Earned Value Formulae: White Paper
Earned Value Formulae: White Paper
Earned Value Formulae: White Paper
This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional
EV resources are available from https://mosaicprojects.com.au/PMKI-SCH.php
Planned Costs
Budget At Completion = BAC
The starting point for establishing the project budget is the ‘contract sale price’ for the project’s deliverables
paid by the client. In commercial contracts this includes the performing organisation’s profit margin and any
other fees and charges the organisation will recover from the client. The project budget is the expected total
cost of doing the work of the project, excluding these profits, etc.
1 www.mosaicprojects.com.au
This work is licensed under a Creative Commons Attribution 3.0 Unported License.
For more White Papers see: https://mosaicprojects.com.au/PMKI.php
White Paper
The project budget is the total allowance for the costs of a project including the Performance
Management Baseline (PMB) - the defined costs of the work; plus any management reserves (MR) held
outside of the project budget to cover the costs of unforseen risk events (unknown-unknowns). Management
reserves are controlled by the organisation, the PMB is controlled by the project manager.
Earned Value Management focuses on managing the PMB component of the overall project cost.
Management Reserves (MR) are the contingencies created to cover unforseen risk events and will only be
transferred into the baseline if an unexpected risk event occurs and is at the discretion of the project sponsor
or authorised senior managers.
The PMB is the authorised or ‘planned’ cost of the work; which in Earned Value terminology is also called
the Budget At Completion (BAC).
The PMB and BAC are closely related, 100% of the PMB is the same as the BAC (budget). This includes the
cost or completing the work (allocated to control accounts and work/planning packages)5, any undistributed
budget and contingency reserves.
Apart from the earliest stages of a project, there should be no undistributed budget; all of the budget should
be allocated to planning packages or work packages as soon as possible.
Contingency reserves are held within the PMB for accepted, but currently unallocated risk events. The
reserves are generally not included in a work package because the cost consequences of the identified risk
have not occurred ‘at this point in time’ and may never occur - risks are uncertain events that may, or may
not happen. When a defined risk event occurs, an appropriate amount of the reserves is transferred to the
affected work packages.
5
For more on work packages, planning packages and control accounts see:
https://www.mosaicprojects.com.au/WhitePapers/WP1011_WBS.pdf
2 www.mosaicprojects.com.au
This work is licensed under a Creative Commons Attribution 3.0 Unported License.
For more White Papers see: https://mosaicprojects.com.au/PMKI.php
White Paper
Level of Effort (LoE) tasks are work packages that have no productive measures allocated (eg, safety
attendants). The costs are simply distributed over the expected time the work will occur. Most authorities
require LoE tasks to be kept to a practical minimum.
Planned Value = PV (also referenced as: BCWS – Budgeted Cost of Work Scheduled6)
PV is the sum of the authorised budget assigned to a specific elements of the work (usually work packages),
within a defined time period. When the budget is fully assigned, the PV for the project equals the BAC.
Actual Cost = AC (also referenced as: ACWP – Actual Cost of Work Performed)
AC is the actual cost incurred in performing the work. Whilst it is to be hoped the actual costs will be
similar to, or less than the planned costs (the budget), AC is a fact derived from the project administrative
systems (usually either the finance system or the timesheet system). The difficult in apply in EV is
determining the AC of work within a few days of it being completed; finance systems can be up to 6 weeks
late in recording and allocating costs to project line items.
EV Formulae
The four components outlined above, BAC, PV, EV and AC, allow current and future performance to be
assessed. The formulae below are the core elements of EV, most standards include more sophisticated
measures in addition to these. The formula can be used for the whole of the work to date (cumulative), for a
set time period or for a defined element of the work (eg, a work package).
Current performance
Cost Performance CV and CPI
The calculation of how efficiently the project is acquiring and using resources to accomplish the work.
• Cost Variance = CV the difference between the value of the work accomplished (EV) and the cost of
accomplishing the work (AC)
o CV = EV – AC
o A negative value means the work is costing more than budgeted (bad news)
o A positive value means the work is costing less than budgeted (good news)
6 The four-letter acronyms are still used by the USA DoD and in the UK standards. These have been updated to the
two letter acronyms used in this paper in the PMBOK® Guide, the Australian, and most other standards. This paper
will use two letter acronyms throughout.
3 www.mosaicprojects.com.au
This work is licensed under a Creative Commons Attribution 3.0 Unported License.
For more White Papers see: https://mosaicprojects.com.au/PMKI.php
White Paper
• Cost Performance Index = CPI a ratio of the difference between the value of the work accomplished
(EV) and the cost of accomplishing the work (AC)
o CPI = EV / AC (Earned Value divided by Actual Cost)
o A CPI of 1 means the cost of the work is exactly the same as the budget for the work.
o A CPI of less than 1 (ie, 0.99 or less) means the work is costing more than budgeted (bad
news)
o A CPI greater than 1 (ie, 1.01 or more) means the work is costing less than budgeted (good
news)
7 Note: SV and SPI do not predict time outcomes, they only compare the amount of work accomplished with the
amount of work planned in a period. To assess the time consequence of this requires either an updated schedule or
the use of Earned Schedule. For more on Earned Schedule see:
https://www.mosaicprojects.com.au/Mag_Articles/N003_Earned_Schedule.pdf
4 www.mosaicprojects.com.au
This work is licensed under a Creative Commons Attribution 3.0 Unported License.
For more White Papers see: https://mosaicprojects.com.au/PMKI.php
White Paper
• EAC #1 Scale the overall cost performance based on actual performance to date
o EAC = BAC / CPI (the Budget At Completion divided by CPI)
o This is the simplest option, only useful in PMI examinations. The overall budget is scaled in
proportion to the cost performance to date.
• EAC #3 Assume future performance will be in alignment with the original budget.
o EAC = AC + (BAC - EV) (Actual Cost + the remaining budget)
o The total estimate is the actual cost to date plus the remaining budget. This formula is used
early in every project to avoid major fluctuations (typically through to around the 15% to
20% stage) and in any circumstances where current performance has no relevance to future
performance.
• EAC #4 Assume future performance will be a combination of current cost and schedule performance.
o EAC = AC + [(BAC - EV) / (CPI x SPI)] (Actual Cost + the remaining budget scaled by
the combination of CPI and SPI - also called the ‘critical ratio’)
o Critical Ratio: CR = CPI x SPI (see Indices section below)
o The total estimate is the actual cost to date plus the remaining budget scaled in proportion to
the cost performance to date, adjusted by SPI. This option is preferred by some authorities
and recognises that schedule performance has an impact on cost performance.
o This tends to be the highest likely cost outcome if the project is over budget and over time.
8
Based on the set numbers that can be included in a PMP question, EAC#1 and EAC#2 are the same.
The key formulae are EAC = AC + ((BAC - EV) / CPI) and CPI = EV / AC the proof is:
Change AC to a factor of EV; If CPI = EV / AC, then AC = EV / CPI
Substituting this formula for AC in the equation EAC#2, where EAC = AC + ((BAC - EV) / CPI) gives….
EAC = EV / CPI + ((BAC – EV) / CPI) writing this as a single statement: EAC = EV + BAC - EV
CPI
Crossing out the positive and negative EVs gives EAC = BAC This is EAC#1, but: make sure you remember
CPI the other options for the exam.
5 www.mosaicprojects.com.au
This work is licensed under a Creative Commons Attribution 3.0 Unported License.
For more White Papers see: https://mosaicprojects.com.au/PMKI.php
White Paper
• VAC = BAC - EAC (the total budget for the project less the estimated total cost)
o This is the predicted Cost Variance at the completion of the work.
• Variance at Completion Percentage (VAC%) VAC% = VAC / BAC * 100%
Earned Duration
Attempts to adjust the predicted completion date using a range of ‘Performance Factors’ (PF).
EAC(t)ED = AT + (max(PD, AT) - ED) / PF
Where: PD = Planned Duration and ED = Earned duration
Earned duration is the time at which the current Earned Value was planned to be achieved.
The PF can be 1 or SPI or SPI * CPI. This method is more accurate than the other traditional EV options but
not as effective as Earned Schedule in predicting the project completion date.
6 www.mosaicprojects.com.au
This work is licensed under a Creative Commons Attribution 3.0 Unported License.
For more White Papers see: https://mosaicprojects.com.au/PMKI.php
White Paper
traditional EV is in predicting the final project cost. ES also performs more accurately than any of the other
time prediction options. For more on ES see: http://www.earnedschedule.com/
The managers responsible for each section of the work (Work Package or Control Account) should be
required to consider the following key questions11 and report on them is the measured variance is outside of
acceptable limits:
• Past Performance
o Are we on schedule? (SV)
o Are we on cost? (CV)
o What are the significant variances?
o Who is responsible?
o What is the trend to date?
o What risks have been reduced or added?
• Future Performance
o What is the "to go" plan?
o How is it resourced?
o When will we finish?
o What will it cost in the end?
o How can we control the trend?
o How can we adjust for risk?
The answers to these questions come from the EVMS. By reflecting on the answer to each, the project team
can focus on "managing the work" using the numbers and not just reporting the numbers.
11
Source, Glen B. Alleman, Herding Cats blog: http://herdingcats.typepad.com/my_weblog/
7 www.mosaicprojects.com.au
This work is licensed under a Creative Commons Attribution 3.0 Unported License.
For more White Papers see: https://mosaicprojects.com.au/PMKI.php
White Paper
Performance Indices
There are a number of performance indices in common use – most are of limited value. The most common
are:
SI typically does not consider performance aspects other then project gain or slippage.
Note: SPI(t) considers the overall time achieved from a 'value' perspective across all activities. Traditional
SPI considers the value of work accomplished from a monetary perspective only, without relating it to time.
12
A detailed analysis of the TCPI and its application, see:
https://www.mosaicprojects.com.au/WhitePapers/WP1097_TCPI_in_EVM.pdf
8 www.mosaicprojects.com.au
This work is licensed under a Creative Commons Attribution 3.0 Unported License.
For more White Papers see: https://mosaicprojects.com.au/PMKI.php
White Paper
Planned PCT
The percent of budget expected to have been expended as of the most recent reporting period. It is calculated
by dividing the cumulative BAC (most recent reporting period) by total budget: (BACcum / BACtotal) / 100.
For example...if you have a total budget of $5,000 and your BACcum as of your most recent reporting period
is $200, your Planned PCT will be 4%. In most cases BACcum = PVcum.
_____________________________
9 www.mosaicprojects.com.au
This work is licensed under a Creative Commons Attribution 3.0 Unported License.
For more White Papers see: https://mosaicprojects.com.au/PMKI.php