CPWD Internship Report
CPWD Internship Report
CPWD Internship Report
Submitted by
PIJUSH AKHULI – 16CE8003
DEEPAK KUMAR– 16CE8043
ACKNOWLEDGEMENT
S.no Description
1 Introduction
2 Conceiving of a project
3 Tendering
8 Road work
INTRODUCTION
ABOUT
The Central Public Works Department of India is a Central Government
owned authority that is in charge of public sector works in the country.
Central Public Works Department (CPWD) under Ministry of Urban
Development is entrusted with construction and maintenance of
buildings for most of the Central Government Departments, Public
undertakings and autonomous bodies. In the Indian History both pre and
post-independence - CPWD has a glorious era of more than 150 year
with dedicated, energetic and committed corps of Engineers and
Architects. Before being re-structured to its present form in 1930
“Central Public Works Department” originated in July 1854 when the
Governor General of India decided to set up a Central Agency:
“to exercise universal control over public works in India with best of
scientific knowledge with authority & system”.
Central Public Works Department, NIT Durgapur Division is the premier
agency of Govt. of India engaged in planning, designing, construction
and maintenance of Government assets in the field of built environment
and infrastructure development. Assets in built environment include
Hospitals, Schools, Colleges, Technical Institutes, Police Buildings,
Prisons, Courts etc; assets in infrastructure development include Roads,
Bridges, Flyovers, Footpaths, Subways etc. CPWD NIT Durgapur Division
also sustains and preserves these assets through a well-developed
system of maintenance which includes amongst others specialized
services like rehabilitation work and roads.
CONCEIVING OF A PROJECT:
the discussion of the project life cycle. The project phases make up a
project life cycle, the phases are designed to fit a project’s needs.
The elements of a project life cycle should define:
Closure
PHASE 1: PROJECT INITIATION
This is the starting phase of the project, and the goal of this phase
is to define the project at a broad level. This phase usually begins with a
Two of the more popular methods for setting goals are S.M.A.R.T. and
C.L.E.A.R:
S.M.A.R.T. Goals :–
This method helps ensure that the goals have been thoroughly vetted.
It also provides a way to clearly understand the implications of the
goal-setting process.
Specific – To set specific goals, answer the following questions: who,
of a goal.
Attainable – Identify the most important goals and what it will take to
achieve them.
Realistic – You should be willing and able to work toward a particular
goal.
Timely – Create a timeframe to achieve the goal.
C.L.E.A.R. Goals :–
A newer method for setting goals that takes into consideration the
environment of rapidly growing competition.
Collaborative – The goal should encourage employees to work
together.
Limited – They should be limited in scope and time to keep it
manageable.
Here are some of the documents a project manager will create during
This is the phase where deliverables are developed and completed. This
often feels like the meat of the project since a lot is happening during
this time, like status reports and meetings, development updates, and
Project Execution phase where the teams involved are informed of their
responsibilities.
Develop team
Assign resources
Status meetings
Update project schedule
management plan.
over the time from the project’s launch to its completion, and
serves as a method to measure and compare the status of the
Using the previously set out meeting times, there must be regular
interaction with everyone involved with the project (or at least
the team managers) and ensuring that all is running smoothly.
This is usually done through the use of KPIs (Key Performance
stakeholder objectives.
Effort and Cost Tracking: PMs will account for the effort and cost
of resources to see if the budget is on track. This type of tracking
informs if a project will meet its completion date based on current
performance.
Project Performance: This monitors changes in the project. It
takes into consideration the amount and types of issues that arise
and how quickly they are addressed. These can occur from
unforeseen hurdles and scope changes.
During this time, project managers may need to adjust schedules and
resources to ensure the project is on track.
PHASE 5: PROJECT CLOSURE
work events for people who participated in the project to thank them
project punch list of things that didn’t get accomplished during the
project and work with team members to complete them. They perform
a final project budget and prepare a final project report.
Finally, they will to collect all project documents and deliverables and
Types of tendering:
Competitive tendering:
Open
Selective
Negotiated tendering:
Serial
Nominative
1. Open Tendering:
not necessarily the lowest price for which his project could be
The engineer advising the employer may think there is a risk that
all such low bids could prove unsatisfactory, but he cannot advise
reject the lowest bid, even if it appears dubiously low – unless that is
due to some obvious mistake.
contract.
there are any queries these are discussed and usually settled
without difficulty. Thus mistakes in pricing can be reduced, so that
both the engineer advising the employer and the contractor are
For any firm to bid for the tender, they must fulfill given
The tendering process usually starts with the procuring entity issuing a
bidding notice in the media, and ends with the signing of contracts.
Below are some of the steps followed by public procuring entities:
Preparation
bidding documents.
Advertisement
committee.
The law provides for arbitration in case of any grievances about the
and services from any country, except where specific sanctions are
declared against a given country.
The major concerns for a client to choose any of the procurement
method are:
To finish the project on time.
The cost of the project.
Performance or quality in relation to both design and
construction of the building.
1) Traditional method:
Designs should be fully prepared ahead of time before
tendering procedure and actual construction can begin.
The client has control over design. There is no design
responsibility on the contractor.
The duration of the project tends to be very long because of
the separate sequential process of design and construction.
The construction cost is well known ahead of time and there
may be need for adjustment as provided for in the contract.
The client appoints a professional consultant to administer the
Secondary Secondary
contractor contractor
Analysis.
The traditional procurement method is very simple to understand by
all classes of client whereas the major problem it has, is that the
design and construction of the work in return for a lump sum price.
To arrive at a choice of contractor, contractors are
Analysis.
The Design-Build approach gives the client a single point of contact.
However, the client commits to the cost of construction, as well as the
cost of design, much earlier than with the traditional approach. Whilst
risk is shifted to the contractor, it is important that design liability
insurance is maintained to cover that risk. Changes made by the client
during design can be expensive, because they affect the whole of the
Design-Build contract, rather than just the design team cost.
which are experienced in this kind of team working, the benefits are
not always realized.
many of the work packages are yet to be tendered for. This often
management.
Construction Management:
This is similar in concept to Management Contracting. The sub-
Analysis:
This method is characterized by a high level of skillful input since
the subcontractors engaged are experts in their various fields. The
public health,
education,
safety,
waste management,
transfers the new facility to the public sector at the end of the
lease period.
The Public sector gains the advantages the private sector offers
such as: ability to design, construct, manage and finance a
project.
Public money is better used and at difficult economic periods
income people.
However, it has the advantage that only the users pay and not
the tax payer.
and works
Generally, the public sector can get cheaper loans than the
private sector.
Layout of Building:
Layout of a building or a structure shows the plan of its
BASELINE:
HORIZONTAL CONTROLS:
Horizontal controls are the points that have known co-ordinates with
respect to a specific point. These points are then used to locate other
driven into existing steps, ledges, footpaths etc. may serve as vertical
controls.
BATTERBOARDS AND OFFSET PEGS:
them. These two points can be joined to make line XX. To locate point
G and H, straight line are set out using 3-4-5 triangle rule and distance
out a large rectangle which will includes the entire building or the
greater part of it. This is shown in Figure 4-2 as HOPQ When this is
established, the remaining portion of the layout will consist of small
rectangles, each of which can be laid out and shown separately. These
rectangles are shown as LMNP ABCQ, DEFG, and IJKO in Figure
EXTENDING LINES:
layout problems:
to batter board 6.
Step 3. After locating and dipping stake D, erect batter boards 7 and
Extend chalk line Z from batter board 5 to batter board 7, over stakes
C and D.
Procedure:
The test consists of driving a split spoon sampler into the soil
through a borehole 55 to 100 mm in diameter at the desired depth.
It is done by a hammer weighing 63.5 kg dropping onto a drill rod
Procedure:
1. Bore hole is made up to a depth at which value of N is to be
calculated.
150mm penetration.
Corrections to be applied:
A. Overburden pressure correction
B. Dilatancy correction
various depth.
If two granular soils possessing the same relative density but
N1= N0CN
Where,
2000
CN=0.77𝑙𝑜𝑔 ( )
𝜎0′
correction is required.
If W.T is below test level then W.T correction is not required.
The S.P.T value is further corrected for presence of W.T and this
1
𝑁2 = 15 + (𝑁1 − 15)
2
N1 = Corrected S.P.T for overburden
The height of fall must be 750mm. Any change from this will
affect the ‘N’ value.
TERMINOLOGY
Cut-Off Level — It is the level where a pile is cut-off in order to make
structural connection to the pile caps or beams or any other structural
components at that level.
Datum Bar — A rigid bar placed on immovable supports.
Total Elastic Displacement — This is the magnitude of displacement of the
pile head during rebound on removal of a given test load. This comprises
two components:
a) Elastic displacement of the soil participating in the load transfer; and b)
Elastic displacement of the pile shaft.
Factor of Safety — It is the ratio of the ultimate load capacity of a pile to
the safe load on the pile.
Gross Displacement — The total movement of the pile top under a given
load.
Group Test — A minimum of three piles shall be considered as group for
the purpose of testing.
Initial Test Pile — One or more piles, which are not working piles, may be
installed to assess the load carrying capacity of a pile.
Kentledge — Dead-weight used for applying a test load on piles.
Net Displacement — The net vertical movement of the pile top after the
pile has been subjected to a test load and subsequently released.
Safe Load — It is the load derived by applying a factor of safety on the
ultimate load capacity of the pile or as determined from load test.
Ultimate Load Capacity — The maximum load which a pile can carry
before failure, that is when the founding strata fails by shear as evident
from the load settlement curve or the pile fails as a structural member.
Working Load/Design Load — The load assigned to a pile as per design.
Pile load test is the only direct method for determining the
routine tests
c) To get an idea of suitability of piling system and
a) For small size projects (for piles less than 1000 numbers), a
minimum of two tests.
b) For large size projects (for piles more than 1000 numbers), a
minimum of two tests for first 1000 piles and additional one test for
piles, subject to a minimum of one (1) test. The number of tests may
be increased up to 2 percent in particular cases depending upon the
nature, type of structure and sub-strata condition.
The piles to be tested for routine tests may preferably be selected
driven piles.
f) Piles under sensitive locations of structures.
g) Any doubt arising from non-destructive test results.
Types of pile load test:
Vertical load test is carried out to establish load settlement
the ultimate load capacity of pile in this test the load on the
The Following are the Field Tests for Cement that are carried out in
order to ascertain the quality of Cement,
Colour
Physical properties
Presence of lumps
Floating test
typical cement colour i.e., grey colour with a light greenish shade.
This is not always a reliable test. But it gives an indication of excess
lime or clay and the degree of burning.
be rejected. This Field tests for cement are carried out to check
lumps.
brick should have deep red cherish colour. Any Other colours
are the indication of under burnt or over burnt.
It consists of
I. Clearing of site.
II. Excavation and construction of fields to bring the road to
desired grade.
III. Shaping the subgrade.
IV. Then the borrowed soil is dumped and well compacted, death
not exceed 10 cm.
V. Make the soil up to optimum moisture content level.
VI. After this it is allowed to dry for few days before opening to
traffic.
It is cheap.
It has easy construction.
It can be built with less skill.
Merits:
Demerits:
Ride is not comfortable.
It can be detoriated.
It cannot hold very heavy traffic.
Construction procedure:
vertically.
The coarse aggregates are spread uniformly to the proper
Materials used:
Tandem Roller
Aggregate grading
Grade of bitumen
Temperature of aggregate
At least one sample for every 100 tons of the mix discharged by
the hot mix plant is collected and tested for above requirements.
Marshall tests are also conducted. For every 100 sq.m of the
compacted surface, one test of the field density is conducted to
check whether it is at least 95% of the density obtained in the
laboratory. The variation in the thickness allowed is 6mm per
4.5m length of construction.
The AC surface should be checked by a 3.0 m straight edge.
The longitudinal undulations should not exceed 8.0 mm and
the number of undulations higher than 6.0 mm should not
surrounding temperature.
Cost)
Materials used:
Equipments used:
Mild steel sections and blocks for making joint grooves for
finishing purpose
Site Preparation:
Before construction begins, the construction site must be
carefully prepared, this includes preparing the grade or road
Construction Process:
Before using form work, it should free from all type material like
used 2.5-5cm thick and 3mtr long wooden sheeting. The depth
of wooden block must be same as level of slab thick. After 24hrs,
form work displaced next length of road. (Wooden sheets,
battens, plywood, fibre hard board, steel plates, angles, rope etc
Construction of joints.
Material mixing using mixer.
problems.
Continuous bay method: Construct one side of road regularly,
and after construction of some part of first side than construct
concrete harden.
There are two kinds of tests which are done on hardened concrete.
These are non destructive test and destructive tests. In non
destructive test, the sample is not destroyed and this test is very
useful in determining the strength of existing buildings or structures
where as in destructive test a sample is made and then destroyed to
find out the strength of concrete.Compression test is the example of
destructive test. Here are the nondestructive tests.
1) For end span with one end fixed and the other continuous
or for intermediate span between supports;
2) For end span with one end free and other continuous , the
effective span shall be equal to the clear span plus half the
effective depth of beam or slab or the clear span plus half
the width of the discontinuous support whichever is less;
3) In the case of spans with roller or rocket bearings , the
effective span shall always be the distance between the
centres of bearings .
c) Cantilever – The effective length of a cantilever shall be taken as
its length of a cantilever shall be taken as it’s length to the face of
the face of the support plus half the effective depth except where
it forms the end of a continuous beam where the length to the
centre of support shall be taken.
d) Frames – In the analysis of a continuous frame , centre to centre
distance shall be used
a)The slab shall be cast integrally with the web or the web and
the slab shall be effectively bonded together in any other
manner; and
Cantilever 7
Simply supported 20
Continuous 26
b) For span above 10 m, the values in (a) may be multiplied by span 10/span in
m , except for cantilever in which case deflection calculations should be
made.
c) Depending on the area and the stress of steel for tension reinforcement. the
values in (a) or (b) shall be modified by multiplying with the modification
factor obtained as per Fig. 4.
Solid Slabs
1. For slabs spanning in two directions , the shorter of the two spans should
be used for calculating the span to effective depth ratios .
2. For two-way slab of shorter spans ( upto 3.5m) with mild steel
reinforcement , the span to overall depth ratios given below may generally
be assumed to satisfy vertical deflection limits for loading class upto 3
Kn/𝑚2
Simply supported slabs 35
Continuous slabs 40
For high strength deformed bars of grade Fe415 , the values given above
should be multiplied by 0.8.
Transverse reinforcement
c) 300 mm
2) Diameter- the diameter of the polygon links on lateral ties shall be
not less than one fourth of the diameter of the largest longitudinal
bar and in no case less than 16 mm.
d) Helical reinforcement
Deep Beams
a) A beam shall be Deemed to be a deep beam when the ratio of the
effective span to the overall depth,l/D is less than :
For span to depth ratio less than Unity, the steel shall be evenly
distributed over a depth of 0.8D measured from the tension face.
Minimum Requirements for Reinforcement in Walls
3) 0.0020 for welded wire fabric wire fabric not larger than 16 mm in
diameter
(e) The stresses in the reinforcement are taken from the stress-
strain curve for the type of steel used
For design purposes, the partial safety factor (Yms) equal to 1.15 shall
be applied.
𝑓𝑦
+ 0.002
1.15 𝐸𝑠
Longitudinal reinforcement
Longitudinal reinforcement shall be designed to resist and
equivalent bending moment 𝑀𝑒1 , given by
𝑀𝑒1 = 𝑀𝑢 +𝑀𝑡
Where
𝑀𝑢 = bending moment at the cross section and
1+𝐷/𝑏
𝑀𝑡 =𝑇𝑢 ( )
1.7
Where
𝑇𝑢 is the torsional moment,D is the overall depth of the beam and
b is the breadth of The Beam.
Transverse Reinforcement
ESTIMATION
rate. But the total cost is worked out in the prescribed form is
1. Report
2. Specification
ii) Location of site: The site of work is selected, such that it should
iii) Local labour charges: The skill, suitability and wages of local
labours are considered while preparing the detailed estimate.
The process of working out the cost or rate per unit of each item is
called as Data. In preparation of Data, the rates of materials and
labour are obtained from current standard scheduled of rates and
while the quantities of materials and labour required for one unit of
charges.
ii) Cost of labour: The exact number of labourers required for unit of
work and the multiplied by the wages/ day to get of labour for unit
item work.