Rate Build Up
Rate Build Up
Rate Build Up
5 Mild steel bar Reinforcement - all sizes ( average ) 145,000.00 per Ton
6 High Tensile bar Reinforcement - all sizes ( average ) 156,000.00 per Ton
Paga 2
ATBU BAUCHI
12 Hollow burnt clay pots size 355 x 250 x 200mm high 300.00 each
13 Rib clay beam size 200 x 140 x 115mm high 250.00 each
15 .7mm Longspan Aluminium Roofing Sheet with alucrom finish 2,400.00 per Sq.m.
16 .7mm Longspan Aluminium Roofing Sheet with plain finish 2,400.00 per Sq.m.
17 .55mm Longspan Aluminium Roofing Sheet with alucrom finish 2,200.00 per Sq.m.
18 .55mm Longspan Aluminium Roofing Sheet with plain finish 1,700.00 per Sq.m.
19 .45mm Longspan Aluminium Roofing Sheet with plain finish 1,900.00 per Sq.m.
23. 44mm Semi-solid cored external quality plywood faced flush door 8,500.00 each
24. 44mm Semi-solid cored mansonia plywood faced flush door 12,000.00 each
Paga 3
ATBU BAUCHI
30 300 x 300 x 6mm Marazzi vitrified anti-acid unglazed ceramic 2,550.00 per Sq.m.
floor tiles
31 200 x 200 x 6mm Unglazed ceramic floor tiles 1,500.00 per Sq.m.
32 300 x 600 x 20mm Royale Perlato unpolished marble floor tiles 9,500.00 per Sq.m.
33 305 x 305 x 10mm Royale Perlato polished calibrated marble 9,500.00 per Sq.m.
wall tiles
34 300 x 300 x 12mm Polished CIBI African multi coloured
granite floor tiles 12,340.00 per Sq.m.
36 152 x 152 x 6mm White glazed cushioned edge ceramic wall tiles 950.00 per Sq.m.
37 152 x 200 x 6mm Coloured glazed cushioned edge ceramic wall tiles 1,000.00 per Sq.m.
39 245 x 64x 15mm Burnt clay facing bricks 3,500.00 per Sq.m.
43 6mm Asbestos cement Ceiling Sheets 850.00 per Sheet of 2.44 x 1.22 m.
46 150 x 5mm Clear sheet louvre blade 600mm long 200.00 each
47 150 x 5mm Clear sheet louvre blade 900mm long 280.00 each
Paga 4
ATBU BAUCHI QS 514
RATE COMPUTION
a. Labourer/day = 1,500.00
d. Carpenter = 2,500.00
e. Foreman = 2,500.00
Page./4
ATBU BAUCHI QS 514
Page./5
ATBU BAUCHI QS 514
B. CONCRETE WORK
Plant
Cost of hiring concrete mixer/day = 7,000.00
20 Litres deisel/day 20 @ 60.00 = 1,200.00
Lubricating oil @ N1300.00/gallon (4 litres) @
2.0 litres/day 2@ 325.00 = 650.00
Cost of plant/day = 8,850.00
Labour
Foreman/day 1@ 2500.00 = 2,500.00
Fitter (Labourer)/day 1@ 1500.00 = 1,500.00
Wheelers (Labourer)/day 4@ 1500.00 = 6,000.00
= 10,000.00
Add for tools @ 7.50% 750.00
Cost of gang/day = 10,750.00
Page./6
ATBU BAUCHI QS 514
Page./7
ATBU BAUCHI QS 514
Materials
1-tonne of reinforcement bars = 156,000.00
Add for cutting and waste @ 10% = 15,600.00
171,600.00
Add for tying wires a.b. = 1,716.00
Cost of Loading and off-loading a.b. = 806.25
Labour cutting, bending and fixing a.b. = 43,000.00
217,122.25
Add GOH & Profit @ 50% = 108,561.13
Cost/tonne = 325,683.38
Cost/Kg. = 325.68 Say = N 326 /Kg
10. BRC Mesh fabric reinforcement ref. No. A. 142 weighing 2.22Kg/m2
Materials
Cost of Mesh/m2 = 1,157.41
Add for tying wires, lapping at joints and waste = 173.61
1,331.02
Labour
Cost of gang /day a.b. = 4,300.00
Output of gang /day = 33.00 m2
Therefore cost of labour/m 2
= 130.30
1,461.32
Add GOH & Profit @ 50% = 730.66
Cost/m2 = 2,191.98 Say = N 2,192 /m2
Page./8
ATBU BAUCHI QS 514
Materials
Cost of timber for formwork/m3 = 28,000.00
Therefore cost of formwork plank size 25 x 300
x 3660mm 0.027 @ 28,000.00 = 768.60
Take 10m2
No. of planks in 10m2 = 9.11
Cost of sawn formwork planks 9.11 @ 768.60 = 7,000.00
Add for bearers, props, brackets etc @ 100% = 7,000.00
14,000.00
Add for waste @ 15% = 2,100.00
Cost of formwork materials useable - 3 times = 16,100.00
Page./9
ATBU BAUCHI QS 514
C. BLOCKWORK
1. 150mm Hollow Sandcrete blockwork filled solid with concrete (1:3:6-20mm aggregates) in substructure
Take 10m2
Materials
Sandcrete blocks/10m2 100 @ 100.00 = 10,000.00
Add for waste @ 10% = 1,000.00
11,000.00
m3 Cement and sand (1:6) mortar 0.20 @ 16249.14 = 3,249.83
Cost of materials = 14,249.83
Labour
2No. Masons /day @ 2500.00 = 5,000.00
2No. Labourers/day @ 1500.00 = 3,000.00
8,000.00
Add for tools @ 7.50% 600.00
Cost of gang/day 8,600.00
Output of gang/day 10.00 m2
Therefore cost of Labour = 8,600.00
22,849.83
Filling cavities with concrete
Volume of cavities of 10m2 in 150mm blocks = 0.57 m3
Concrete (1:3:6-20mm aggregates) 0.57 @ 17919.17 = 10,213.93
33,063.75
Add GOH & Profit @ 50% = 16,531.88
Cost / 10m2 = 49,595.63
Cost/m2 = 4,959.56 Say = N 4,960 /m2
2. 150mm Hollow Sandcrete blockwork filled solid with concrete (1:3:6-20mm aggregates) in superstructure
Page./10
ATBU BAUCHI QS 514
35,389.10
Add GOH & Profit @ 50% = 17,694.55
Cost / 10m2 53,083.65
Cost/m2 = 5,308.37 Say = N 5,308 /m2
Page./11
ATBU BAUCHI QS 514
5. 230mm Hollow Sandcrete blockwork filled solid with concrete (1:3:6-20mm aggre gates) in substructure
Take 10m2
Materials
100No. Sandcrete block/10m2 @ 150.00 = 15,000.00
Add for waste @ 10% = 1,500.00
Cost of materials 16,500.00
m3 Cement and sand (1:6) mortar 0.3 @ 16,249.14 = 4,874.74
21,374.74
Labour
Gang /day a.b. = 8600.00
Ouput of gang /day = 9.00 m2
Therefore cost of labour/10m2 = 9,555.56
30,930.30
Filling cavities
Volume of cavities of 10m2 in 230mm blocks = 1.20 m3
Concrete (1:3:6-20mm aggregates) @ 17919.17 = 21,503.00
52,433.30
Add GOH & Profit @ 50% = 26,216.65
Cost / 10m2 = 78,649.95
Cost/m2 = 7,864.99 Say = N 7,865 /m2
6. 230mm Hollow Sandcrete blockwork filled solid with concrete (1:3:6-20mm aggre gates) in superstructure
Page./12
ATBU BAUCHI QS 514
Page./13
ATBU BAUCHI QS 514
D. ROOFING COVERING
Take 10m2
Materials
10m2 of plain finish 10 @ 2,400.00 = 24,000.00
Allow for laps @ 15% = 3,600.00
27,600.00
Allow for screw nails and waste @ 10% = 2,760.00
Cost of materials = 30360.00
Labour
1No. Carpenter /day 1 @ 2500.00
1No. Labourers/day 1 @ 1500.00
Cost of labour = 4000
Add for tools @ 7.50% = 300.00
Cost of gang/8hr-day 4300.00
Output of gang / 2 hours 10.00 m2
Therefore cost of Labour/10m2 = 1,075.00
31,435.00
Add GOH & Profit @ 50% = 15,717.50
Cost / 10m2 = 47,152.50
Cost/m2 = 4,715.25 Say = N 4,715 /m2
Page./14
ATBU BAUCHI QS 514
Page./15
ATBU BAUCHI QS 514
E CARPENTRY
Materials
Cost per cubic meter (1547m) = 30,000.00
Add for nails and waste - 10% = 3,000.00
33,000.00
Allow for seasoning @ 10% = 3,300.00
Treatment:
0.50 Drum of solignum per m3 hardwood 0.5 @ 2150.00 = 1,075.00
Labour for treatment:
Labourer 2@ 1500.00 = 3000.00
Tools @ 7.50% = 225.00
Cost of gang/day = 3225.00
Output of gang/day = 1.50 m3
Therefore cost of labour in treatment for 1m3 = 4837.50
Labour cutting and fitting:
Carpenter 1@ 2500.00 = 2,500.00
Labourer 1@ 1500.00 = 1,500.00
4000.00 4,000.00
Tools @ 7.50% 300.00
Cost of gang/day 4300.00
Output of gang - say 200m/day 0.50 m3
= 8600.00
Therefore cost/m3 = 50,812.50
Add GOH & Profit @ 50% = 25,406.25
Cost/400m = 76,218.75
Cost/m = 190.55 Say = N 191 /m
Materials
Cost per cubic meter (1372m) = 30,000.00
Add for nails and waste - 10% = 3,000.00
33,000.00
Allow for seasoning @ 10% = 3,300.00
Treatment:
0.42 Drum solignum per m3 hardwood 0.42 @ 2150.00 = 903.00
Labour for treatment:
Cost of gang/day = 3225.00
Output of gang /day 1.80 m3
Therefore cost of labour in treatment for 1m 3
= 1,791.67
Labour cutting and fitting:
Cost of gang/day = 4300.00
Output of gang /day-say 134m/day 0.80 m3
Therefore cost of labour cutting and fitting = 5375.00
44,369.67
Add GOH & Profit @ 50% = 22,184.83
Cost of 267/m = 66,554.50
Cost/m = 249.27 Say = N 249 /m
Page./16
ATBU BAUCHI QS 514
Page./17
ATBU BAUCHI QS 514
Page./18
ATBU BAUCHI QS 514
G METALWORK
H FLOOR FINISHINGS
Materials
Bags of cement 9.44 @ 1750.00 = 16,520.00
m3 of sand 1 @ 3400.00 = 3,400.00
19,920.00
Add for stockpile and waste @ 15% 2,988.00
Cost of materials = 22,908.00
Add for Plant a.b. 590.00
Add for Labour a.b 716.67 = 1306.67
Cost of cement and sand (1:3) mortar/m3 = 24,214.67
Take - 100m2 area
Quantity of mortar (1:3) 100 @ 0.050 = 5.00
Add for application waste @ 10% = 0.50
5.50 m3
Cost of mortar (1:3) 5.50 @ 24214.67 = 133,180.67
Labour
Mason 1 @ 2500.00 = 2,500.00
Labourer 2 @ 1500.00 = 3,000.00
5,500.00
Add for tools @ 7.5% = 412.50
Cost of gang/day = 5,912.50
Output of gang /day = 10.00 m2
Therefore cost of labour per 100m2 = 59,125.00
192,305.67
Add for screes @ 2.5% = 4,807.64
197,113.31
Add GOH & Profit @ 50% = 98,556.65
Cost/100m2 = 295,669.96
Cost/m2 = 2,956.70 Say = N 2,957 /m2
Take - 100m2
Quantity of mortar 100 @ 0.03 = 3.00
Add for application waste @ 10% = 0.30
3.30 m3
Cost of mortar (1:3) 3.30 @ 24214.67 = 79,908.40
Cost/m2 = 450.00
Take 10m2
Materials
Cost of tiles 10 @ 450.00 = 4,500.00
Add for waste @ 10% = 450.00 = 4,950.00
PVC tile adhesive 1 @ 1000.00 = 1,000.00
Spread/gallon 15.00 m2
Cost of adhesive/10m2 = 666.67
5,616.67
6. 300 x 300 x 1.4mm PVC tile paving (cont'd)
Labour:
Tiler 1 @ 2500.00 = 2,500.00
Labourer 1 @ 1500.00 = 1,500.00
4,000.00
Add tools @ 7.5% = 300.00
Cost of gang /day = 4,300.00
Output of gang/day = 14.00 m2
Therefore cost of labour/10m2 = 3,071.43
8,688.10
Allow for cleaning surfaces @ 2% = 173.76
8,861.86
Add GOH & Profit @ 50% = 4,430.93
Cost/10m2 = 13,292.79
Cost per m2 = 1,329.28 Say = N 1,329 /m2
Take - 100m2
Quantity of mortar 100 @ 0.05 = 4.80
Add for application waste @ 10% = 0.48
5.28 m3
Cost of mortar (1:3) 5.28 @ 24214.67 = 127,853.44
Take - 100m2
Quantity of mortar 100 @ 0.04 = 4.40
Add for application waste @ 10% = 0.44
4.84 m3
Cost of mortar (1:3) 4.84 @ 24214.67 = 117,198.99
Take - 100m2
Quantity of mortar 100 @ 0.04 = 3.80
Add for application waste @ 10% = 0.38
4.18 m3
Cost of mortar (1:3) 4.18 @ 24214.67 = 101,217.31
J WALL FINISHINGS
Materials
Bags of cement 7.55 @ 1750.00 = 13,212.50
m3 of plaster sand 1.064 @ 3400.00 = 3,617.60
Sika Plastiment BV40 plasticiser/2000 litre drum @ 85,000.00
Consumption-1.5lit/m3 1.5 @ 85,000.00 = 637.50
17,467.60
Add for stockpile and waste @ 15% = 2,620.14
Cost of materials = 20087.74
Add for Plant a.b. = 590.00
Add for Labour a.b. = 716.67 = 1306.67
Cost of cement and sand (1:4)/m3 = 21,394.41
Take - 100m2 area
Quantity of mortar (1:4) 100 @ 0.013 = 1.30
Add for application waste @ 10% = 0.13
1.43 m3
Cost of mortar (1:4) 1.43 @ 21394.41 = 30,594.00
Labour
Mason 1 @ 2500.00 = 2,500.00
Labourer 1 @ 1500.00 = 1,500.00
4,000.00
Add for tools @ 7.5% = 300.00
Cost of gang/day = 4,300.00
Output of gang = 12m2/day = 12.00 m2
Therefore cost of labour per 100m2 = 35,833.33
66,427.33
Add for arises @ 2.5% = 1,660.68
68,088.02
Add GOH & Profit @ 50% = 34,044.01
Cost/100m2 = 102,132.03
Cost/m2 = 1,021.32 Say = N 1,021 /m2
K CEILING FINISHINGS
Take 10m2
Materials
Cost of particle board in 10m2 10 @ 477.02 = 4,770.22 =
50x20mm Wrought hardwood cover strips = 76 @ 30.00 = 2,280.00 =
7,050.22
Allow for nails and waste @ 10% = 705.02
Cost of materials = 7755.25
Labour
Carpenter 1 @ 2500.00 = 2,500.00
Labourer 1 @ 1500.00 = 1,500.00
4,000.00
Add for tools @ 7.50% = 300.00
Cost of gang/day = 4,300.00
Output of gang /day = 12.00 m2
Therefore cost of labour per 10m2 = 3,583.33
11,338.58
Add GOH & Profit @ 50% = 5,669.29
Cost/10m2 = 17,007.87
Cost/m2 = 1,700.79 Say = N 1,701 /m2
Take 10m2
Materials
Cost of celotex board in 10m2 10 @ 873.42 = 8,734.21 =
50x20mm Wrought hardwood cover strips = 76 @ 30.00 = 2,280.00 =
11,014.21
Allow for nails and waste @ 10% = 1,101.42
Cost of materials = 12115.63
Cost of labour per 10m2 a.b. = 3,583.33
15,698.97
Add GOH & Profit @ 50% = 7,849.48
Cost/10m2 = 23,548.45
Cost/m2 = 2,354.84 Say = N 2,355 /m2
Take 10m2
Materials
Cost of celotex board in 10m2 10 @ 797.84 = 7,978.37 =
50x20mm Wrought hardwood cover strips = 76 @ 0.95 = 72.20 =
8,050.57
Allow for nails and waste @ 10% = 805.06
Cost of materials = 8855.62
Cost of labour per 10m2 a.b. = 3,583.33
12,438.96
Add GOH & Profit @ 50% = 6,219.48
Cost/10m2 = 18,658.43
Cost/m2 = 1,865.84 Say = N 1,866 /m2
Take 10m2
Materials
Cost of Asbestos board in 10m2 10 @ 285.54 = 2,855.42 =
50x20mm Wrought hardwood cover strips = 76 @ 0.95 = 72.20 =
2,927.62
Allow for nails and waste @ 10% = 292.76
Cost of materials = 3220.38
Cost of labour per 10m2 a.b. = 3,583.33
6,803.71
Add GOH & Profit @ 50% = 3,401.86
Cost/10m2 = 10,205.57
Cost/m2 = 1,020.56 Say = N 1,021 /m2
5 13mm Cement and sand (1:4) rendering to
soffit
Take - 100m2 area
Cost of mortar (1:4) a.b. = 30,594.00
Labour
L GLAZING
Take 100m2
Materials
Covering capacity of gloss paint:
Knotting-1litre/50m2 100 @ 0.02 = 2.00 lit
Priming -1litre/16m2 100 @ 0.06 = 6.25
1st,2nd &3rd Coats a.b. = 43.65
51.90
Add for waste @ 10% = 5.19
57.09 lit
Add for stopping @ 1.0% 0.57
57.66 lit
Gloss paint in 3 coats 57.66 @ 1000.00 = 57,661.78
Concrete works
SR FUTY34
Federal University of Technology, Yola.
Blockwork
Roofing
Finishings
SR FUTY35
Federal University of Technology, Yola.
6mm Asbestos cement ceiling or other equal and
5
approved in ceiling lining
Glazing
SR FUTY36