Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Comments Remarks King Room: - F13 Brass Trims in Floor and Wall

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 3

Comments Remarks

King Room -Include Artwork


- Please double check W 08 I cannot find in the BOQ
- Include connecting doors.
Suite Rooms - W 05 - Tinted Mirror
- Sliding Door
- Sheer and Main curtain please separate
- Compute pelmets in Linear meter and specify width
- Include Glass door
Suite 1 - C1: Please recalculate area actual quantity is 84sqm
- C3: Please recalculate area actual quantity is 43sqm
- Full length mirror W05
Twin Room - W05 - 2 Nos. with different dimensions
- W04 - No included (Not part of TV Unit)
- LS - 05 Flat base sofa Missing in BOQ
Main Lobby - Door included interior
- Finishes for the Water Feature
- Did you include Sales Marketing Room area in terms of
wall finishes also?
- Aside from the Gypsum, there is also Ceiling Louver
(MDF Veneer) detail for ceiling. Please compute in Linear
meter.
- F06 - Missing in BOQ (Main Entry)
Lobby Column Cladding in reception area (incl all finishes-
Lump Sum)
- Oak Timber Dado Height rail - Compute in Running
meter
- W-30 Ash timber rail - Compute in Running meter
Include artworks
All Day Dining - F13 Brass trims in Floor and Wall
-Wall Panel (D36-102-02)
- These are missing: Cold Food Preparation counter and
Hot Food Preparation counter
- Column Cladding D37-104-04
- Server counter (2 Nos.)
- Wall panels D37-102-20
- Classify Banquet seating length and Nos. of each
Ballroom -Concealed Double Door room
-Concealed Door
- Side table and chairs missing in BOQ (Seen in Section)
- LED Strip light
- Folding/Sliding Partition - Compute in Area
- Chandelier (We will confirm from client)
- Brass Mashrabiya Curved light - Compute in Nos. (Check
in Section and D37-103-01)
- Full Height Door Handle - (6 Nos.) (Add in Boq but we
will confirm details from Client)
- Vanity Counter - 1 Item
- Projector Screen - 2 Nos (Add in BOQ, To be confirm)
- Mirror above console (1 No.)
Brides Room - Glass Partition w/ Shower door- in Sqm
- Artwork - 1 No.
- Full Height Mirror (Section D-D)
- IP Spotlight (4 Items)
- Spotlight (2 Items)
- Artwork
- Mirror @ Sink
Please separate these 3 areas, we - Ballroom Toilet
need to be specific in our pricing: - Reception Toilet Female
- Reception Toilet Male
Reception Prayer Room - Graphic Wall Design (RAL 5024)
- Include Doors
Receptionist Toilet - Teak Shoe Shelves
Include disabled extra facilities: - Emergency chord
- Assist Bar
Ballroom Prayer Room - Bill Nr -1 - F22 - Porcelain Tile Missing
- Teak Shoe Shelve - 1 Item
Please change Bill Nr-11 from - W27- Porcelain Tile Missing
Reception Prayer room to Ballroom - Recessed LED Strip light Ceiling (Linear meter)
Prayer Room - W29 mosaic wall tile
- Sanitary Items: Ablution Hoes (Nos.)
- Artwork
Gym BOQ is Missing because no PDF Drawing, note that the PDF drawings in Gym folder
is only for Gym Corridor therefore Gym Quantity where not made.
Gym Corridor - Artwork
- Add W30 in Linear Meter
- Led Strip Lights
- Ceiling Spotlight
- Directional Spotlight
Meeting Room - F-06 will be laid the entire floor area because carpet is
inlay only. (actual quantity: 62 sqm)
- Spotlight (
- Directional Spotlight (
- Strip Light (
- Please reduce C1 quantity, and compute C8 quantity.
- Compute W-30 in Linear Meter
- Artwork
- Chair Rails in Running meter
- Wood panel cladding is missing in BOQ (Wall and ceiling
connecting)
Guest Lift Lobby - LS- 64 (Mirror)
- Computed in F-10, Skirting for F-10, W-11, W-31 and C1 is
not including corridors, only Lift lobby on 3 floors only.
- Include doors
- Art work
- Lift Lobby CNC Panel
Avani Kids - Include doors
- Hessian Fabric Curtain
- Paint to resemblance aged castle
- MDF Spray finish, compute area
- 3D Wall Art in MDF, compute area
- MDF 3D Feature Tree, put 1 QTY
- TV Cabinet with shelves (Section A-A)- 1 No.
- Combine Points A (Locker) and B (Shelves) into 1 Unit
only - 1 No.
- Toilet floor and wall tile area missing
- MDF partition with spray and acid.... (Section A-A) - 1 No.
- Strip Light
- IP rated Spotlight
- Spotlight
- Compute wall without hatch not matching the Block
Wall hatch (Seen in Plan)
Changing Room - Include all Bench seating
- Include all kinds of door
- Include Vanity Mirror
Spa and Massage - Massage table - 1 No. (Confirm to client)
- IP Spotlight
Spa, Massage, Steam room and Sauna all included in Spa and Massage BOQ?
Guest Rooms Corridor - Carpet Area to be rechecked (Actual area for 1 floor is
240sqm) for 3 floors = 740 sqm; add 212sqm from
quantity computed
- LS -41 Wall Mounted Light
- Artwork
- W-13 (Actual Quantity=291) Add 10sqm on the quantity
computed
- C4 add 91sqm; (Actual quantity= 126.0 + 20%for side
panel of bulkheads (25)= 151sqm)
- W-11 Add 293sqm; 1panel=11sqm (Actual quantity=
891sqm + 50sqm for every bigger end panels near
staircase) Total= 941sqm
- C1 add 119sqm; (actual quantity 589sqm)
- Wood Panel on the door side
-Wall Panel (Same with C4 Finish) - 1 panel= 0.90sqm;
Total= 146sqm

General Comments:
- As what we discuss its okay not to compute lighting but include these on list, we will do
the quantity
- Include number of Artwork in each area, you can see Artwork schedule included in the
file.
- Please separate Sheer and Main Curtain, please provide in Linear meter per location
please not by Nos.
- Include Nos. of doors as per size, please base in thru Cad drawings since there are no
Door schedule.
- Also include all sliding doors, Shower glass doors, Wall partitions/panels.
- There are Mirror separated with the Main Vanity mirror please specify the dimension and
Nos
- There are brass trim details in some locations/rooms please compute in Linear meter.
-
-

You might also like