Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Ethics Assignment Questions

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 13
At a glance
Powered by AI
The document discusses various scenarios involving engineers and their responsibilities to safety. Key aspects include enforcing safety protocols, addressing unsafe practices, and determining when to escalate issues up the management chain or to regulatory bodies.

Engineer A should continue escalating the safety issues by directly contacting the appropriate regulatory body and filing a formal complaint about the unsafe operations and management's refusal to address the problems.

Engineer A and Geoscientist B should work together to document the safety issues and file a formal report with the mine safety regulator given management's unwillingness to address the problems.

VelTechRangarajanDr.

Sagunthala R&D Institute of Science and Technology

(Deemed to be University Estd. u/s 3 of UGC Act, 1956)

SCHOOL OF COMPUTING

DEPARTMENT OF CSE

1151CS111- COMPUTER NETWORKS

Assignment-1 Questions

Faculty Name: Dr.K.Arthi Slot: S6

Group Question Vtu No.


No.
1. Engineer A was Chief Engineer of a plant that processed raw ore. The
refining process involved several dangerous chemicals, which were re-
captured and recirculated; however, careful operation was essential to
prevent these chemicals from escaping into the wastewater. Engineer A
worked alongside the Operations Manager, and both of them reported to
the Plant Director. Engineer A was responsible for technical matters, such
as design, maintenance, and safety. The Operations Manager was
responsible for hiring, scheduling, and meeting production targets. Both
the Operations Manager and the Plant Director were older than Engineer vtu10191
A, but neither was a Professional Engineer nor a Professional Geoscientist. vtu10196
During the first few months on the job, Engineer A reviewed,
vtu10293
updated, and improved the plantOperating Manual prepared by the
previous Chief Engineer. Engineer A ensured that copies ofthe manual
were available to the plant operating staff and personally conducted
several trainingsessions for key operating staff. In spite of these efforts,
however, Engineer A observed manyinfractions of the Operating Manual
throughout the plant, and he could see that the toxicchemicals were
possibly escaping into the wastewater. Engineer A considered this lax
attitudetoward safety to be very risky. Tests of the wastewater effluent
showed wide variations of theescaping chemicals, with concentrations that
occasionally reached the legal limits. On severaloccasions, Engineer A
initiated disciplinary measures against operating staff, but these weredealt
with lightly by the Operations Manager, for whom the staff worked.
Engineer A eventuallycame to understand that the Operations Manager put
production ahead of safety and was casualabout enforcing the safety
provisions in the Operating Manual.
Finally, Engineer A warned the Operations Manager about these
unsafe practices in writing anddemanded that infractions be disciplined
more severely. As a last resort, Engineer A wentdirectly to the Plant
Director and explained the problem, but the Director simply said, “Work
itout among yourselves.”
Question: If you were Engineer A, what would you do at this point?

2. Engineer A, the Chief Engineer for a long-established mine,


engagedGeoscientist B to study the mine operations and to devise more
efficient methods for extractingore from the old mine. During a site
inspection, the geoscientist travelled down the shaft into thedrifts
(tunnels) which led to the ore face. During this detailed tour of the mine,
Geoscientist Bobserved many infractions of safety provisions: methane
detectors were missing from the deepestparts of the mine; ventilation was vtu10637
poor in many areas of the mine; shoring was old and appearedto be vtu10642
deteriorating; thick dust covered equipment and could have been a source
vtu10645
of dangerousdust explosions. Although Geoscientist B had not been hired
to examine mine safety, thegeoscientist nevertheless mentioned these
concerns to Engineer A, who agreed that safety was amajor worry.
Engineer A explained that several proposals for safety improvements had
beenmade over the years, but the senior mine management had rejected
them, citing the marginalprofitability of the mine and the fact that costly
changes could cause the mine to close.
Question: If you were Engineer A or Geoscientist B, what would you do at
this point?

3. Engineer A, who recently moved to British Columbia from Ontario,learned


from a classmate at a reunion that a mining company needed a design for a
bridge over acreek, near a mine in the mountains. Engineer A had designed
a single-lane timber loggingbridge over a creek in northwestern Ontario
but had no other bridge experience. He approachedthe mining company,
stated that he had extensive experience in bridge engineering,
andeventually received the contract for the design. The site was at the base vtu10777
of a steep slope, and the creek was full of rocky debris. No flow records vtu11130
were available for the creek, so Engineer Adetermined the span and
vtu11154
clearance based on the creek’s high-water marks. He felt that the sitewas
adequate and did not arrange for geotechnical investigation or advice. He
designed astandard concrete box-girder bridge with a 15 m span and pile-
driven abutments. A buildingcontract was also hired. The contractor was
familiar with mine construction and mechanicalplants, but had no
experience in bridges. Nevertheless, the construction went smoothly.
Thebridge served well for five years, but a debris torrent during a
particularly rainy winter seasondestroyed the bridge in the sixth year.
Question: Did Engineer A act ethically in this project?

4. Engineer A, an experienced civil engineer, was engaged by


anenvironmental advocacy organization to provide a report on past road-
building practice by amajor forest company, in a forested area where
cutting ceased in the late 1970s. He found manyexamples of road-building
practice that, over the past 25 years, had led to serious erosion.Engineer A vtu11184
photographed and described these obsolete practices in his report, to vtu11245
illustrate whatdamage they can cause and why they must be avoided. The
vtu11252
environmental advocacy organizationused the report in a submission to
government, urging tighter enforcement of road-buildingregulations.
Engineer A then wrote an article for a national magazine in which
he castigated the governmentand the forest company and called on readers
to mount a “write-in” campaign. He also impliedthat the forest company
might still be using these poor road-building practices. Engineer A
laterstated that he believed that this “hard-hitting” approach would help to
get the article published.In the magazine article, Engineer A acknowledged
the assistance he received from the logging superintendent of the forest
company, but did not mention that the environmental
advocacyorganization had financed his study.
A reporter on a local weekly newspaper read the magazine article
and wrote a “rehash” of thearticle. That is, the reporter wrote a newspaper
story, based on the article, but implying that thestory was the result of a
personal interview—a questionable journalistic practice. In the
newspaper story, the facts were simplified and made even a little more
“hard-hitting.” Thereporter pretended to quote Engineer A as saying that
the forest company’s unacceptable roadbuildingpractice was “still
widespread throughout the province.” Before publication, the
reporterphoned Engineer A, to justify the claim that the story was an
interview. The reporter explainedthat she had written the story from the
magazine article, but it was too long to read over thetelephone. She gave a
rough verbal outline. Engineer A said he was satisfied with the story,which
then appeared in the next issue of the newspaper.
The forest company, after reading the magazine article and the newspaper
story, felt that they cooperatedwith a constructive attempt to study and
improve road-building practices, but they had,instead, been misled and
defamed. They complained to the provincial Association and asked
theAssociation to discipline Engineer A.
Question: Should Engineer A be disciplined? If so, on what basis?

5. Engineer A was a member of an ad-hoc citizens’ committee, whichwanted


the municipality to build a small recreation centre in their neighbourhood.
The ad-hoccommittee believed that the Municipal Council would not
approve the project if they knew thetrue estimated cost. Engineer A vtu11347
volunteered to prepare a “low-ball” estimate for constructing therecreation vtu11348
centre, at about 60 percent of the realistic likely cost, and the ad-hoc
vtu11381
committeeformally presented this estimate to the Council. The committee
presented Engineer A as anindependent and impartial consultant. There
was no information in the documents submitted to show that Engineer A
resided in the neighbourhood or was, in fact, a member of the ad-
hoccommittee making the proposal.
Question: Did Engineer A act ethically in this project?

6. An equipment dealer was developing a new depot (warehouse) in a


smalltown. A large architecture/engineering firm from a distant city
designed the building for thedepot. Engineer A was Project Manager for the
firm. Engineer B, a sole practitioner, lived in thesmall town and offered her
services to Engineer A, to perform site inspection. She said that heroffice
was close to the site, and she could easily serve as a resident engineer.
Although theproject was large, Engineer A declined Engineer B’s offer vtu11404
because there was not enough moneyin the fixed-sum contract to cover the vtu11618
costs of a resident engineer. Instead, Engineer A intendedto make short
vtu11620
visits to the site, every second week, on a regular basis.The depot building
was to be built of concrete block, with a partial second storey for
offices.There was some structural steel in travellers and roof trusses. The
foundation for the walls was astrip footing, about 1.2 m below grade. When
the contractor excavated for the footing, theground was uneven, and the
contractor poured one side of the strip footing on exposed,thoroughly
frozen ground. This work was done while Engineer A was absent from the
site andbackfilled before his next visit. Engineer B observed how the
pouring had been done andreported it to Engineer A. She again offered her
services, offering to reduce the cost by attendingthe site only at critical
stages, on short notice from the contractor, when these critical
eventsoccurred between Engineer A’s visits. Engineer A again declined and
took no action with respectto her report of poor workmanship in the
footing construction.
Question: Was Engineer A acting in a professional manner by attempting to
monitor and inspect
a project from a distant location?

7. Engineer A is the only civil engineer in a small town in a remote area


ofCanada; the other engineers in the area are all mining engineers.
Engineer A has a broadbackground, including sewer and water, roads,
bridges, structural design, and buildingconstruction and inspection. His
wife owns four commercial buildings in the downtown area. Ona sunny
day last summer, a major earthquake shook the town and caused
widespread damage.Although there were no deaths, several people were
injured, and several of the largest and oldestcommercial buildings suffered
significant cracking and settlement. Many buildings were built
ofunreinforced masonry, and a few had obvious cracks. Immediate
structural inspection wasessential before authorities could allow people to vtu11628
re-enter the buildings to live and work. vtu11644
The Town Administrator asked Engineer A to undertake a contract
vtu12213
for immediate structuralinspection of the damaged buildings. Engineer A
declined. He explained that his wife ownedfour of the buildings requiring
inspection, and it would be a clear conflict of interest if he were toinspect
his wife’s property. The Town Engineer asked whether Engineer A would
skip herproperty and just inspect the buildings owned by others. Engineer
A again declined, saying thatif he condemned any of the buildings, he
would still have a perceived conflict of interest, sincehis wife was in
competition with other owners for tenants. Moreover, in this crisis he
shouldassist his wife to rehabilitate her buildings and could not place her
behind other owners in asimilar situation.
The Town Administrator stressed the emergency nature of the
situation. He pointed out thatoutside help was unavailable because of poor
road conditions and also because other engineerswere busy, dealing with
other communities that were similarly affected.
Question: Does Engineer A have a conflict of interest? What should he do?

8. Engineer A was hired as an electrical engineer by Company B, a


smallmanufacturer of control systems for heavy lifting equipment used by
loggers and contractors.The total market consisted of about 200 logging
firms, and the company had about a quarter ofthat market. That is, about
50 of the logging firms used the control system and were repeatcustomers,
providing about 90 percent of Company B’s sales volume. The control
system wasnot patented. Although the device was patentable, Company B’s
owner had decided to keep theconcept secret, and all employees, including vtu12220
Engineer A, signed trade secret documents, agreeingthat they would not vtu12517
disclose or otherwise duplicate, use, or sell the concept.
vtu13154
After about three years as an employee, Engineer A resigned from
Company B to set up her ownfirm. She designed a more advanced control
device, improving upon the concept invented byCompany B. To sell her
device, Engineer A contacted Company B’s 50 key repeat customers toget
them to switch allegiance to her new firm and to her improved product.
Company B usedEngineer A in civil court for breach of the confidentiality
agreement, and won the case. In herdefence, Engineer A stated that, during
her employment at Company B, she became aware offlaws in the original
device and her improved device overcame those flaws.
Testimonyconfirmed that she had never told colleagues at Company B that
she was aware of such flaws,nor did she suggest improvements to the
device while employed there. After the civil courtjudgment, the owner of
Company B asked the provincial Association to discipline Engineer Afor
unprofessional conduct.
Question: Is Engineer A guilty of professional misconduct?

9. Engineer A was one of several consultants asked to submit proposals fora


feasibility study for a deep-water bulk-loading facility on the client’s site.
To increase thechances of getting the assignment, Engineer A submitted a
proposal with a very low fee, whichwas about half the realistic fee for the
work. The reasoning behind the low fee was that theconsultant who got the
feasibility study would be better placed to win the subsequent—and far vtu13186
more lucrative—design competition (providing, of course, that the client vtu13372
decided to go aheadwith the proposed facility).Engineer A won the
vtu14248
contract for the feasibility study and found that the study required far
moretime and expense than originally envisioned. The contract payments
covered only about 40percent of the actual costs. However, the most
depressing part was that Engineer A’s studyrevealed that
soil conditions would require very deep piles to support the massive
quay-side equipment;
railway links and highway connections were far from the site;
the harbour did not have enough depth for bulk carriers without
dredging; and
prevailing winds and wave action would cause constant problems for
ships waiting to moor.
In other words, it really was not economically feasible to construct the
bulk-loading facility on
the site, and Engineer A’s final report explained this fact. Engineer A had
spent several months
on a project that had cost money to complete.
Question: Was Engineer A’s behaviour ethical?

10. Engineer A had been practising engineering for over two decades; butfor
the past 10 years, she has been in a management position: supervising
traffic flowmeasurements and highway planning for the provincial
government. Recently, she left thegovernment job to enter private practice,
and one of her first contracts was to design a structurethat had to satisfy
the National Building Code. Although Engineer A had extensive vtu14276
experiencewith this type of structure prior to entering government service, vtu14303
she had not designed suchstructures for more than10 years. She was
vtu14334
aware that there had been some changes to theBuilding Code in recent
years, but she was very familiar with the older code, and she argued
thatthe old code was likely to be over-conservative. To be certain that the
structure was safe, Engineer A increased the design loads required by the
code by an additional 10 percent, andprepared, signed, and sealed the
construction drawings.
The client submitted the drawings to the municipality for approval. Upon
inspection, themunicipal engineer immediately recognized that the
wording and style indicated that theengineer had followed the older
building code. Moreover, some load data required by the morerecent
building code was missing. The municipal engineer rejected the drawings.
The clientcomplained to the provincial Association.
Question: Should the Association discipline Engineer A for professional
misconduct?

11. Engineer A, a recent university graduate, moved to a small town


afterobtaining the P.Eng. designation and was hired by Engineer B, who
had a small civil engineeringconsulting firm. The firm included a technician
and a secretary. Within a few months of arriving,Engineer A was elected to
the executive of the local chapter of the Association. There wereseveral
towns in the chapter territory, and the evening meetings were in different
townsthroughout the year. To get to the more-distant meetings on time, vtu14335
Engineer A had to leave workearly to allow travel time. Engineer A asked vtu14353
Engineer B for permission to leave work an hourearly, but offered to make
vtu14358
up the time by working late on other days. Leaving early would occurabout
twice per month (including executive meetings) but would not be a major
disruption, soEngineer B agreed. Engineer B rarely attended the monthly
chapter meetings. After a year of employment with the firm, Engineer A
expressed interest in taking a computersoftware course at a nearby
college. Although it was not a university-level course, it was directlyrelated
to the work that Engineer A was performing. It would have required
attendance on thecollege campus, three hours per week, for 10 weeks.
Engineer A asked for permission to attendthe course, offering to work late
on other days to make up the lost time. Engineer B refused thepermission,
saying that the work schedule was already disrupted when Engineer A left
early to
attend the chapter meetings. Engineer A decided not to take the course.
Question: Does the employer have an obligation to assist Engineer A in his
professional
activities?

12. Engineer A was Chief Engineer of a large manufacturing corporation.His


main responsibilities were product design and heavy manufacturing
(mainly metal cutting).He was also the head of the corporation’s
Specifications Committee, which set standards andspecifications for
purchasing new manufacturing equipment. He typically sent the
committee’sspecifications to the purchasing division, which solicited bids,
evaluated the bids in consultationwith the Specifications Committee, and
prepared the final purchase documents. The manager ofthe purchasing
department was a chartered accountant.
The sales agent for Company B, an equipment supplier, invited Engineer A
and his wife to jointhem for a week’s holiday in Mexico, at Company B’s vtu14395
expense. Since the purchasing department arranged all purchases, vtu14592
Engineer A did not feel that he had any conflict of interest in
vtu14624
acceptingCompany B’s generosity, so Engineer A and his wife left for an
enjoyable week in the sun.Shortly after his vacation, however, Engineer A
was informed by one of his assistants that anexpensive new numerically
controlled milling machine supplied by Company B was notproducing
close-tolerance parts reliably and appeared to have a defective
controller.Engineer A met with the purchasing manager and explained that
machinery supplied byCompany B appeared to be defective. The
purchasing manager contacted Company B and askedthem to repair or
replace the machine, which was still under warranty. Company B refused
tohonour the warranty, claiming the equipment was being used under
“speed and feed” conditionsthat exceeded specifications. Engineer A and
the purchasing manager then met with their boss,the corporation
president, to discuss the problem. After hearing the details, the
corporationpresident instructed Engineer A to deal with Company B
directly, concerning the technicalreasons for the poor-tolerance parts, and
if Company B would not honour the warranty, to begin
legal action to recover damages.
At this point, Engineer A explained that he had just spent a week in Mexico
with most of thestaff from Company B and would feel very awkward now
trying to take such a hard line withthem. The corporation president,
astounded at this news, agreed that Engineer A should have nofurther
dealings with this problem. He assigned the task of dealing with Company
B to thepurchasing director and told him to contact Engineer A’s assistant
for the technical informationneeded. Later that week, the president issued
a memo stating that Engineer A had “steppeddown” from the Specifications
Committee, and his assistant would replace him.
Question: Did Engineer A have a conflict of interest? Under what conditions
would it beacceptable to accept such a gift from supplier, client, or
professional colleague?

13. Engineer A was resident engineer on a construction project, with


theresponsibility for monitoring the quality of materials used and
inspecting the work quality.Occasionally, changes were necessary to the
plans and specifications. Since these changes werenot included in the
construction contract, the contractor was paid extra. Engineer A vtu14634
monitoredthe changes and approved these extra charges on behalf of the vtu7382
client, when they wereappropriate. However, Engineer A often disallowed
vtu7587
claims for “extras.” In fact, Engineer A hadcome to believe that the
contractor submitted a very low bid for this contract, expecting to makea
big profit on the “extras.”Near the end of the project, the contractor
submitted a claim for an extra payment that wasclearly inflated and
unreasonable. Engineer A was infuriated at the unprofessional attitude of
thecontractor and even angrier that the contractor would believe that a
professional engineer wouldagree to such flagrant over-billing. In anger,
Engineer A simply scribbled a rude four-letterexpression across the claim
in large letters and returned the document to the contractor.
Thecontractor complained to the client that Engineer A was unprofessional
and vindictive in refusingthis claim (and in refusing several earlier claims)
and sent a copy of the rude note as evidence ofEngineer A’s unprofessional
conduct.
Questions: Was Engineer A’s conduct unprofessional? When faced with
unprofessional conduct,
is it acceptable to respond with unprofessional conduct? What should
Engineer A have done?

14. A client hired Engineer A to design a small industrial building andprovide


field services (inspection) during the construction. The construction
contract went totender and was awarded to a contractor who started work
immediately. The contractor observedthat the structure appeared to be vtu7931
grossly over-strength, requiring piles and thick concrete pads,poured vtu8338
separately from the main floors of the building. This part of the structure
vtu8419
would be veryexpensive, requiring special sub-contracts for the piles and
complex concrete formwork. Thecontractor further observed that, based
on his experience constructing shopping malls, the costs would decrease
significantly. Presumably, the client and the contractor would split any
savings,so it was worth exploring.
To convince Engineer A to change the design, the contractor independently
engaged Engineer Bto review the design and prepare a report
recommending the change. Engineer B obtainedpreliminary design
information from the contractor, examined the drawings and
specifications,and then visited the site to examine the footing locations.
Engineer B did not contact Engineer A,
who was, in fact, on-site at the time.
Engineer B, after visiting the site and reviewing the drawings and soil
reports, could see noreason why this portion of the structure had to be so
strong. He wrote a report, which heprudently marked “preliminary,”
supporting the contractor’s cost-reduction proposal. Thecontractor sent
copies of the report to the client and to Engineer A, recommending a
deviationfrom the original design.
Question: Is it ethical for Engineer B to review the work of Engineer A under
thesecircumstances?

15.
A small town hired Engineer A, a consulting mechanical engineer, todesign
a water system that would replace their small public-utility system, fed
from several wellswith water of doubtful quality. Engineer A proposed to
pump water from a nearby river that had an adequate flow all year, but
was subject to intermittent ice jams that, on the average, stoppedthe flow
for about 6 to 12 hours, once each winter. She proposed to overcome this
stoppage byconstructing a small reservoir, which pumps would keep filled.
This reservoir had a volumeequal to 48 hours’ consumption. The electric
power lines serving the area were subject to icingand power failures,
which occurred, on the average, for about 12 hours, once per year. vtu8672
EngineerA proposed to maintain power by installing a standby diesel vtu8718
generator in the pump-house so thatwhen line power was lost, the
vtu8742
generator would power the pumps. She presented the concept tothe
municipal Council, and the daily newspaper reported the story.
On reading the newspaper story, Engineer B, a chemical engineer with no
water supplyexperience, concluded that Engineer A was putting the
taxpayers (including him) to unnecessaryexpense by installing the standby
pumps. Engineer B reasoned that the 48 hours’ supply in thereservoir
would be more than adequate to take care of both the ice-dams in the river
and thepower supply failure, even if both occurred simultaneously.
Without getting in contact withEngineer A, he immediately wrote a
stinging letter to the municipal Council, with a copy to thenewspaper,
identifying himself as a Professional Engineer and criticizing what he
called“unnecessary and expensive duplication.” The letter closed with a
flippant comment questioningeither Engineer A’s honesty or competence.
The municipal Council discussed the letter and,since a qualified engineer
wrote it, the Council concluded that it would be politically unwise toignore
it. The Council voted to ask Engineer A to respond in writing to Engineer
B’s allegations.
Engineer A was surprised at this request from the Council, but felt obliged
to honour it. Shedropped all other tasks and summarized her calculations
in a report, which she had printed and
bound. She then returned to the municipal Council the following week and
explained herreliability calculations, which confirmed the configuration
that she was recommending. Sheexplained that, while the newspaper story
quoted average values, her calculations required“worst-case” probabilities.
Moreover, the local hospital depended on the water supply andrequired
higher reliability. In addition, it was indeed statistically probable that the
ice-jams and
power failures would occur simultaneously. Other pumping or piping
components might also failand prolong a water shortage, or the ice cover
on the reservoir might limit the flow available.
Moreover, the proposal included a contingency for town expansion during
the next 40 years. Itsoon became clear that Engineer A’s proposal was a
very reasonable solution to the problem.Engineer A calculated her
additional time and report preparation costs at about $5,000. Whileshe
expected her design to undergo public scrutiny, she did not expect an
uninformed attack froma fellow engineer. She knew that the Code of Ethics
required public opinions to be founded upon“adequate knowledge and
honest conviction,” so she called the provincial Association to askwhether
such thoughtless public criticism from Engineer B was unprofessional
conduct.
Question: Was the opinion in Engineer B’s letter founded upon “adequate
knowledge andhonest conviction,” as required by almost every Code of
Ethics? Is Engineer B guilty ofunprofessional conduct?

16. Engineer A was a consultant in a specialty of process control. He had


asmall consulting firm, employing one computer technician and a shared
secretary. The specialtywas well paid, and Engineer A had no local
competitors. A large utility company hired EngineerA to design a key part
of a major gas distribution facility. Engineer B, an employee of the
gasutility, was resident engineer for the project, responsible for the site
installation. The projectinvolved several specialties, but since the system
was complex, changes frequently affectedeveryone, so close
communication and co-operation were essential. vtu8763
During the project, the utility company decided to revise the specifications, vtu8800
and many fieldchanges had to be made to Engineer A’s design in order to
vtu8801
accommodate the changes. EngineerA’s time was paid as an “extra.”
Nevertheless, Engineer B could rarely communicate withEngineer A, and it
was almost impossible to get a quick response. Although Engineer B
wasskilled in process control, Engineer B could not, of course, change
Engineer A’s design withoutcontacting him and receiving approval.
Eventually, Engineer B prepared a communications logof key calls and
meetings with Engineer A, which read as follows:
The first time B needed to contact A, he was unsuccessful. Engineer A
was absent on
vacation, but had not left his staff with a phone number.
(2) The next contact was successful, and A replied with a fax containing
details of the needed
change. However, the change later proved to be in error. Engineer A sent a
second fax with
correct data, the following day.
(3) The next contact was successful.
(4) & (5) The next contact required an early afternoon meeting at A’s
office. Engineer A
arrived 45 minutes late, provided no explanation, but clearly had
consumed alcohol. Engineer
B made an appointment for the next day and this meeting took place in a
satisfactory manner. (6) & (7) The next two contacts were successful.
(8) & (9) The next contact, by telephone, was satisfactory, and Engineer
A promised to fax a
drawing to B that day. The fax had not arrived by 4 pm, so B phoned A, but
was told by thesecretary that A had already left, and neither the secretary
nor the technician were aware ofthe promised drawing. Engineer B phoned
A the next day and A apologized profusely, sayingthe drawing was ready,
but he had simply forgotten to fax it. Engineer A sent the drawing byfax,
several hours later.
When the facility was completed, a dedication ceremony was held,
attended by workers,politicians, and local residents. Engineer B invited A
to attend, to sit on the platform and to beintroduced to the audience, but he
was not required to speak. Engineer A agreed to be there, but
did not show up. When contacted later, A said he had an urgent meeting
with another client and
forgot to phone to explain the change of plan.
Shortly after the completion of the project, Engineer A bid on a similar
design contract, but didnot receive it. When he contacted Engineer B to
discuss the loss of the contract, he was informed
that his lack of attention to the previous contract swayed the decision
against him.
Question: Was Engineer A negligent in his communication with Engineer B?
Was it appropriate
for Engineer B to consider the poor communication as a factor in awarding
the subsequentcontract?

17. Engineer A, a civil engineer specializing in road design, was hired


byLawyer B to assist as an expert witness in a lawsuit. Lawyer B’s client
was suing themunicipality for an automobile accident which resulted in
injuries. The injured client claimedthat the intersection where the accident
occurred was unsafe because of the municipality’snegligent design.
Engineer A examined the intersection and told Lawyer B that he thought vtu8809
thedesign might indeed be a contributing cause in the accident. Lawyer B vtu8847
then explained that theclient had no money, that Lawyer B was
vtu8852
representing the client on a contingency basis, andasked Engineer A to
prepare a report and appear in court on a contingency basis. Engineer
Aestimated that his fee should be $10,000, but because of the risk involved,
he would want$12,000 if the client won the case. (Of course, he would get
nothing if the client lost.) Lawyer Band the client agreed with this
arrangement, and engaged Engineer A on the $12,000 contingencybasis.
Question: Is it ethically appropriate for Engineer A to appear as an expert
witness on a
contingency basis?

18. Engineer A was a competent consulting engineer, specializing


inmanufacturing plant layout, but she was always very busy. A client asked
Engineer A to review aproposed plant layout and prepare an evaluation
report. Engineer A reluctantly agreed. Becauseof the pressure of other vtu8853
work, Engineer A assigned the task to an employee, Technologist B, vtu8948
whowas experienced in construction, but had little background in plant
vtu9014
layout.Technologist B did his best to evaluate the layout, but several key
points were beyond hisknowledge. Although he tried to get advice from
Engineer A, he was unable to do so, becauseEngineer A was always too
busy with her other projects. Technologist B finally prepared a draftreport
for Engineer A to correct and complete. Technologist B sent the report to
Engineer A witha note saying that the report was an incomplete draft and
that A should “give it detailed study.”By this time, Engineer A was even
busier than before, and she had to complete several majortasks before
going overseas for a month’s vacation. Engineer A simply had her secretary
reformatthe draft report and print it on high-quality paper. Engineer A
signed, sealed, and mailedthe report, without even reading it.

Questions: What clauses of the Code of Ethics have been violated by


Engineer A’s actions?
What disciplinary actions could she expect?

19. A long-established town was rapidly expanding in size because of


therecent development of a pulp-mill and a mine, both near the town. The
downtown was changingrapidly. New four-storey buildings were replacing
the old single-storey false-front buildings. Themain street, originally a two-
lane blacktop with rudimentary drainage ditches and short sectionsof
asphalt sidewalk, was being widened and improved. The town Council
envisioned a four-laneasphalt road with concrete curbs, gutters, and
sidewalks, and storm sewers with a long outfall.
The town would receive 25 percent of the capital cost of the project as a
grant from the province,but the town’s finances were low, and funding for
the balance was unavailable. However, thetown would be able to raise the
remaining 75 percent of the cost when the mill and mine were vtu9271
inproduction and tax revenues increased. The town therefore decided to vtu9411
proceed on a staged basis over four years, starting with the storm sewer
vtu9559
construction in the first year. The town engagedEngineer A to provide the
design and the field services.
Engineer A was aware that cost was an issue, and using an accepted
statistical approach, heproceeded to design the storm sewer based on a 20-
year storm, which he believed was theminimum capacity that was
reasonable under the circumstances. However, his preliminary cost
estimate was much higher than the town Council expected. After a brief
discussion, the clerk of
Council met with Engineer A, asked if costs could be further reduced, and
told him how muchmoney the Council believed that it could afford.
Engineer A accepted this cost limitation without
comment. He calculated that the limit could be met only if the criteria were
reduced to that for a
2-year storm, then he redesigned the storm sewer to this lower capacity.
The Council approved
the re-designed project, issued contracts for construction, and built the
storm sewer.
Question: Is it ethical for Engineer A to accept a cost limitation even when
he knows that it will
reduce the design below accepted standards? What should Engineer A have
done in this case?

20. The owner of a manufacturing firm hired Engineer A, a consultant


inprocess control, to assist in developing a new production line for
hydrocarbon distillation,involving high temperatures and toxic chemicals.
The owner welcomed her to the company andintroduced her to “Engineer
B.” Although “Engineer B” presented a business card stating that hewas a
Professional Engineer and the sign on his office door said “Chief Engineer,”
he was notactually licensed. The project required Engineer A to design the
new production line in conjunction with “Engineer B,” who would then
supervise the construction and commissioningof the new line.
Engineer A worked with “Engineer B” for several months, designing the
new production line,but gradually became aware that “Engineer B” lacked vtu9601
engineering knowledge in several basicareas. When she mentioned this to vtu9634
the owner privately, the owner admitted that “Engineer B”was not a
vtu9681
licensed engineer, but he had “many years” of experience, was very good at
producing
and selling the company’s product, and the “Chief Engineer” designation
gave him credibilitywith customers. The owner was aware that the new
line involved some dangerous components,
and that was why Engineer A was hired. Her job was to design the
dangerous parts of the lineand to sign any documents that required a
Professional Engineer’s qualifications. When EngineerA suggested that this
was a rather unprofessional arrangement, the owner pointed out that
sinceshe was designing the equipment, no harm would result. Moreover, if
“Engineer B” were aProfessional Engineer, then her services probably
would not be required. Although Engineer Acontinued to believe that this
arrangement was unprofessional, she took no action to report B tothe
provincial Association.
Question: Should Engineer A have reported the illegal actions of “Chief
Engineer” B?

21.
Geologist A was a groundwater specialist, licensed and employed as
ageological consultant in several provinces. While working on a project to vtu9690
develop safe waterwells in a remote municipality, Geologist A was vtu9806
dismayed by several ignorant comments madeby the political candidate
vtu9914
running for election in that riding. The candidate made several rash
anduninformed statements about oil-, gas-, and water-well drilling and vtu9929
criticized the provincialministry responsible for monitoring these
activities. Among other demands, the candidate calledfor the abolition of
all regulations on well drilling, claiming that they caused needless delays in
developing the province’s resources. Geologist A recognized these
comments as absurd electionrhetoric, but was amazed by the number of
people who called radio talk shows and wrote lettersto the local
newspaper supporting this opinion. The editor of the newspaper also
wrote a stirringeditorial supporting the candidate’s position.
Geologist A, although very busy with the groundwater development,
nevertheless felt aprofessional obligation to correct these rash statements.
As a professional geoscientist, withmany years in this field, Geologist A
wrote a polite but factual letter to the newspaper, withcopies to the
candidate and to the party leader, explaining that, unless well drilling is
carefullycontrolled, dangerous pollution of the water table can occur. Oil
and gas can migrate from onestratum to another, and since drilling
operations usually include the injection of various fluids,such as drilling
“mud,” or salt water (to increase pressure and production), these fluids
couldmigrate to the water table as well. Since the municipality was seeking
to develop moregroundwater sources, such pollution was not an idle or
academic matter. Moreover, Geologist Aconcluded the letter by
emphasizing that unless well sites are carefully documented, including
precise locations and the collection of data from well logs, then this lack of
information wouldimpede the search for new resources. To improve
resource development, the province shouldengage more professionals to
examine methods of improving the monitoring process, thusmaintaining
control without impeding developers.
The newspaper published the letter, and future editorials did not mention
the issue again. Thepoliticians acknowledged the receipt of Geologist A’s
letter, without comment. The candidatewho had proposed the reduction in
drilling regulations was narrowly defeated in the election.
Question:Although Geologist A was licensed in the province on a temporary
permit, he was aresident of another province. As a non-resident geoscientist,
was it ethical of him to express anopinion on a technical topic during an
election, or was he meddling?

You might also like