Bill of Quantities and Cost Breakdown Electrical Work: Project: Capstan Project

Download as xls, pdf, or txt
Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1/ 1

PROJECT : CAPSTAN PROJECT

BILL OF QUANTITIES AND COST BREAKDOWN


ELECTRICAL WORK
Rev.0

LABOR MATERIAL EQUIPMENT OTHERS TOTAL COST REMARKS


FWBS CODE DESCRIPTION UNIT QUANTITY MANHOURS Php/MH COST Php/BQ COST COST COST (12)
(1) (2) (3) (4) (5) (6) (7)=(5x6) (8) (9)=(4x8) (10) (11) =(7+9+10+11)

1380 GENERAL
1 Scaffolding
1.1 Supply, erection and dismantling scaffolding Set 1
1.2 Mobilization and transfortation Set 1

2 Cable Trench
2.1 Excavation M3 192
2.2 Sand Filling M3 119
2.3 Back Filling M3 72
2.4 Cable Protection Tile M2 240
Cable Warning Sheet M2 240

1381 SUBSTATION EQUIPMENT


1 Motor Control Center-MCC
Supply and install of the following MCC according to typical
installation details:
1.1 Low Voltage MCC (MCC-JETTY1-301) Panel 1
Suitable for Outdoor Application
1.2 Low Voltage MCC (MCC-JETTY2-301) Panel 1
Suitable for Outdoor Application

1382 POWER WORK


1 Local Control Station pcs 10
Supply and install of LCS, according to typical installation details
Explosionproof Zone2, IIA, IIB T3, Start Push Buttons
with emergency stop, indicator lights and selector swich for
forward and reverse motor direction.

2 Cabling and wiring


Supply and install of cable

2.1 LV Power Cable, 0.6/1 kV