lime: Applied with mechanical spreaders over 
entire planting areas and contained planters.  
.1  Do not apply by hand. 
.2  Mix thoroughly into the top 100 mm of 
Growing Medium. 
.3  Do not allow lime to come into direct 
contact with nitrogen ‐ phosphate ‐ potash 
fertilizers. 
.2  Fertilizer: Applied with mechanical spreaders 
over entire planting areas and contained 
planters. Do not apply by hand. Do not mix into 
Growing Medium. 
3.6  Finish Grading  Delete 3.6.1 and  Manually fine grade Growing Medium installation to
replace with the  contours and elevations shown on drawings or as
following  directed by Contract Administrator and the City.
Eliminate rough spots and low areas to ensure positive
drainage. 
  Add 3.6.3  Finish Grade of Growing Medium shall be 25 mm from
finished elevation of adjacent curb or planter wall unless
otherwise noted on drawings.
3.9  Clean‐up  Delete 3.9 and  .1 Ensure all paved areas, tops of planters, adjacent
add the following  surfaces have been thoroughly cleaned. Ensure all
discoloration of adjacent surfaces as a result of
Growing Medium installation have been removed.
.2 Dispose of materials not required and repair any
damage to adjacent surfaces (as determined by the
Contract Administrator  and  the  City) off site at no
additional cost to the Owner.
3.10  Weed Control  Add 3.10  .1 Ensure all weeds and weed roots that have
germinated during the course of work of this section
have been eliminated from Growing Medium.
.2 Provide the City Representative and Consultant with
a written outline of weed removal methodology
seven (7) days prior to starting weed removal
operations.
3.11  Structural Soil  Add 3.11  .1 Refer to 2.9 in this specification and as shown on
the Contract Drawings.
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 92 19S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  Road and Site Improvements  SS PAGE 51  
SUPPLEMENTARY SPECIFICATIONS  Hydraulic Seeding  2016 
 
MMCD Section 32 92 19S  Hydraulic Seeding 
 
1.0   GENERAL     
 
1.3  Scheduling  Delete 1.3 and  .1 Schedule  all  operations  to  ensure  optimum 
  replace with the  environmental  protection,  grading,  growing 
following  medium  placement,  planting,  seeding  or  sodding 
operations as outlined in the specifications. 
.2 Schedule  seeding  to  coincide  with  preparation  of 
soil surface. 
.3 Organize  scheduling  to  ensure  a  minimum  of  on‐
site  storage  of  seed  and  fertilizer  material, 
minimum  movement  and  compaction  of  growing 
medium,  and  prompt  watering  operations. 
Coordinate  work  schedule  with  scheduling  of 
other trades on site. 
.4 Plan,  schedule  and  execute  the  work  to  ensure  a 
supply  of  water  for  landscape  purposes  in 
adequate amounts and at adequate pressures for 
satisfactory irrigation of all seeded areas. 
 
1.4  Handling and  Add 1.4.2  Protect  existing  Site  features  against  damage  or 
Storage  contamination due to Work of this Section.  Make good 
  all  damage  or  contamination  which  occurs  to  the 
satisfaction of the Contract Administrator and the City. 
 
  Add 1.4.3  Deliver  seeds,  mulch,  fertilizers,  tackifier  and  other 
products  to  the  Site  in  manufacturer’s  original 
containers, clearly identified.  Do not remove or deface 
labels or other identification. 
 
1.5  Drainage Control  Delete 1.5 and  Provide for proper water management and drainage of 
  replace with the  site  during  work  of  this  section.  Water  management 
following  shall  include  silt  traps,  erosion  control  measures, 
  temporary  water  collection  ditches,  as  well  as  their 
adequate  maintenance  to  ensure  that  storm  water 
which may become laden with soil or growing medium 
or  hydraulic  seed  is  detained  and  cleaned  prior  to 
discharge from site. 
 
1.6  Samples  Add to 1.6.1  The  Contract  Administrator  and  the  City  may  test  for 
  purity and germination. 
 
1.7  Site Examination  Delete 1.7.1 and  Examine  site  prior  to  the  commencement  of  work  to 
  replace with the  verify  surface  preparation  is  complete  and  has  been 
following  accepted by the Contract Administrator and the City. 
 
 
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 92 19S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  Road and Site Improvements  SS PAGE 52  
SUPPLEMENTARY SPECIFICATIONS  Hydraulic Seeding  2016 
 
1.10  Quality  Add 1.10  .1  Contractor  to  provide  seed  analysis  that  will 
Assurance  include but is not limited to: 
  .1 Name and address of supplier 
.2 Analysis of seed mixture 
.3 Percentage of pure seed 
.4 Year of production 
.5 Date and location of bagging 
.6 Percentage germination 
 
    .2  The  sample  accepted  by  the  review  will  form  the 
standard by which the project will be supplied. 
 
    .3  Should  the  Contractor  require  the  source  of  seed 
supply to change during the construction a written 
request  must  be  provided  to  the  Contract 
Administrator  and  the  City  48  hours  in  advance. 
The request shall be followed up by submission of 
proposed  seed  supplier  and  substitution  seed 
analysis  for  Contract  Administrator  and  the  City 
review prior to the start of supply to the site. 
 
    .4  All  seed  shall  be  delivered  and  stored  in  original 
containers  in  enclosed  storage  facility  protected 
from the damage, weather, insects and rodents. 
 
2.0  PRODUCTS     
 
2.1   Grass Seed  Delete 2.1 and  .1  Grass  Seed  shall  be  mixed  and  supplied  by  a 
replace with the  recognized  seed  house  and  delivered  in  original 
following  containers,  in  accordance  with  Federal  and 
Provincial  seed  laws  having  a  minimum 
germination  of  75%  and  minimum  purity  of  97%, 
and meet the requirements of the Government of 
Canada Seed Act for Canada No. 1 seed. 
 
    .2  Seed  mixtures  to  be  approved  by  the  Contract 
Administrator  in  the  original  packaging.  The  seed 
mixture for boulevards and landscaped areas shall 
be made up from a minimum of three (3) varieties 
of  Perennial  Rye,  one  (1)  of  Kentucky  Bluegrass 
and  three  (3)  varieties  of  Fescue  from  Coquitlam 
Approved Products List. 
.1 Seed  Mix  shall  be  50%  Perennial  Rye,  35% 
Fescues, 15% Kentucky Bluegrass. 
.2 Seed Rate shall be 50g per square metre. 
 
 
    .3  Table Guideline of Approved Seed Mix Ratios. 
File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A
CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 92 19S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  Road and Site Improvements  SS PAGE 53  
SUPPLEMENTARY SPECIFICATIONS  Hydraulic Seeding  2016 
 
% Seed  % Weight  Seed Varieties 
Count 
15%  25%  All‐Star Perennial Rye Grass 
5%  15%  Elka II Perennial Rye Grass 
20%  15%  Cindy Creeping Red Fescue 
15%  15%  Shamrock Kentuck 
Bluegrass 
20%  10%  Cindy Lou Creeping Red 
Fescue 
15%  10%  Longfellow II Chewing 
Fescue 
10%  10%  Gator 3 Perennial Rye 
Grass 
Acceptable products shall be an all purpose sun / 
shade mix’ conforming to the above mix ratios  
     
2.2  Hydraulic Mulch  Delete 2.2 and  .1 Provide  hydraulic  seeding  solution  containing  a 
  replace with the  mulch of wood cellulose fibre specifically designed 
following  for  hydraulic  seeding  containing  no  growth  or 
  germination inhibiting factors, and dyed green for 
visual metering during application. 
.2 Hydraulic  mulch  to  be  capable  of  dispersing 
rapidly  in  water  to  form  a  homogeneous  slurry 
and  remaining  in  such  a  state  when  agitated  or 
mixed  with  other  specified  materials.    When 
applied,  hydraulic  mulch  is  to  be  capable  of 
forming absorptive mat, which will allow moisture 
to  percolate  into  the  underlying  soil  and  to 
contain  no  growth  or  germination  inhibiting 
factors. 
.3 Mulch is to be dry and free of weeds, weed seeds 
and  other  foreign  material,  and  to  be  supplied  in 
packages  bearing  manufacturer’s  label  clearly 
indicating the weight and product name. 
.4 Mulch  shall  contain  a  colloidal  polythacuride  (or 
equivalent)  tackifier  which  is  to  be  adhered  to 
mulch to prevent separation during shipment and 
to avoid chemical agglomeration during mixing in 
hydraulic  mulching  equipment.  It  shall  be  ‘M‐
Binder’ or approved alternative. 
 
2.3  Water  Delete 2.3.1 and  Water  shall  be  potable,  free  of  impurities  that  would 
  replace with the  inhibit  sod  growth.  Contractor  to  ensure  adequate 
  following  water  is  available  to  maintain  seeded  areas  during 
    germination and in a vigorously growing, healthy state 
  until Total Performance of work of this section.  
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 92 19S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  Road and Site Improvements  SS PAGE 54  
SUPPLEMENTARY SPECIFICATIONS  Hydraulic Seeding  2016 
 
2.5  Dolomite Lime  Add 2.5  .1  Dolomite  lime  shall  be  finely  ground,  containing 
  not less than 90% calcium carbonate. 
 
2.6  Wood Posts  Add 2.6  .1  Wood posts shall be 38 mm x 38 mm x 1.5 m No. 1 
  Grade or better Hem/Fir, untreated wood. 
 
2.7  Binder Twine  Add 2.7  .1  Bidner Twine shall be hemp based multiple strand 
  string. 
 
2.8  Flagging Tape  Add 2.8  .1  Flagging tape shall be 30 mm wide, biodegradable 
  ribbon  tape  made  of  non  woven  cellulosic 
material, colour: red, or an approved equal. 
3.0  EXECUTION     
 
3.1  Finish Grade  Delete 3.1.2 and  Prior  to  the  broadcast  of  seed  Contract  Administrator 
Preparation  replace with the  and  the  City  to  review  and  direct  minor  adjustments 
  following  and  refinements  of  finish  grades  prior  to  the 
Contractor  proceeding.  Review  includes  grades, 
Growing  Medium  depth  and  condition  of  finished 
surface. Subsequent to the Contract Administrator and 
the  City  review  the  Contractor  shall  re‐grade,  add 
Growing Medium and make adjustments as directed by 
Contract Administrator and the City. 
  Delete 3.1.5 and  Finish  grade  smooth  to  extent  required  for  class  of 
replace with the  seeding to be carried out, firm against footprints, lose 
following  textured  and  free  of  all  stones,  roots,  branches,  etc. 
larger than 25 mm or required for removal for class of 
seeding to be carried out.   
3.2  Seeding‐General  Delete 3.2.1 and  Carry  out  hydraulic  seeding  during  periods  which  are 
replace with the  most  favourable  for  the  establishment  of  a  health 
following  stand of grass within the following calendar seasons: 
.1 Spring (April 1st to June 15th) 
.2 Fall (August 15th to September 30th).   
.3 Hydraulic  seeding  shall  not  take  place  during 
periods  of  rain,  freezing  and/or  abnormally  hot 
and dry weather. 
3.4  Protection  Add 3.4.4  Protect  all  seeded  areas  against  trespassing  and  from 
damage at all times clearly marked, staked, string and 
flagging tape.  
  Add 3.4.5  Perimeter  Protection:  All  seeded  areas  shall  be 
surrounded  by a 900 mm high barrier made up of the 
following components: 
.1 Wood posts placed at 1.8 metres on centre.  
.2 Wood Posts to be driven to a depth of 300 mm  
.3 String two (2) strands of hemp based binder twine 
(or equal product)  between posts. Insure one full 
wrap of twine around each post. 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 92 19S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  Road and Site Improvements  SS PAGE 55  
SUPPLEMENTARY SPECIFICATIONS  Hydraulic Seeding  2016 
 
.4 Tie  300 mm  strands  of  ‘red’  flagging  tape  at 
450 mm  intervals  along  the  entire  length  of  both 
strands of twine. 
.5 Maintain  perimeter  protection  until  Total 
Performance  issued  for  seeded  area.  Upon 
acceptance  remove  perimeter  fence  and  dispose 
of off site. 
  Add 3.4.6  Hydraulic  seeded  areas  that  have  been  damaged  by 
construction operation, construction/ site personnel or 
construction traffic shall be replaced at no cost to the 
Owners. Replacement shall include removal of Growing 
Medium,  regarding  of  subgrade,  replacing  Growing 
Medium and reseeding as required. 
     
3.5  Application for  Delete 3.5 and  .1 Thoroughly  mix  seed,  fertilizer  and  hydraulic 
Hydraulic  replace with the  mulch  in  water  slurry  and  distribute  uniformly 
Seeding  following  over surface with an approved hydraulic mulcher. 
.2 All seeding is to be done during calm weather and 
on  soil  that  is  free  of  frost,  snow,  and  standing 
water.    Do  not  perform  the  work  when  wind 
exceeds  10  km/hr  or  when  the  soil  is  excessively 
dry. 
.3 Measure quantities of each material to be charged 
into  hydraulic  seeder/mulcher  tank  accurately 
either in mass or by commonly accepted system of 
mass‐calibrated  volume  measurements.  Add 
materials to tank while it is being filled with water 
and in following sequence: 
.1 Seed 
.2 Fertilizer 
.3 Mulch 
.4 Tackifier 
.4 Thoroughly  mix  materials  into  a  homogeneous 
water  based  slurry  and  distribute  uniformly  over 
the  area  and,  all  disturbed  areas,  to  be 
hydraulically seeded. 
.5 Seeding Rate:  
.1 Apply  at  435  kg/ha  or,  as  recommended  by 
supplier  and  approved  by  the  Contract 
Administrator and the City. 
.2 Fertilizer at the following rate: Evergrow 28‐3‐
8 @ 29g/m2 
.3 Fibre Mulch at the following rate: 15kg/m2 
.4 Tackifier at the following rate: 45 kg/ha. 
.6 Carry  out  hydraulic  seeding  with  care  to  ensure 
homogeneous  slurry  does  not  come  in  contact 
with  foliage  of  trees,  shrubs  or  other  susceptible 
vegetation.  
.7 Do  not  spray  homogeneous  slurry  on  objects  not 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 92 19S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  Road and Site Improvements  SS PAGE 56  
SUPPLEMENTARY SPECIFICATIONS  Hydraulic Seeding  2016 
 
expected to grow grass. 
.8 Promptly  rectify  any  overspray  or  damage  that 
occurs during hydraulic seeding. 
.9 Do  not  leave  seed,  fertilize,  mulch  and  water 
slurry  in  tank  for  mire  than  4  hours.  Slurry  left  in 
tank  over  maximum  allowed  time  shall  not  be 
used for seeding and shall be disposed offsite. 
.10 Follow  up  seeding  with  all  maintenance 
procedures  required  to  maintain  the  approved 
grades  and  obtain  uniform  germination.    The 
Contractor is to carry out at no cost to the Owner, 
reseed operations at two (2) week intervals where 
germination  has  failed  or  wash  outs  have 
occurred. 
3.7  Clean‐up  Add 3.7.2  Flush  all  walks  and  paved  areas  clean  to  the 
satisfaction of the Contract Administrator and the City. 
3.8  Grass  Delete 3.8 and  .1 Maintenance of hydraulic seeded areas shall begin 
Maintenance  replace with the  immediately after hydraulic seeding operation and 
following  shall  continue  until  all  deficiencies  noted  in  the 
Substantial  Performance  review  have  been 
rectified  to  the  satisfaction  of  the  Contract 
Administrator  and  the  City  and  conditions  for 
Total Performance been achieved. The Contractor 
is to notify the Contract Administrator and the City 
in  writing  forty  eight  hours  (48)  prior  to  stopping 
maintenance operations. 
.2 Grass  Cutting:  After  the  ‘first’  cut  of  hydraulic 
seeded  areas  grass  cutting  operations  shall  be 
carried  out  on  a  weekly  (seven  day)  basis  until 
Total  Performance  by  Contract  Administrator  and 
the City: 
.1 First  cut  of  seeded  areas  shall  occur  when  a 
uniform  grass  height  of  75 mm  has  been 
attained.  First  cut  shall  be  to  a  height  of 
65  mm. 
.2 Continue regular weekly cutting at a height of 
50 mm until Total Performance.  
.3 Cutting operations shall be such that each cut 
is at right angles to the previous cut. 
.4 Contractor  to  remove  grass  clippings  after 
each cut and dispose of off site. 
.5 Roll  when  required  to  remove  any  minor 
depressions or irregularities. 
.6 Immediately  repair  seeded  areas  that  show 
deterioration  or  bare  spots.  Top‐dress  all 
areas  showing  shrinkage  due  to  lack  of 
watering and seed with seed mix that matches 
the original seed mix.  

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 92 19S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  Road and Site Improvements  SS PAGE 57  
SUPPLEMENTARY SPECIFICATIONS  Hydraulic Seeding  2016 
 
.3 Fertilizer  analysis  shall  conform  to 
recommendations  provided  with  Growing 
Medium  analysis.  Application  of  fertilizer  shall 
follow  manufacturers’  recommendations  noting 
that  after  October  1  lawn  areas  shall  not  be 
fertilized until April 15th of the following spring. 
.4 Hydraulic  seeded  lawn  areas  to  be  kept  free  of 
invasive  and/or  noxious  broadleaf  weeds,  grasses 
including  but  not  limited  to  poa  annua,  disease, 
fungi,  detrimental  nematodes  and  detrimental 
insects. 
 
3.9  Conditions for  Delete 3.9 and  .1 Conditions  for  Total  Performance  of  Hydraulic 
Total  replace with the  Seeded areas: 
Performance  following  .1 Hydraulic  seeded  areas  are  vigorously 
growing,  well  established  with  a  thick,  dense 
and healthy green appearance. 
.2 Hydraulic  seeded  areas  shall  not  have  any 
eroded or wash out areas, bare or dead spots 
and  are  free  of  invasive  and/or  noxious 
broadleaf weeds and grasses. 
.3 No  surface  Growing  Medium  is  visible  when 
established hydraulic seeded areas have been 
cut to height of 38 mm  
.4 Hydraulic seeded areas have been cut at least 
two  (2)  times,  to  a  height  of  38 mm  a 
minimum of (7) days apart. 
.5 Grass  is  free  of  grass  varieties  other  than 
those specified. 
.6 Grass  is  sufficiently  established  that  its  roots 
are growing into underlying Growing Medium. 
.7 Specified  maintenance  procedures  have  been 
carried out. 
.2 Areas  hydraulic  seeded  after  September 30th will 
not be reviewed for Total Performance until April 
30th the next year. 
 
 
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 92 20S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  Road and Site Improvements  SS PAGE 58  
SUPPLEMENTARY SPECIFICATIONS  Seeding  2016 
 
MMCD Section 32 92 20S  Seeding 
 
1.0  GENERAL     
 
1.5  Drainage Control  Delete 1.5.1 and  Provide for proper water management and drainage at 
  replace with the  Place  of  Work.  Water  management  shall  include  silt 
following  traps,  erosion  control  measures,  temporary  water 
  collection  ditches,  as  well  as  their  adequate 
maintenance  to  ensure  that  storm  water  which  may 
become laden with soil or growing medium is detained 
and cleaned prior to discharge from Place of Work. 
1.7  Site Examation  Delete 1.7.1 and  Examine Place of Work prior to the commencement of 
  replace with the  work to verify surface preparation is complete and has 
following  been  accepted  by  the  Contract  Administrator  and  the 
City.  
 
1.10  Quality  Add 1.10  .1  Contractor  to  provide  seed  analysis  that  will 
Assurance  include but is not limited to: 
  .1 Name and address of supplier 
.2 Analysis of seed mixture 
.3 Percentage of pure seed 
.4 Year of production 
.5 Date and location of bagging 
.6 Percentage germination 
 
    .2  The  sample  accepted  by  the  review  will  form  the 
standard by which the project will be supplied. 
    .3  Should  the  Contractor  require  the  source  of  seed 
supply to change during the construction a written 
request  must  be  provided  to  the  Contract 
Administrator  and  the  City  48  hours  in  advance. 
The request shall be followed up by submission of 
proposed  seed  supplier  and  substitution  seed 
analyses  for  Contract  Administrator  and  the  City 
review prior to the delivery. 
    .4  All  seed  shall  be  delivered  and  stored  in  original 
containers  in  enclosed  storage  facility  protected 
from the damage, weather, insects and rodents. 
2.0  PRODUCTS     
 
2.1  Grass Seed  Delete 2.1 and  .1  Grass seed shall be Certified Canada No. 1 Grade to 
  replace with the  Government  of  Canada,  Seeds  Regulations  and 
  following  having minimum germination of 75% and minimum 
    purity of 95%.  
   
 
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 92 20S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  Road and Site Improvements  SS PAGE 59  
SUPPLEMENTARY SPECIFICATIONS  Seeding  2016 
 
 
    .2  Seed  mixtures  shall  be  approved  by  the  Contract 
    Administrator  and  the  City  in  the  original 
  packaging.  The  Seed  mixture  for  boulevards  and 
  landscaped  areas  shall  be  made  up  from  a 
  minimum    of  three  (3)  varieties  of  Perennial  Rye, 
  one  (1)  of    Kentucky  Bluegrass  and  three  (3) 
  varieties  of  Fescue  from  the  list  of  approved 
varieties shown below: 
.1 Seed Mix shall comprise of: 
50%  Perennial  Rye:  Elka  II,  Gator  3,  Top  Hat, 
Charismatic, All Star, Derby Supreme 
35%  Fescues:    Cindy,  Longfellow  II,  Cindy  Lou, 
Quatro, Shademaster II 
15%Kentucky  Bluegrass:  Shamrock,  Broadway, 
Midnight, Julius, Allure 
    .3  Table Guideline of Approved Seed Mix Ratios 
% Seed Count % Weight
15% 25% All‐Star Perennial Rye Grass
5% 15% Elka II Perennial Rye Grass
20% 15% Cindy Creeping Red Fescue
15% 15% Shamrock Kentuck Bluegrass
20% 10% Cindy Lou Creeping Red Fescue
15% 10% Longfellow II Chewing Fescue
10% 10% Gator 3 Perennial Rye Grass
Seed Rate: 50g per square metre 
Acceptable products shall be an all purpose sun / shade mix
conforming to the above mix ratios  
     
2.2  Water  Delete 2.2.1 and  Water  shall  be  potable,  free  of  impurities  that  would 
  replace with the  inhibit sod growth. Contractor to ensure adequate water 
  following  is available to maintain seeded areas during germination 
    and  in  a  vigorously  growing,  healthy  state  until  Total 
  Performance of work of this section.  
2.3  Fertilizer  Delete 2.3.1 and  Fertilize  shall  be  complete  synthetic  slow  release 
replace with the  fertilizer. Type and application shall be as required by the 
following  growing medium analysis report. 
 
2.4  Wooden Posts  Add 2.4  .1  Wooden  Posts  shall  be  38 mm  x38 mm  x  1500 mm 
long No. 1 grade or better Hem/fir, untreated wood. 
2.5  Binder Twine  Add 2.5  .1  Binder  Twine  shall  be  hemp  based  multiple  strand 
string. 
2.6  Flagging Tape  Add 2.6  .1  Flagging  Tape  shall  be  30 mm  wide,  biodegradable 
ribbon tape made of non woven cellulosic material, 
and red color, or an approved equivalent. 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 92 20S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  Road and Site Improvements  SS PAGE 60  
SUPPLEMENTARY SPECIFICATIONS  Seeding  2016 
 
3.0  EXECUTION     
 
3.1  Finish Grade  Delete 3.1.2 and  Prior  to  the  broadcast  of  seed  Contract  Administrator 
Preparation  replace with the  and  the  City  to  review  fine  grading  of  growing  medium.  
following  Review  includes  grades,  growing  medium  depth  and 
condition  of  finished  surface.    Subsequent  to  the 
Contract  Administrator  and  the  City  review  the 
Contractor  shall  re‐grade,  add  growing  medium  and 
make adjustments as directed by Contract Administrator 
and the City. 
  Delete 3.1.5 and  Finish  grade  smooth  to  extent  required  for  class  of 
replace with the  seeding carried out, firm against footprints, textured and 
following  free loose of all stones, roads, branches, etc. larger than 
25 mm or required for removal for class of seeding to be 
carried out. 
3.2  Seeding ‐ General  Delete 3.2.1 and  Seeding  operations  shall  be  carried  out  in  the  following 
replace with the  calendar seasons; 
following  .1  Spring (April 1st to June 15th) 
  .2  Fall (August 15th to September 30th)   
.3  Seeding  shall  not  take  place  during  periods  of  rain, 
freezing and/or abnormally hot and dry weather. 
  Delete 3.2.2 and  Application  Methods:  Apply  seed  by  Method  A  – 
replace with the  Mechanical Dry Seeding or Method B – Hydraulic Seeding 
following  unless  otherwise  specified.  Ensure  Hydraulic  Seeding  in 
accordance  with  Section  32  92  19  –  Hydraulic  Seeding. 
Hand seeding is not recommended. Hand seed only when 
site conditions preclude above two methods. Do not use 
hand  seed  method  unless  approved  by  the  Contract 
Administrator. 
  Delete 3.2.3 and  Seed Application: Seed rates as per seed manufacturers’ 
replace with the  recommendations and table 2.1.3. 
following  .1  Sow  seed  during  calm  weather  with  wind  speeds 
  less  than  8  kph,  using  wheeled  or  hand  held  rotary 
broadcaster.   
.2  Sow  half  of  required  amount  of  seed  in  one 
direction and remainder at right angles. 
.3  Carefully  incorporate  seed  into  top  of  growing 
medium  with  light  chain  harrow  or  wire  rakes  to  a 
minimum  depth  of  6 mm  as  seeding  operation 
progresses or within one (1) hour after seeding.  
.4  Immediately after seed application roll seeded area 
with  90kg  water  ballast  type  lawn  or  agricultural 
roller.  If  seeded  area  becomes  wet  due  to  rain 
suspend  rolling  operations  until  area  has  dried  to 
the point where growing medium will not adhere to 
the surface of the roller. 
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 92 20S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  Road and Site Improvements  SS PAGE 61  
SUPPLEMENTARY SPECIFICATIONS  Seeding  2016 
 
  Add 3.2.4  Watering Operation: Apply water with fine spray to avoid 
  seed  wash  out.  Watering  procedure  shall  ensure 
penetration  of  minimum  50mm  into  growing  medium 
and  be  at  sufficient  duration  and  intervals  to  keep 
growing  medium  evenly  moist  during  germination  and 
grow in period. 
  Add 3.2.5  The  Contractor  shall  carry  out  at  no  cost  to  the  Owner, 
reseed  operations  at  two  (2)  week  intervals  where 
germination has failed or wash outs have occurred. 
  Add 3.2.6  Perimeter  Protection:  All  seeded  areas  shall  be 
surrounded  by  a  900  mm  high  barrier  made  up  of  the 
following components: 
.1 Wood posts placed at 1.8 metres on centre.  
.2 Wood Posts shall be driven to a depth of 300mm  
.3 String  two  (2)  strands  of  hemp  based  binder  twine 
(or  equal  product)  between  posts.  Insure  one  full 
wrap of twine around each post. 
.4 Tie 300 mm strands of ‘red’ flagging tape at 450 mm 
intervals  along  the  entire  length  of  both  strands  of 
twine. 
.5 Maintain  perimeter  protection  until  issued  Total 
Performance  of  seeded  area  by  Contract 
Administrator.  Upon  acceptance  remove  perimeter 
fence and dispose of off site. 
  Add 3.2.7  Seeded  areas  that  have  been  damaged  by  construction 
operation,  construction/  site  personnel  or  construction 
traffic  shall  be  replaced  at  no  cost  to  the  Owners. 
Replacement  shall  include  removal  of  growing  medium, 
regarding  of  sub  grade,  replacing  growing  medium  and 
reseeding as required. 
3.6  Grass  Delete 3.6 and  .1  Maintenance  of  seeded  areas  shall  begin 
Maintenace  replace with the  immediately  after  seeding  operation  and  shall 
  following  continue  until  all  deficiencies  noted  in  the 
  Substantial Performance review have been rectified 
to the satisfaction of the Contract Administrator and 
the City and conditions for Total Performance been 
achieved.  The  Contractor  shall  notify  the  Contract 
Administrator  and  the  City  in  writing  forty  eight 
hours  (48)  prior  to  stopping  maintenance 
operations. 
    .2  Maintenance  shall  follow  the  BC  Landscape 
Standard,  current  edition,  Level  2  ‘Groomed’.  Over 
and above this maintenance protocol the Contractor 
shall monitor the application of water to the seeded 
areas  and  ensure  that  watering  procedures  are 
continuous.  
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 92 20S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  Road and Site Improvements  SS PAGE 62  
SUPPLEMENTARY SPECIFICATIONS  Seeding  2016 
 
.1 Apply water with fine spray to avoid seed wash 
out.  Watering  procedure  shall  ensure 
penetration  of  minimum  50mm  into  growing 
medium  and  be  at  sufficient  duration  and 
intervals to keep growing medium evenly moist 
during germination and grow in period. 
.2 Monitor watering on a regular interval to ensure 
that  watering  operations  are  not  causing  wash 
out of seeded area. Should wash outs occur as a 
result  of  watering  or  rain  fall  related  wash  out, 
reseed and continue maintenance and watering 
procedures. 
    .3  Grass  Cutting:  After  the  ‘first’  cut  of  seeded  areas 
  grass  cutting  operations  shall  be  carried  out  on  a 
weekly (seven day) basis until Total Performance by 
Contract Administrator and the City. 
.1 First  cut  of  seeded  areas  shall  occur  when  a 
uniform  grass  height  of  75 mm  has  been 
attained. First cut shall be to a height of 64 mm  
.2 Continue  regular  weekly  cutting  at  a  height  of 
50 mm until Total Performance.  
.3 Cutting operations shall be such that each cut is 
at right angles to the previous cut. 
.4 Contractor  to remove grass clippings after each 
cut and dispose of off site. 
.5 Roll  when  required  to  remove  any  minor 
depressions or irregularities. 
.6 Immediately  repair  seeded  areas  that  show 
deterioration  or  bare  spots.  Top‐dress  all  areas 
showing  shrinkage  due  to  lack  of  watering  and 
seed  with  seed  mix  that  matches  the  original 
seed mix.  
    .4  Fertilizer  analysis  shall  conform  to 
  recommendations  provided  with  growing  medium 
analysis.  Application  of  fertilizer  shall  follow 
manufacturers’  recommendations  noting  that  after 
October  1  lawn  areas  shall  not  be  fertilized  until 
April 15th of the following spring. 
    .5  Seeded  lawn  areas  shall  be  kept  free  of  invasive 
and/or  noxious  broadleaf  weeds,  grasses  including 
but  not  limited  to  poa  annua,  disease,  fungi, 
detrimental nematodes and detrimental insects. 
3.7  Conditions for  Delete 3.7 and  .1  Conditions for Total Performance of Seeded areas: 
Total  replace with the  .1 Seeded  areas  are  vigorously  growing,  well 
Performance  following  established  with  a  thick,  dense  and  healthy 
    green appearance. 
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 92 20S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  Road and Site Improvements  SS PAGE 63  
SUPPLEMENTARY SPECIFICATIONS  Seeding  2016 
 
.2 Seeded areas shall not have any eroded or wash 
out  areas,  bare  or  dead  spots  and  are  free  of 
invasive  and/or  noxious  broadleaf  weeds  and 
grasses. 
.3 No  surface  growing  medium  is  visible  when 
established  seeded  areas  have  been  cut  to 
height of 38 mm  
.4 Seeded  areas  have  been  cut  at  least  two  (2) 
times,  to  a  height  of  38 mm  a  minimum  of  (7) 
days apart. 
.5 Grass shall be free of grass varieties other than 
those specified. 
.6 Grass  shall  be  sufficiently  established  that  its 
roots  are  growing  into  underlying  growing 
medium. 
.7 Specified  maintenance  procedures  have  been 
carried out. 
.8 Areas  seeded  after  September  30th  will  be  not 
be  reviewed  for  Total  Performance  until  April 
30th the following year. 
 
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 92 23S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 64  
SUPPLEMENTARY SPECIFICATIONS  Sodding  2016 
 
MMCD Section 32 92 23S  Sodding 
 
1.0 GENERAL  Delete 1.0.2 and  This  section  is  based  on  the  “British  Columbia 
  replace with the  Landscape  Standards  and  the  B.C.  Nursery  Trades 
following  Association. This standard is intended to set a level of 
  quality which is equaled or bettered in the construction 
documents. 
1.4  Handling and  Delete 1.4.3 and  Schedule  sod  deliveries  such  that  sod  installation 
Storage  replace with the  occurs  within  twenty‐four  (24)  hours  of  being  lifted 
following  from the source sod farm. 
     
  Delete 1.4.4 and  Sod shall be neatly stacked or rolled at the source sod 
replace with the  farm,  delivered  and  unloaded  on  sturdy  pallets  which 
following  are no more than 3 pallets high.  
 
     
1.5  Drainage Control  Delete 1.5.1 and  Provide for proper water management and drainage of 
replace with the  site  during  work  of  this  section.  Water  management 
following  shall  include  silt  traps,  erosion  control  measures, 
temporary  water  collection  ditches,  as  well  as  their 
adequate  maintenance  to  ensure  that  storm  water 
which may become laden with soil, growing medium or 
hydraulic  seed  is  detained  and  cleaned  prior  to 
discharge from Place of Work. 
1.6  Samples  Add 1.6.2  Submit  one  (1)  square  metre  of  sod  to  the  Contract 
  Administrator and the City for review. Ensure sample is 
complete  with  name  of  sod  farm,  base  soil  type,  seed 
mix percentage. 
  Add 1.6.3  Contract  Administrator  and  the  City  shall  review  sod 
  sample  for  approval  prior  to  installation.  The  sample 
accepted by the review will form the standard by which 
the project will be supplied.  
 
  Add 1.6.4  Should the Contractor require the source of sod supply 
to  change  during  the  construction  a  written  request 
must  be  provided  to  the  Contract  Administrator  and 
the  City  48  hours  in  advance.  The  request  shall  be 
followed  up  by  submission  of  proposed  sod 
substitution sample and include the name of sod farm, 
base  soil  type,  seed  mix  percentage  for  Contract 
Administrator and the City review prior to the delivery. 
 
 
 
 
 
 
2.0  PRODUCTS     

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 92 23S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 65  
SUPPLEMENTARY SPECIFICATIONS  Sodding  2016 
 
 
2.1  Sod  Delete 2.1.1 and  Sod  to  be  approved  by  the  Contract  Adinistrator  and 
replace with the  the  City  and  to  be  nursery  grown,  true  to  type, 
following  conforming  to  standards  of  nursery  Sod  Growers’ 
  Association  and  their  Nursery  Sod  Specifications.  Sod 
to  be  quality,  cultured  turf  grass  grown  from  seed 
approved by Canada Department of Agriculture, free of 
disease, clovers, stones, pests and debris. 
  Add 2.1.1.1  Nursery sod: 
  .1 Shall be No. 1 Premium grade and contain only 
species  of  grass  indicated  on  the  supplier’s 
certificate.  
.2 Sod shall be ‘non‐netted’ 
  Add 2.1.1.2  Table Guideline of Approved Sod Mix Ratios 
 
Supreme Soil Base Sod 
(Elka II) Perennial Ryegrass  40% 
(Shamrock) Kentucky Bluegrass  30% 
(Cindy) Chewing Red Fescue  30% 
Seed Rate:    
50g per square metre 
     
  Add 2.1.8  All  sod  shall  be  completely  free  of  invasive  and/or 
  noxious  broadleaf  weeds,  grasses  including  but  not 
limited  to  poa  annua,  disease,  fungi,  detrimental 
nematodes and detrimental insects. 
     
2.2  Water  Delete 2.2.1 and  Potable,  free  of  impurities  that  would  inhibit  seed 
replace with the  germination.  Contractor  to  ensure  adequate  water  is 
following  available to maintain seeded areas during germination 
  and  in  a  vigorously  growing,  healthy  state  until  Total 
Performance of work of this section. 
     
2.3  Fertilizer  Add 2.3.2   Fertilizer  shall  be  complete  synthetic  slow  release 
fertilizer.  Type  and  application  shall  be  as  required  by 
the growing medium analysis report. 
 
2.4  Wooden Pegs  Add 2.4  .1  Wooden Pegs shall be 19 mm x 19 mm x 150 mm 
long No. 1 grade or better Hem/fir. 
 
2.5  Binder Twine  Add 2.5  .1  Binder Twine shall be hemp based multiple strand 
string. 
 
2.6  Flagging Tape  Add 2.6  .1  Flagging Tape shall be 30 mm wide, biodegradable 
ribbon  tape  made  of  non  woven  cellulosic 
material,  and  red  color,  or  an  approved 
equivalent. 
3.0  EXECUTION     

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 92 23S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 66  
SUPPLEMENTARY SPECIFICATIONS  Sodding  2016 
 
 
3.1  Finish Grade  Delete 3.1.2 and  Prior  to  the  placement  of  sod  Contract  Administrator 
Preparation  replace with the  and  the  City  to  review  and  direct  minor  adjustments 
following  and  refinements  of  finish  grades  prior  to  the 
Contractor  proceeding.  Review  includes  grades, 
growing  medium  depth  and  condition  of  finished 
surface. Subsequent to the Contract Administrator and 
the  City  review  the  Contractor  shall  re‐grade,  add 
growing medium and make adjustments as directed by 
Contract Administrator and the City. 
  Delete 3.1.5 and  Fine  grade  growing  medium  to  lines  and  levels  shown 
replace with the  on  Contract  Drawings.    Ensure  that  all  low  spots, 
following  humps and irregularities are eliminated prior to review 
  by Contract Administrator and the City. 
3.2  Sodding  Delete 3.2 and  .1  Sod  shall  not  be  placed  during  hot  dry  summer 
replace with the  periods,  at  freezing  temperatures,  or  over  frozen 
following  growing medium. 
    .2  Allow sod to dry sufficiently during wet weather to 
prevent tearing during lifting and handling. 
    .3  Handle  sod  carefully  to  minimize  tearing  and 
dropping of soil. 
    .4  Placement of Sod: 
.1 Lay sod in rows smooth and flush to adjoining 
grass  areas  and  paving  and  top  surfaces  of 
curbs  unless  shown  otherwise  on  Contract 
Drawing.  Ensure  there  is  a  full  roll  width 
between  the  new  sod  and  any  adjoining 
surfaces.  Small  cut  pieces  from  a  full  roll  will 
not be accepted.  
.2 Stagger joints and ensure that sod sections are 
butted  closely  together  without  overlapping 
or leaving gaps between sections.  
.3 Cut out irregular or thin sections with a sharp 
knife. 
.4 Cut  sod  to  fit  tight  around  landscape 
elements. 
.5 Cut sod to create clean, smooth lines along all 
plant beds.  
 
    .5  Placement of Sod on Slopes: 
.1 Lay  sod  with  the  length  of  each  sod  section 
parallel  to  slope  taking  extra  care  to  ensure 
that  sod  sections  are  butt  tight  and  each  sod 
section is set in a staggered formation. 
.2 On  slopes  exceeding  3:1  gradient  ensure  sod 
is  secured  with  wooden  pegs  at  intervals  of 
not  more  that  450 mm  along  the  center  of 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 92 23S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 67  
SUPPLEMENTARY SPECIFICATIONS  Sodding  2016 
 
each  section.  Ensure  wooden  pegs  are  driven 
flush with the sod. 
.3 Prior  to  acceptance  of  sod  areas  that  have 
been  secured  with  wooden  pegs  either 
remove  the  wooden  pegs  or  drive  each 
wooden  peg  at  least  50 mm  below  finished 
grade. 
.4 Where  required,  place  erosion  control  mesh 
or  netting  and  secure  with  stakes  or  staples 
sunk  firmly  into  ground  to  a  minimum  depth 
of 150 mm at maximum intervals of 4 meters 
along  pitch  of  slope.  Place  stakes  or  staples 
horizontally  across  slope  at  intervals  equal  to 
width  of  mesh  or  netting  minus  150 mm  and 
drive flush with top of sod. 
 
    .6  Use a light roller to ensure that there is full, close 
contact  between  sod  and  growing  medium.    Use 
of a heavy roller to correct irregularities in grade is 
not permitted. 
    .7  Ensure all sodded areas are watered immediately 
after installation. Verify that water applied to has 
penetrated  through  sod  into  top  100 mm  of 
growing medium. Continue watering operations as 
needed to ensure that adequate moisture content 
is  maintain  to  encourage  deep  root  growth  and 
healthy, vigorous leaf growth. 
    .8  Protect  newly  placed  sod  from  heavy  foot  traffic 
during  installation  and  until  acceptance  by  the 
Contract  Administrator  and  the  City.  Protection 
shall  include  but  is  not  limited  to  placement  of 
wood planks or plywood of sufficient thickness to 
bear  the  imposed  weight  and  prevent  damage  to 
sod  or  displacement  and/or  compaction  of 
sod/growing medium. 
    .9  Sod  that  has  been  damaged  by  construction 
operation,  construction  /  site  personnel  or 
construction traffic shall be replaced at no cost to 
the  Owner.  Replacement  shall  include  removal  of 
growing  medium,  regarding  of  sub  grade, 
replacing growing medium and sod as required. 
    .10  Water  sod  area  immediately  with  sufficient 
amounts  to  saturate  sod  and  upper  100  mm  of 
growing medium. Do not allow the sod to dry out 
so that the joints become visible. 
 
3.4  Grass  Delete 3.4 and  .1  Maintenance  of  sodded  areas  shall  begin 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 92 23S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 68  
SUPPLEMENTARY SPECIFICATIONS  Sodding  2016 
 
Maintenance  replace with the  immediately  after  sodded  operation  and  shall 
following  continue  until  all  deficiencies  noted  in  the 
  Substantial  Performance  review  have  been 
rectified  to  the  satisfaction  of  the  Contract 
Administrator  and  the  City  and  conditions  for 
Total  Performance  have  been  achieved.  The 
Contractor is to notify the Contract Administrator 
and the City in writing forty eight hours (48) prior 
to stopping maintenance operations. 
    .2  Sod  Cutting:  After  the  ‘first’  cut  of  sodded  lawn 
areas cutting operations shall be carried out on a 
weekly  (seven  day)  basis  until  Total  Performance 
by Contract Administrator and the City: 
.1 First  cut  of  sodded  lawn  areas  shall  occur 
when  a  uniform  grass  height  of  75 mm  has 
been attained. First cut shall be to a height of 
65 mm. 
.2 Continue regular weekly cutting at a height of 
65 mm until Total Performance.  
.3 Cutting operations shall be such that each cut 
is at right angles to the previous cut. 
.4 Contractor  to  remove  grass  clippings  after 
each cut and dispose of off site. 
.5 Roll  when  required  to  remove  any  minor 
depressions or irregularities. 
.6 Immediately  repair  seeded  areas  that  show 
deterioration  or  bare  spots.  Top‐dress  all 
areas  showing  shrinkage  due  to  lack  of 
watering and seed with seed mix that matches 
the original seed mix.  
    .3  Fertilizer  analysis  shall  conform  to 
recommendations provided with growing medium 
analysis.  Application  of  fertilizer  shall  follow 
manufacturers’  recommendations  noting  that 
after  October  1  lawn  areas  shall  not  be  fertilized 
until April 15th of the following spring. 
    .4  Sodded  lawn  areas  shall  be  kept  free  of  invasive 
and/or noxious broadleaf weeds, grasses including 
but  not  limited  to  poa  annua,  disease,  fungi, 
detrimental nematodes and detrimental insects. 
    .5  All  maintenance  equipment  and  practices  are  to 
conform  to  the  BC  Landscape  Standard  Level  2 
‘Groomed’. 
 
 
    .6  Protect  all  sodded  areas  against  trespassing  and 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 92 23S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 69  
SUPPLEMENTARY SPECIFICATIONS  Sodding  2016 
 
from  damage  at  all  times  clearly  marked,  staked, 
string and flagging tape.  
    .1  Perimeter Protection: Where directed by the 
Contract  Adinistrator  and  the  City,  sodded 
areas shall be surrounded by a 900 mm high 
barrier  made  up  of  the  following 
components: 
.1 Wood  posts  placed  at  1.8  metres  on 
centre.  
.2 Wood  Posts  to  be  driven  to  a  depth  of 
300mm. 
.3 String  two  (2)  strands  of  hemp  based 
binder twine (or equal product) between 
posts.  Insure  one  full  wrap  of  twine 
around each post. 
.4 Tie 300 mm strands of ‘red’ flagging tape 
at  450  mm  intervals  along  the  entire 
length of both strands of twine. 
.5 Maintain perimeter protection until Total 
Performance  issued.    Upon  acceptance 
by  Contract  Administrator  and  the  City, 
remove  perimeter  fence  and  dispose  of 
off site. 
 
3.5  Condition for  Delete 3.5.1 and  Conditions for Total Performance of Sodded areas: 
Total  replace with the  .1 Sodded  areas  exhibit  fully  established  root 
Performance  following  systems.  
  .2 No seams are visible between sod sections.  
.3 Sod  areas  are  smooth  and  evenly  graded.  No 
depressions, foot marks or vehicle tracks. 
.4 Sod  is  free  of  bare  and  dead  spots  and  does  not 
have  any  broadleaf  weeds,  noxious  grasses 
including but not limited to poa annua. 
.5 No  surface  growing  medium  is  visible  when  grass 
has been cut to height of 65 mm. 
.6 Sodded areas have been cut a minimum of two (2) 
times, at seven (7) day intervals. 
.7 Sodded areas are a uniform green colour with no 
discoloured sections or patches. 
.8 Sodded  areas  exhibit  a  thick,  dense,  uniform  and 
healthy appearance. 
  Add 3.5.2  Lawns  sodded  after  September  30th  will  be  not  be 
reviewed for Total Performance until April 30th the next 
year. 
 
3.6  Guarantee /  Delete 3.6.1 and  The  Contractor  hereby  guarantees  that  the  sod  will 
Maintenance  replace with the  remain  free  of  weeds  and  defects  for  a  period  of  one 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 92 23S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 70  
SUPPLEMENTARY SPECIFICATIONS  Sodding  2016 
 
following  (1) year from the date of Substantial Performance.  The 
  Contractor shall make all corrections, adjustments and 
replacements  required  as  a  result  of  failure  of  all 
products  in  this  section.  During  the  Maintenance 
Period,  the  Contractor  will  replace  sodded  areas, 
determined by Contract Administrator and the City, to 
be  dead  or  failing  at  the  end  of  the  Maintenance 
Period.  Replacements  to  be  made  at  next  appropriate 
season  and,  conditions  of  guarantee  will  apply  to  all 
replacement seeding for one full growing season. 
  Delete 3.6.2 and  The  Owner  reserves  the  right  to  extend  the 
replace with the  Contractor's  Maintenance  Period  and  responsibilities 
following  for  one  (1)  additional  year  if,  at  end  of  the  initial 
  guarantee period, the development and growth of the 
sod is not sufficient to ensure future survival. 
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 93 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 71  
SUPPLEMENTARY SPECIFICATIONS  Planting of Trees, Shrubs and Ground Covers  2016 
 
MMCD Section 32 93 01S  Planting of Trees, Shrubs and Ground Covers 
 
1.0  GENERAL  Delete 1.0.1 and  Section 32 93 01 refers to those portions of the Work 
replace with the  that  are  unique  to  the  sourcing,  supplying,  placing 
following  and  maintaining  the  plant  material  indicated  on  the 
Contract  Drawing  and  the  Plant  List(s).  This  section 
must  be  referenced  to  and  interpreted 
simultaneously  with  all  other  sections  pertinent  to 
the Work described herein. 
1.2  References  Delete 1.2.2 and  Canadian  Nursery  &  Landscape  Association  (CNLA) 
replace with the  Standard for Nursery Stock (current edition). 
following 
  Add 1.2.4  The  British  Columbia  Landscape  &  Nursery 
Association (BCLNA). 
  Add 1.2.5  ANSI A‐300 Tree Pruning Guidelines 
 
1.3  Source Quality  Delete 1.3 and  .1  Seven  (7)  days  prior  to  the  Contract 
Control  replace with the  Administrator  and  the  City  review  of  plant 
following  material  at  source  the  Contractor  shall  confirm 
in writing availability of plant material noted on 
plant list.  
.2  Plant  material  will  be  supplied  from  nurseries 
who  are  certified  by  the  Clean  Plants  program, 
Canadian  Nursery  Certification  Institute  (CNCI), 
current  certification  standard 
http://cleanplants.ca/.  The  certification  shall 
include but is not limited to the requirements of 
the  current  active  module(s),  e.g.  P.  Ramorum 
module.  The  certification  must  extend  to  all 
fields and allied nursery operations where plant 
material  is  sourced.  Only  nurseries,  fields  and 
allied  nursery  operations  that  are  certified  will 
be  permitted  to  supply  plant  material  for  this 
project. 
.1 Prior  to  the  review  of  plant  material  by  the 
Contract  Administrator  and  the  City  the 
Contractor  shall  submit  written 
documentation  with  CNCI  certification 
stamp  stating  that  the  nursery  has 
undergone  all  components  of  a  certification 
program and has been audited to verify that 
all components are properly implemented. 
.2 The  documentation  submitted  shall  include 
but is not limited to the nurseries CNCI Clean 
Plants certification number. 
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 93 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 72  
SUPPLEMENTARY SPECIFICATIONS  Planting of Trees, Shrubs and Ground Covers  2016 
 
 
.3  Plant Material Review at the source nursery. 
.1 Contractor  shall  request  for  review  of  the 
plant  material  at  source  nursery  to  be  a 
minimum  of  seven  (7)  days  prior  to 
scheduled review. 
.2 Shipping  of  plant  material  to  the  Place  of 
Work  shall  not  proceed  until  Contract 
Administrator  has  reviewed  the  plant 
material at the source nursery.  
.3 Contract  Administrator  and  the  City  shall 
make  one  (1)  visit  to  source  nursery  for 
review of plant material for entire project. 
.4 All  plant  material,  including  substitutions 
shall be gathered at one location for review. 
.5 Contractor  shall  accompany  Contract 
Administrator  during  plant  material  review 
at the source nursery.  
.4  Plant Material Review at the Place of Work  
.1 All  plant  material  shall  be  reviewed  at  the 
Place of Work by the Contract Administrator 
and the City prior to planting.  
.2 Plant  material  that  is  rejected  by  the 
Contract Administrator shall be immediately 
removed  from  the  Place  of  Work  and 
replaced at the Contractor`s expense.  
.5  Imported Plant Material  
.1 Plant  material  imported  from  out  of 
province  and  out  of  country  shall  be 
accompanied  with  necessary  federal  and 
provincial permits and import licenses.  
.2 The  Contractor  shall  conform  to  all  federal 
and  provincial  laws  and  regulations  with 
regard  to  horticultural  inspection  of 
domestic and imported plant material. 
.6  Condition of Plant Material  
.1 Plant  rootballs  and  containers  shall  be 
completely  free  of  noxious  weeds  and 
volunteer  plants  including  Horsetail  and 
Morning Glory. 
.2 Plant  materials  grown  or  supplied  in  Fabric 
Containers are not acceptable. 
    .7  All materials and execution to conform to the 
latest edition of the BCNTA Guide Specifications 
for Nursery Stock and the BCNTA Guide 
Specifications for Landscape Construction. 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 93 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 73  
SUPPLEMENTARY SPECIFICATIONS  Planting of Trees, Shrubs and Ground Covers  2016 
 
 
1.4  Submittals and  Delete 1.4 and  .1 Submit inspection certificates as required by law 
Scheduling  replace with the  for each shipment of plant material. 
following   .2 Contractor  shall  provide  in  writing  to  the 
  Contract  Administrator  and  the  City  a  minimum 
of  seven  (7)  days  prior  to  review  of  plant 
material  at  the  source  nursery  a  plant  list 
confirming  the  quantity,  botanical  name, 
common name and size of plants specified. 
.3 Substitutions 
.1 Contractor  shall  provide  in  writing  to  the 
Contract  Administrator  and  the  City  a 
minimum of seven (7) days prior to review of 
plant material at the source nursery a list of 
proposed substitutions for review.  
.2 Plant  substitutions  shall  be  of  similar  genus 
and  species  and  of  equal  or  greater  size  as 
those  originally  specified.  The  list  shall 
contain the following information: 
.1 Botanical  name,  common  name  of  the 
specified plant 
.2 Botanical  name,  common  name  of  the 
proposed substitute plant 
.3 Pot size and plant size in the nursery 
.4 Planting Schedule 
.1 Contractor  shall  provide  in  writing  to  the 
Contract  Administrator  and  the  City  upon 
award  of  the  Contract  a  detailed  Planting 
Schedule  outlining  dates  and  duration  of 
planting operations. 
.2 Revisions to the Planting Schedule as a result 
of  delays  of  any  kind  shall  be  submitted  to 
the Contract Administrator and the City in a 
timely  manner  prior  to  the  start  of  planting 
operations. 
.3 Schedule  all  planting  to  ensure  optimum 
environmental  protection,  grading,  growing 
medium  placement,  planting,  seeding,  or 
sodding  operations  as  outlined  in  these 
Specifications.  Organize  scheduling  to 
ensure  a  minimum  duration  of  on‐site 
storage  of  plant  material,  minimum 
movement  and  compaction  of  growing 
medium, and prompt mulching and watering 
operations.  Coordinate  Work  schedule  with 
schedule of other trades on‐site. 
.4 Coordinate  and  schedule  plating  such  that 
no  damage  occurs  to  plant  material  before 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 93 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 74  
SUPPLEMENTARY SPECIFICATIONS  Planting of Trees, Shrubs and Ground Covers  2016 
 
and  after  placement.  In  particular,  meet 
requirements of living plant material. 
.5  Product Data 
.1 Contractor  to  submit  a  one  (1)  litre  sample 
of  Composted  Mulch  to  the  Contract 
Administrator  and  the  City  for  review  prior 
to delivery. 
.2 Contractor  to  submit  a  one  (1)  litre  sample 
of  the  Prepared  Growing  Medium  to  the 
Contract  Administrator  and  the  City  for 
review prior to delivery. 
.3 Contractor to submit three (3) copies of the 
anti‐desiccant  manufacturer  product  data 
and  specification  for  Contract  Administrator 
and the City review. 
.4 Contractor to submit three (3) copies of the 
fertilizer  manufacturer  product  data  and 
specification  for  Contract  Administrator  and 
the City review. 
.5 Contractor to submit three (3) copies of the 
Guying  assembly  including  clamps,  collar, 
guying  wire,  anchors  and  wire  tighteners 
manufacturer  product  data  and 
specifications for Contract Administrator and 
the City review. 
1.5  Handling and  Delete 1.5 and  .1  Coordinate  shipping  of  plant  material  and 
Storage  replace with the  excavation  of  planting  pits  to  ensure  minimum 
following   time  lapse  between  nursery  digging  and  on  site 
  planting. 
.2  Ensure  branches  of  trees  and  shrubs  are  bound 
securely  into  a  confined  mass  during  handling 
and transport. 
.3  Do not bind planting stock with rope or wire that 
would  damage  bark,  break  or  damage  branches 
or damage the natural shape of the plant. 
.4  Protect  plant  material  against  abrasion,  and 
exposure to extreme temperature change during 
transit.  
.5  Cover  plant  foliage  and  branches  with  tarpaulin 
to prevent loss of moisture during transit. 
.6  Fully  support  root  ball  of  large  trees  during  all 
lifting operations.  
.7  Do  not  lift  trees  or  shrub  by  the  trunk  or 
branches.  Plant material to be moved by lifting 
the root ball or container. 
.8  Remove  broken  and  damaged  roots  with  clean 
File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A
CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 93 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 75  
SUPPLEMENTARY SPECIFICATIONS  Planting of Trees, Shrubs and Ground Covers  2016 
 
cuts using sharp pruning shears. 
 
.9  Temporary  Storage/  Heel‐In  of  Plant  Material 
onsite 
.1  Temporarily  store  trees,  shrubs  and 
miscellaneous plant material that can not be 
planted  immediately  by  heeling‐in. 
Acceptable  heel‐in  material  include 
approved growing medium or sawdust. 
.2  Ensure  temporary  storage/heel‐in  area  is 
shaded and protected from the wind. 
.3  Provide  sufficient  water  at  regular  intervals 
to  ensure  health  of  plant  material  in  the 
temporary storage/heel‐in area. 
.4  Plant  material  that  has  not  been  properly 
maintained  in  the  storage/heel‐in  area  and 
illustrates signs of degradation or stress will 
be  rejected  by  the  Contract  Administrator 
and the City. Rejected plant material shall be 
replaced by the Contractor. 
1.11  Substitutions  Add 1.11  .1  If  it  is  impossible  to  obtain  the  particular  plant 
  material  listed  on  the  Landscape  Drawing,  the 
  Contractor  may  be  permitted  to  suggest 
substitutions  with  types  and  variations 
possessing  the  same  characteristics.    The 
Contractor  must  request  any  substitutions  of 
trees  in  writing  at  least  one  (1)  month  and 
shrubs  and  groundcover  at  least  one  (1)  month 
prior  to  planting.    Substitutions  must  be 
approved by the Contract Administrator and the 
City. 
1.12  Plant Material  Add 1.12  .1  Before  substitutions  of  plant  material  are 
Supply and    proposed,  documented  proof  that  materials  are 
Search Area    not  available  through  search  on  the  west  coast 
of  Canada  and  United  States  must  be  provided.  
Area  of  supply  shall  include,  but  not  be  limited 
to, all of Western North America. 
1.13  Plant Material  Add 1.13  .1  Plant  material  that  has  been  located  by  the 
Identificaton    Contract  Administrator  and  the  City  and  tagged 
  for  the  project  is  to  have  the  identification  tags 
removed only after inspection and instruction by 
the  Contract  Administrator  and  the  City  after 
delivery to the Place of Work. 
1.14  Plant Material  Add 1.14  1.  The  Contractor  shall  remove  from  the  Place  of 
Replacement    Work  and  immediately  replace  any  plant 
  material  that  has  been  determined  by  the 
Contract Administrator and the City to have died 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 93 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 76  
SUPPLEMENTARY SPECIFICATIONS  Planting of Trees, Shrubs and Ground Covers  2016 
 
or failed to grow in a satisfactory manner during 
the guarantee or maintenance period. 
 
.2  The  Contractor  shall  extend  the  guarantee  on 
this replacement plant material for one (1) year 
from the date of replacement. 
.3  The  Contractor  shall  continue  such  replacement 
and  guarantee  of  plant  material  until  the 
Contract  Administrator  and  the  City  has 
determined  that  the  Conditions  for  Total 
Perfomance have been met. 
.4  All  required  replacements  shall  be  plants  of  the 
same  size  and  species  as  specified  on  the  plant 
list  and  shall  be  supplied  and  planted  in 
accordance with the drawings, specifications and 
change orders thereto. 
.5  The  cost  of  replacements  resulting  from  theft, 
accidental  damage,  vandalism,  carelessness, 
neglect on  the part of others, shall be borne by 
the  Contractor  until  the  date  of  Substantial 
Performance. 
2.0  PRODUCTS     
 
2.1  Plant Material  Delete 2.1 and  .1  Plant Material Size  
replace with the  .1 Overall  plant  spread  to  be  measured  when 
following  branches are in their natural position. 
  .2 Height and spread dimensions refer to main 
body  of  plant  and  not  from  branch  tip  to 
branch tip. 
.2  Grade  of  plant  material  to  be  No.  1  grade  or 
better. 
.3  Plant  material  obtained  from  areas  with  milder 
climatic  conditions  from  those  of  the  Place  of 
Work is acceptable provided: 
.1 Plant material is moved to the Place of Work 
prior to the breaking of buds at their original 
climatic zone. 
.2 Plant  material  is  heeled‐in  at  a  protected 
area until the climatic conditions are suitable 
for planting. 
.4  Plant  material  shall  have  structurally  sound, 
strong  fibrous  root  system  free  of  disease, 
insects,  defects  or  injuries.  All  plants,  typical  of 
their  species  or  variety,  have  a  normal  habit  of 
growth and shall be first quality, sound, healthy, 
vigorous,  well  branched,  and  densely  foliated, 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 93 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 77  
SUPPLEMENTARY SPECIFICATIONS  Planting of Trees, Shrubs and Ground Covers  2016 
 
free of disease, insect pests, eggs or larvae. 
.5  Root Pruning at Source Nursery 
.1 Plant  material  shall  have  been  root  pruned 
on a regular basis at the source nursery.  
.2 Plant  material  shall  be  root  pruned  at  least 
one growing season prior to delivery. 
.3 Large  trees  shall  be  half  root  pruned  during 
each of two successive growing seasons. The 
second root pruning shall have carried out a 
minimum  of  one  growing  season  prior  to 
delivery. 
.6  Shade, Ornamental and Evergreen Trees: 
.1 Trees  shall  have  straight  trunks  and  a  well‐
formed  branch  system  which  is 
characteristic of the species  
.2 Trees  shall  exhibit  clear  signs  of  vigorous 
growth. 
.3 Trees shall have good twig extension growth, 
branch spacing and trunk taper. 
.4 Tree  foliage  shall  be  evenly  distributed  on 
upper 2/3 of the tree. 
.5 Trees  shall  not  have  upright  branches  other 
than leaders. 
.6 Trees  shall  have  spreading  branches  with  a 
single  trunk  and  a  single  leader  and,  unless 
otherwise noted on plans or plant list. 
.7 Tree trunks and branches shall not have any 
mechanical damage. 
.8 Trees  shall  be  in  good  health  with  no 
presence of insects or disease. 
.9 Trees shall not have been ‘headed back’. 
.10 Tree  root  balls  shall  be  solid,  kept  moist  at 
all times and/or protected from drying.  
.11 Trees  shall  not  exhibit  symptoms  of  root 
circling or girdling. 
.7  Container Grown Plant Material:  
.1 Root ball to container relationship shall be of 
sufficient  ratio  to  ensure  room  for  healthy, 
vigorous root development.   
.2 Plant  material  shall  have  been  container 
grown  for  a  minimum  of  one  (1)  growing 
season  but  not  longer  than  two  (2)  growing 
seasons.  
.3 The plant root systems that do not have the 
ability  to  "hold"  growing  medium  when 
removed from the container will be rejected.  
.4 Root bound plant material will be rejected.   

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 93 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 78  
SUPPLEMENTARY SPECIFICATIONS  Planting of Trees, Shrubs and Ground Covers  2016 
 
.8  Balled and Burlapped Plant Material:   
.1 Coniferous and broadleafed evergreens over 
2.4 metre tall shall be dug with firm soil root 
ball.  
.2 Deciduous  trees  in  excess  of  3.0  metre 
height shall be dug with firm soil root ball.   
.3 Root  ball  diameter  shall  be  a  minimum  of 
230 mm (for each 25 mm caliper size.   
.4 Secure  root‐balls  with  burlap,  heavy  twine 
and rope.  
.5 Large  tree  root  balls  shall  be  double  layer 
burlap  wrapped.  Burlap  to  be  secured  with 
drum  laces  made  up  of  10 mm  (minimum) 
diameter rope. 
.9  Tree Spade Dug Plant Material 
.1 Plant material shall be dug with mechanized 
hydraulic  spade  or  clamshell  type  digging 
equipment. 
.2 Root  ball  diameter  shall  be  a  minimum  of 
230 mm for each 25 mm caliper size.   
.3 Wire basket shall be lined with burlap.  Root 
ball  shall  be  laced  and  tied  to  wire  basket 
with heavy rope.  
.4 Ensure trunk of tree is not damaged by wire 
basket, ties or rope.  
 
2.2  Water  Delete 2.2.1 and  Potable and free of minerals and impurities which are 
replace with the  detrimental to plant growth. 
following 
2.3  Fertilizer  Add 2.3.2  Fertilizer  shall  be  prolonged‐release  fertilizer  tablets 
  containing  a  minimum  of  20%  nitrogen,  10% 
phosphoric  acid,  and  5%  potash  (20‐10‐5)  as  per 
Approved  Products  List.  Store  in  weatherproof 
storage space. 
 
2.4  Mulch  Delete 2.4.1 and  Composed  mulch  shall  be  9 mm  black/brown  in 
replace with the  colour  with  no  cedar  or  redwood  bark  or  wood
following  material as per Approved Products List. 
 
2.5  Stakes  Delete 2.5.1 and  Stakes shall be prressure treated Hem/Fir, 75 mm dia. 
replace with the  round,  2500 mm  long.  Stake  fasteners  shall  be  hot 
following  dipped galvanized or stainless steel. 
 
2.8  Guying Wire  Delete 2.8.1 and  Guyingwire  shall  be  direct  burial  or  screw  type  disc 
replace with the  guy anchor and guy system as per Approved Products 
following  List. 
   
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 93 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 79  
SUPPLEMENTARY SPECIFICATIONS  Planting of Trees, Shrubs and Ground Covers  2016 
 
2.11  Anti‐Desiccant  Delete 2.11.1 and  Anti‐Desiccant  shall  be  wax‐like  emulsion,  as  per 
replace with the  Approved  Products  List,  that  will  provide  a 
following  transpiration reducing film over the plant surface. 
 
2.12  Flagging Tape  Delete 2.12.1 and  Flagging tape shall be 30mm wide ‘Red’ PVC flagging 
replace with the  tape as per Approved Products List. 
following   
2.13  Tree Trunk  Add 2.13  .1  Tree  trunk  protection  shall  be  extrusion  mold 
Protection  process, polyethylene with UV protectors as per 
Approved Products List. 
 
2.14  Burlap  Add 2.14  .1  Burlap  shall  be  untreated,  free  from  toxic 
contaminants  and  of  sufficient  strength  to  hold 
the rootball in a compact, stable mass that does 
not move relative to the main stem(s) of the tree 
or shrub. 
 
2.15  Wire Baskets  Add 2.15  .1  Wire  baskets  shall  be  non‐galvanized  metal 
basket  designed  and  manufactured  for  the 
purpose of tree moving.  Basket shall be shaped 
to  ensure  that  the  root  ball  will  allow  a  stable 
planting condition in accordance with standards 
noted. 
 
2.16  Tree Ties  Add 2.16  .1  Tree  ties  shall  be  Flat  woven  polypropylene 
material.  20  mm  wide,  544  Kg,  break  strength. 
extrusion  mold  process,  polyethylene  with  UV 
protectors as per Approved Products List. 
 
3.0  EXECUTION     
 
3.1  Pre‐Planting  Delete 3.1 and  .1  Place  stakes  on  site  to  identify  location  trees, 
Operations  replace with the  shrubs  and  plant  beds  in  accordance  to  the 
  following   Landscape Plans.   
 
.2  Contract Administrator and the City to review all 
tree locations and plant bed layout prior to start 
of plant bed preparation and planting operation. 
.3  Anti‐desiccant  shall  be  applied  only  as  directed 
by  the  Contract  Administrator  and  the  City. 
Application  of  anti‐desiccant  shall  be  in 
accordance with manufacturer's instructions. 
.4  Coordinate  planting  operations  with  other 
trades and project schedule. 
.5  All planting operations shall be done in a timely 
manner in accordance to the Planting Schedule. 
.6  Planting  Schedule  shall  be  updated  as  required 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 93 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 80  
SUPPLEMENTARY SPECIFICATIONS  Planting of Trees, Shrubs and Ground Covers  2016 
 
by the Contractor to coincide with status of site 
and coordination with other trades. Provide the 
Contract  Administrator  and  the  City  with 
updates to the schedule as required throughout 
the planting process.  
3.2  Subgrade  Delete 3.2 and  .1  The Contractor is responsible for confirming the 
Preparation  replace with the  location  and  extent  of  existing  utilities  prior  to 
following   the start of all planting operations. All  attempts 
  should  be  made  to  ensure  that  utility  services 
are  maintained  to  all  on  and  off  site  parties 
through out the entire planting operation. 
2. Tree Pits 
.1  Tree Pit Depth 900 mm minimum. 
.2  Width  of  tree  pit  shall  be  a  minimum  of 
450 mm to 600 mm greater than diameter of 
the root ball.  
.3  Prior  to  the  placement  of  growing  medium 
scarify  the  sides  and  bottom  of  tree  pits 
created  with  a  tree  spade  to  eliminate 
glazed surface.  
.3  Ensure tree pits dug in heavy or compacted soils 
exhibit  the  ability  to  drain  freely  by  filling  each 
tree  pit  with  a  minimum  of  20  litres  of  water. 
Water should freely drain through subsoil within 
ten (10) minutes.  
.1  Notify Contract Administrator and the City if 
tree  pits  in  any  soil  condition  do  not  drain 
freely or if tree pit fills with ground water.  
.2  There  shall  be  no  standing  water  in  the 
bottom of tree pit at time of planting. 
.4  Protect bottom of tree pit(s) against freezing. 
.5  Ensure  tree  pits  and  plant  beds  are  kept  well 
drained  and  free  of  contaminants  and 
construction debris. 
.6  Planting  Areas  shall  be  excavated  to  the 
following depths: 
.1  Shrub  beds,  perennials,  ornamental  grasses 
shall be 450 mm. 
.2  Ground  covers  and  annual  flowers  shall  be 
300 mm. 
.3  Trees shall be 900 mm. 
 
 
3.3  Planting  Delete 3.3 and  .1  Planting  operations  shall  be  carried  out  under 
replace with the  conditions  that  are  conducive  to  healthy, 
following   vigorous growth of plant material. 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 93 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 81  
SUPPLEMENTARY SPECIFICATIONS  Planting of Trees, Shrubs and Ground Covers  2016 
 
  .2  Plant  material  shall  be  planted  vertical,  straight 
and  plumb  at  locations  staked  in  field  and  or 
noted on landscape plans.  
.3  Ensure  orientation  of  plant  material  will  give 
best  appearance  in  relation  to  views  from 
adjacent buildings, roads, walks or use areas. 
.4  Ensure planting depth of root ball is equal to the 
depth  of  root  ball  originally  established  in  the 
nursery.  The  top  of  root  ball  shall  be  level  with 
adjacent growing medium.  
.5  Ball  and  Burlap  Plant  Material:  After  plant  has 
been lowered into plant bed or tree pit cut away 
all  root  ball  ties  from  around  trunk.  Loosen 
burlap  from  around  trunk  and  cut  away 
minimum top 1/3 without disturbing root ball.  
.6  Container  Grown  Plant  Material:  Remove  entire 
container  (including  biodegradable  containers) 
without  disturbing  root  ball.  Score  root  ball 
vertically  at  six  (6)  locations  evenly  spaced 
around  entire  root  ball  to  minimize  girdling  of 
roots.  
.7  Tree  Spade  Dug  Root  Balls:  Cut  wire  basket 
around entire perimeter of root ball.  Bend down 
top  2/3  of  wire  basket  without  disturbing  root 
ball.  Cut  away  all  root  ball  ties  from  around 
trunk. Loosen burlap from around trunk and cut 
away  minimum  top  1/3  without  disturbing  root 
ball. 
.8  Backfill planting areas in 150 mm  lifts to 2/3 of 
the  depth  tamping  each  lift  of  growing  medium 
around  root  system  to  eliminate  air  voids.  Do 
not use frozen or saturated growing medium for 
backfill operation. 
.9  Prior  to  placing  remaining  growing  medium, 
thoroughly  water  planting  areas,  fill  tree  pits 
with  water.  Complete  backfill  operation  only 
after  water  has  completely  penetrated  into 
growing medium. 
.10  Build 100 mm high by 150 mm wide (4” high by 
6” wide) saucer around outer edge of tree pit to 
assist with maintenance watering. 
.11  Tree Stabilization 
.1 Guy  or  stake  trees  as  directed  by  Contract 
Administrator and the City.  
.2 Ensure  guy  pins  and  stakes  are  not  placed 
File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A
CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 93 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 82  
SUPPLEMENTARY SPECIFICATIONS  Planting of Trees, Shrubs and Ground Covers  2016 
 
through the root ball.  
.3 Trees that have had root balls penetrated by 
guy pins and stakes will be rejected.  
.4 Tie  one  (1)  to  two  (2)  flagging  tape  flags  to 
all guy wires at a height that is clearly visible.
.12  Place  tree  trunk  protection  around  base  of  tree 
trunk as per manufacturer instructions. 
.1 Trees  100mm  caliper  or  less  shall  have  one 
protector.  Do  not  interlock  ends  of  tree 
protector. 
.2 Trees greater than 100mm caliper shall have 
a  minimum  of  two  interlocked  protectors. 
Do not interlock outside ends. 
.13  Fertilize  as  per  recommendations  based  on  soil 
testing  and  place  planting  tablets  at  the 
following  rates  in  prepared  planting  holes.  
Spread the tablets in each hole before planting. 
 
  Plant/Container  Table Size  Tablets per 
Size  Plant 
.1  Trees  21g    1 per every 
1.25mm of 
trunk caliper 
.2  #15/ 45 cm tub  21g    3 
.3  #7/ 35 cm tub  21g    3 
.4  #5/ 30 cm pot  21g    2 
.5  #3/ 27 cm pot  21g    2 
.6  #2/ 21 cm pot  21g    1 
.7  #1/ 15 cm pot  21g    1 
     
3.4   Tree Support  Delete 3.4 and  .1  Guy  and  stake  all  trees  immediately  after 
replace with the  planting.    Plant  material  not  guyed  or  staked 
following  immediately shall be replaced if damaged. 
.2  Drive  one  (1)  stake  per  tree  vertically  into  the 
ground  to a  depth of 750 – 1000 mm,  in such a 
manner so as not to injure the root or root ball. 
.3  Fasten  tree  to  the  crotch  and  midway  between 
the  crotch  and  the  ground  with  galvanized  wire 
protected by hose. 
.4  Trees  to  stand  plumb  upon  completion  of  this 
operation. 
 
3.6   Pruning  Delete 3.6 and  .1  All pruning cuts shall be made with pruning saws 
replace with the  or  hook  and  blade  pruning  tools  designed  and 
following   manufactured  for  pruning  operations.    Anvil‐
  type  pruning  tools  shall  not  be  used  in  any 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 93 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 83  
SUPPLEMENTARY SPECIFICATIONS  Planting of Trees, Shrubs and Ground Covers  2016 
 
pruning operations. 
.2  Prune  trees  and  shrubs  after  planting  operation 
as  directed  by  Contract  Administrator  and  the 
City. 
.3  Prune  each  tree  and  shrub  planted  to  preserve 
the  natural  character  of  the  plant  and  in  a 
manner  appropriate  to  its  particular 
requirement in the landscape design.  Pruning in 
general  shall  be  heavier  on  collected  than  on 
nursery‐grown  plants.    Remove  all  soft  wood 
sucker  growth  and  all  broken  or  badly  bruised 
branches with a clean cut. 
.4  Employ clean sharp tools and make cuts without 
damaging the branch collar.   
.5  Do  not  damage  the  leader  or  lead  branches. 
Plants  which  have  had  the  main  leader  or  lead 
branches  damaged  or  removed  will  be  rejected 
and replaced by the Contractor at no cost to the 
Owner.  
.6  Do  not  remove  minor  twig  branches  along  the 
main structural branches.  
3.7  Mulching  Delete 3.7 and  1.  Prior to the application of composted mulch; 
replace with the 
.1 Manually  remove  all  weeds  and  weed  roots 
following 
from  root  balls  and  adjacent  growing 
medium.  
.2 Remove  all  deleterious  material  and  debris 
from planting areas. 
.3 All  fine  grading  shall  be  completed,  the 
growing medium shall be loose and friable.  
.4 The Contract Administrator and the City has 
reviewed of all planting areas.  
.2  Spread  composted  mulch  to  minimum  depth  of 
50 mm.  
.1 Ensure  finish  composted  mulch  layer  is  a 
minimum  of  12 mm  below  adjacent  hard 
landscape surfaces and edges. 
.2 Ensure  mulch  is  kept  125  mm  away  from 
tree trunks and 75 mm away from stems of 
shrubs. 
 
 
3.8  Clean‐up  Delete 3.8 and  .1  Growing  medium  spilled  onto  pavement  and 
replace with the  growing medium stains on pavement or adjacent 
following  hard surfaces shall be cleaned up immediately. 
 
.2  Remove  from  the  site  all  pots,  cans,  surplus 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 93 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 84  
SUPPLEMENTARY SPECIFICATIONS  Planting of Trees, Shrubs and Ground Covers  2016 
 
materials,  and  other  debris  resulting  from 
planting operations. 
.3  Ensure  complete  removal  of  planting  tags, 
labels,  strings,  or  other  materials  prior  to 
substantial completion. 
.4  Neatly  dress  and  finish  all  planting  areas  and 
flush  all  walks  and  paved  areas  clean  to  the 
satisfaction of the Consultant and Owner. 
3.9  Maintenance  Delete 3.9 and  .1  Maintenance  of  plants  shall  begin  immediately 
replace with the  after planting operation and shall continue in an 
following  uninterrupted fashion until all deficiencies noted 
  in the Substantial Performance review have been 
rectified and the Contract Administrator and the 
City  has  provided  to  the  Contractor  written 
confirmation of the date of Total Performance. 
.2  If  for  any  reason  the  Contractor  elects,  on  his 
own without the written consent of the Contract 
Administrator  and  the  City  to  suspend 
maintenance  operations,  the  Contractor  shall 
provide the  Contract Administrator and the City 
written  notice  of  such  action.  Any  damages  or 
requirement  for  the  replacement  of  plant 
material  that  as  a  result  of  the  suspension  of 
maintenance  operations  shall  be  the  borne  by 
the Contractor at no cost to the Owner. 
.3  Maintenance  of  plant  material  includes  but  is 
not  limited  to  watering  at  intervals  sufficient  to 
maintain  healthy,  vigorous  growth,  weeding  of 
plant  beds  and  tree  pits,  cultivating  of  growing 
medium,  pruning,  treatment  of  insects,  molds, 
fungi or disease to the Level 2 “Groomed’ as per 
the  BCNLA  Landscape  Standard,  Current  Edition 
or as directed by consultant. 
.4  Plant  material  shall  be  deep  watered  at  least 
once  per  day  when  temperatures  exceed  25 
degrees Celsius. 
.5  Water  sufficiently  to  maintain  soil  moisture 
conditions  for  optimum  establishment,  growth 
and  health  of  plant  material  without  causing 
erosion. 
 
.6  Supply  equipment  such  as  pumps,  portable 
sprinklers  systems,  tank  trucks,  hose  and 
sprinklers  required  for  watering  operations.  
Water  trucks,  if  used  for  watering  operations, 
must  service  the  site  from  adjacent  roads  until 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 32  MMCD SECTION 32 93 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  ROAD AND SITE IMPROVEMENTS  SS PAGE 85  
SUPPLEMENTARY SPECIFICATIONS  Planting of Trees, Shrubs and Ground Covers  2016 
 
irrigation system is operational. 
.7  Contractor to ensure adequate moisture in plant 
root zone prior to winter freeze‐up. 
.8  Reset all plants that have settled to plant depths 
approved by the Contract Administrator and the 
City prior to the placement of composted mulch. 
.9  Ensure tree guards, stakes, flagging tape on tree 
guy  wire  and  tree  ties  are  kept  secure,  taught 
and in proper repair. 
3.10  Conditions for  Delete 3.10 and  .1  Conditions for Total Performance: 
Total  and replace with  .1 Substantial  Performance  shall  have  been 
Performance  the following  granted  by  the  Contract  Administrator  and 
     the  City  and,  Final  Inspection  at  the  end  of 
the guarantee/warranty period. 
.2 All plant material is healthy; exhibiting signs 
of  vigorous  growth  and  meets  the 
requirements of this specification. 
.3 Plant material installed less than ninety (90) 
days  prior  to  frost  will  be  accepted  in 
following  spring,  thirty  (30)  days  after  start 
of  growing  season  provided  that  final 
acceptance conditions are fulfilled. 
.4 Unless  otherwise  indicated  in  the  Contract 
Drawing  the  original  shape  and  form  of  the 
plant  as  reviewed  by  the  Contract 
Administrator  and  the  City  has  been 
maintained, leaders are in tact, there are no 
wounds or abrasions on trunks or branches. 
.5 Mulch  has  been  maintained  to  specified 
depths. 
.6 All  planting  areas  continue  to  be  free 
draining with no signs of standing water. 
.7 All  plant  beds  are  completely  free  of  weeds 
and noxious grasses. 
.2  The  Contractor  shall  continue  to  maintain  the 
work  of  this  section  until  the  Contract 
Administrator  and  the  City  provides  written 
confirmation  that  Total  Performance  conditions 
have been met. 
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 33  MMCD SECTION 33 01 30.1S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  UTILITIES  SS PAGE 86  
SUPPLEMENTARY SPECIFICATIONS  CCTV Inspection of Pipelines  2016 
 
MMCD Section 33 01 30.1S  CCTV Inspection of Pipelines 
 
1.0 GENERAL         

1.2  References  Delete 1.2.2.1 and  National  Association  of  Sewer  Service  Companies’ 


replace with the  (NASSCO’s)  Pipeline  Assessment  and  Certification 
following  Program,  version  6.x  including  addendums,  or  latest 
version.  
1.3  Submission of  Delete 1.3.1 and  Submit  copy  of  the  CCTV  operator’s  current  NAASCO 
Certification  replace with the  certification certificate to the Contract Administrator at 
following  least one week prior to the start of the CCTV inspection 
operations.  
2.0 PRODUCTS     

2.1  Equipment  Delete 2.1.4 and  The  individual  digital  video  playback  files  to  be  of 
replace with the  MPEG file format. 
following   
  Add 2.1.5  The digital data file delivered to the City to be in PACP 
standard database file format version 6.x or latest. 
3.0   EXECUTION     

3.1  CCTV Inspection  Delete 3.1.1 and  CCTV  operator  to  be  certified  by  NASSCO 
replace with the  (PACP/MACP/LACP). 
following 
 
  Delete 3.1.2 and  NASSCO  certified  software  must  be  used  to  produce 
replace with the  inspection report and the data will be submitted in the 
following  PACP standardized database format.  The review of this 
  statement will be part of the evaluation of the tender.  
Submission to satisfy all of the specifications and report 
submissions  per  NASSCO’s  PACP  (MACP/LACP)  will  be 
used as a benchmark for subsequent inspection report 
submission.  
  Delete 3.1.11 and  Note  condition  of  pipe  joints  at  manhole  walls  at  the 
replace with the  beginning and end of each pipeline; At the beginning of 
following  each  pipeline  or  where  surface  wear  of  the  pipe 
  changes, pan to the invert and any direction as needed 
to report and record surface wear condition of the pipe 
using PACP (MACP/LACP) codes; Fill under remarks the 
observations  if  no  surface  wear  observed  due  to  good 
condition  of  pipe  or  unable  to  determine  stating 
reason. 
  Delete  3.1.14  and  Stop camera at each defect, change of condition of pipe 
replace  with  the  and service connection to record defect in accordance 
following  with PACP (MACP/LACP) codes. 
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 33  MMCD SECTION 33 01 30.1S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  UTILITIES  SS PAGE 87  
SUPPLEMENTARY SPECIFICATIONS  CCTV Inspection of Pipelines  2016 
 
  Delete  3.1.15  and  Add PACP (MAC/LACP) code overlay to digital video at 
replace  with  the  defects or connections in addition to continuously 
following  displayed data. 
  Add 3.1.19  The inspection measurement and reporting units must 
be in metric system. 
3.3  Site Coding  Delete 3.3.1 and  Each  pipeline  length  to  be  recorded  according  to  the 
Sheets  replace with the  PACP.    Any  variation  from  the  manual  to  be  noted  in 
following  the survey report. 
  Delete 3.3.2 and  Use standard coding form and standards of PACP: 
replace with the 
following 
  Delete 3.3.2.1   
 
  Delete 3.3.2.2    
 
  Delete 3.3.2.3 and  Note  observations  as  to  condition  of  service 
replace with the  connections  beyond  mainline  in  remarks  column  using 
following  standards codes as per PACP. 
3.7  Photographs and  Delete 3.7.1 and  Photograph  all  major  defects  as  defined  by  condition 
/or Digital  replace with the  codes in PACP: B, CC, CL, CM, TFD, TBD, TSD, TRD, D, FC, 
Images  following  FL, FM, H, IR, IG, JO, OB, JS, RM, RB, RT, and X. 
  Delete 3.7.2.5 and  PACP/MACP/LACP Condition Defect Code. 
replace with the 
following 
3.8  Inspection  Delete 3.8.2 and  Present  machine  printed  (hardcopy)  and  computer 
Reporting Hard  replace with the  generated  data  base  reports  according  to  the  PACP 
Copies & Digital  following  format. 
Format      
  Delete  3.8.2.2  and  Hardcopy reports to be presented in PACP standard 
replace  with  the  format. 
following    
3.10  Root cutting &  Delete 3.10.1 and  Remove roots for condition codes RT, RM, and   RB. 
Removal   replace with the   
following 
3.12  Coding Accuracy   Delete 3.12.1.2  Detail accuracy 90% 
and replace with 
the following  
  Delete  3.12.4 and  An operator failing to meet the accuracy requirements 
replace with the  on two occasions will not be permitted to code on the 
following   remainder  of  the  project  until  they  have  successfully 
  re‐attended  an  Operator’s  Certification  course,  re‐
write  and  pass  the  NASSCO  Pipeline  Assessment 
Certification Program. 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 33  MMCD SECTION 33 11 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  UTILITIES  SS PAGE 88  
SUPPLEMENTARY SPECIFICATIONS  Waterworks  2016 
 
MMCD Section 33 11 01S  Waterworks 
 
2.0 PRODUCTS     

2.2  Mainline Pipes,  Add to 2.2.1.1  Pipe:  to  AWWA  C151,  and  shall  meet  the  following 
Joints and  Pressure Class or Thickness Class: 
Fittings 
.1 100 mm – 350 mm – Thickness Class 50 
.2 400 mm & greater – PC 350 
  Delete 2.2.2.2 and  Joints:    It  is  mandatory  that  the  push‐on  integrally 
replace with the  thickened bell and spigot type conform to ASTM D3139 
following  Clause 6.2 with single elastomeric gasket to ASTM F477.
 
  Delete 2.2.4.13  Joint Restrain Devices:  General Requirements: 
and replace with   
the following  .1 Ductil iron castings to ASTM A536. 
.2 Anti‐corrosion  coating  of  ductile  iron  castings  to 
AWWA  C219,  AWWA  C210,  AWWA  C213  or 
AWWA C550. 
.3 Bolts  and  nuts  high  strength  low  alloy  steel  to 
AWWA  C111  or  as  specified  in  Contract 
Documents, stainless steel to ASTM F593 or ASTM 
F738  for  bolts  and  ASTM  F594  or  ASTM  F836  for 
heavy hex nuts.  Rolled threads, fit and dimensions 
to AWWA C111. 
.4 Tie rods to 2.2.3.8 of this Section 
.5 Restrainers  for  ductile  iron  pipe  shall  be 
mechanical  joint  fittings  or  push‐on  joint  fittings 
with tie rod. 
.6 Restrainers  for  PVC  pipe  shall  be  mechanical  joint 
fittings or push‐on joint fittings with tie rod lugs. 
.7 Restrained  harnesses  or  integral  restrain  systems 
manufactures as part of the pipe joint. 
.8 All  joint  restraint  systems  for  PVC  pipe  be 
approved  by  the  specific  PVC  pipe  manufacturer, 
and  that  they  do  not  derate  the  pipe 
manufacturer’s recommended working pressures. 
.9 Restrainers for PVCO pipe shall be mechanical joint 
fittings or push‐on joint fittings with tie rod lugs. 
.10 All  joint  restraint  systems  for  PVCO  pipe  be 
approved by the specific PVCO pipe manufacturer, 
and  that  they  do  not  derate  the  pipe 
manufacturer’s recommended working pressures. 
 
 
 
 
 
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 33  MMCD SECTION 33 11 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  UTILITIES  SS PAGE 89  
SUPPLEMENTARY SPECIFICATIONS  Waterworks  2016 
 
  Add 2.2.7  Oriented Polyvinyl (PVC) Pressure Pipe: 
   
.1  Pipe:   
.1  Pipe  to  be  manufactured  to  specifications  for 
pipe size ranges as follows: 
.1  Pipes  100  to  600  mm  diameter  – 
AWWA C909. 
.2  Pipes to be certified by Canadian Standards 
Association for pipe size ranges 100 mm to 
600 mm dia. – CSA B137.3.1. 
.2  Cast iron pipe equivalent outside diameter. 
.3  To  be  compatible  with  specified  mechanical 
joint  and  push‐on  joint  fittings  and  valves 
without use of apecial adapters. 
.2  Joints:  Push‐on integrally thickened bell and spigot 
type  to  AWWA  C909  Clause  4.3.3.2  (a.)  with  single 
elastomeric gasket to ASTM F477. 
 
2.3  Valves and Valve  Delete 2.3.1.3 and  Valves 400 mm and larger shall be butterfly valves. 
Boxes  replace with the   
following 
 
  Delete 2.3.1.4   
 
  Delete 2.3.4 and  Blow‐Down  or  Blow‐Off  Valves:  50  mm  to  300  mm  as 
replace with the  specified for mainline gate valves. 
following 
 
  Delete 2.3.6.1.1    
 
  Delete 2.3.6.1.2  Circular type valve box shall be Nelson style cast iron. 
and replace with   
the following 
  Delete 2.3.7.1 and  Curb  stop  valve  boxes  on  19 mm  dia.  to  38 mm  dia. 
replace with the  shall  be  as  shown  on  Coquitlam  Standard  Detail 
following  Drawings COQ‐W2b, COQ‐W2j. 
 
  Delete 2.3.7.2   
  Delete 2.3.7.3 and  Curb  stop  valve  boxes  (300  mm  from  property  line) 
replace with the  alternative  on  19  mm  dia.  to  38  mm  dia.  services 
following  without operating rods to be assembled as specified for 
Mainline  Valve  Boxes  2.3.6.1.2,  and  shown  on 
Coquitlam  Standard  Detail  Drawings  COQ‐W2b,  COQ‐
W2j.    Service  boxes  may  be  Nelson  style  PVC,  except 
when located in driveways. 
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 33  MMCD SECTION 33 11 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  UTILITIES  SS PAGE 90  
SUPPLEMENTARY SPECIFICATIONS  Waterworks  2016 
 
  Delete 2.3.7.5 and  Corporation  stop  valve  boxes  (at  mainline  tees  or 
replace with the  tappings) on services 50 mm dia. and larger as specified 
following  for Mainline Valve Boxes per Coquitlam Standard Detail 
Drawings COQ‐W2e, COQ‐W2f. 
2.5  Service  Delete 2.5.1 and  Pipe diameter 19 mm to 75 mm to be Type K annealed 
Connections,  replace with the  copper to ASTM B88M. 
Pipes, Joints and  following 
Fittings 
2.6  Hydrants  Delete 2.6.1.6 and  Pump  nozzle  shall  be  “quick  connect”  STORZ  type. 
replace with the  STORZ type nozzle must be painted gloss black. 
following 
 
  Delete 2.6.2 and  Colour: Tremclad Rust Paint 
replace with the    Body – Fire Red 
following    Hose Caps and Bonnet – Bright Yellow 
 
2.8  Granular Pipe  Add 2.8.3   Bedding and surround material shall be Type 1 under 
Bedding and  Section 31 05 17 – 2.7 or 19 mm minus clear crushed 
Surround  gravel. 
Material  
 
3.0 EXECUTION     

3.6  Pipe Installation  Add 3.6.15  When  the  watermain  crosses  a  storm  or  sanitary 
sewer,  the  watermain  shall  be  installed  a  minimum 
0.5  m  clear  above  the  sewer.  Where  this  is  not 
possible, the  watermain shall have a minimum 0.3 m 
clearance under the sewer with all joints within a 3.0 
m  horizontal  distance  from  the  sewer  wrapped  with 
heat  shrink  plastic  or  packed  and  wrapped  with 
petrolatum  tape  in  accordance  to  the  following 
standards: 
.1 ANSI/AWWA C214 (factory applied) 
.2 ANSI/AWWA C209 (field applied) 
.3 ANSI/AWWA C217‐90 (petrolatum tape) 
.4 All materials used are to have zero health hazard 
Installation  shall  be  in  accordance  with  the 
requirements  of  the  Regional  Health  Engineer  under 
the Health Act. 
3.10  Service  Delete 3.10.4   
Connection 
Installation 
  Delete 3.10.5 and  Tappings  in  cast  iron  or  ductile  iron  mains  to  AWWA 
replace with the  CISI  pipe  to  be  made  using  double  strap  saddles 
following  specified in 2.5.3 of this Section. 
  Add 3.10.13  Water  service  connections  (19 mm  and  25 mm)  must 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 33  MMCD SECTION 33 11 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  UTILITIES  SS PAGE 91  
SUPPLEMENTARY SPECIFICATIONS  Waterworks  2016 
 
be installed as one continuous length of pipe. 

3.18  Cleaning and  Add 3.18.5  Water mains 400 mm and larger shall be swabbed as 


Preliminary  per the following procedure: 
Flushing 
    1. Purpose and Scope 
.1 To remove any possible contaminants 
introduced into the water main through pipe 
storage or installation activities. 
 
2. Swab Requirements 
.1 Swabs are to be of a polyurethane foam 
construction, minimum 2 lb/ft3 density 
.2 Swabs are to be new.  Used swabs will not be 
accepted. 
.3 Swab outside diameter must be minimum 
1 nominal size larger than the largest 
diameter main to be swabbed (eg. 150 mm 
main requires minimum 200 mm diameter 
swabs) 
.4 Swab length must be minimum 1.5 times the 
outside diameter. 
 
3. Swab Entry Point 
.1 2 swabs are to be inserted into the beginning 
of the first length of water main installed into 
the trench.  Swabs are to have a minimum of 
1 meter separation between them. 
.2 Minimum 300 grams of calcium hypochlorite 
granules are to be installed in between the 
2 swabs. 
 
4. Swab Discharge Point 
.1 Swabs are to be discharged from the water 
main at the end of the installation (ie‐
permanent or temporary dead end) 
.2 A temporary connection for a discharge 
assembly of minimum 150 mm (100 mm is 
acceptable for 100 mm water main only) is to 
be made to the end of the new water main 
pipe (connection to a blow off assembly is 
not acceptable). 
.3 The discharge assembly must consist of a 
90 degree elbow and appropriate fittings to 
adapt to 150 mm “camlock” style layflat 
hose.  The assembly must have adequate 
thrust protection to avoid blowing off during 
the swabbing procedure. 
.4 The 150 mm layflat hose must extend above 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 33  MMCD SECTION 33 11 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  UTILITIES  SS PAGE 92  
SUPPLEMENTARY SPECIFICATIONS  Waterworks  2016 
 
the surface of the existing ground. 
 
5. General Swabbing Requirements 
.1 Swabbing to be performed after the 
satisfactory completion of all pipe work (as 
determined by the city inspector), and prior 
to flushing, pressure testing, and chlorination 
of the new water main. 
.2 Swabbing of the water main is to be 
witnessed by the City of Coquitlam. 
.3 Although a minimum of 2 swabs must be 
used for each run, additional swabs may be 
required depending on the time required for 
the water to run clear after swab discharge.  
This determination will be made by the City 
of Coquitlam. 
.4 Swabs are to be used once only.  Additional 
new swabs will be required for additional 
swab runs if deemed necessary by the city. 
.5 Swabs must be stored and handled 
hygienically. 
.6 The contractor must provide all labour and 
materials required to carry out the swabbing 
procedure. 
.7 Swabbing should be completed from a low 
point to a high point where possible. 
.8 A plan to complete the swabbing must be 
submitted to the City of Coquitlam prior to 
the work taking place for approval. 
.9 The contractor must take all necessary action 
to prevent flooding of the discharge area. 
 
6. Swabbing Procedure 
.1 The length of main within the swabbing run 
must have all connections larger than 25 mm 
isolated by closing appropriate valves. 
.2 The new main is to be filled and swabs 
propelled via a certified backflow prevention 
device (double check valve assembly) and 
water meter from the existing system.  The 
connection to the existing system will form 
part of the plan submitted to the city for 
approval. 
.3 Appropriate flow is to be used to propel the 
swabs at approximately .75 meter per second 
velocity.  See following list for appropriate 
flow: 
Main  Approximate flow required 
diameter  to produce 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 33  MMCD SECTION 33 11 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  UTILITIES  SS PAGE 93  
SUPPLEMENTARY SPECIFICATIONS  Waterworks  2016 
 
(mm)  0.75 m/s velocity (l/s) 
100  6.3 
150  12.6 
200  25.2 
250  37.9 
300  56.8 
600  227.2 
.4 Upon discharge of the swabs, the main must 
be flushed until the water runs clear. 
.5 The supply point can then be slowly closed. 
.6 Additional swabs must be run through the 
water main if excessive debris is noted to be 
discharged from the main or there is 
excessive clean up time after the swabs are 
discharged. 
3.23  Connection to  Delete 3.23.1 and  Connections  to  existing  waterworks  systems  will  be 
Existing Mains  replace with the  made by the Contractor under the supervision of the 
following  Contract  Administrator.  Make  all  necessary 
arrangements  with  the  Contract  Administrator  and 
the  City  to  schedule  work  to  prevent  construction 
delays. 

  Add 3.23.2   Provide written notification to all affected residents a 
minimum 48 hours prior to service interruption. 

  Add 3.23.3   Arrange  shutdown  of  the  existing  valves  by  the  City. 
Contractor shall not operate any valves without prior 
approval of the Contract Administrator and the City. 

  Add 3.23.4   Provide temporary water service while existing service 
is  interrupted  as  detailed  in  Contract  Drawing  or 
Project Specific Specifications. 

  Add 3.23.5   Fittings  used  for  tie  ins  should  be  cleaned  of  all 
foreign  material  and  sprayed  with  a  1%  hypochlorite 
solution  prior  to  assembly.  Disinfect  all  pipes  and 
fittings installed at the connection. 

  Add 3.23.6   Contractor  shall  be  responsible  for  the  costs  for  the 
City to flush and purge all air from existing mains and 
services  in  the  area  affected  by  the  water  service 
interruption. 

  Add 3.23.7  Procedures  for  Bateriological  Tests  shall  be  as 


described  in  AWWA  C651‐99.No  connection  to 
existing  watermains  will  be  authorized  until  final 
results  of  coliform  bacterial  testing  have  been 
received and reviewed by the Water Superintendant. 

All samples shall be taken by the City Water Utility. 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 33  MMCD SECTION 33 11 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  UTILITIES  SS PAGE 94  
SUPPLEMENTARY SPECIFICATIONS  Waterworks  2016 
 
All valve operation shall be handled by the City Water 
crews. 

The  Contractor  shall  provide  sampling  points,  one 


every  366m  plus  the  end  of  each  main  segment.  The 
Contractor  shall  provide  all  labour  to  temporarily 
connect  and  disconnect  the  new  main  in  order  to 
properly acquire test samples. 

Initial  flushing,  testing  and  chlorination  will  be 


undertaken  by  the  Contractor  from  a  water  source 
approved by the Water Superintendent. 

Coordination  for  the  bacterial  testing  and  tie  in  shall 


be  coordinated  by  the  project  Engineering  Inspector 
and the Water Superintendent prior to final flushing. 

The  Contract  Administrator  shall  review  with  the 


Water  Superintendent  and  the  Contractor  sampling 
locations and appurtenances. 

The  Contract  Administrator  shall  check  and  record 


chlorine residual prior to final flushing. 

After final flushing the City Water crew will collect two 
sets of samples 24 hours apart. Samples will be taken 
at  least  every  366m  of  the  new  main  as  well  as  the 
terminus and all branches. 

Test  results  will  be  delivered  to  the  Water 


Superintendant  who  will  provide  a  copy  to  the 
Contract Administrator. 

The Water Superintendent will judge the adequacy of 
the test results and issue an authorization to connect. 

City  Water  crews  will  provide  shutdown  and  flushing 


as required. 

3.25  Permanent  Add 3.25  Permanent  capping  of  existing  water  service 


Capping of  connections  to  be  completed  as  per  Coquitlam 
Existing Water  standard Detail Drawings COQ‐W2g, COQ‐W2h, COQ‐
Service  W2i. 
Connections 
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 33  MMCD SECTION 33 30 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  UTILITIES   SS PAGE 95  
SUPPLEMENTARY SPECIFICATIONS  Sanitary Sewers  2016 
 
MMCD Section 33 30 01S  Sanitary Sewers 
 
2.0 PRODUCTS     

2.1  Concrete  Add to 2.1.1 and  Prior  approval  from  Contract  Administrator  and  the 
2.1.2  City  for  use  of  concrete  pipe  in  a  sanitary  sewer 
  installation. 
     
Delete 2.1.3.4 and  Lift insert opening not required to be grouted provided 
replace with the  it does not extend beyond the depth of the engineered 
following  design. 
 
2.3  Service  Delete 2.3.8.1   
Connections 
  Delete 2.3.8.2 and  Connections  to  mainline  PVC  pipe  to  be  made  with  a 
replace with the  manufactured  wye  fitting  when  mainline  pipe  is 
following  250 mm and smaller. 
   
For new connections to existing mainline greater than 
250 mm use of insertable tee will be permitted 
  Add 2.3.8.3  Insertable  tee  fitting  shall  have  a  rubber  collar  which 
inserts into the mainline  pipe  to form a tight seal  and 
shall have stainless steel band to secure the tee insert. 
The tee insert shall be a standard bell  end with depth 
control lugs. The joint shall provide a minimum seal of 
90 kPa on concrete and polyethylene pipe, and 190 kPa 
on PVC pipe. 
  Add 2.3.8.4  Rubber couplings for gravity sewers shall have stainless 
  steel shear bands along the body of the coupling. 
2.5  Granular Pipe  Add 2.5.3  Pipe  bedding  shall  be  19  mm  clear  crushed  rock  or  as 
Bedding and    approved by the Contract Administrator and the City. 
Surround   
 
Material 

3.0 EXECUTION     

3.8  Connections to  Delete 3.8.3 and  For new connections to existing PVC mainlines 250 mm 


Existing Mainline  replace with the  and smaller shall be made by removal of the section of 
Pipe  following  the main and replacement with a preformed extrusion 
  molded  PVC  wye  fittings  complete  with  stubs  and 
double hub PVC couplings for PVC mains and approved 
shear band couplings for other mainline materials. 
For new connections to existing mainline greater than 
250 mm use of insertable tee will be permitted. 
 
 
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 33  MMCD SECTION 33 30 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  UTILITIES   SS PAGE 96  
SUPPLEMENTARY SPECIFICATIONS  Sanitary Sewers  2016 
 
3.10  Service  Delete 3.10.3 and  Inspection  chambers  shall  be  provided  on  all  sanitary 
Connection  replace with the  service connections as per Standard Detail Drawing S7. 
Installation  following  If  inspection  chamber  is  located  in  driveway,  lane,  or 
  paved surface, Series 37 concrete box with lid shall be 
installed as per Standard Detail Drawing S9. 
 
3.18  Video Inspection  Delete 3.18.1 and  The  contractor  shall  video  inspect  completed  sanitary 
replace with the  sewers  under  900 mm  in  diameter  and  all  service 
following  connections  following  completion  of  the  installation.  
The video inspection report shall be in a form specified 
by the Contract Administrator and the City.  Copies of 
the video DVD and written report shall be forwarded to 
the  Contract  Administator  and  the  City.    Refer  to 
Section 33 01 30.1 and 33 01 30.1S CCTV Inspection of 
Pipelines. 
3.21  Permanent  Add 3.21.1  Permanent  capping  of  existing  sanitary  service 
Capping of  connections  to  be  completed  as  per  Coquitlam 
Service  Standard Detail Drawing COQ‐S18. 
Connections 
  Add 3.21.2  A trenchless method of permanently capping a service 
may be required on an arterial road or on a road which 
has  been  paved  within  5  years,  as  directed  by  the 
Manager.  
 
The trenchless technology used to cap the service must 
be approved by the Manager. 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 33  MMCD SECTION 33 34 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  UTILITIES   SS PAGE 97  
SUPPLEMENTARY SPECIFICATIONS  Sewage Force Mains  2016 
 
MMCD Section 33 34 01S  Sewage Force Mains 
 
2.0 PRODUCTS     

2.3  Valves and Valve  Delete 2.3.5.1.1   


Boxes 

2.5  Granular Pipe  Delete 2.5.1 and  Pipe bedding and surrounding material shall be Type 1 


Bedding and  replace with the  as  specified  in  Section  31  05  17  –  Aggregates  and 
Surround  following  Granular Materials.  
Material   

3.0 EXECUTION     

3.15  Pressure Testing  Delete 3.15.2 and  Pipeline  to  be  submitted  to  a  test  of  1.5  x  Working 
Procedure  replace with the  pressure  applied  at  highest  elevation  in  each  section 
  following  minimum  700  kPa.  At  no  time  shall  test  pressure 
exceed  pipe  or  thrust  restraint  design  pressures.  
Maximum  allowable  leakage  rate  at  test  pressure  to 
not  exceed  1.25  litres  per  millimetre  diameter  of  pipe 
per  kilometre  per  24  hour  period.  Minimum  duration 
of test period to be 2 hours. 
 
 
   

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 33  MMCD SECTION 33 40 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  UTILITIES   SS PAGE 98  
SUPPLEMENTARY SPECIFICATIONS  Storm Sewers  2016 
 
MMCD Section 33 40 01S  Storm Sewers 
 
2.0 PRODUCTS     

2.2  PVC Pipe,  Delete 2.2.1 pipe  200 mm dia. – 375 mm dia. to ASTM D3034 


Mainline Smooth  size ranges and 
450 mm dia. – 1,200 mm dia. to ASTM F679 
Wall  replace with the 
following 
2.3  PVC Pipe,  Delete 2.3   
Mainline Profile 

2.6  Service  Delete 2.6.1 and  Storm  service  connectons  to  be  PVC  DR  28  150  mm 
Connections  replace with the  diameter minimum or as specified on Contract Drawings.  
following 
  Delete 2.6.8.1   
  Delete 2.6.8.2 and  Connections  to  PVC  pipe  to  be  made  with  a  performed 
replace with the  wye  fitting  where  mainline  pipe  is  300  mm  diameter  or 
following  smaller.  For connections to PVC mainline pipe larger than 
300  mm  diameter  an  insertable  tee  for  PVC  pipe  is 
 
permitted.  
  Add 2.6.8.3  Insertable  tee  fitting  shall  have  a  rubber  collar  which 
inserts  into  the  mainline  pipe  to  form  a  tight  seal  and 
shall  have  stainless  steel  band  to  secure  the  tee  insert. 
The  tee  insert  shall  be  a  standard  bell  end  with  depth 
control lugs. The joint shall provide a minimum seal of 90 
kPa  on  concrete  and  polyethylene  pipe,  and  190  kPa  on 
PVC pipe. 
2.9  Granular Pipe  Delete 2.9.3   Pipe  bedding  shall  be  19  mm  clear  crushed  rock  or  as 
Bedding and  approved by the Contract Administrator and the City. 
Surround   
Material 

3.0 EXECUTION   

3.8  Connections to  Delete 3.8.3 and  For  new  connections  to  existing,  smooth  wall  or  profile, 
Existing Mainline  replace with the  mainline  sewers  300  mm  and  smaller,  shall  be  made  by 
Pipe  following  removal of the section of the main and replacement with 
  a  preformed  PVC  wye  fitting  complete  with  stubs  and 
double  hub  PVC  couplings  for  PVC  mains  and  approved 
shear band couplings for other mainline materials. 
For  new  connections  to  existing  mainline  greater  than 
300 mm, use of insertable tee will be permitted. 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 33  MMCD SECTION 33 40 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  UTILITIES   SS PAGE 99  
SUPPLEMENTARY SPECIFICATIONS  Storm Sewers  2016 
 
3.10  Service  Delete 3.10.3  Inspection  chambers  shall  be  provided  on  all  storm 
Connection  replace with the  service connections as per Standard Detail Drawing S7.  If 
Installation  following  inspection chamber is located in driveway, lane, or paved 
  surface,  Series  37  Brooks  concrete  box  with  lid  shall  be 
installed as per Standard Detail Drawing S9. 
3.12  Inspection and    The contractor shall video inspect completed storm 
Testing  sewers under 900 mm in diameter and all service 
  connections following completion of the installation.  The 
video inspection report shall be in a form specified by the 
Contract Administrator and the City.  Copies of the video 
DVD and written report shall be forwarded to the 
Contract Administator and the City.  Refer to Section 33 
01 30.1 and 33 01 30.1S CCTV Inspection of Pipelines. 
3.16  Permanent  Add 3.16.1  Permanent  capping  of  existing  storm  sewer  connections 
Capping of  to  be  completed  as  per  Coquitlam  Standard  Detail 
Service  Drawing COQ‐S18. 
Connections 
  Add 3.16.2  A  trenchless  method  of  permanently  capping  a  service 
may  be  required  on  an  arterial  road  or  on  a  road  which 
has  been  paved  within  5  years,  as  directed  by  the 
Manager. 
The  trenchless  technology  used  to  cap  the  service  must 
be approved by the Manager. 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 33  MMCD SECTION 33 42 13S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  UTILITIES   SS PAGE 100  
SUPPLEMENTARY SPECIFICATIONS  Pipe Culverts  2016 
 
 
MMCD Section 33 42 13S  Pipe Culverts 
 
3.0 EXECUTION     
 
3.10  Endwalls  Delete 3.10 and  Construct  endwalls  as  shown  on  Standard  Detail 
replace with the  Drawings S14, S15, Coquitlam Standard Detail Drawing 
following  COQ‐S15A  or  as  shown  otherwise  on  contract 
  drawings. 
 
 
 
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 33  MMCD SECTION 33 44 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  UTILITIES   SS PAGE 101  
SUPPLEMENTARY SPECIFICATIONS  Manholes and Catchbasins  2016 
 
 
MMCD Section 33 44 01S  Manholes and Catchbasins 
 
1.0 GENERAL     
 
1.1  Related Work  Add 1.1.6  Hot Mix Asphalt Concrete  
  Pavement  Section 32 12 16 
 
  Add 1.1.7  Portland Cement Concrete  
  Paving  Section 32 13 13 
 
2.0 PRODUCTS     

2.1  Materials  Add 2.1.7.3  Any frame and cover assembly creating a point load on 


the concrete riser rings will not be permitted. 
 
  Delete 2.1.12 and  Catchbasin lids manufactured to ASTM C478M 
replace with the 
following 
     
Delete 2.1.16.2 
     
Delete 2.1.17 
     
     
3.0 EXECUTION     
     
3.1  Excavation and  Add 3.1.2  For  manholes,  when  base  gravels  are  complete, 
Backfill    excavate for grade rings and manhole frame assembly.  
  Do  not  disturb  the  compacted  road  base  beyond  the 
excavation requirement. 
 
3.3  Manhole  Delete 3.3.12.2  Allowable  products  are  precast  concrete  risers  and 
Installation  and replace with  cast‐in‐place form system.  Individual riser heights shall 
the following  be 50mm, 75mm, or 100mm. 
     
Delete 3.3.12.5  Proper  layer  of  grout  between  the  spacers,  covering 
and replace with  the entire surface of the rings, should be utilized. 
the following 
     
Delete 3.3.15 and  Install  drop  structures  as  shown  on  the  contract 
replace with the  drawings  to  Coquitlam  Standard  Detail  Drawing  COQ‐
following  S4  and  Standard  Detail  Drawing  S3.  Maximum 
allowable inside ramp shall be 250 mm invert to invert. 
     
Delete 3.3.17 and  Ensure frames conform to design contour of pavement 
replace with the  or  existing  surface.  Manhole  lids  left  raised  in 
following  preparation for overlay paving shall have a rubberized 
  protector  ring  or  asphalt  ramp.    The  use  of  riser  rings 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


CITY OF COQUITLAM  DIVISION 33  MMCD SECTION 33 44 01S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  UTILITIES   SS PAGE 102  
SUPPLEMENTARY SPECIFICATIONS  Manholes and Catchbasins  2016 
 
 
  for adjusting manhole frames will not be permitted. 
 
3.5  Catchbasin  Delete 3.5.1 and  Install  catchbasins  as  shown  on  Coquitlam  Standard 
Installation  replace with the  Detail  Drawings  COQ‐S11A,  COQ‐S11B  and  Standard 
following  Detail  Drawing  S11,  to  general  standards  and 
  installation  procedures  described  under  3.3  of  this 
Section. 
 
 

File #: 11-5330-01/000/2015-1 Doc #: 2105578.v4A


SUPPLEMENTARY SPECIFICATIONS  
DIVISION 34 – TRANSPORTATION 
CITY OF COQUITLAM  DIVISION 34  MMCD SECTION 34 41 13S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  TRANSPORTATION  SS PAGE 104  
SUPPLEMENTARY SPECIFICATIONS  Traffic Signals  2016 
 
MMCD Section 34 41 13S  Traffic Signals 
 
1.0 GENERAL     

1.3  Shop Drawings  Delete 1.3.4 and  Shop  drawings  for  pole  structures,  where  required,  to 
replace with the  be  sealed  by  a  Professional  Engineer  registered  in 
following   British Columbia. 
   
1.4  Electrical Energy  Add 1.4.4  The  Electrical  Contractor  will  process  a  letter  of 
Supply    application  to  the  City  of  Coquitlam  for  the  Utility 
Company and attain all required permits.  
 
1.5  Contractor  Add 1.5.3  All  on‐site  traffic  signal  installations  shall  be  under  the 
Qualifications    responsibility of a primary journeyman  electrician with 
IMSA  Level  2  Signal  Certification  and  have  successfully 
completed  at  least  five  (5)  traffic  signal  system 
installations.  This  primary  journeyman  electrician  is 
expected to have to be at the Place of Work and report 
work progress to City of Coquitlam’s Traffic Operations 
staff,  in  addition  to  reporting  to  the  Contract 
Administrator. 
 
  Add 1.5.4  Fibre Optic Cable: 
.1  All  fibre  optic  cable  installations  workmanship, 
material  and/or  installation  practices  and  activity 
will  be  equal  to  or  better  than  the  standards 
established  by  the  CAN/CSA  T529‐530‐M90 
Standards and the Canadian Electrical Code. 
.2  Those  retained  to  complete  the  work  must  be 
authorized,  trained  and  certified  by  the 
manufacturers  they  represent.  They  must  have  a 
minimum of two (2) years experience installing and 
testing  multimode  and  single  mode  cables  of  all 
types  as  well  as  experience  with  LC  and  SC 
connectors. 
.3  Those  retained  to  complete  the  work  must  have 
experience  installing  cabling  for  FDDI  (Distribution 
System  Data  Interface)  compliant  100  Mbit/sec, 
SONET, ATM, Token Ring or Ethernet networks using 
industry accepted systems and practices. Experience 
with  leading  manufactures  fiber  products  and 
systems would be beneficial. 
.4  Those  retained  to  complete  the  work  must  be 
prepared, trained and equipped to properly test the 
fibre cabling system, including the fibre transmission 
media  and  connectors.  Each  optical  fibre  of  each 
section of cable will be tested using an "Optical Time 
Domain  Reflectometer"  (OTDR)  and  will  meet  the 
CITY OF COQUITLAM  DIVISION 34  MMCD SECTION 34 41 13S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  TRANSPORTATION  SS PAGE 105  
SUPPLEMENTARY SPECIFICATIONS  Traffic Signals  2016 
 
specifications  before  installation.  After  installation 
an  "Optical  Light‐loss  Testing  Sets"  (OLTS)  will  be 
mandatory  to  determine  cable  length,  locate  any 
fibre  breaks  or  anomalies,  measure  attenuation  of 
fibre's,  connectors  and  assess  fibre  uniformity. 
Those retained to complete the work will provide a 
report  showing  all  values  measured  during  these 
tests. 
1.6  Permits and  Add 1.6.5  Contractor shall provide the BC Safety Electrical Permit, 
Tests    and arrange all inspections with the City. The inspection 
entails,  but  not  limited  to,  Coquitlam’s  “Intersection 
and Cabinet Start‐up Checklist”, which can be obtained 
from Coquitlam’s Traffic Operations staff. 
 
1.8  Record Drawings  Add 1.8.2  Final payment(s) will be withheld until record drawings 
are received.  
2.0 PRODUCTS     

2.1  General   Delete 2.1.2 and  All  products  supplied  to  be  new,  in  accordance  with 
replace with the  Contract Documents. All products are to meet Canadian 
following  Electrical Code requirements and be certified by either 
CSA,  UL©,  or  Intertek  Testing  Systems  (Warnock 
Hersey) and be supplied with the certifier’s label. 
 
  Delete 2.1.3 and  All  products  shall  be  in  accordance  with  the  City  of 
replace with the  Coquitlam’s  List  of  Approved  Materials  and  Products 
following  List.  Any  products  not  listed  with  in  the  Approved  List 
  shall default to the current BCMOTI specification. 
 
  Delete 2.1.5 and  Equipment models listed within the City of Coquitlam’s 
replace with the  List  of  Approved  Materials  and  Products  shall  be 
following  confirmed  with  the  City  immediately  prior  to  their 
  order  to  ensure  that  they  are  current.  Cut‐sheets, 
equipment  make,  model  and  serial  number  list  to  be 
provided  to  the  City  by  the  Contractor  for  each  traffic 
signal  location.  Material  supplied  by  City  of  Coquitlam 
and  installed  by  Contractor,  shall  be  shown  in  the 
Contract Documents.  
 
2.2  Conduit  Add 2.2.1.3  All exposed metallic surfaces to be hot dip galvanized.  
 
2.3  Trench marker  Add 2.3.2  Detectable  (manetic)  market  tape  shall  be  used  in  all 
Tape   trenches  containing  interconnecton  (communications) 
conduit.  

2.5  Concrete  Delete 2.5 and  Refer to the City of Coquitlam’s List of Approved 


Junction Boxes   replace with the  Materials and Products. For Concrete Vaults: Refer to 
following  Coquitlam Standard Detail Drawing SS‐E2.5. 
 
CITY OF COQUITLAM  DIVISION 34  MMCD SECTION 34 41 13S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  TRANSPORTATION  SS PAGE 106  
SUPPLEMENTARY SPECIFICATIONS  Traffic Signals  2016 
 
2.8  Conductor Tags   Delete 2.8 and  Refer to the City of Coquitlam’s List of Approved 
replace with the  Materials and Products. 
following   
 
2.10  Fuse and Fuse  Delete 2.10 and  Refer to the City of Coquitlam’s List of Approved 
Holders  replace with the  Materials and Products. 
following   
 
2.11  Service Panels  Add 2.11.5   Refer to the City of Coquitlam’s List of Approved 
  Materials and Products. 
 
2.16  Traffic and  Delete 2.16.1 and  Traffic  signal  heads  to  be  yellow  polycarbonate  with 
Pedestrian  replace with the  300  mm  round  signal  indications,  and  conform  to 
Signals  following  Section  601  Signal  and  Pedestrian  Heads  BCMOTI 
  E&SMS V1. All primary and secondary signal heads shall 
have yellow aluminum backboards with 75 mm border 
of  yellow  prismatic  retro‐reflective  sheeting  (3MTM 
ScotchliteTM  Diamond  GradeTM  VIP  Reflective  Sheeting 
Series 3990 or approved alternate).  
 
  Delete 2.16.2 and  Fire  signal  head  assembly  as  per  Coquitlam  Standard 
replace with the  Detail Drawing SS‐E5.19. 
following   
 
  Add 2.16.3  Signal  head  backboards  with  plumbizer  gaps  or  knock 
  out sections will not be accepted for adjustable bracket 
signal head mounting method. 
 
2.17  LED Signal  Delete 2.17 and  Refer to the City of Coquitlam’s List of Approved 
Modules  replace with the  Materials and Products. 
following   
 
 
2.19  Signal Mounting  Add 2.19.8  Primary signal head safety cable to be 3/32” 
Hardware    galvanized steel aircraft cable. 
 
  Add 2.19.9  Refer to the City of Coquitlam’s List of Approved 
  Materials and Products. 
 
2.20  Audible Signals  Delete 2.20 and  Refer to the City of Coquitlam’s List of Approved 
replace with the  Materials and Products. 
following   
 
2.21  Pedestrian  Delete 2.21 and  Refer to the City of Coquitlam’s List of Approved 
/Cyclist  replace with the  Materials and Products. 
Pushbuttons  following   
 
2.22  Luminaires  Add 2.22.6   Refer to the City of Coquitlam’s List of Approved 
  Materials and Products. 
CITY OF COQUITLAM  DIVISION 34  MMCD SECTION 34 41 13S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  TRANSPORTATION  SS PAGE 107  
SUPPLEMENTARY SPECIFICATIONS  Traffic Signals  2016 
 
2.29  Illuminated  Delete 2.29 and  Refer to the City of Coquitlam’s List of Approved 
Crosswalk Signs  replace with the  Materials and Products. Illuminated sign safety cable 
following  to be 3/32” galvanized steel aircraft cable. 
3.0 EXECUTION     
 
3.1  General   Add 3.1.5  During  the  installation  of  the  traffic  signal  system, 
  maintain  the  existing  traffic  signal  and/or  signs  as 
noted  on  the  Contract  Drawing.  If  temporary  or 
permanent  relocations  of  related  traffic  signal 
equipment or signs are required, such equipment shall 
be  reinstated  as  required  under  the  Contract 
Documents  or  as  directed  by  the  Contract 
Administrator. 
3.3  Concrete Bases  Add 3.3.7  Concrete  service  bases  detailed  on  Standard  Detail 
  Drawings  CE1.3  and  CE1.4,  Type  C1  and  C3  service 
bases  shall  have  five  (5)  conduits.  See  Coquitlam 
Standard Detail Drawing SS‐E7.3. 
  Add 3.3.8  Lifting  cables  on  concrete  controller  bases  shall  be 
  removed after base installation. 
  Add 3.3.9  All  concrete  bases  shall  be  pre‐cast  concrete  only, 
  unless  noted  on  Contract  Drawing  or  directed  by  the 
Contract Administrator.  
3.4  Junction Boxes  Delete 3.4.1 and  Install  junction  boxes  as  shown  on  Standard  Detail 
and Vaults   replace with the  Drawings  E2.2  to  E2.4.  Install  vaults  as  shown  on 
following  Coquitlam Standard Detail Drawing SS‐E2.5. 
  Add 3.4.5  Bell  end  fittings  shall  be  installed  in  all  conduits 
  entering junction boxes or vaults. 
  Add 3.4.6  Junction  boxes  requiring  3  or  more  sections  must  be 
  approved by the City of Coquitlam’s Traffic Operations 
staff. 
  Add 3.4.7  All junction boxes shall be provided with RPVC bars to 
support  electrical  connections  and  fuse  holders.  The 
RPVC bars shall be attached into the junction box side 
walls with the electrical connections/fuse holders tie‐
wrapped in place and installed in the up‐right position. 
3.5  Underground  Delete 3.5.2 and  Minimum  cover  over  conduits  to  be  600  mm  in 
Conduit  replace with the  boulevard areas and 900 mm in roadway areas. 
following 
 
CITY OF COQUITLAM  DIVISION 34  MMCD SECTION 34 41 13S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  TRANSPORTATION  SS PAGE 108  
SUPPLEMENTARY SPECIFICATIONS  Traffic Signals  2016 
 
  Delete 3.5.3 and  Place  trench  marker  tape  300  mm  above  installed 
replace with the  conduit in trench. Trench marker tape not required for 
following  conduits installed via trenchless technology. 
  Delete 3.5.5 and  Empty  conduits  shall  have  a  No.  8  HB  Yellow/Green 
replace with the  Mk pull string and capped at both ends. 
following 
  Add 3.5.6  Conduit run shall contain no more than the equivalent 
  of 4 – 90 degree bends. 
  Add 3.5.7   Conduits shall be blown out with compressed air, from 
  both  ends  if  necessary,  then  swabbed  out  to  remove 
stones, dirt, water and other material which may have 
entered during installation. 
  Add 3.5.8  All  conduits  entering  poles  and  cabinets  shall  be 
  sealed with “Duct Seal”. 
  Add 3.5.9  Conduit  depth  of  bury  to  be  recorded  when  a 
  trenchless technology method is used. 
  Add 3.5.10  Traffic  signal  communications  conduit  shall  enter  and 
  leave  junction  boxes  through  bell  end  fittings  in  the 
horizontal  position  (no  bends)  and  shall  run  straight 
through the junction box unless a change in alignment 
occurs,  or  as  otherwise  specified  on  the  Contract 
Drawing. 
  Add 3.5.11  Conduit  shall  not  be  bent  in  the  field.  Only  factory 
bends will be accepted. 
3.7  Traffic Signal and  Delete 3.7.1 and  Install  traffic  signal  and  pedestrian  signal  heads  as 
Pedestrian Head  replace with the  shown  and  Standard  Detail  Drawings  E5.2  and  E5.9 
Mounting  following  only.  Banding  straps  shall  be  used  for  primary  signal 
  heads. 
  Add 3.7.5  Primary traffic signal heads shall be safety cabled to 
  the traffic signal pole arm using 3/32” galvanized steel 
aircraft cable looped through the traffic signal 
backboard and fastened with a rope clip. 

3.8  Audible Signals   Delete 3.8.1 and  Install  audible  signal  in  accordance  with  Coquitlam 
replace with the  Standard Detail Drawing SS‐E5.12. 
following 
3.10  Luminaires and  Add 3.10.4  NEMA  wattage  label  shall  be  visible  at  the  bottom  of 
Photocells   the luminaire on all fixtures. 
CITY OF COQUITLAM  DIVISION 34  MMCD SECTION 34 41 13S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  TRANSPORTATION  SS PAGE 109  
SUPPLEMENTARY SPECIFICATIONS  Traffic Signals  2016 
 
3.13  Electrical Service  Delete 3.13.1 and  Mount  electrical  service  panels  in  service  base  or  on 
Panels  replace with the  poles as shown on Standard Detail Drawings E7.2, E7.6 
following  to E7.9, as well as Coquitlam Standard Detail Drawings 
SS‐E7.3 to SS‐E7.5. 
3.14  Wiring   Delete 3.14.3 and  With  the  exception  of  conductor  spliced  of  detector 
replace with the  loop  wires  to  shield  cables,  make  conductor  splice  in 
following  pole handholes. Make splices of detector loop wires to 
shielded cable in junction boxes.  
  Delete 3.14.13  Bond  all  signal  heads  and  luminaires  with  No.  12 
and replace with  RW90  green  conductor,  and  steel  junction  box  lids 
the following  with No. 8 RW90 green conductor. 
  Add 3.14.14   Detector  loop  cable  splices  shall  be  soldered  with 
rosin  core  solder  (no  acid  core  or  acid  flux)  then  cap 
with waterproof gel filled wire nut and tape with vinyl 
di‐electric tape. Suspend and ty‐wrap splices at top of 
junction box with open end of wire nut pointing down. 
Loop  shield  drain  conductor  shall  cut  and  be  isolated 
from  the  system  ground.  See  Coquitlam  Standard 
Detail Drawing SS‐E8.4.  
3.16  Traffic Controller  Add 3.16.8   Silicone  sealant  shall  be  applied  to  both  sides  of  the 
rubber  gasket,  which  is  placed  between  the  traffic 
signal  cabinet  and  the  concrete  base  to  ensure  a 
weather tight seal. 
  Add 3.16.9  Traffic  cabinet  interior  shall  be  kept  dry  during 
inclement weather. 
3.17  Detector Loops   Delete 3.17.1 and  Detector loops are to be round type or as specified on 
replace with the  the  Contract  Drawing  and  approved  by  the  City  of 
following  Coquitlam’s  Traffic  Operations  staff.  Install  in 
accordance  with  Standard  Detail  Drawings  E8.1,  E8.3 
and  Coquitlam  Standard  Detail  Drawings  SS‐E8.2  and 
SS‐E8.4. 
  Add 3.17.3  Loops  in  adjacent  lanes  shall  be  wound  in  opposite 
  directions,  i.e.;  clockwise,  counter  clockwise, 
clockwise, etc. 
  Add 3.17.4  Detector  loops  should  be  installed  in  the  base  lift  of 
asphalt,  unless  otherwise  specified  by  the  Contract 
Administrator. 
3.19  Advance  Add 3.19.2  Contrary  to  Standard  Detail  Drawing  E10.3,  Item  A 
Warning Signs    shall  be  a  300  mm  signal  head  section  with  LED 
display. 
 
CITY OF COQUITLAM  DIVISION 34  MMCD SECTION 34 41 13S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  TRANSPORTATION  SS PAGE 110  
SUPPLEMENTARY SPECIFICATIONS  Traffic Signals  2016 
 
  Add 3.19.3  Advance warning signs shall have yellow prismatic 
  retro‐reflective sheeting (3MTM ScotchliteTM Diamond 
GradeTM VIP Reflective Sheeting Series 3990 or 
approved alternate). 
3.20  Grounding &  Add 3.20.5  Ground plates and grounding conductors are to have a 
Bonding     minimum  of  5  meters  clearance  between  them  and 
other utility grounding. 
  Add 3.20.6  Grounding rod or plate electrodes shall not be 
  installed inside the traffic signal cabinet base. 
  Add 3.20.7  Remove  all  paint  around  bonding  studs  on  inside  of 
  pole to expose the galvanized or metal surface prior to 
bonding equipment. 
3.22  Pole Finish  Delete 3.22 and  .1 Prior  to  producing  a  powder  finish  product  the 
Application   replace with the  supplier  must  provide  a  Certificate  of  Compliance 
following  indicating  that  they  have  met  or  exceeded  the 
  following  specifications.  The  supplier  will  name 
their  independent  testing  agency  and  this 
information  will  be  submitted  to  the  City  for  their 
files. 
.2 The application process will be as follows: 
.1 The pole or product will be hot dip galvanized. 
.2 Powder will only be applied after the product is 
completely  fabricated.  No  welding  or  bending 
will take place after the powder is applied. 
.3 The pole or product will be thoroughly cleaned 
by brush blasting in accordance with SSPC‐SP7. 
The brush blast will maintain a minimum profile 
of 0.5 mils. If brush blasting is done off site then 
the  product  will  be  covered  and  shielded  from 
any  dirt  or  moisture  during  its  return  to  the 
powder  applicators  facility.  Where  poles  or 
products are not kept clean and dry or have any 
signs  of  flash  rust  they  will  be  returned  for 
further brush blasting. 
.4 Once  at  the  applicators  facility  the  pole  or 
product  will  be  thoroughly  cleaned  and  dried 
with an air gun. All hand marks or grease spots 
will be cleaned with a mild solvent. 
.5 After  brush  blasting  the  entire  pole  or  product 
will  be  pre‐baked  in  an  oven  at  220  degrees  C 
for at least 30 minutes to 1 hour, depending on 
steel thickness. The pre‐baking must be done to 
prevent out‐gassing during the curing cycle. 
.6 The  base  powder  coat  will  then  be  applied 
electrostatically  while  the  pole  or  product  is 
cooling from the 220 degrees C pre‐bake period 
CITY OF COQUITLAM  DIVISION 34  MMCD SECTION 34 41 13S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  TRANSPORTATION  SS PAGE 111  
SUPPLEMENTARY SPECIFICATIONS  Traffic Signals  2016 
 
to  allow  the  powder  to  melt  and  fuse  to  the 
surface.  The  base  coat  will  be  a  minimum  of  3 
mils in thickness. 
.7 After  base  coat  is  applied  and  set  the  topcoat 
will be applied to a thickness of 3 to 5 mils. The 
pole  or  product  will  be  returned  to  the  oven 
and  heated  to  190  to  220  degrees  C 
(temperature  will  not  exceed  pre‐bake)  for  a 
minimum  of  25  minutes,  depending  on  steel 
thickness. Thicker product material may require 
longer  bake  cycles  to  fully  cure.  Upon  removal 
of the pole or product from the oven it will be 
left  to  rest  until  the  pole  or  product  is  cool 
enough to the touch. 
.8 Once  the  topcoat  has  cured  and  the  poles  or 
product  cooled,  they  will  then  be  individually 
wrapped  (min  4”  overlapping  method)  with 
1/8”  foam  wrap  over  the  entire  pole  or 
product.  The  poles  or  product  will  be  bundled 
together  and  separated  with  suitable  wood 
dunnage  to  avoid  contact  between  the  poles, 
product  or  other  bundles.  All  bundles 
themselves will be fully wrapped with foam and 
with stretch‐wrap as noted above. The poles or 
products  will  be  handled  and  shipped  with 
great  care  to  prevent  damage;  damaged 
product  will  be  cause  for  rejection  of  the 
item(s). 
.3 Testing process will be as follows: 
.1 Each run of product in an oven will have at least 
one sample tested for: 
.2 Adhesion  –  The  finished  powder  surface  will 
have minimum pull‐off strength exceeding 1000 
PSI as tested in accordance with ASTM D4541. 
.3 Quality  –  The  finished  powder  surface  will  be 
free  from  any  holidays  (skips  or  misses)  as 
tested  in  accordance  with  ASTM  D4541.  The 
product will also be free from wrinkles, orange 
peel,  cracking,  pinholes,  fish  eyes,  blisters,  etc 
by visual inspection. 
.4 Color – The color will be verified to be within 3 
DE of specialized color. 
.5 An  independent  firm  such  as  CanSpec  Testing 
who  are  qualified  to  test  powder  finish  will  do 
the testing at the supplier’s expense. The result 
of  tests  must  accompany  the  Certificate  of 
Compliance  and  will  be  made  available  to  the 
CITY OF COQUITLAM  DIVISION 34  MMCD SECTION 34 41 13S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  TRANSPORTATION  SS PAGE 112  
SUPPLEMENTARY SPECIFICATIONS  Traffic Signals  2016 
 
City  or  their  representative  upon  request.  A 
supplier  who  fails  to  test  product  as  noted 
above will have their product rejected until the 
testing  is  completed  and  the  product  deemed 
acceptable by the testing agency.  
.6 Where  the  tested  product  fails  on  a  given 
production run then a minimum of 30 % of the 
entire production run will be tested. If no other 
failures  are  found  then  the  individual  failed 
product  will  be  stripped,  reapplied  and  re‐
tested  until  it  passes.  If  any  of  the  30%  of 
product  tested  fails  then  the  entire  order  will 
be  stripped,  reapplied  and  retested  until  it 
passes. 
.4 Field  repairs  will  be  undertaken  as  required  to  fix 
any  scratches  or  imperfections  in  the  final  finish. 
Field repairs will be done as follows: 
.1 Feather the damaged area with sandpaper. 
.2 Clean area with solvent. 
.3 Let dry. 
.4 Neatly  brush  on  an  application  of  Aliphatic 
Urethane Acrylic Semi‐Gloss High Build applied 
at  2‐4  mils  DFT  over  the  entire  sanded  and 
damaged  area.  The  ambient  conditions  will  be 
dry  and  over  10  degrees  C  when  the  paint  is 
applied. 
.5 The pole supplier will warranty the integrity of 
the  surface  for  a  minimum  of  1  year  from  the 
date of installation. The warranty will include all 
labour  and  materials  required  to  provide 
replacement  product  if  required.  The  powder 
finish  will  be  the  responsibility  of  the  pole 
supplier.  The  warranty  will  apply  to  fading, 
blistering, cracking or chipping of the surface. 
 
3.26  Uninterruptable  Add 3.26.2  Uninterruptable  power  supply/cabinet  to  be  installed 
Power Supply    on  the  side  of  the  traffic  controller  cabinet  as  detailed 
on the Contract Drawing and Coquitlam Standard Detail 
Drawing SS‐E7.24.  
 
3.28  Illuminated  Add 3.28.1  Install illuminated street name signs as detailed on the 
Street Name    Contract  Drawing  and  Coquitlam  Standard  Detail 
Signs  Drawing SS‐E5.18 
 
CITY OF COQUITLAM  DIVISION 34  MMCD SECTION 34 41 13S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  TRANSPORTATION  SS PAGE 113  
SUPPLEMENTARY SPECIFICATIONS  Traffic Signals  2016 
 
  Add 3.28.2  Illuminated street  name signs shall be  safety cabled to 
the  traffic signal pole arm using 3/32”  galvanized steel 
aircraft cable. 
3.29  Emergency  Add 3.29.1  Emergency  vehicle  pre‐emption  system  to  be  installed 
Vehicle Pre‐   as  detailed  on  the  Contract  Drawing  and  Coquitlam 
emption  Standard Detail Drawing SS‐E5.16.  
  Add 3.29.2  Cable  shall  be  continuous  with  a  minimum  of  2m  of 
cable slack to be provided at each end, with no splices. 
Cabinet termination to be completed by City.  
3.30  PTZ/CCTV  Add 3.30.1  PTZ/CCTV  cameras  to  be  installed  as  detailed  on  the 
Cameras    Contract  Drawing.  Contact  the  City  of  Coquitlam’s 
Traffic Operations staff prior to installation.  
  Add 3.30.2  Cable  shall  be  continuous  with  a  minimum  of  2m  of 
cable slack to be provided at each end, with no splices. 
Cabinet termination to be completed by City. 
3.31  Radio  Add 3.31.1  Radio  communications  equipment  to  be  installed  as 
Communications    detailed  on  the  Contract  Drawing.  Contact  the  City  of 
Equipment  Coquitlam’s Traffic Operations staff prior to installation. 
  Add 3.31.2  Cable  shall  be  continuous  with  a  minimum  of  2m  of 
cable  slack  to  be  provided  at  each  end,  and  with  no 
splices. Cabinet termination to be completed by City. 
3.32  Owner Supplied  Add 3.32.1  Those  retained  to  complete  the  work  must  notify  the 
Materials    City in writing (seven) 7 days prior to the time materials 
  are required. 
  Add 3.32.2  Unless otherwise noted, those retained to complete the 
  work will make all necessary arrangements and pay all 
costs for the collection of the materials and for delivery 
to the Place of Work. They will assume responsibility for 
materials at the time they are picked up. 
  Add 3.32.3  Owner  supplied  materials  generally  consist  of  the 
  following: 
.1 Traffic controller equipment and cabinet. 
.2 Uninterruptable  power  supply  equipment  and 
cabinet. 
.3 Emergency pre‐emption equipment. 
The exact list of materials supplied by the Owner to be 
confirmed with the City of Coquitlam Traffic Operations 
staff and Contract Administrator. In the case of private 
development projects requiring City supplied materials, 
the  cost  for  supply  and  installation  of  these  materials 
will be borne by the Developer. 
3.33  Fibre Optic Cable  Add 3.33  .1 Fibre  optic  cables  will  be  terminated  to  a  twelve 
    (12) port LC coupler panel. 
CITY OF COQUITLAM  DIVISION 34  MMCD SECTION 34 41 13S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  TRANSPORTATION  SS PAGE 114  
SUPPLEMENTARY SPECIFICATIONS  Traffic Signals  2016 
 
.2 When  installing  Fibre  Optic  Communications 
Conduit,  Fibre  optic  warning  tape  (150  mm  wide 
orange  plastic  tape  labelled  "WARNING  FIBRE 
OPTIC  COMMUNICATIONS  CABLE")  and  Detectable 
(Magnetic)  marker  tape  is  to  be  placed  over  all 
conduits containing fibre optic cable.  
.3 During installation of new boxes or with all existing 
boxes  ensure  that  they  have  been  cleared  of  any 
soil,  sand  or  gravel  and  other  materials  that  have 
accumulated in the base of the junction box. Ensure 
that  all  empty  conduits  have  a  proper  RPVC 
coupling  and  cap  inserted  (friction  fit  ‐  DO  NOT 
GLUE)  into  each  duct.  Once  the  conduit  is 
populated,  replace  cap  with  bell  coupling  and  glue 
in place. 
.4  All  communication  conduits  will  be  flushed  with 
water  and  dried  with  compressed  air.  This  process 
will  be  followed  by  pulling  through  a  suitable  size 
Blowing Mouse, a clean soft cloth and new No. 8 HB 
Yellow/Green Mk pull string  
.5 Perform  a  visual  inspection  of  the  proposed  cable 
route and be aware of any potential problem areas. 
Locations  in  which  cables  will  be  terminated  must 
be  inspected  and  plans  made  for  hardware  and 
cable  slack  storage.  Space  and  access  for 
termination of the cable should be considered prior 
to starting the job. Develop a cable placement plan 
based  upon  the  cable  route  survey  and  your 
available  equipment  and  personnel  resources. 
Submit  a  plan  to  the  City  for  acceptance  prior  to 
starting work. 
.6 Be aware that any damage due to excessive pulling, 
bending,  or  crushing,  may  alter  the  cable's 
transmission  characteristics  to  the  extent  that  the 
cable  section  will  have  to  be  replaced  at  the 
Project’s expense. 
.7 Fibre  optic  cables  will  be  installed  in  continuous 
runs in conduit between the traffic signal controller 
cabinets (no splices are allowed). 
.8 DO  NOT  EXCEED  THE  MINIMUM  BEND  RADIUS  OF 
THE  FIBRE.  During  installation  do  not  exceed  the 
minimum  bend  radius  as  specified  by  the 
manufacture.  
.9 DO NOT IMPROPERLY PULL OR EXCEED THE CABLE'S 
RATED  PULLING  TENSION  as  specified  by  the  cable 
manufacturer. Excess pulling may not actually break 
CITY OF COQUITLAM  DIVISION 34  MMCD SECTION 34 41 13S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  TRANSPORTATION  SS PAGE 115  
SUPPLEMENTARY SPECIFICATIONS  Traffic Signals  2016 
 
the  fibre,  but  it  can  cause  the  fibre  attenuation  to 
increase  so  that  the  installed  system  may  not 
operate within the specified requirements. 
.10 DO NOT EXCEED THE VERTICAL RISE SPECIFICATION 
as  specified  by  the  cable  manufacturer  unless 
intermediate tension relief is used. Secure the cable 
to new or existing supports wherever possible.  
.11 Take  precautions  to  protect  reeled  and  unreeled 
cable  from  any  source  of  damage,  whether 
attended  or  unattended.  Be  particularly  careful 
with  pre‐connected  sections  of  cable  produced  to 
meet  specific  length  requirements  as  any  damage 
to the cable may require replacement of the entire 
section.  
.12 If  the  cable  must  be  unreeled  during  installation, 
the  "figure‐‐eight"  configuration  should  be  used  to 
prevent kinking or twisting. Do not coil the cable in 
a  continuous  direction  except  for  lengths  of  30 
meters  or  less.  The  preferred  size  of  the 
"figure‐eight"  is  about  4.5  meters  in  length,  with 
each  loop  about  1.5  meters  to  2.4  meters  in 
diameter. 
.13 If  a  cable  puller  is  used,  ensure  that  the 
recommended  pulling  tension  of  the  cable  is  not 
exceeded.  Do  not  pull  through  junction  boxes, 
especially  90‐degree  conduit  fittings,  unless 
precautions  are  taken  to  maintain  the  minimum 
bend radius. 
.14 When  installing  cable  in  conduits,  ensure  the 
conduit does not exceed the minimum bend radius. 
Avoid  pull  boxes  unless  the  maximum  bend  radius 
can  be  maintained.  In  controller  cabinets,  fibre 
optic  cables  will  be  tied  together  with  ty‐wraps. 
Each  cable  will  be  labelled  within  10  cm  of  the 
terminated  ends  with  a  tag  and  text  stating  the 
street  intersection  of  the  opposite  cable  end. 
Cables  will  be  tagged  in  the  controller  cabinet  and 
all other access points with "CAUTION, FIBRE OPTIC 
CABLE"  tags.  Leave  enough  cable  slack  at 
termination  points  to  allow  the  cable  to  be  routed 
through  the  termination  hardware  to  a 
polishing/splicing  table,  plus  a  minimum  of  3 
meters  additional  slack.  Cable  slack  will  be  coiled 
and  secured  with  Velcro  ties  for  breakaway 
protection.  Cable  to  termination  panel  will  be 
secured to cabinet with ty‐wraps 
CITY OF COQUITLAM  DIVISION 34  MMCD SECTION 34 41 13S 
ENGINEERING AND PUBLIC WORKS DEPARTMENT  TRANSPORTATION  SS PAGE 116  
SUPPLEMENTARY SPECIFICATIONS  Traffic Signals  2016 
 
.15 If  cable  lubricants  are  necessary,  ensure  that  they 
are compatible with the cable's outer sheath. Refer 
to  the  lubricant  specification  sheet  to  ensure 
compatibility.  In  all  cases  avoid  the  use  of 
detergent‐based  lubricants,  as  these  types  of 
lubricants promote stress cracks. 
.16 Excess  cable  inside  pull  boxes  will  be  coiled  and 
mechanically  secured  in  place  with  Velcro  straps 
such that the minimum bend radius is not exceeded 
and the cable is suspended above the pull box. The 
Velcro straps are to provide `breakaway' protection 
in  the  event  of  an  accidental  dig‐up  between  pull 
boxes. 
.17 Adhesive  warning  labels  3M  –  5016  –  FO  type  or 
accepted  alternate  will  be  affixed  to  each  fibre 
optic  cable  in  each  access  point.  Access  points 
include  pull  boxes  and  traffic  signal  controller 
cabinets.  Decal  strip  holders,  3M  –  5012  or 
accepted alternate, will be used and will be secured 
in  place  using  cable  ties.  Warning  labels  will  be 
oriented so they are visible and are not blocked by 
other cables or equipment. 
.18 After  installation,  each  segment  of  each  fibre  will 
be  tested  using  an  Optical  Time  Domain 
Reflectometer  (OTDR)  and  power  meter 
equipment.  Testing  will  be  done  in  each  direction 
on  each  fibre  and  at  both  1310nm  and  1550nm 
wavelengths.  Launch  cable  will  be  used  as  per  the 
OTDR manufacturer’s specifications. Those retained 
to complete the work will provide a report detailing 
the results of each test including OTDR test results 
in  graphical  format,  cable  length,  any  fibre  breaks 
or anomalies, attenuation of fibre’s, connectors and 
fibre uniformity. 
.19 Final testing and inspection of the cable installation 
will be conducted with the City on‐site. 
 
STANDARD
DETAIL
DRAWINGS
Standard Detail Drawings
General Details
Trench Details For Standard Section COQ-G4
Storm and Sanitary Sewers
Inside Drop Manhole COQ-S4
Side Inlet Catch Basin Assembly COQ-S11A
Typical Top Inlet Catch Basin With Offset Sump COQ-S11B
Storm Sewer Ditch Inlet COQ-S13A
Driveway Culvert With Concrete Block Endwalls COQ-S15A
Manhole Cover & Frame COQ-S16
Forcemain Service Connection Detail COQ-S17
Permanent Cap For Sanitary And Storm Services COQ-S18
Waterworks
Water Service Connection 19 to 38mm Diameter COQ-W2b
Water Service Connection 50mm Diameter COQ-W2e
Typical Water Service Connection 100mm Diameter and Greater COQ-W2f
Permanent Cap For Water Services 19mm to 25mm Only COQ-W2g
Permanent Cap For Water Services 19mm to 50mm with Gate Valve At Main COQ-W2h
Permanent Cap For Water Service 100mm & Larger with Gate Valve At Main COQ-W2i
Water Service Connection Replacement (Re-Use Ex. Corporation Stop) COQ-W2j
25mm Double Acting Air Release Valve COQ-W6
Typical Watermain Blow-Off Assembly COQ-W8
Transportation
Arterial Streets COQ-R2A
Collector Streets COQ-R2B
Local Streets COQ-R2C
25.2m R.O.W. Higher Density Community Collector With Cycle Track COQ-R3
Arterial, Collector & Local Streets Boulevard COQ-R4
Hillside Local Streets Boulevards COQ-R5
Hillside Local Streets COQ-R6
Narrow Street COQ-R7
Rural Street COQ-R8
Standard Lane (New) Construction COQ-R9
Primary Access Lane 8.0m Right-of-Way COQ-R10
Standard Lane Construction (Existing) COQ-R11
25.2m Community – 20.0m Collector Intersection COQ-R12
25.2m Community – 17.4m Local Intersection COQ-R13
20.m Collector – 17.4m Local Intersection COQ-R14
17.4m Local Street Intersection (Low Density) COQ-R15
20.0m Collector Street and Industrial /Service Commercial 4-Way Intersection COQ-R16
20.0m Standard Collector Street 3-Way Intersection COQ-R17
Collector or Higher Density Local 4-Way Intersection w/ Curb Extensions COQ-R18
Collector or Higher Density Local 3-Way Intersection COQ-R19
Curb Extensions And On-Street Parking Bay COQ-R20
High Density Urban Walkway Greenway or Cycle Route 6.0m Row COQ-R21
Urban Walkway Non-Cycling Route 3.0m Row COQ-R22
Walkway Details COQ-R23
Lane Turn Around COQ-R24
Pre-Cast Reinforced Concrete ‘No-Post’ Barrier COQ-R25

File #: 11-5210-01/000/2016-1 Doc #: 2212744.v1 1


Concrete and Miscellaneous Details
Tree Protection Fence COQ-R26
Boulevard – Sidewalk Utility Strip COQ-C1
Curb On Gravel Base COQ-C6
Local, Collector Crossing Of Curb, Gutter And Sidewalk COQ-C7
Industrial, Commercial Sidewalk Crossing With Driveway COQ-C7A
Typical Curb/Sidewalk Driveway Letdown- Separated Sidewalk COQ-C7B
Monolithic Sidewalk COQ-C8
Single Letdown at Intersection Boulevard Less Than 3m COQ-C9A
Monolithic Wheelchair Ramp For Sidewalk COQ-C9B
Single Letdown at Intersection Boulevard Less Than 3m With Tactile COQ-C9C
Split Letdown at Intersection With Boulevard COQ-C9D
Tactile Strip Placement COQ-C9E
Stairway Details COQ-C15
Typical Handrail Details For Stairs With Bicycle Ramp COQ-C16
Stormwater Management
Perforated Pipe Subdrain COQ-SW1
Curb Cut COQ-SW2
Boulevard Retention Trench (Low Side Of The Road) COQ-SW3
Boulevard Retention Trench (High Side Of Road) COQ-SW4
Boulevard Lawn Basin With Retention Trench COQ-SW5
Curb Bulge Rain Garden COQ-SW6
Permeable Pavement With Exfiltration To Soil Subgrade COQ-SW7
Green Lane Standard COQ-SW8
Green Lane Standard Plan and Profile COQ-SW9
Irrigation
Double Check Assembly (Model: Watt 007QT) COQ-I1
Electrical
Concrete Vault SS-E2.5
Audible Signals SS-E5.12
Emtrac Antenna Mounting Details SS-E5.16
UPS (“On Battery”) Indicator Light Detail SS-E5.17
Illuminated Street Name Sign Mounting Details SS-E5.18
Fire Signal Head Mounting Details SS-E5.19
Service Panel In Service Base (Mounting Details) SS-E7.3
Service Panel In Service Base (Panel Details) SS-E7.4
40A & 60A (120/240V) Street Lighting Service Panel In Service (Wiring Diagram) SS-E7.5
Typical Street Tree Lighting Receptacle Detail (New Installations) SS-E7.19
Typical Post Mounted Tree Receptacle Detail SS-E7.20
Street Lighting and Tree Receptacle Service Panel Detail (In Service Base) SS-E7.21
Street Tree Lighting Installations Details (For ‘Short’ Pedestrian Scale Poles) SS-E7.22
Street Tree Lighting Installations Details (For ‘Tall’ Roadway Poles) SS-E7.23
UPS Field Wiring Diagram SS-E7.24
Detector Loops SS-E8.2
Detector Loop to Shielded Cable Splices SS-E8.4
Round Steel Sign Post Installations Details SS-E11.1
Trapezoidal Concrete Base For Round Steel Sign Post (Precast) SS-E11.2
Landscaping
Street Tree – Metal Grate In Hard Service COQ-L1A
Street Tree – Metal Grate In Hard Service COQ-L1B

File #: 11-5210-01/000/2016-1 Doc #: 2212744.v1 2


Boulevard Tree Planting Without Swale COQ-L2A
Boulevard Tree Planting With Swale COQ-L2B
Boulevard Tree Planting Behind Sidewalk COQ-L2C
Median Type 1 Trees, Shrubs With Apron COQ-L3A
Median Type 2 Trees With Lawn COQ-L3B
Shrub Planting COQ-L4
Fence Type 1 Single Rail Trail Fence COQ-L5A
Fence Type 2 Double Rail Trail Fence COQ-L5B
Trail Marker Trail Entry And Park Fence COQ-L6
Aggregate Trail COQ-L7
Removable Steel Bollard COQ-L8

File #: 11-5210-01/000/2016-1 Doc #: 2212744.v1 3


2/7/2014 2:41:58 PM, Plotted By: R.F.

City of Coquitlam

SS-E2.5
2/7/2014 2:45:23 PM, Plotted By: R.F.

City of Coquitlam

SS-E5.12
City of Coquitlam

Ave.
Street Name
2/7/2014 2:45:35 PM, Plotted By: R.F.

SS-E5.16
2/7/2014 2:45:48 PM, Plotted By: R.F.

City of Coquitlam

SS-E5.17
2/7/2014 2:46:02 PM, Plotted By: R.F.

City of Coquitlam

SS-E5.18
2/7/2014 2:46:16 PM, Plotted By: R.F.

City of Coquitlam

SS-E5.19
2/7/2014 2:46:28 PM, Plotted By: R.F.

City of Coquitlam

SS-E7.3
2/7/2014 2:46:41 PM, Plotted By: R.F.

City of Coquitlam

SS-E7.4
2/7/2014 2:46:54 PM, Plotted By: R.F.

City of Coquitlam

SS-E7.5
2/7/2014 2:47:07 PM, Plotted By: R.F.

City of Coquitlam

SS-E7.19
2/7/2014 2:47:22 PM, Plotted By: R.F.

City of Coquitlam

SS-E7.20
2/7/2014 2:47:38 PM, Plotted By: R.F.

City of Coquitlam

SS-E7.21
2/7/2014 2:47:49 PM, Plotted By: R.F.

City of Coquitlam

SS-E7.22
2/7/2014 2:48:03 PM, Plotted By: R.F.

City of Coquitlam

SS-E7.23
2/7/2014 2:48:20 PM, Plotted By: R.F.

City of Coquitlam

SS-E7.24
2/7/2014 2:48:32 PM, Plotted By: R.F.

City of Coquitlam

SS-E8.2
2/7/2014 2:48:51 PM, Plotted By: R.F.

City of Coquitlam

SS-E8.4

You might also like