Ntnu 2012 PDF
Ntnu 2012 PDF
Ntnu 2012 PDF
This project would not have been possible without the help of our supervisors, sponsors, fami-
lies and friends. The team would like to sincerely thank all of the student who have helped us
during the project. We would specially like to thank:
Bjarne Stolpnessæter, Knut Einar Aasland, Børge Holen, Iver Johnsen and Per Øystein Nordtug at
the institute of product development and materials.
Eker Design and Paal Fediuk at High Performance Composites in Fredrikstad for helping us
produce the monocoque. Gylling Teknikk for making a second battery pack on very short notice,
just in time for the competition. SmartMotor for exceptional help with the motor controller. We
would like to thank the rest of the team for all the good times and great experiences.
Finally we would like to thank our main sponsor Det Norske Veritas (DNV) and Kristina Dahlberg
for their continued support of the NTNU Shell Eco-marathon team.
ECO-MARATHON 2012 1
2 ECO-MARATHON 2012
ABSTRACT
A team of 13 NTNU students have developed and built a car to compete
in the Shell Eco-Marathon 2012 competition. This master project is a
continuation of the specialization project done in the autumn semes-
ter 2011. Production started in February and the car was ready on the
start line the 18th of May. Out of 22 competing teams in the battery-
electric category, the DNVFuelfigher2 came in 5th place. The best result
achieved was 163km/kWh which can be calculated into an equivalent
of 1581km/liter of gasoline. This report includes the design and produc-
tion process of all sub systems. In addition project management, system
engineering, media and the race itself is described.
SAMMENDRAG
Et team bestående av 13 NTNU-studenter har utviklet og bygget en
bil for å konkurrere i studentkonkurransen Shell Eco-Marathon Europe
2012. Dette master prosjektet er en videreføring av fordypningspros-
jekt gjennomført høstsemesteret 2011. Produksjonen startet i februar
og bilen sto klar på startstreken 18. mai. Ut av 22 konkurrerende lag i
batteriklassen, kom DNVFuelfigher2 på femte plass. Det beste resulta-
tet ble 163km/kWh som kan omregnes til en ekvivalent på 1581km/
liter bensin. Denne rapporten omfatter design og produksjonen av alle
delsystemer. I tillegg er prosjektledelse, system engineering, media og
selve løpet beskrevet.
ECO-MARATHON 2012 3
4 ECO-MARATHON 2012
ECO-MARATHON 2012 5
TABLE OF CONTENTS
1 INTRODUCTION 8 3.1.2.1 Boundary Conditions 72
3.1.2.2 Layup 73
1.1 Shell Eco-marathon 10 3.1.2.3 Resuslts 75
1.2 The Team 12 3.1.2.4 Conclusion 76
3.1.3 Designing the Molds 78
3.1.4 Production 80
2 NON-TECHNICAL 14
3.1.4.1 Milling 80
3.1.4.2 Layup 86
2.1 Project Management 16
3.1.4.3 Doors 92
2.1.1 Planning 18
3.1.4.4 Firewall 92
2.1.1.1 Individual Managment Plans 19
3.1.4.5 Wheel Well Covers 94
2.1.1.2 Creating WBS 22
3.1.4 Assembly 96
2.1.1.3 Scheduling Project 22
3.1.4.1 Monocoque 96
2.1.1.4 Budgeting 27
3.1.4.2 Wheel Well Covers 98
2.1.1.5 Risk Identification and Assessment 28
3.1.4.3 Doors 102
2.1.1.6 Risk Identification and Assessment
3.1.4.4 Surface Finish 104
Challenges 30
3.1.5 Windows 106
3.1.5.1 Molds 108
2.2 Systems Engineering 32
3.1.5.2 Vacuum Table 110
2.2.1 Knowledge Managment 34
3.2.5.3 Production 110
2.2.1.1 Capturing Knowledge with LEAN
3.1.5.4 Assembly 111
Techniques 36
3.1.6 Lights 112
2.2.1.2 Storing and Sharing Knowledge
3.1.6.1 Former Lights 112
with Model-Based SE 40
3.1.6.2 Interfaces 113
2.2.2 Visual Workflow Management 41
3.1.6.3 List of Requirements 113
2.2.2.1 Stand-Up Meetings and Visual
3.1.6.4 Materials and Technology 114
Project Board 41
3.1.6.5 Concept Development 115
2.2.2.2 Visualizing Project Progress 42
3.1.6.6 Final Concept 116
2.2.2.3 Avarege Risk Level as a Tool for
3.1.6.7 Production 117
Tracking Progress 42
3.1.7 Details 118
2.2.2.4 The Timeline 43
3.1.7.1 Door Details 119
2.2.2.5 Project Progress in a Micro-Level 44
3.1.7.2 Wiper 124
2.2.3 Verification, Validation and Testing
3.1.7.3 Back Hatch Mounting 129
Activities of the DNVFF2 44
3.1.7.4 Side Cover Mounting 130
2.2.3.1 Unit Testing
3.1.7.5 Towing Hook 132
2.2.3.2 Assembly Testing 44
3.1.8 Foil 134
2.2.3.3 Performance Test 46
3.1.8.1 Paint VS Foil 134
3.1.8.2 Inspiration 135
2.3 Promotion 48
3.1.8.2 Production and Mounting 138
3.1.9 Wind Tunnel Testing 140
2.4 Rotterdam 56
3.1.9.1 Wind Tunnel 141
2.4.1 Shell Eco-marathon 58
3.1.9.2 Experimental Setup 142
2.4.1.1 Track 58
3.1.9.3 Results 143
2.4.1.2 Technical Inspection 60
3.1.9.4 Conclusion 144
2.4.1.3 Testing 64
2.4.1.4 Race 65
3.2 Interior 146
3.2.1 Introduction 148
3 TECHNICAL 66 3.2.2 Dashboard 150
3.2.2.1 Last Cars Dashboard 150
3.1 Exterior 68 3.2.2.2 Interfaces 151
3.1.1 Introduction 70 3.2.2.3 Ergonomics 152
3.1.2 Strength Analysis 72 3.2.2.4 Analysis of Functions 153
6 ECO-MARATHON 2012
3.2.2.5 List of Requirements 154 3.4.1.2 Tie Rod Mount 236
3.2.2.6 Cooperation with Other Students 155 3.4.1.3 Cable Mount 237
3.2.2.7 Concept Development 156 3.4.1.4 Additonal Drag Link Parts 237
3.2.2.8 Final Concept 157 3.4.2 Steering Column 237
3.2.2.9 Placement of Buttons and Display 158 3.4.2.1 Analysis 238
3.2.3 Steering Wheel 160 3.4.3 Pulleys and Kevlar Cable 238
3.2.3.1 Last Cars Steering Wheel 160 3.4.4 Assembly and Testing 240
3.2.3.2 Necessary Functions 161 3.4.5 Race and Conclusion 241
3.2.3.3 Production Methods 162
3.2.3.4 Inspiration 163 3.5 Brakes 244
3.2.3.5 List of Requirements 164 3.5.1 Brake Pedal 247
3.2.3.6 Idea Generation 166 3.5.1.1 Pedal Arm 247
3.2.3.7 Ergonomic Testing 166 3.5.1.2 Brake Pedal Box 249
3.2.3.8 Three Different Concepts 168 3.5.1.3 Master Cylinders 250
3.2.3.9 Production 172 3.5.2 Other Brake Circuit Parts 250
3.2.4 Seat 174 3.5.3 Assembly and Testing 252
3.2.4.1 Former Seat 174 3.5.4 Race and Conclusion 253
3.2.4.2 Inspiration 175
3.2.4.3 Possible Materials 176 3.6 Wheels 254
3.2.4.4 Interfaces 177 3.6.1 Strenght Analysis 256
3.2.4.5 Basic Ergonomics 178 3.6.2 Production 257
3.2.4.6 List of Requirements 179 3.6.3 Performance 259
3.2.4.7 Idea Generation 180 3.6.4 Further Recommendations 259
3.2.4.8 Three Ideas 182
3.2.4.9 Selecting Ideas 185 3.7 Propulsion 260
3.2.4.10 Detailing of the Final Concept 186 3.7.1 Motor Design 262
3.2.4.11 Production 187 3.7.1.1 Requirements 262
3.2.5 Rear View Mirrors 188 3.7.1.2 Concept Description 262
3.2.5.1 Mirrors on DNVFF 188 3.7.1.3 Hubs and Axle 262
3.2.5.2 Inspiration 189 3.7.1.4 Rotors 265
3.2.5.3 List of Requirements 190 3.7.1.5 Rim Adapter 265
3.2.5.3 Idea Generation 191 3.7.1.6 Test Rig and SM-Adapter 266
3.2.5.4 Different Concepts 192 3.7.2 Motor Development 268
3.2.5.5 Production and Finished Product 193 3.7.2.1 Rotor 268
3.7.2.2 Stator Production 271
3.3 Suspension 194 3.7.2.3 Mold Production 271
3.3.1 Front Suspension 196 3.7.2.4 Open Casting 271
3.3.1.1 Hubs 204 3.7.2.5 Vacuum Casting 272
3.3.1.2 Axles 205 3.7.2.6 Spacer Ring 272
3.3.1.3 Steering Knuckles 206 3.7.2.7 Assembly of the Motor 273
3.3.1.4 Linkages 210 3.7.2.8 Problems Regarding the Construction 273
3.3.1.5 Mounting Points 214 3.7.2.9 Testing the Existing Motor 276
3.3.1.6 Conclusion 215 3.7.2.10 Conclusion 278
3.3.2 Rear Suspension 216
3.3.2.1 Introduction 216 2.8 Control System 280
3.3.2.2 Knuckle 216 2.8.1 Car Control System 282
3.3.2.3 Lower A-arm Connector 222 2.8.1.1 Characteristics 282
3.3.2.4 Coilover 224 2.8.1.2 Changes to the Car Control System 282
3.3.2.5 Toe Link Extension 227 2.8.2 Propulsional Control System 284
3.3.2.6 Rods and Rod Ends 228 2.8.2.1 Characteristics 284
3.3.2.7 Assembly 228 2.8.2.2 Changes in the Car Control System 284
3.3.2.8 Further Recommendations 230
4 CONCLUSION 286
3.4 Steering 232
3.4.1 Drag Link 235
3.4.1.1 Length Adjustment 235
5 REFERENCES 290
ECO-MARATHON 2012 7
1 IN
TRODUCTION
1.1 SHELL ECO-MARATHON
The Shell Eco-marathon (SEM) challenges high The vehicles may use one of the following fuel or
school and college student teams from around energy types:
the world to design, build and test energy ef-
ficient vehicles. With annual events in the Ameri- • Gasoline • Natural gas
cas, Europe and Asia, the winners are the teams
• Diesel • Hydrogen
that go the farthest distance using the least
amount of energy. • Biofuels • Solar
• Ethanol • Battery
The competition is devided into different vehicle
and energy categories: In 2012 the competition was held in an urban en-
vironment for the first time in Shell Eco-marathon
• Prototype: Vehicles in this category aim to Europe’s history. This was a way of showcasing
build the most aerodynamic and fuel-effi- the exciting student innovations and futuristic
cient vehicle possible. The rules for this class vehicles on a more realistic stage.
impose few limitations and allows for very Shell selected Rotterdam in the Netherlands
radical designs. to provide this urban stage given it is centrally
• UrbanConcept: The UrbanConcept category located in Europe. Shell Eco-marathon Europe
offers participants an opportunity to design 2012 ran from 17-19 May on the Ahoy track in
and build fuel-economy vehicles that are the middle of Rotterdam. The competition was
close in appearance to today’s passenger a huge success with many spectators and great
cars. racing happening on track.
10 ECO-MARATHON 2012
The story of NTNUs participation in the Shell Eco- the car a reality, supporting the team with
marathon started in the fall of 2007. During the materials, knowledge and production facilities.
first 4 years NTNU participated with the DNV Fuel The team designed, built, assembled and tested
Figher (DNVFF). This car used a hydrogen fuel cell the car in just 9 months, making it ready for the
as a energy source to power its electric motor. competition in May.
Many prizes and awards were achived with this
car, including two second prizes and a world When the car arrived in Rotterdam it was im-
record in its class. mediately recognized as an eye catcher. Several
teams, spectators and tv-crews wanted to have
The 2012 team decided to build a brand new a look at the car. The team was very happy to see
vehicle to continue competing in the Urban their hard work being appreciated by the crowd.
concept class, but this time using plug-in battery Due to extensive testing in Trondheim the car
technology. The new urban setting for the com- only needed minor adjustments before it was
petition demanded a more robust car and a well fully ready for the race. A total of three long
made suspension system. Experiences gained distance runs were completed; one test run and
throughout the years from the DNVFF meant that two race attempts (ny record for ntnu?). The
improvements could be made within every sub best result achieved was 163 km/kWh in a near
system. perfect run. The competition level in the battery
class was very high and the team ended up in 5th
DNV was willing to continue the role as main place.
sponsor for 2012. The car was appropriately
named the DNV Fuel Fighter 2 (DNVFF2) as a con-
tinuation of NTNU and DNVs cooperation in this
project. Transnova, a Norwegian governmental
organisation promoting environmentally friendly
transportation, sponsored the team with addi-
tional fundings.
Several other important sponsors helped make
ECO-MARATHON 2012 11
1.2 THE TEAM
The 2012 team consists of 13 master students from the
Norwegian University of Science and Technology
Fariborz A. Heidarloo
Industrial Engineering, Project Management, 2-year master
Project manager
Benjamin Gutjahr
Engineering Cybernetics, 5-year master
Control system
Fredrik V. Endresen
Energy and Environmental Engineering, 5-year
Motor
Aksel Qviller
Engineering Science & ICT, 5-year master Itsaso Yuguero Garmendia
Suspension Mechanical Engineering, 5-year master
System engineering
Petter Thorrud Larsen
Mechanical Engineering, 2-year master Hans Gudvangen
Exterior Mechanical Engineering, 2-year master
Suspension & rims
Aslak Brage Espeland
Mechanical Engineering, 2-year master Oluf Tonning
Exterior Engineering Science & ICT, 5-year master
System engineering
Mats Herding Solberg
Industrial design, 5-year master Eivind Sæter
Design Industrial design, 5-year master
Design
Silje Kristine Skogbrann
Media Communication and Information Technology, 5-year Håkon Johan Seiness
master Engineering Science & ICT, 5-year master
PR and media Steering and Brakes
12 ECO-MARATHON 2012
ECO-MARATHON 2012 13
2
NON-
TECHNICAL
2.1
PROJECT
MANAGEMENT
2.1 PROJECT MANAGMENT
Shell Eco-marathon 2012 was a New Product 2.1.1 PLANNING
Development (NPD) project. One of the distinct
characteristics of this type of projects is sig-
The planning stage comprises those course of
nificant uncertainty. According to Tatikonda &
actions executed to found the scope of the pro-
Rosenthal (2000) technology novelty and pro-
ject, clarify the goals, and develop the processes
ject complexity are sources of uncertainty while
needed to achieve those goals.
a team tries to make new product that can be
brand new or result of improvements on its prec-
According to Verganti (1997) two planning styles
edent. Comparing to regular NPD projects, Shell
may be utilized for new product development
Eco-marathon 2012 has unique feature which is
projects, feedback planning or reactive approach
not having marketing perspective. In high level,
and feed-forward planning or proactive ap-
the goal of project is learning through executing
proach. Choosing how the project is going to be
a project and challenge students’ knowledge in
planned in early phase in order to save time and
practical case. High level of uncertainty on the
money is another challenge. By using reactive
one hand and a project team that is formed by
approach, project team does not spend signifi-
non professional members (students) on the
cant time on solving uncertainties and gathering
other hand makes planning stage of the project
information for accomplishing tasks. This method
very prominent. Therefore, the focus of project
which is based on the notion of uncertainty
management chapter in this report is on plan-
reduction during project advancement, doesn’t
ning Shell Eco-marathon project.
need substantial financial resource and it is not
18 ECO-MARATHON 2012
time consuming but it increases the risk of facing planning but if complete change is expected
late changes during execution phase that puts feed-forward planning was used.
sizeable financial burden on project. Unlike this, For accomplishing this stage through Shell
by following proactive approach, project team Eco-marathon 2012 project, following processes
shall allocate considerable time to think about were carried out: developing individual manage-
what may go wrong during project development ment plans, creating work break down structure,
and come up with solution for each opportuni- scheduling project, budgeting and risk identifica-
ties or constraints. Performing this method is tion and management.
expensive as processing data and having experts
for anticipating uncertain information need 2.1.1.1 Individual Management Plans
substantial financial support and the danger of Why previous leaders of NTNU’s Shell Eco-
losing track of time due to drowning into analyz- marathon team were not totally successful for
ing details. Project manager shall choose suitable handling all project management knowledge
technique for planning based on project char- areas? Why same level of management was not
acteristics. In Shell Eco-marathon 2012 project applied on various knowledge areas? The answer
both feedback and feed forward approaches for these questions can be inferred from project
were used. During initiating phase Table 2.1.1 reports of prior teams as following:
was prepared which illustrates the improvement
points in developing new vehicle based on study • Absence of management plans.
performed on status of various systems of prec- • Unsuccessful efforts to properly implement
edent car DNVFF. management plans during project lifecycle
This table helped project manager to know due to lack of experience.
which type of planning approach is suitable for
various parts or systems of the future vehicle. If Lack of experience is not an avoidable factor
the scope of change is not huge, then feedback since team members including project manager
ECO-MARATHON 2012 19
are chosen among master students who are not plan of different systems of vehicle and project’s
experts. According to available project reports, goal needs to be defined during this time. A
preceding team leaders preferred to decide week after by taking team members’ individual
upon the way of managing different processes plans into account, team leader has to propose
right before their executing time. This approach an initial schedule. Project schedule should be
caused various troubles for team leaders such as realistic; meaning using large leads, lags or slack
losing track of time, inefficient data distribution is not approvable. Proposal may be reviewed and
and communication. Avoiding similar difficulties, modified by team during group sessions and
project manager needs to think about strategies be finalized (baseline) in one week. Shell Eco-
to manage and control different knowledge areas marathon 2012 will have deterministic weighted
(scope, time, cost, communication…) before schedule. The schedule shall contain work break-
starting with course of actions. Not only experi- down structure in two levels (excluding level
ence is an important factor to develop strategies 0), estimated duration of each work package,
(individual management plans), also stakehold- relations among them, their weight factor and list
ers’ opinion and comments, lessoned learned of important milestones. Preventing complexity
from preceding projects and university’s policies and delivering an easy to understand schedule,
are key factor to build a basis. Project manager resource allocation will not be considered in
shall not consider planning processes as one time schedule’s network calculations. For accurate and
task while request changes from stakeholders or realistic result out of project schedule. Updat-
project team, unexpected events and feedbacks ing work packages have to be weighted. Project
from executing and monitoring stages make manager is responsible for breaking the weight
reviewing and revising plans repetitively critical. factors and assigning them to project schedule
Precluding lack of enough time to proceed with elements. Microsoft Project 2012 is going to be
other project’s stages, it is important to spend used as time management tool. For tracking
sufficient time on planning processes. Therefore, time, each week team members have to send a
based on importance of project and required summary to project manager that includes ‘what
level of management, project manager needs to they have done’ and ‘what they will do’. Project
think how detailed the initial plans should be. schedule will be updated and be compared with
By taking progressive elaboration into account, baseline based on received summaries. Among
making a comprehensive and perfect plan on with different updating approaches available
inceptive steps which demands a lot of informa- in Microsoft Project 2012 software, recording
tion is misleading point of view about planning elapsed actual duration will be used. Results of
project. Following individual plans were gener- weekly evaluation have to be communicated
ated for Shell Eco-marathon 2012 project, after with authorized stakeholders. These weekly
few modifications: reports shall cover the status of project, roots
of variance and forecasts to be illustrated with
Time Management Plan tables, charts and especially S-curves. This plan
Team members have to read previous project can be altered by any change request confirmed
reports and choose their role in project within by project manager.
two weeks after introductory session. Next two
weeks should be assigned to think about master Cost Management Plan
20 ECO-MARATHON 2012
Project team is responsible for developing list of engineer may define risks in different systems of
activities in order to estimate demanded financial the vehicle by involvement of other team mem-
resources. Proposed budget for securing spon- bers to prepare risk register. Project manager has
sors shall be calculated by bottom-up approach. responsibility to assure that not only technical
Rough estimations from team members have risks but also organizational risks are consid-
to be aggregated to calculate required funds ered. Preventing confusion, only qualitative risk
for higher work packages. Contingency reserve analysis will be performed to determine the likeli-
has to be considered in final approximation of hood and impact of each risk. With help of other
proposed budget. This reserved will be evaluated members, system engineer is in charge of prepar-
for each level 1 work package. If project team ing preventive or mitigation actions. Reviewing
is not successful to gather enough funds as as risk register has to be done each two weeks to
proposed budget, project manager is responsible ensure proper monitoring. All team members
to do top-down budgeting based on available are in charge of reporting emergence of new
money after securing sponsors. Project manager risk by weekly summary. If required, both project
has to have a categorization for different costs manager and system engineer have to make sure
within project to have better control over them. risk response is applied completely. Risk register
Spent amount of money on each system of may be updated anytime during project planning
vehicle needs to be communicated with project and executing by anyone in the team. In order to
manager by weekly summary. Project manager communicate status of project risk, online shared
is in charge of generating clear report of finan- spreadsheet on Google Document platform will
cial status of project that includes comparison be made to simplify data gathering and distri-
of actual expenses and baseline (budget) for bution. This plan can be altered by any change
each work package. Any purchase that values request confirmed by project manager.
less than 1500 NOK can be carried on without Although these plans were improved and de-
project manager confirmation. Project manager tailed by passing time but due to lack of enough
has authority to block further procurement and information at start-up to create comprehensive
money transaction of work package if associated framework, above mentioned plans sufficed
budget has reached its limit. As reviewing money to make a foundation for managing different
transactions and tracking expenses is essential, knowledge areas. Collecting individual plans
project team members must preserve procure- result in cohesive structure that is called “project
ment documents appropriately. management plan’” Project management plan is
endorsed, confirmed, live document that de-
Communication Management Plan fines project requirements, determine expected
Apart from any communication which includes outcome, and lead project execution and control.
technical data, team leader shall be the hub for This document is integral point of team leader’s
any external communication and responsible to responsibility and s/he needs to receive the
distribute information to right person in team. approval from key stakeholders and the commit-
Due to the fact that reviewing history of com- ment of team members on its content to solve
munications may be necessary any time in future, further conflicts as it becomes project control
project team has to avoid relying on exchanging reference.
information via telephone or any other methods
that they are not traceable. Using same email
address (e.g. NTNU’s) for any communication Individual Plans Challenges
is imperative. In case of sharing information By defining individual management plans, team
with whole team, individuals can use either leader determines what have to be done during
shared project calendar on Google or use pro- project life cycle. By this mean, she/he specifies a
ject mailing list. Precluding misunderstanding, framework which team members are expected to
interchangeable information must be clear and perform in. Apart from feature of the plans, strict
easy to understand. Language of all different or easy to deal, detailed or abridged, project
types of communication (verbal and non-verbal) manager shall not assume all of team members
should be English. This plan can be altered by any will accept management style right away. The
change request confirmed by project manager. point about Shell Eco-marathon project that
should not be neglected is how individuals form
Risk Management Plan the team, voluntarily. Therefore project manager
Project manager and system engineer are re- cannot impose own preferred style of manage-
sponsible persons to handle project risks. System ment plans to team members because it might
ECO-MARATHON 2012 21
have negative impact on team performance or proper level of detailing in WBS. Level of detail
in the worst case may result in disbanding of one has influence on how project cost, duration and
or more members which put the project in huge technical complications will be taken care of. In
danger. Confusion, rejection or not having same another word, it deals with the manageability of
comprehension of project management plans, WBS segments. Reaching the smallest (lowest) el-
from team members was one of the challenges ements of WBS makes more information available
during planning stage of Shell Eco-marathon but it also has to be considered that it requires
2012 project. Due to facing rigid deadlines, re- more data processing and calculation. Sticking
sponsibilities and clear expectation from project to high level work packages makes the road of
manager, team felt limited and tried to bring achieving goal vague and less comprehensible.
comments in order to alter the content of plans Based on project goal, functional work break-
and make them easy to deal which mostly result down structure was chosen for Shell Eco-mar-
into less structured arrangement. Although some athon 2012 project. Different systems of final
opinions were considered project manager put deliverable (vehicle) were assumed as high level
endeavor to give the understanding that indi- work packages and almost the same logic was
vidual plans are required and essential to handle considered for decomposing them: specify-
project in integrate manner. If it is required one- ing reusable parts from previous vehicle if it is
on-one meeting with each team member should possible, making a list of general requirement
be held to ensure same level of comprehension is for the system, conceptual designing, finalizing
shared among them. Not following same path for design of system, production and/or purchasing
reaching goal or working out of project scope are of parts. Avoiding confusion, WBS was detailed
possible outcomes if team does not not work in down to two levels (excluding level 0) and sup-
predefined frame. Important rules and deadlines porting efforts such as PR and media activities or
shall be printed and put on the wall or a place team building sessions cannot be found in WBS
where everyone can easily see them as oral com- because this type of efforts did not have influ-
munication is not reliable method for conveying ence on scope of final deliverable but they are
important information that need to be last till considered in project schedule as milestones.
end of project. More levels were prepared by team members to
not miss any single task for delivering a system,
2.1.1.2 Creating Work Breakdown Structure but including them in work break down struc-
Work breakdown structure (WBS), (figure 2.1.1) ture was totally unnecessary as they could make
is a hierarchical arrangement which shows how time tracking, budgeting and resource planning
the project work is decomposed to manage- complicated. In presence of other team mem-
able and understandable pieces. This structure bers bottom-up assessment was done to assure
visualizes the project scope; meaning it defines all deliverables and tasks were involved. Tasks
what is and is not going to be done and delivered related to work breakdown structure of Shell Eco-
during project life cycle. As all of required steps marathon 2012 project was created as following.
to accomplish project has to be determined in Due to lack of information regarding time and
WBS, missing a work package may cause unfa- place of testing the vehicle as integrated whole,
vorable consequences. Depending on project this task is not mentioned in WBS and considered
manager’s preference and the purpose of execut- as milestone in project schedule.
ing project, WBS may be created in several ways.
Garcı´a-Fornieles et al. (2003) have introduced 2.1.1.3 Scheduling Project
following approaches (classifications) for mak- “Develop schedule is the process of analyzing
ing WBS: product oriented, process or functional, activity sequences, durations, resource require-
organizational, project life cycle, geographic loca- ments and schedule constraints to create project
tion of people. Suitable WBS is not only a tool for schedule” (PMI, 2008). Project schedule has differ-
understanding scope; also it is useful to estimate ent types of elements which may be used based
time and budget. Furthermore, work breakdown on scheduler’s choice, but following components
structure provides holistic view of project to are essential:
stakeholders which help them to comprehend
what project team is going to do. Jung and Woo • Activities: Lowest level of work breakdown
(2004) stated that the WBS provides a common structure also known as operation or tasks
view toward project for involved parties and it which are steps to accomplish work pack-
provides shared project language. Based on im- ages. Time, budget and resource can be
portance of project, manager has to decide upon allocated to this element.
22 ECO-MARATHON 2012
• Milestones: A milestone is a principal ent that this method uses predefined probability
mostly indicates completion of a deliverable distribution (beta) that results into definite
or a major step during project execution. value, it is classified in deterministic ap-
• Precedence relations: This element shows in proach.
what sequence activities or milestones shall • Probabilistic (stochastic): in this approach, a
be to reach the goal. Four precedence rela- unique statistical distribution curve is as-
tions in duling are: Finish to Start (FS), Finish signed to each activity or work package
to Finish (FF), Start to start (SS) and Start to which determines the duration by generating
Finish (SF). a random number from defined curve.
Before start with scheduling, project Each approach has advantages and dis
manager needs to decide upon advantages. Deterministic approach is easy to do
the approach for generating the and understand. It needs less time and knowl-
framework. Generally, two approaches edge compared to probabilistic approach. But
exist: according to Pohl and Chapman (1987) determin-
istic scheduling is unable to take uncertainty into
• Deterministic: Assuming fixed duration for account and it leaves no opportunity for project
project schedule’s elements is fundamental manager to handle it. Although stochastic sched-
of this approach. Two methods are widely uling aims at considering uncertainty of activ-
use in this class: Critical Path Method (CPM) ity or work package, but this approach needs
and Program Evaluation and Review Tech- considerable experience and knowledge and it
nique (PERT). By using CPM, duration of task takes more time to make a framework compared
or work package will be a single number to deterministic one.
which is derived from past similar projects or
technical opinion of experts. In PERT, three Project manager has to put enough time to pre-
numbers, optimistic (minimum) time, most pare a flexible schedule that covers entire scope
likely time and pessimistic (maximum) time, of project, nothing more or less. Project schedule
are generated for estimating duration. As is a framework to include essential elements that
24 ECO-MARATHON 2012
within a systems and among systems of the vehi- Sheduling Challenges
cle have correctly set. The outcome of this meet- How can the best fitted schedule for project be
ing was the baseline. S-curve related to baseline developed? Answering this question is a chal-
was sketched afterwards in order to be a tool to lenge for project manager during scheduling.
compare actual performance with planned one. Scheduling a project should be done by consid-
According to time management plan, Microsoft ering its resource, activities and performance
Project (MSP) 2012 software was chosen to im- measure characteristics. If project manager does
plement the framework. For sketching planned not put enough thought on identifying what is
S-curve which shows expected cumulative the status of three mentioned factors, she/he
progress, two new columns were defined in MSP might have a result that is not realistic. Herroe-
file, ‘Weight Factor’ and ‘Weighted %Complete’. len et al. (1997) have mentioned that for dealing
Following formula was set for Weighted %Com- with complexities during scheduling, knowing
plete column: its three features is essential. According to them,
three elements shall be assumed for resources to
[% Complete]*[Weight Factor]/100 analyze them properly:
By updating the project schedule weekly in 1. Number of resource type that can be zero,
software (moving status date), MSP calculates one or more than one.
%Complete column (cumulative progress) based 2. Whether the resources are renewable or non
on proportion of elapsed duration to total dura- renewable and their accessibility time period,
tion. But this does not count the importance if it is for whole project duration or specific
of element into account. That is why weighted one.
%Complete is more realistic value to rely on. 3. Availablity of renewable resources if it is in
Planned S-curve of Shell Eco-marathon 2012 constant amounts or in variable amounts.
project including weight factors was sketched as
shown in Figure 2.1.3. Six elements are recommended for understand-
ing the activties’ attributes:
As it is shown, no progress is expected between
weeks 14 to 17 due to Christmas break. The slope 1. If activities can be resumed in time of inter-
of S-curve is considerably increased between ruption or not.
weeks 24 to 30 because the work packages with 2. Constraints between activities that can be
huge weight factor had to be accomplished in mandatory, external or discretionary
this period. 3. The network of activities is probabilistic or
deterministic.
ECO-MARATHON 2012 25
4. Activities duration that can be random inte- Regarding performance measures, project man-
ger number, or random continuous duration ager shall know if penalty functions for delivering
or all tasks have same duration equal to Td. the final product, result or service in due time
5. Project deadline which means if there is no exist or not. Former condition is called regular
deadline, there is deadline imposed on activi- and latter is named non-regular measure. Mini-
ties and there is deadline on project. mizing the project delay is an example for regular
6. If cash flows are considered with activities or measures and maximizing quality of the project
not. Both amount and timing of cash flows is an instance for non-regular measure.
can be arbitrary or predetermined numbers.
Analysis of Shell Eco-marathon 2012 project
schedule by considering resources, activities
and performance measure characteristics are as
Name of Work Package Weight below:
Exterior 14
• Resources: project had two types of resourc-
Interior 9 es, work and material. Both renewable and
nonrenewable (with variable amount avail-
Propulsion 11
ability) resources were accessible for limited
Suspension 12 and specific period of time.
• Activities: Shell Eco-marathon 2012 project
Wheels and Rims 9
had deterministic schedule. Both resum-
Braking and Steering 9 able (testing a system) and non-resumable
(producing monocoque) activities were taken
Cybernetics 11
into account. Project manager thought over
Project Managment 8 three types of contraints in time of defining
relations among tasks. All of activities had
Important Milestones 27 integer number as duration which were not
Total 100 random as they were calculated based on
members’ judgement and historical data.
Table 2.1.2: Weighting of different elements Non of tasks had specified deadline but pro-
26 ECO-MARATHON 2012
ject had strict deadline of May 17, 2012 for manded money to finish project work: “Bottom-
competing in the race. Up” and “Top-Down’” In bottom-up approach,
• Performance measure: Schedule of project cost estimation has to be done for the lowest
were developed based regular measure, level components of work breakdown structure.
minimizing the project tardiness. Then estimation of activities which are related to
same work package shall be summed. By con-
2.1.1.4 Budgeting tinuing this, essential fund for the highest level of
According to Huang and Xu (1998) best solution WBS can be calculated. This approach has follow-
for financing projects with high uncertainty is ing advantages:
external subsidization. This is exactly how Shell
Eco-marathon project is financed every year. It • The most important advantage of this
is up to project team to find sponsors for project method according to Venkataraman and
and university plays no role in supporting project Pinto (2008), is forcing project team to make
financially. Kamien and Schwartz (1978) indicated detailed breakdown structure at planning
two main difficulties with external financing stage
compared to self-financing for project associated • Within this approach, as the knowledge of all
with high uncertainty: involved persons in project, even those who
are responsible for the lowest level activities
1. Finding external sponsor may be hard in such will be used for such important process; mo-
endeavors because if the project fails, few tivation of team members will be increased
tangible assets will be left which lender can due to feeling of involvement with project.
make claim on them.
2. Receiver of the fund may reveal some in- But this method also has a down side:
formation about project which might be
valuable for existing or new rivals of lender’s • By applying this method, the role of project
business. manager (or top management) in such criti-
cal task will be reduced at first steps as team
members in lower level of hierarchy who has
For attracting external sponsor(s), project team the responsibility of activities shall estimate
has to calculate proposed budget which will the costs and project manager has no control
be the basis of financial negotiations in further over the process till analysis are presented.
steps. • The chance of overestimating within bot-
An estimate should be calculated for all project tom-up approach is higher compared to
works or any element of project schedule that top-down because project team members
needs financial resource to be taken care of. This might tend to exaggerate the cost in order to
estimation that has to be approved by key stake- increase the flexibility.
holders is the budget. Taking all project costs • By considering before mentioned character-
into account is essential for budgeting. Project istics, repetitive adjustments to have best es-
manager has to classify costs in order to not miss timation is expected and this makes bottom-
any and have better control over them. There is up approach time consuming.
no single categorization logic for grouping them
and suitable approach may be chosen depend- In bottom-up approach, demanded financial
ing on project condition. resources is calculated and then provided but
in top-down approach, project team has to deal
As unexpected events which burden extra costs with predefined amount of money that has been
on project happen during execution, contingen- allocated to project by upper managers and try
cy reserve shall also be included in budgeting to proportion it appropriately among high level
process. Contingency reserve is critical financial work packages and this process continues to the
resources to reduce the risk of cost overrun. For lowest level of WBS. Top-down method has fol-
estimate the reserve, project manager needs to lowing advantages:
go through the result of qualitative or quantita-
tive analysis of risks. By considering the risks • “The advantage of top-down budgeting is
that have significant financial impact on budget, that top management’s estimate of project
required fund can be estimated. costs, in aggregate terms, often tend to be
quite accurate” (Venkataraman & Pinto, 2008).
There are two approaches for calculating de- • On contrary to bottom-up approach, project
ECO-MARATHON 2012 27
manager has full control over disaggregat- what team planned for, budget was revised by
ing the budget to work packages, which top-down approach by project manager. Practic-
results in more accurate estimations and cost ing this method, available fund was distributed
control. among high level work packages which resulted
in following figure (cost baseline).
Disadvantages of this method are as following:
2.1.1.5 Risk Identification and Assessment
• Project costs might be underestimated due An undetermined event with either positive or
to cost saving. negative impact on project is called risk. One of
• Experience is essential to perform this meth- the critical responsibilities of project manager is
od. If project manager doesn’t have enough ensuring that project’s risk are identified and as-
knowledge or understanding about work sessed. Registering risks and their characteristics
packages and related activities, improper should be performed as first step. Involving pro-
fund allocation is largely possible. ject manager, project team and stakeholders in
this step is crucial. Team members’ participation
Shell Eco-marathon 2012 project costs were clas- is important as they have to take responsibility
sified into followings: of determined risks and their responses. Involve-
ment of stakeholders is critical as they provide
• Direct costs that are particularly related to supplemental goal information. Identifying risks
activities on project. Following items are and making associated plans to respond them
included in this category: for whole project life cycle at planning stage is
• Human resource costs: this includes salary not possible as new risks emerge during project
of two team members that had to be paid advancement. Because of this, project manage-
because of their student assistant con- ment team should analyze the status of project
tract with department. iteratively in order to be sure that all kinds of risks
• Material Costs are considered. Project feature (low/high uncer-
• Operational Costs tainty) defines how often such analysis shall be
• Indirect costs which do not have direct im- done. According to PMBOK (2008) five processes
pact on the work of project. Mostly, adminis- can be accomplished in planning stage to follow
trative expenses are put in this category. best practices in risk management area:
Budgeting this project requires both bottom-up 1. Plan risk management: Within this process,
and to-down budgeting approaches. First for project manager define how risks are go-
negotiating with sponsors, project team needed ing to be handled through project life cycle.
to come up with proposed budget. In this order Importance of making this plan is having
based on historical data from previous project an accepted basis among team members to
reports and team members’ judgments, rough evaluate undetermined events. Risk manage-
calculations were done for WBS work pack- ment plan is explained in section.
ages. Using bottom-up approach, the proposed
budget was estimated at 1.095.000 NOK includ- 2. Identify risks: Result of finishing this process
ing contingency reserve. Table 2.1.3 shows more is a list of categorized risks. Chapman (2002)
detail about it. has stated that although present models
and methods in project management make
Lots of effort were put by project team and man- valuable tools available but still experts’
ager to secure sponsors in order to decrease the judgments are the key input for identifying
amount of demanded money in different items project risks. This process is fundamental for
of the budget. Beside, by gaining more informa- all of risk management efforts; therefore ac-
tion about structure and design of various sys- curacy is very important. Various methods are
tems, team found overestimations in some items available for gathering such inputs. Chapman
which was expected after utilizing bottom-up R. J. (1998) has classified all methods into
approach because for not facing any trouble in- three groups:
dividual’s assessments were associated with high • Identification managed by one risks ana-
uncertainty. At last, NTNU’s team could receive lyst e.g. reconsidering historical data.
financial contribution from Det Norske Veritas • Identification performed by analyst inter-
(DNV) of 600.000 (main sponsor) and Transnova viewing project’s key players.
of 150.000 NOK. As taken fund was less than • Identification conducted by presence of
28 ECO-MARATHON 2012
Budget item Planned Contingency all key players in form of group sessions
Cost (NOK) Reserve that is leaded by analyst e.g. brainstorm-
(NOK) ing.
From above mentioned classes, first and
Propulsion 150.000 20.000 third were used in Shell Eco-marathon 2012
Exterior 300.000 50.000 project. First, different engineers based on
historical data from previous years’ reports
Wheels and Rims 55.000 5.000 and their experience, tried to list risks associ-
Suspension 110.000 20.000 ated to systems that they were responsible
for. Afterwards, by using scenario building
Braking and Steering 15.000 5.000 (analysis) technique in group sessions leaded
Interior 10.000 5,000 by project engineer and supervised by pro-
ject manager, risks related to system interfac-
Cybernetics 50.000 10.000 es were determined. By using this technique
various possible events and their outcomes
Shipments 40.000 10.000
were identified. While scenario building, one
Trip to Rotterdam 142.000 8.000 does not count historical data and does not
include them into assessment; but it provides
Misc 40.000 0
a picture of future which is linked to past. Be-
Safety Margin 50.000 side technical (low level) risks, team members
and project manager identified managerial
Total 912.000 183.000
and organizational (high level) risks which are
mostly connected to team, its performance
Table 2.1.3: Detailed budget and managing project.
ECO-MARATHON 2012 29
the likelihood of risk occurrence and its
3. Perform qualitative risk analysis: The purpose impact that mostly measured in terms of cur-
of following this process is organizing of rency. According to Apostolakis (2004) this
identified risks in order to enhance execution approach has following benefits:
of project by concentrating on high-priority • Delivering thorough comprehension of
risks. High-priority risks are those which have system failure manners by considering
significant impact on time, cost and quality significant number of scenarios include
of project. For deciding how critical each risk different style of failures.
is, two criterions are used: probability and • It is unified method, so determining the
impact. For assessing subjectively, a scale requirements from various disciplines
shall be defined for each parameter in order involved in project.
to have common understanding of rating • By using this approach, the chance of
system. Depending on project manager and taking intricate interactions between
project feature defined structure for scales systems and operators into account will
varies. Often, “High, Medium, Low” or nu- be increased.
meric “1-10’”scale is used for measuring both • Unlike qualitative risk assessment ap-
probability and impact of risk, if occurred. proach, output of quantitative method
Project manager needs to be aware that in can be used in cost-benefit analysis.
qualitative assessment “risk is relative to the
observer” (Kaplan & Garrick, 1981). Specified This technique has following limitations:
risk characteristics may differ from one team • Not modeling human errors in time of
member to another as the knowledge and facing risk
experience of the observer are important • Not considering the culture of people
factors in organizing risks. Probability and im- who have the responsibility of handling
pact matrix was used in order to accomplish the risk, as it is influential factor in how
qualitative risk analysis in Shell Eco-marathon individuals will react when accidents hap-
2012 project. Numeric “1-5’”rating system was pen
fixed for assessing two parameters of each • Not taking design and production errors
risk. Numbers have following definition given into account.
in table 2.1.4. This approach wasn’t used in Shell Eco-mar-
athon 2012 project because it is time con-
This tool helps project team to know which suming and team members didn’t have the
risks need immediate response and which experience and knowledge about following
ones needs to be reviewed later as they are quantitative risk analysis.
not critical. Qualitative risk analysis has some
advantages and disadvantages. Startienė and 5. Plan risk responses: Considering the outputs
Remeikienė (2007) have indicated followings of identify risks process and all possible up-
as its advantages: coming and expected events, team members
• It is useful when enough experience is developed mitigation actions individually (for
not avaliable. responsible system) or in group (for inter-
• It is flexible as scales can be altered easily faces of systems). Also, project manager build
because no complicated calculations exist a list of responses for managerial and organi-
behind them. zational (high level) risks.
• It is less time consuming and cheaper
compared to quantitative risk assessment 2.1.1.6 Risk Identification and Assessment
Challenges
But this approach has following downsides There is no guarantee for reaching expected out-
as well: come out of group sessions that are dedicated to
• Less precise compared to quantitative risk identification and assessment. What makes
approach because results are shown in it uncertain is the group effectiveness during
subjectvely manner. meetings. This is a challenge for project manager
• Cost-benefit analysis cannot be done with to comprehend the status of team’s effective-
outputs from this method ness and make proper decision if it is low. This
evaluation is very critical because in time of low
4. Perform quantitative risk analysis: For accom- efficiency, not only time is wasted but also the
plishing this process, team tries to quantify results are not reliable and the chance of facing
30 ECO-MARATHON 2012
troubles during project advancement will be in- • The environment: It is important that
creased if risk management processes are based participants in risk identification and as-
on untrustworthy judgments. Chapman (1998) sessment meeting feel that the location
has developed a model for evaluating group ef- of session is proper. Quiet room that has
ficiency. According to model two factors can be enough facilities where people can find
assessed related to group sessions: “The Givens” a comfortable seat gives good sense to
and “Intervening Factors”. In his paper each factor team member and they can carry on the
is detailed into few determinants but in this re- tasks in effective way. Members don’t
port only those that are connected to the project want to spend their time in assemblies in
are discussed. which the outcome of it is not communi-
cated or put into effect. Therefore, team
• Givens: this feature describes the status of leader or director of meeting should pro-
the group, the tasks and the environment vide an environment in that participants
that are inputs for risk identification and as- feel its significance for project e.g. to hold
sessment. the meeting in structured or organized
• The group: Size of the group matters. manner.
Although increasing the number of the • Intervening Factors: The most important item
group for each session guarantees the in intervening factor is motivation. Risk iden-
involvement of various disciplines and tification and assessment sessions should be
knowledge but project manager should presented by team leader in way that team
be aware that this might result in decreas- members wish to be part of them and ap-
ing the individual contribution. Compat- prove the objective of meetings.
ible members shall be present in meet-
ings. Discordant members will decrease For Shell Eco-marathon 2012 project, risk iden-
the effectiveness of group work. While tification was done by individuals and in group
productivity of sessions is the common for ensuring, each team member benefits of own
goal for all participants, project manager contribution and team work. Meetings weren’t
shall have this awareness that members held for more than five members including sys-
may try to include their personal objec- tem engineer as director. Director had the knowl-
tives as well e.g. imposing own interest edge about technical group gathering to not let
or trying to grab the lead. Therefore, an the members distract the flow of proceedings
unbiased person who has enough knowl- by their personal interest. All of team assemblies
edge to guide the meeting should be were carried on in presentation room in order
present. to provide appropriate physical location. Before
• The tasks: Team leader must be sure that each meeting, participants were informed about
team members take their responsibilities agenda and topic, so they could make their opin-
seriously and handling various tasks is im- ions ready. Minute of each meeting was prepared
portant for them. Individuals show more of system engineer to communicate the result
commitment if they consider the task with all team members with purpose of show-
prominent. Lucidity of the tasks is impor- ing the importance of assemblies to them. Not
tant factor on group effectiveness as well. only project manager explained the significance
When the expected performance and of this step to team members, but also director
outcome is less ambiguous for partici- of meetings, clarified why project needed it and
pants in a meeting who have same level what the goal was. Therefore, everyone had clear
of comprehension about what they have and common understanding of process and its
to do, effectiveness will be increased. objective.
1 Very Low
2 Low
3 Medium
4 High
5 Very High
ECO-MARATHON 2012 31
2.2
SYSTEMS
ENGINEERING
2.2 SYSTEMS ENGINEERING
The SEM 2012 team has integrated for the first 2.2.1 KNOWLEDGE MANAGEMENT
time a systems engineering team. The Systems
Engineering team consist of two system en- One of the Systems Engineering tasks of 2012
gineers. The SE effort lays on the knowledge was to secure a seamless transition from this
management, Visual Workflow Management, risk year’s team to the next, and to put in place a
analysis and management and in designing and system for capturing and sharing knowledge for
performing a technology qualification. years to come. This is the topic for Oluf Tonning’s
master’s thesis, and more details about this will
be found there (Tonning, 2012). This section gives
a summary of the contents of Tonning’s thesis.
34 ECO-MARATHON 2012
ECO-MARATHON 2012 35
Figure 2.2.1: The template uses a Plan-Do-Check-Act approach, meaning the problem is solved
through analysis, testing, verification and then implemented
2.2.1.1 Capturing Knowledge with LEAN K-brief that Tonning (2012) has designed for cap-
Techniques turing knowledge about sub-systems and com-
A much-employed technique in Lean Thinking ponents of the DNVFF2. This technical K-brief is
(a theory for efficient development and produc- meant as a deliverable at the end of the process,
tion from Toyota) is the Knowledge brief, better summarizing the entire development, produc-
known as K-briefs. These are A3 sheets of paper tion and utilization process.
containing short and visual explanations of a
lesson learnt or a problem encountered and An example of a K-brief are available in Appendix
solved. The idea is to make the K-brief inviting to G.
the reader, and to explain to the reader in short,
summarized terms how to deal with a problem
or about the decisions leading up to a certain
design choice made in the development process.
To best capture knowledge, the process needs
to be standardized. Lean Thinking recommends
having certain learning events at equal intervals
during a development process. The most com-
mon is to have many milestones throughout the
development process, and to have the learning
events at these milestones. The teams will spend
that day or period capturing knowledge from
that interval. In particular interest are problems
solved and decisions made.
36 ECO-MARATHON 2012
Figure 2.2.2: The front page is dedicated to listing components, interface diagrams, describing major decisions
and the manufacturing process. The components are categorized as ‘New Product Development’ (NPD) meaning
designed by this year’s team, ‘Reused’ (R) meaning an unaltered design or ‘Purchased’ (P) meaning bought from a
manufacturer. Also, the components are rated for satisfaction stating how well the component behaved relative to
its expected behaviour ECO-MARATHON 2012 37
Figure 2.2.3: Page 2 is dedicated to the 3D-models, simulations and analyzes
38 ECO-MARATHON 2012
Figure 2.2.4: Page 3 is dedicated to perceived risks, a description of problems and how they were solved, and
proposed future work
ECO-MARATHON 2012 39
Figure 2.2.5: The sub-system “Wheel” broken down into its components
Requirements, functions and components are Figure 2.2.7: A requirement is satisfied by a function
strongly related to each other. A requirement and assigned to a component. A function satisfies
says why a function or component is chosen. A a requirement and is realized by a component. A
function describes what a component or sub- component realizes a function and is associated
system is intended to do, and components are with a requirement
Figure 2.2.6: The elements that make up the wheel are positioned along the diagonal. Lines between the elements
show interfaces between them (emphasized by diamonds). The Hub is the part that links the sub-system to the rest
of the system
40 ECO-MARATHON 2012
the actual realization of the concept idea. Figure 2.2.2 VISUAL WORKFLOW MANAGE-
2.2.7 explains the relationships.
MENT
It is imperative that the system model show these
relationships. When studying a single element in The Systems Engineering team employed Visual
the model, the model must visualize the relation- Workflow Management (VWM) to monitor pro-
ships this element has with the rest of the model. ject progress, enhance communication between
team members and spot problems before they
The decision to use MBSE in knowledge manage- occur. The tools used are Stand-up meetings
ment is based on MBSE’s perceived benefit of with a tailored Visual Project Board, risk man-
increasing learning and easier training of new agement, and two methods developed by the
members of a team. This is achieved by so-called SE team themselves. Details about these tools
Model-based Documentation. This means linking may be found in Oluf Tonning’s master’s thesis.
documentation directly to the element in the This report gives a summary of the tools and the
model of which is describes. E.g. a K-brief about process.
the production of the windshield could be linked
directly to the element Windshield in the model. 2.2.2.1 Stand-Up Meetings and Visual Project
This way, the model acts as a repository for Board
information. Anyone searching for information Stand-up meetings are short team meetings
about a certain element may navigate through where the team communicated to each other
the model to the element-of-interest and retrieve what they have done since last time, what will be
a list of documents, CAD files or photos that done till next time and whether or not they are
directly describe the element. For PDF files, the facing problems.
hyperlinks may also link directly to specific pages
within the document. Tonning tailored a Visual Project Board (VPB) for
using during the meetings. This is a whiteboard
The system model is found in the root directory template, where every team member lists their
of the server space for the 2012 team. It opens in tasks over the next fourteen days. Colour codes
the web browser, and the user navigates through tell whether a task is on-schedule or slipping.
the model much like Wikipedia. Figure 2.2.8 shows the VPB for DNVFF2.
Figure 2.2.8: VPB for DNVFF2. Tasks are numbered on the right-hand side. The Gantt-diagram in the middle shows
what day a certain task is due. Colors tell whether a task has slipped or not. The left-hand side is for information and
exchanging messages
ECO-MARATHON 2012 41
The SE team made these conclusions about • Average risk level; for early discovery of prob-
Stand-up meetings and the VPB: lems and mitigation
• Timeline; for overall system progress and om-
• Maximum number of active participants munication
is 7 or 8 • Wall-Architecture; for system progress on a
• 12 minutes is the maximum time micro level and communication
limit.
• Location matters during production periods. 2.2.2.3 Avarege Risk Level as a Tool for
The meetings must be held in or Tracking Progress
close to the workshop. The system engineers made a huge effort in the
risk analysis and management of the project. The
• Addressing the three questions (“what have first step in the risk management process was
I done since last time”, “what will I do till next to identify the risk. To do so a “risk session” was
time” and “what is preventing me from pro- organized. By arranging “risk sessions” the team
gressing”) makes the meetings shorter and identified and analyzed risks on a component
more relevant to the listeners level. Using a 1 to 5 scale, the team assessed the
• The meetings are best held in the morning, likelihood and impact of each risk.
during production periods due to the acces- The risks were stored in a Google spreadsheet
sibility of machines. that everyone had access to. The average risk of
• Stand-up meetings are very important during
the competition, due to the ever-changing
environment that a competition is.
• Stand-up frequency
• During production: three times a
week is sufficient
• During competition: At least twice a day
• VPBs are great tools for managing team
work on a micro-level, and for communi-
cating important messages between team
members.
Figure 2.2.10: Curve showing how average risk level developed through the project
42 ECO-MARATHON 2012
This way of visualizing project progress is a very early as possible. Since the SEM 2012 team deliv-
powerful tool for identifying possible problems, ers their risk analysis to the next year’s team – an
and monitoring whether the team is good at analysis based on experience and knowledge –
solving problems as they are identified. the next year’s team may utilize this tool to its full
In industry related projects the amount of risks potential.
that must be still in the project when the produc-
tion phase is entered should be as low as pos- 2.2.2.4 The Timeline
sible. For monitoring overall project progress the SE
team developed a way of visualizing every sub-
system’s progress using a timeline. This timeline
was drawn on the big whiteboard in the office,
next to where the team has its Monday meetings.
The timeline was also meant as a place to show
important happenings, and to induce a competi-
tive attitude in the team.
One of the main focuses of Systems Engineer- The first testing day was done indoors with a
ing in the SEM project has been to design and smooth surface. The NTNUI let the team use
perform a qualification strategy. The decision of Dragvoll’s sport center. It was an excellent place
making such a strategy was based on the SEM to test the visibility of the car, to check Shell
history where previous teams have had a lack of requirements and also to test the mechanical
testing that made the car less reliable. Besides, subsystems. The team thought that it would be
the DNVFF2 is a complete new car and therefore a good idea to test the car for the first time on a
testing all the components and its performance smooth surface where the car was not going to
is of great importance. be extremely demanded.
During the first day of testing some cones were
The Verification, Validation and testing strategy set in zigzag. At the beginning the cones were
was divided into four different and consequent quite far from each other, the steering was
Figure 2.2.13: Template for the Wall-Architecture. Orange means “in production”, red is “critical”, yellow is “pend-
ing”, green is “produced” and blue is “assembled”
44 ECO-MARATHON 2012
performing well, then the distance between the The complete drive train was tested on test
cones was narrowed and at the 3rd trial one of bench with different loadings at different speeds
the pulley mounting points that are used to sup- to measure efficiency for different operating
port the Kevlar cable of the steering fell off. The points. The test bench was also used to study
surface where the pulley’s mounting point was battery behavior for low battery voltage and over
glued to the carbon fiber was not big enough. current. The DNVFF2 had two different types of
This problem was fixed by increasing the contact batteries, one was provided by Altitec and the
area between the pulley and the monocoque. two others by Gylling.
After the first test, when the car was in the work- The second battery pack from Gylling was or-
shop one of the rims experienced a small crack, dered since the team thought that the one that
the team thinks it was due to some problem dur- was already delivered was not going to be able
ing manufacturing at HPC. See chapter 3.6. to provide enough energy to finish one attempt.
This decision was made based on the tests made
After testing and verifying the car at a smooth at SmartMotors. The issue with this decision is
surface the next step was to use Dragvoll’s park- that it was based on the tests done to Altitec’s
ing lot to test the mechanical properties of the battery, it was seen afterwards that it was not
car under a more demanding surface. The engine necessary to have ordered another battery from
was not on the car yet so the team members Gylling since the first one was able to supply
pushed the car to check rolling, braking and more than enough energy. The cybernetic and
steering capabilities. electric engineers of the DNVFF2 had almost no
time to test and that is the reason why the test
An example of the test procedures that were per- were made for just one of the batteries, the one
formed during the assembly test can be found in that was supposed to be the race battery.
appendix H.
The outcome of these tests was used to discover
The other assembly test part refers to the engine that under voltage protection was needed to
and the control system. The assembly test of prevent complete stop while racing, torque limi-
these two subsystems was held at SmartMotors. tation to prevent under voltage and over current
In order to test the propulsion with the control to prevent still stand while racing. Measurements
system a test bench that is located at SmartMo- were used to find the most energy efficient veloc-
tors was used. Not having an in house test bench ity/torque profile for the given track.
made nimpossible to test as much as the team
wanted as the sponsor was not always available.
46 ECO-MARATHON 2012
Left: SEM team at Dragvoll’s parking lot
Right: Performance test
2.3
PROMOTION
The whole project was depending on support from
sponsors to survive, and to keep them interested,
different kinds of promotion were done. Events,
newspapers, TV and social media gave both the
team and the sponsors important attention.
Graphical Profile
This years graphical profile was a
simplified version of the previous years
logo. The small collibri was still the
main part, but with green colors and a
simplified font.
Promotion Video
Student TV was hired to make a
promotion video for the team and the
project. The result was a 2:29 minutes
video that could be found on the
webpage of the team.
The monocoque was already designed and in production when the design of the interior
started.
Homepage
When deciding what kind of webpage was
wanted, the whole team agree that it was
important that each member could edit it on
their own. In this way one would get more
updates, and therefore more visitors.
53
X.X.X.X TV AND NEWSPAPERS
tekst
TV and Newspapers
To get as much media coverage as possible, the
team hired a person to be responsible for PR
and media. Even though the team got several
TV interviews and a lot of newspaper articles, it
was never close to the goal of 150 articles and 3
appearances on TV.
ECO-MARATHON 2012 55
2.4
ROTTERDAM
58 ECO-MARATHON 2012
Figure: 2.4.1: Map of the Ahoy. The track is highlighted in red. The numbers indicate corners and driving direction
ECO-MARATHON 2012 59
DNV FF2 being weighted
2.4.1.2 Technical Inspection Shell Marshalls made sure the Shell logos and
The team leader, both drivers and a fourth team team stickers fulfilled the rules. Also the suitcase
member are allowed to the technical inspection. dimensions were measured.
The SEM 2012 team decided that the cybernet-
ics engineer would be the fourth team member, The next step was to measure the brake effective-
so he could answer the specific battery electric ness. This was done on a 20% slope. Visual in-
questions. spection of the brake system was also performed.
The technical inspection started Tuesday May The next step was the visibility check. It was obvi-
15th. It was important to be one of the first cars ous to the Marshalls that the front visibility was
through technical inspection. This way more time not a problem, so it was not checked. The driver
could be spent fixing the car if it did not pass. The was fully harnessed while the rear visibility was
car entered the queue at 07.00. Seven cars was checked.
already in the queue and more kept on coming.
A Marshall walked behind the car with a stick.
First the car and both drivers were weighed. The driver had to say when he/she first saw the
Then the dimensions of the car were checked. stick and when it was no longer possible to see.
60 ECO-MARATHON 2012
ECO-MARATHON 2012 61
After the visibility check, both drivers had to be to answer the thousands of questions of the Mar-
able to vacate the car in less than 10 seconds. shall. The team was not lucky is this part because
it was the first battery electric car in the inspec-
The following test were related to mechani- tion and it was used by the responsible of battery
cal parts. Marshalls measured the tires dimen- electric cars to brief the other marshall about the
sions. They also made sure there were no sharp information that they need to ask the teams.
edgesinside the car that might hurt the driver.
The lights and the windshield wiper was also The team did not pass the technical inspection
checked. at the first attempt. Questions related to the BMS
of the auxiliary battery was not answered precise
The last step in the technical inspection is the enough. The Marshall was later brought to the
one that studies and verifies the propulsion paddock. After some research the team was able
system. In the SEM team the car is battery electric to answer the question satisfactorily and passed
so the last test was to give information and to the technical inspection.
show the electrical system of the car. This part of
the technical inspection was terribly hard for the
team, luckily the Cybernetic Engineer was there
62 ECO-MARATHON 2012
ECO-MARATHON 2012 63
2.4.1.3 Testing would no longer set reference speed to zero.
On Wednesday, May 16th, the track was open 3.5 Pressing the coasting button triggered a decel-
hours for testing. During the first test the upper eration function. The car was then consuming
part of the door flew open. a small amount of energy. To coast without any
The door was taped as a temporary fix so the energy consumption, the driver had to activate
testing could continue. The car reached its top the brake pedal.
speed of 36 km/h in section 1. High speed during
cornering was not a problem. On May 17th, it was the last testing day and UC
cars had 2,5 hours of testing. A test plan was de-
In section 2 the car shut down. The same thing veloped to test both batteries and the new code
happened twice and also one time in the mid- for the Gylling battery. The plan was to start the
dle of section 1. Due to small elevations on the testing with the Gylling battery to check if the
road the engine needed to supply a higher problem with the BMS was solved. The car run for
torque than expected. After the first shut down, 3 laps with the Gylling battery and the result of
the team was highly concerned that the battery the testing was successful.
might be damaged. The battery was checked and
found to be in perfect condition. Then another Once the team had proved that the Gylling bat-
attempt was done. Again the car shut down tery worked, the Altitec battery was checked. It
in section 2. During the last attempt this day was not able to supply the same energy as the
another battery was used. This ruled out battery Gylling battery. The acceleration was slower and
problems as the car shut down again. the top speed was not reached. After the first
stop, the car was not able to start again. The bat-
Back in the paddock it was discovered that the tery could not supply enough energy to start the
BMS shut off the battery due to high current. car.
There was also a problem with the coasting code,
causing the battery BMS to shut down. It was chosen to use the Gylling battery for the
last test. The car drove12 laps and the battery
It was decided to test both batteries to see which supplied sufficient energy.
one would provide the best chance of having a
successful attempt. The code of the propulsion More information about the batteries is provided
system was changed to reduce the maximum in the K-brief in appendix G.
torque that the engine could supply. Coasting
64 ECO-MARATHON 2012
2.4.1.4 Race result of163 km/kWh. Winds were favourable and
Friday 18th was the first race day for Urban the vehicle did not have to overtake any cars.
Concept cars. 3,5 hours were set aside for racing.
The first attempt was a safe run, where the motor The last attempt ended in failure. One of the
parameters were set to safe values. This gave a steering cords snapped on the fourth lap. The
valid attempt, and more risky parameters could cords were inspected before starting the at-
be used. tempt, and showed no signs of wear. From
inspecting the vehicle and photos taken during
Due to poor preparation routines the first at- the attempts, the team concluded the snapped
tempt was not valid. The door came loose, and cord was a result of multiple factors. Photos show
the driver was forced to end the attempt as she that the outer front wheel does not touch the
could not fix the door while driving. ground in some of the turns. From inspecting the
vehicle, it was discovered that the grease on the
The door was quickly fixed and properly secured, draglink was saturated with dust from the track,
and the second attempt was started. This at- causing the draglink to slide with high friction.
tempt was valid, and the team registered a result These factors – along with the Z-rod (section 3.4)
of 136 km/kWh. in the front suspension – may have contributed
to undesired stresses on the steering cord.
It was decided to to reduce the air gap in the mo-
tor to increase the efficiency. The result from the third attempt became the
final result for the team, giving the DNVFF2 a
Saturday the 19th was the second race day. 5th place in the Urban Concept battery electric
Urban Concept cars had 4,5 hours available for category. 22 teams entered, 20 teams passed the
racing. The first attempt was successful, earning a inspection and 15 achieved a valid result.
ECO-MARATHON 2012 65
3
TECHNICAL
3.1
EXTERIOR
3.1.1 INTRODUCTION
The design of the body and production planning Exterior graphical design was defined and ap-
was completed in autmn 2011. plied by Bilreklame to the surface of the car.
Final models were made and milling of the molds
was executed at Eker Design. Actual layup and To verify the computational fluid dynamics
production was preformed at High Performance results, the exterior has been tested in the wind
Composites in Fredrikstad. A lot of work went tunnel at NTNU.
into the final assambly of the body in the work-
shop at NTNU.
Detailed components, such as hinges, covers,
towing hook and windshield wiper have been
designed and produced. Windows for the mono-
coque had to be produced in-house, and special
equipment was made for this purpose.
70 ECO-MARATHON 2012
ECO-MARATHON 2012 71
3.1.2 STRENGTH ANALYSIS
This work is a continuation of the work per- would give the highest stress concentrations in
formed in the autumn 2011 (Endresen, et al., the car is when the car is cornering and experi-
2011). A more detailed load case and better ence unevenness in the ground. The load values
boundary conditions have been developed. The for this case are given by the calculations from
load cases are reduced to the worst case, and 2011 (Endresen, et al., 2011):
applied in the most critical part of the vehicle. A
layup configuration for the monocouqe has been Driver 70 kg
optimized and tested. The material data used in Cornering 510 N
2011 was changed due to change in production Bump 780 N/960 N
method.
These loads are applied in the left front wheel
3.1.2.1 Boundary conditions well. This is considered to be the weakest part of
To reduce the complexity of the problem, it was the vehicle, due to the door opening and little
decided to reduce the number of load cases and transverse support in the front. The suspension
only focus on the most critical load. The case that loads are located in the wheel and connected to
72 ECO-MARATHON 2012
Figure 3.1.1: Suspension system modeled with RB2 elements, loads and moments are applied in the wheel center
and transferred into the body through the stiff suspension system.
the body through RB2 elements. When applying this load case, the car is fixed in
each hub with free rotating in longitudinal direc-
When simulating the loads on the front left tion, which will represent real testing conditions.
wheel, all other wheel wells are fixed. This is to re-
move the large reaction forces in these areas. The 3.1.2.2 Layup
forces will generate a high moment in the other The layup started with applying two layers of
wheel wells, creating unrealistically high stress DB420 (Appendix B) on the entire body in a
concentrations. The focus will only be on the crisscross pattern. The floor of the car was rein-
front wheel well, therefore, the other wheel wells forced with 10 mm thick Divinycell 80 core to add
are of no interest. To remove any high stress stiffness and to withstand the stresses from the
concentrations in these areas, the wheel wells are driver. Two extra layers of DB420 on both sides
sufficiently fixed. of the core were added to give the sufficient
strength to the underside of the body.
To verify that the car is sufficient durable, the The wheel wells were considered to be the most
load case given by the SEM rules are also tested. critical parts and needed the most reinforce-
ments. A 6 mm Divinycell 80 core was placed on
Driver 70 kg the side walls and total of 4 layers of DB420 were
Roll bar load 700 N laid over the entire wheel wells. The roof was
Towing hook load 2000 N reinforced with 6 mm thick Divinycell 80 core.
Figure 3.1.4 shows the overall layup for the car.
ECO-MARATHON 2012 73
4 mm disp.
8 mm disp.
6 mm H-80
2 x DB420
10 mm H-80
Figure 3.1.4: Layup for the car, placement of 4 layers (top), core reinforcemenst (middle) and 2 layers (bottom)
ECO-MARATHON 2012 75
Stress concentrations
Figure 3.1.5: Stresses in the most highly stressed carbon fiber ply
3.1.2.4 Conclusion
The FEM analysis of the monocouqe will make a
basis for the production. This work also reveals
critical areas and gives an indication on how the
laminates will behave. The final configuration of
how to implement the different laminates will be
decided in cooperation with the experts in this
field. The final configuration will also be highly
influenced on the expert’s expertise and produc-
tion technique during production.
76 ECO-MARATHON 2012
ECO-MARATHON 2012 77
Figure 3.1.6: A draft angle analysis done in Catia to discover what needed to be improved before the production.
78 ECO-MARATHON 2012
Lines around the rear hatch
and what should be changed before production. The final result was a .step-file that was sent to
Some of the draft angles needed to be improved Eker Design, and the production could begin.
(up to 7°), and the split line had to be moved. To
find the split line, a split line analysis was done
in Catia, and then added to the models. (Since
SolidWorks do not have such functions)
ECO-MARATHON 2012 79
3.1.4 PRODUCTION
In autmn 2011 different production methods were decided to be made with seamless mod-
were considered. The method chosen was highly eling paste. Jackopor would deliver the base
dependent on sponsors and expertise. At the end molds and Svas Kjemi would deliver the epoxy
of the semester in 2011 all sponsors were in place paste. Further information about the production
and the production method of the monocouqe method and molds is given in the project report
and molds was finally set. of 2011 (Endresen, et al., 2011).
For the production of the monocouqe it was
chosen to use vacuum infusion in cooperation 3.1.4.1 Milling
with Paal Fediuk at HPC in Fredrikstad. The molds Before milling could start, the expanded polysty-
80 ECO-MARATHON 2012
rene (EPS) (Jackopor 300), delivered by Jackon, The two blocks were first rough milled down with
had to be glued together to form the correct an offset of 10 mm to form the basis for a hard
size. Since the mold was wider than the standard shell. Secondly, a finer milling was performed to
block size, two and two blocks had to be glued even out the rough grooves from the first milling.
together. The blocks were glued together and
glued to a piece of MDF plate. A plate of MDF After the milling, all the milled off EPS had to be
was used on both molds to be able to fasten removed and the surface was cleaned to ensure a
the molds to the milling machine. Screws were good bonding between the EPS and epoxy paste.
used to attach the plate to the floor in the milling A layer of epoxy paste (P25) was laid over the two
machine. Epoxy glue was used to glue the EPS parts in a thickness of 15 – 25 mm. The epoxy
blocks and the MDF plate. The final result was paste consists of two components mixed togeth-
two EPS blocks of 1555 x 3124 x 920 mm (top) er forming a hard material. This material can be
and 1555 x 3124 x 560 mm (bottom). milled and shaped into the desired form.
ECO-MARATHON 2012 81
Rough milling of EPS blocks at Eker Design in Fredrikstad
After curing of the paste, a new round of rough material. The final part of the top mold had to
milling was performed followed by a round of be laid with P26, a material with higher density
fine milling, resulting in a 10 mm thick layer of and viscosity. There were some concerns that the
epoxy paste. This round of fine milling cut down differences in material properties could create
preparation work before the layup, ensuring a cracks during hardening, but the likelihood of
smoother surface. these concerns was considered too be small.
Since there was not an option in postponing the
Due to some calibration and cleaning of the mold production, the last part of the top was
mixing machine, there was a lot of P25 material therefore laid with P26.
going to waste. This resulted in a shortage of P25
82 ECO-MARATHON 2012
Epoxy paste being applied by Markus Potthoff, a representative from Ebalta
Epoxy paste finished laid at the top part. The difference between P25 and P26 is clearly shown (P25 in light brown)
After the milling was finished at Eker Design, of polyurethane paint. This is an important step
the molds were transported to HPC were the to fill all the pores and protect the molds. Some
final preparations before layup was performed. types of paint can react to the epoxy resin mak-
Cavities and imperfections in the epoxy layer was ing the final product impossible to extract from
filled and fixed and a final sanding smoothed out the mold. It is therefore important to use the cor-
the surface. The molds were finalized with a coat rect type of paint for this purpose.
84 ECO-MARATHON 2012
Tracing of lines for the lights was the final step for the milling machine
Finished prepared molds, treated with a layer of blue polyurethane paint at HPC
86 ECO-MARATHON 2012
Waxing of molds
The mounting points for the suspension were and used to mark out the suspension mounting
reinforced with carbon fiber patches, creating a points in core material. Then a round cut of 70
solid carbon fiber piece to mount the suspension mm in diameter was made around the marks,
in. This was done to prevent drilling holes in the creating circular holes in the core material. The
core material, which will weaken and ruin the size and number of layers of carbon fiber patches
sandwich construction. A template was prepared was decided on site.
88 ECO-MARATHON 2012
Side wall reinforced with 6 mm Divinycell thick core and carbon fiber patches for the mounting points
6 mm Divinycell + 2 x DB420
10 mm Divinycell + 2 DB420
2 x DB420
6 mm Divinycell + 4 x DB420
4 x DB420
6 mm Divinycell + 4 x DB420
3 mm Sorix + 4 x DB420
8 x DB420
The carbon fiber mat used for layup was a ±45°, When all of the carbon fiber and core material
the orientation on the car was not considered to was placed onto the mold, the molds were ready
be that important as long as the mats were laid to be prepared for the resin infusion.
in the most material efficient way. This resulted in
crisscross pattern, ensuring strength in all direc-
tions, and minimum loss in material.
ECO-MARATHON 2012 89
Peel ply applied to the top part, held in place with textile spray glue
First a layer of peel ply was placed over the car- with the same sealer tape.
bon fiber. This is a layer that is easily removed af-
ter curing, preventing resin flow mesh, tubes and After placing tubes for resin inlet and outlet,
plastic bag from sticking to the finished product vacuum was applied on the edges of the mold.
and ensuring a clean surface. Air leakages were discovered with the use of an
air leak detector and sealed with tape. Then the
One layer of resin flow mesh goes on top of the resin was sucked from the center and out to the
peel ply. This is used to easier distribute the resin edges.
through the carbon fiber.
The infusion was stopped by clamping the inlet
At the edges of the mold, the resin flow mesh tube after the resin started to exit all the outlet
was placed 80 mm from the edge. This is to slow tubes. Vacuum on the outlet tubes was still run-
down the resin at the edge, preventing the resin ning after the infusion was completed to extract
to exit before all the fibers are infused. By using air trapped inside the fibers. The parts were set to
multiple exit tubes and clamps, it is possible to cure in room temperature. Plastic bag, resin flow
further control the resin. mesh and peel ply was removed after the curing
process. The bottom and top part was removed
Finally the vacuum bag was placed over the from the mold with the use of wood wedges and
molds. The bag must have sufficient size and brute force. Final stage was to post cure the parts
slack to fit into every corner of the mold when at 80°C for 6 hours. Right after the first curing, the
vacuum is applied. The plastic bag is attached carbon fiber can be soft and pliable. To ease the
to the vacuum sealer tape around the edges. process of releasing the carbon fiber from the
When attaching the plastic to the edge, waves mold, it can be a good idea to perform this task
are added along the edge, to create the sufficient before final curing.
slack that is needed. These are then sealed off
90 ECO-MARATHON 2012
Resin flow mesh, held in place with pieces of vacuum Resin flow mesh at the edges of the mold, the resin
sealer tape slows down considerable
Tubes for vacuum and resin. Resin trap is placed before the vacuum pump, preventing any resin entering the pump
Layup of the back hatch
92 ECO-MARATHON 2012
Indent made for the window with the use of 3 mm Sorix
3.1.4.5 Wheel well covers The production of the front covers was made in
Since the bottom part of the monocouqe has four parts. The two molds that made up the front
integrated wheel wells it was not possible to use covers on each side were not glued together,
the bottom and top molds to produce the wheel making it easier to fix it on the car on a later
well covers, as done in 2008. Therefore separate stage. Because of the porosity of the mold mate-
molds were produced at NTNU. rial, it was not possible to use vacuum to apply
pressure during production. To apply pressure
The milling machine at IPD is a 3-axis milling to the fibers, a new method was established.
machine capable of milling maximum 70-100 By creating a water reservoir over the mold, the
mm deep. The molds were milled in two separate pressure from the water is used to apply pressure
parts for every wheel well cover. On the sides an to the wet carbon fiber. After filling up the reser-
additional of 40-50 mm was milled to ensure suf- voir with water, it is possible to remove wrinkles
ficient size on the covers. and air inside the fiber with the use of a roller. All
parts of the front wheel well covers were made
Front covers are design to be an integrated with one layer of carbon fiber.
part of the car. To cut costs in production, it was
decided to mill the molds in a cheaper material. For the rear wheel well covers, the two molds
Since these covers only needed to be produced that made up one cover were glued together.
once, and then be fixed on the car, the molds Rear covers are produced with one layer of
could be scrapped after production. carbon fiber twill on the sides (exposed carbon
fiber), one sheet of carbon fiber covering the
The molds were sanded down and filled with whole part and strips of reinforcements on the
filler and then sanded down again. After final edge to further stiffen the cover.
sanding the surface was painted and coated with
release agent. First the rear wheel covers were produced with
wet layup and vacuum, but due to air leakage,
94 ECO-MARATHON 2012
vacuum was not achieved. This resulted in air reduce weight. For the front, the assembly tech-
bubbles trapped inside the fibers and heavy cov- nique will result in a total of two layers, making
ers, these were not approved. New covers were the front part more than capable to withstand
produced with the much simpler and successful the stress of normal use. Lifting or similar actions
water reservoir method. should never occur on the covers or in the wheel
wells. Lifting should always be done onto the
Since none of the wheel well covers will contrib- original monocoque structure on both sides of
ute to the overall stiffness of the car, the parts are the wheel, by four or more persons.
produced with a minimum use of carbon fiber to
96 ECO-MARATHON 2012
Gluing of the firewall to the bottom part
Screw connection plates were made to hold the two parts together
Rough cutting of the monocoque. Thin red tape was used to strengthen the marks from the divider, making sure
that the line would not disappear during cutting
After curing and post curing at 80°C for 6 hours, The outer side of the seams and all edges of the
the additional flange was cut away using a pneu- monocouqe and doors were sanded by hand to
matic cutting tool. Since the carbon fiber dust ensure smooth and even edges. The edges and
conducts electricity, the major part of the cutting seams were sanded with the use of rough grit
was done outside with sufficient protective gear sand paper and files. A divider was used to mark
such as respirator, glasses, hearing protection the cutting line, 10 mm from the indent edge.
and two pair of gloves. By using pneumatic tools,
the dust would not be able to ruin the tools, and 3.1.4.2 Wheel well covers
ventilation do not become that critical when The front wheel well covers was cut around the
working outside. Rough cutting the windows and edges and fastened to the monocouqe with
doors was also performed outside. the same technique as for the firewall, with
one carbon fiber strip of 100 mm. The task was
98 ECO-MARATHON 2012
Carbon fiber strips in the seams, holding the three parts together
performed in two operations. First the side part layers of carbon fiber after fastening the covers to
of the wheel well covers was fastened, the molds the monocouqe. This is more than adequate ac-
was used to hold the side part in the correct cording to strength and stiffness for the covers.
position throughout the fastening and curing
process. The decision to postpone the final cutting of the
covers was made to ensure that they would be
Secondly, the bottom part was fastened, using as tight as possible around the tires. This proved
the same method with support from the bottom to be difficult since the alignment of the front
part molds. suspension is a challenging process and even
harder without being able to mount the wheel. A
In total, the front wheel well covers consist of two template of the wheel was prepared and after a
ECO-MARATHON 2012 99
Both parts of the front wheel covers fastened to the monocouqe
quick alignment of the suspension it was possible covers, the covers were constantly adjusted due
to make marks for the perimeter on the covers. to ongoing tweaking of the rear suspension. The
final cuts for the rear covers were also performed
The final cut of the bottom part was done after in Rotterdam.
the front suspension and steering was in place. Fastening method of the rear wheel covers is
Some modifications to these parts had to be ex- described in section 3.1.7.4.
ecuted during the whole process, mainly due to
constantly fine adjustments on the front suspen- The constantly realignment of the suspension in
sion. The final cut was performed in Rotterdam, front and rear lead to a bigger air gap around the
the day before race day. wheels than what was desirable. But taken in to
account the complex process of fine adjusting
The rear wheel well covers were cut around the a suspension system and eliminating any risk of
edges and fitted to the car. A rectangular slot was scrubbing, the end result is more than satisfying.
cut out for the wheel. As for the front wheel well
3.1.4.4 Surface finish production. After all the gaps, seams and imper-
To create a smooth transition between top and fections were evened out with body filler, all the
bottom part and the front wheel well covers and surfaces were sanded down. The car was sanded
body, the seams were filled with body filler. The down 3 times; first with 120 grit paper, followed
filler was sanded down and new filler was applied by 400 grit paper and finally 600 grit paper.
to fill in the remaining gaps. This process was
repeated until the seams were perfectly smooth. Just before foiling, the surface was cleaned
several times with alcohol to remove any dirt and
The body filler was also applied to areas around dust.
the car was there were imperfections from body
After a quick hardening of the gel-coat, several layers of fiberglas infused with polyester was applied
Vacuum forming of the side window
Milling of air channels in the vacuum table, connecting Windows assembled on the car
the holes drilled out in the ply wood
The lights of the former car was vacuum formed in plastic, and used three different LED-lights for high beam, low
beam and indicator lights.
3.1.6 LIGHTS
As a normal car, the Urban Concept cars in Shell tic had melted, but everything did still work as
Eco-Marathon needs to have the same lights that it should. The front lights were attached to the
are required on the streets body with velcro on the inside.
Team goals
- Each light must not weigh more than 150 g.
3.1.6.5 Concept Development The sketches and ideas could later be combined
Since the overall shape of the lights were into CAD models in solid works, where it would
developed last semester, the work that had to be be easier to plan and place LEDs. In the end all
done was to figure out how to finalize the design the best ideas were combined into one finished
and make it possible to produce. concept.
Indicators
Indicators
Low beam
Figure 3.1.13: The final front light and rear light concepts.
3.1.6.6 Final Concept used. The indicator lights are orange Star LEDs
The final concept basically looks like last semes- palced between the strips.
ters concepts, but have diods as light sources
instead of the laser lights. The front lights have All the LEDs are mounted on a vacuum formed
strips of LEDs in top and in the bottom, and in plastic part, made of spraypainted PET. The whole
between one can find the indicator lights, which light is mounted on to the car with velcro.
also are 5 mm LEDs. For high beams, one Star LED
is place on each side of the car, in the middle of
the two low beam strips.
The final front and rear lights mount in the finished car. The lights are attached to the car with velcro on the inside.
Gulwing
Lambo
Suicide
Spring loaded door handle made in aluminum safetly secures the door in place. A flush finish ensures little
interference with air flow.
3.1.7.3 Back Hatch Mounting The brackets performed very well in mounting
Attachment of the back hatch was considered to the back hatch. The flexing of the door and the
be easy and development of a mounting fixture tight fit of the brackets made a perfect attach-
was postponed until final assembly. Many dif- ment. During racing, strips of foil were added
ferent concepts were considered, but the desire around the seam of the door. This was to make
to keep the surface clean and smooth gave a lot the door waterproof and to improve aerodynam-
of restrictions. In figure 3.1.22 some of the early ics.
concepts are seen. A new SEM rule also stated
that all covers and doors must be mechanically
attached, so the old solution with Velcro and a
tight fit was not adequate for the new car.
3.1.7.4 Side Cover Mounting mate foil were applied around the seam before
Attachments of the side covers were also post- racing. This further improved the transition and
pone until final assembly. A solution to attach attachment between the monocoque and side
the covers was not established until a couple covers.
of weeks before departure, due to other more
prioritized tasks. As for the back hatch, a smooth The solution proved to be sufficient and no prob-
and clean look was the most important factors lems were experienced during testing and racing.
when designing the mounting fixtures. Different Assembly and disassembly of the side covers can
concepts were evaluated and a final concept was be a bit difficult. The screw connection is not easy
chosen. See figure 3.1.23 for the different con- to access, but sliding under the car when placed
cepts evaluated. on the ground makes it easier. A new solution to
improve assembly can be developed, but since
A solution with the use of rubber bands and the covers are just essential during race , this
screws was the solution chosen. Two screw con- should not have a high priority.
nections were placed on the underside of the
covers. Threaded aluminum disks were glued
onto carbon fiber brackets and glued onto the
side of the wheel well.
3.1.7.5 Towing Hook The towing hook was milled down to the correct
A new towing hook was design and produced for dimensions and a rectangular slot was prepared
the new car. The old towing hook for the DNVFF in the monocoque. Araldite glue was used to
consisted of a steel threaded bar formed in a U- fasten the hook to the monocoque.
shape, attached to a steel plate glued inside the
car. Reusing this solution was never considered. The towing hook has never been tested in real
There was improvement potential concering conditions or but should withstand loads up to
weight, looks, strength and aerodynamics. 2000 N. Final towing hook weighed 40 g, com-
pared to the old towing hook of 120 g, is this a
To keep the weight down, the towing hook great improvement. The hook is placed in the
should be produced in aluminum. Because of the split line, standing horizontally outwards. This
material properties of aluminum, welding was is the placement where the hook has minimum
not an option. With a T-profile in aluminum the influence on the airflow. The car should never
towing hook could be produced in one piece. be lifted in the towing hook, since the hook is
designed to handle horizontal loads only.
Figure 3.1.25: Strength analysis of the towing hook. The 2000 N load yield maximum stress of 110 MPa.
3.1.8 FOIL
The surface of the car is important for the perfor- the years, four layers of paint have therefore been
mance of the car. Just surface friction could have put on the car, which in the end have added a lot
a large impact on the result, so the team was of weight. This problem would be avoided if foil
determined to put a lot of work into making it as had been used all the way, as well as the surface
perfect as possible. would have been smoother. Based on these argu-
ments, the team desided to foil the new car.
3.1.8.1 Paint VS Foil
The former car have been painted every year,
exept the first year when it was foiled. Through
Idea generation
The ideation process of the foil had to be done really
fast, the desition to print drawings of the car and
sketch on these would be the fastest way to do the
job. When a large number of drawings had been
produced, selected ideas were tested in solidworks
to see the result properly.
3.1.8.2 Production and Mounting surface that was wanted. All edges and scratches
The printing of the foil was done and sponsored were patched with foil, so that the final result was
by Printing in Oslo, while the mounting was an almost perfect surface with minimal aerody-
sponsored by Trondheim Bilreklame. Illustrator namic friction.
files of the material was sent to Printing, and
when the car was transported to Bilreklames
graage. The foiling job was done in less than a
day.
Before any testing can commence the equipment When calibrating the wind tunnel for the DNVFF2
in the wind tunnel needs to be calibrated. There there were some problems. The sensor signals
are two main measuring systems that needs to displayed random interference on all channels,
be calibrated; the load cells for measuring drag, and a lot of time was spent on trying to identify
lift and moments, and the pitot/monotube sen- and eliminate this. Different amplifier channels
sor for measuring the air speed in the tunnel. were tested, signal filters were used and even a
All sensors are routed through amplifiers and power supply filter was employed, all to no avail.
optional filters to get more accurate and visible The team even searched the building for any
readings. These amplifiers have to be tuned to equipment that might have been causing the
get the signal within a desirable range, so that interference, but could not find anything. In the
it always can be visually checked during the end the only solution was to run very long sam-
calibration process. A base reading has to be per- ple periods, which meant the calibration process
formed at the start of the calibration process, this took a very long time to complete. To shorten
is done with the test specimen securely in place the calibration time only the horizontal load cells
and the wind tunnel fan turned off. The program measuring drag were calibrated and the rest of
used to read and sample values is a LabView the calibration factors were taken from a previous
3.1.9.4 Conclusion top of the body, and the only signs of turbulent
Wind tunnel testing verified the results from the flow were behind the front wheel wells (as ex-
CFD analysis performed in autumn 2012. The CFD pected). This flow separation can be reduced by
analysis gave a drag force of 6.33 N when travel- developing efficient front wheel covers.
ling at 30 km/h. Compared to the results from the
wind tunnel testing, which gave a drag of 9.03 N Covering the tunnel geometry proved to have
with air speed of 33.7 km/h. Measured in same a negative effect. The drag increased and lift
speed, the result from the testing would give a decreased. But due to the wind tunnel testing
drag of 8 N. configuration, the decrease in lift can be proven
An increase of 20 % in drag from the CFD to the to increase down force in real conditions.
wind tunnel results is as expected. The details on
the real car are much more complex than for the Diffusor guide vanes proved to have a positive
simplified 3D model. All seams, unevenness and contribution to the drag. But more thorough
misalignments of doors and covers will all lead to analysis of the effect and placement must be
an increase in drag. These are all factors that were executed before these changes can be imple-
not considered in the CFD analysis. mented.
The large variance in lift is mainly due to lifting
the car higher in the wind tunnel to eliminate It is also important to note that the aerodynamics
the moving road problem. An increase in ground counts for only about 50 – 60 % of the total resist-
clearance will increase the lift. The lift is also in- ance in the car when travelling at 30 km/h. With
fluenced by the fact that the ground is stationary, the recent changes in the competition over the
moving more air over the car, creating lift. years with more stops and turns, 30 km/h is the
maximum speed used only for small parts of the
The results from the wind tunnel testing show track. Therefore, large aerodynamically changes
that the car has a very low drag coefficient. There which will increase total weight can be proven to
was observed very little flow separation over the be negative for the fuel efficiency.
car. The flow was completely attached over the
3.2.2 DASHBOARD
To have a dashboard is not a requirement from car stiffer. The top surface was effectively hiding
the Eco-marathon rules, but it would help cov- most of the components in the front of the car,
ering all the mechanical and electrical parts in and making the overall impression a lot tidier.
the front of the car, as well as being a mounting Most of the buttons used by the driver during the
surface for buttons that did not fit on the steer- race were mounted on the dashboard instead of
ing wheel. the steering wheel. This would make the driver
change the grip everytime a new command
3.2.2.1 Last Cars Dashboard needed to be initiated. Sometimes this would
The dashboard in the former car was made of probably affect the drivers performance.
pre -impregnated carbon fiber with a foam core.
It was attached to the wheel wells on each side The dashboard was attached to the wheel wells
of the cockpit, and did in addition to being a with screws, and could therefore be taken out
dashboard, work as a cross beam to make the anytime if reparations or adjustments needed to
be done. This could be useful both when working Control System
on the dashboard, and when when working on All cable from the steering wheel and from the
the mechanics and electronics in the front. buttons on the dashboard needs to be organised
and led to the control system.
3.2.2.2 Interfaces
When designing the dashboard, the interfaces to Monocoque
four different sub-systems needed to be conci- The dashboard needs to be attached to the
dered. monocoque in some way. Preferably to a rigid
part, like the wheel wells to support the steering
Steering Wheel wheel in a best possible way, but it could also be
The dashboard needs to be able to support the attached to the floor or the shell.
steering wheel and keep it stable all the time
while driving. In addition to the steering rod, Steering
the cables from the steering wheel needs to go Must be a bridge between the steering wheel
through the dashboard, either through the rod or and the steering system.
in another way.
Figure 3.2.2: An 3D-model with the outlines for the dashboard were given to group
working with idea generation
The students working on the dashboard were using UGS NX for the surface modelling, while the rest of the interior
was designed in SolidWorks
3.2.2.6 Cooperation With Other Students ideas. In this way one could make sure that the
The design process around the dashboard were process moved in the direction that was wanted,
done in cooperation with fourth year students at and that the finished product would fit into the
Institute of production and materials. As a part of car.
the course PuMA 8, where one of the goals was
to learn surface modelling in NX. The final delivery from the PuMa students was
several early concepts that could be used as
The design process were a iterative process a baseline to develop the finished dashboard.
where the team gave the students an outline Because of a short time limit, the last part of the
of what was wanted in the form of 3d-models, design process was done by the designers on the
basic dimensions and rules. In a few weeks the team. The product was taken from early concept
students produced initial sketches and came up phase into a finished concept and production in
with a lot of ideas. In the start the goal was not to a short time, to make sure that no other sub-sys-
limit the students to much, and in this way come tems would be delayed due to the late produc-
up with as many new ideas as possible. tion of the dashboard.
Figure 3.2.4: Concept 2 consisted of a light construction attached to both the monocoque shell and the floor. It had
no removeable parts.
Figure 3.2.5: 3D-model of front beam mold ready for Finished mold ready for production of the front beam.
milling. The mold is milled in two parts and then glued
together later.
3.2.2.8 Final Concept the the second concept it would also give bet-
After a short meeting the team decided to make ter mounting access beacuse of the removable
a dashboard similar to the first concept, but with cover on the top. This would make the job for the
simplified curves. This way the concept would mechanics and the cybernetics a lot easier. The
have few double curved surfaces and be easier to production would also be a lot easier.
produce in carbon fiber.
The dashboard was produced in two separate
The reason why the first concept was chosen, parts, the front beam and the top cover. The
was mostly because it would provide much free molds were milled out of ebaboard and sanded
space for the feet and simple access. The team down. The carbon fiber was then layed. Three
could not risk that the driver would not be able layers of carbon fiber was used in each part. The
to evacuate the car quick enough, and therefore front beam was reinforced with a Rohacell core.
not pass the technical inspection. Compared to The end result was glued in place inside the car
and then foiled with matt black foil.
Start/Stop
The finished dashboard with holes for emergency shut-off button, start/stop button, windshield wiper button
and steering rod.
Both the front beam and the top cover weas foiled with matt black foil for a better finish.
The main sponsor logo was also placed on the top cover.
The former steering wheel in the DNVFF was made of carbon fiber wrapped around around a foam core. This,
in addition to the use of really lightweight buttons gave the steering wheel a low weight.
Because of the way it was contructed, the steer- • 6 engine control buttons.
ing wheel had no cover for the wires in the back. • Horn.
This could be an advantage when mounting it, • Indicators (left/right).
but did not look very nice. • High beam.
• Low beam
3.2.3.8 Three Different Concepts with the thumb, and the rest with the index fin-
All the ideas from the ideation process were ger. On each side of the steering wheel remove-
grouped into three different concepts, all made able lids will be placed to make the mounting
with different production methods. and wiring simpler. All the wires are pulled from
the buttons, through the tube and the steering
Concept 1 rod, and out behind the dashboard.
The first concept can be produced by cutting out
a foam core in two parts, and put a tube for wires Because of the production method, this would be
through it. Carbon fiber can be wraped around it, a really lightweight product, with quite rough fin-
and holes for easy access cut out. ish. The production is simple, but a bit more time
consuming than the other concept.
The basic idea is that all buttons can be accessed
without changing grip; all the control buttons
The steering wheel was vacuum formed in two Holes for the buttons were drilled in the plastic
parts
3.2.4 SEAT
To be able to performance the best, the driver the finish and ergonomics have generally been
needs to have a comfortable driving position. poor beacuse of an extreme weight focus. Three
The seat is one of the most important factors in different seats have been made for the DNVFF
providing this. over the years. Two of them have had the pos-
sibility for adjustments, while one of them was
3.2.4.1 Former Seats customized to fit only the selected driver. All the
When looking back at former project reports, it seats were made of carbon fiber to make them as
seems the seat have never been prioritized. It has light as possible.
always been one of the last parts to be made, and
Firewall
Seat belts
Dashboard
Door
Monocoque/Firewall Door
The monocoque and the firewall are surrounding According to the rules the driver must be able to
the interior, and the seat must be attached to one evacuate the vehicle in less than10 seconds. This
of these. means that the seat must not prevent the driver
from opening the door and getting out in time.
Dashboard/Steering wheel
The seat has to be placed in a way that makes it Seat belt
possible for the driver to reach both the dash- A 5 point seat belt must be mounted, and it has
board and the steering wheel, while still having to fit around the driver sitting in the seat.
a comfortable driving position. Some of the
buttons on the dashboard are rearly used in a
driving situation and does not have to be within
Lumbar support
15-30°
3.2.4.5 Basic Ergonomics The parameters were set by doing a lot of test-
The car was already designed and put into ing, first in the car mock-up, and later in the
production when the design of the seat started. finished car. A test person, either the driver or a
The seat had to be designed to make the driver girl at about the same size were used. In addi-
comfortable while driving the car. tion recommended dimensions and angles were
found in the Human Scale collection.
A normal car seat is usually designed to fit the
range of people between 5 percentile women When driving a car in Shell Eco-marathon, it is
and 95 percentile men. It was already known that hard to determine wanted driver position.Most
the driver was 50 percentile woman. Parameters times the decitions were based on the drivers
like the distance from driver to steering wheel, wishes. It was always important to keep a good
perfect arm angle, back angle and where to place balance between a close steering wheel, and one
the lumbar support could be set to exact values further away which would be more comfortable.
instead of a range. It has to be remembered that
the seat should also be usable for other persons.
A full scale mock-up was used for testing before the monocoque could be used for this purpose
Fast mock-ups of different concepts were built during the process to validate the diffent ideas
Figure 3.2.16: Idea 1
3.2.4.8 Three Ideas support when tightened. This idea would prob-
The ideation process resulted in a lot of sketches, ably be the lightest solution, but it would not
and to get an overview of these, they were or- be adjustable as it was planned at this stage. If
ganized into three different idea groups. Because the idea had been developed further, adjustable
of the lack of time, these were not finished con- fastening points could have been added, and
cepts but rather more developed ideas. therefore made it more flexible.
3.2.4.9 Selecting Ideas most logical choice. It was light, had adjustments
It was hard to choose the final concept. Discuss- and would be easy to produce. This also needed
ing with team members and other designers, it to be developed further, but this was not con-
was early agreed that idea number 3 would prob- cider beeing a time consuming job.
ably create problems during the technical inspec-
tion. Both idea 1 and 2 were very interesting. Idea
1 was really lightweight, while idea 2 had all the
adjustment possibilities.
3.2.4.10 Detailing of the Final Concept there was no time left in the end to produce this
To make a final concept the basic ideas from idea mechanism.
2 were taken further. A lot of changes were made.
The angle adjustments in the pillow were re-
The back support got a totally new and more moved. It was found unnecessary during testing,
exciting shape. Stretched mesh was replaced by and it would add extra weight to the car. The final
thin pillows along the spine supports and across pillow was milled out of lightweight foam, and
the lumbar support. attached to the floor with velcro.
To get an idea of how big the mirrors should be, different cardboard models were made with the required area. By
using these models together with the sketches it was possible to make 3D-models of the ideas
Concept 3
Concept 1
Figure 3.2.23: The three different concepts seen from the drivers view. Closeup of the different concepts are shown
below
3.2.5.5 Different Concepts small, they can be hard to use when mounted on
The result from the ideation process was devel- the outside of the car.
oped into three different concepts. All of them
were really small (25-30 cm2). One was exterior, Concept 2
while two were interior. Was the first interior concept. It had a long shape
so it could be placed on the a-beam. With joints
Concept 1 in each end it could be adjusted to fit the driver.
The only exterior concept, and it has a flat shape When testing the mirrors later in the process it
which gives it a light and floating look. The shape was discovered that it could be hard to spot cars,
is made as aerodynamic as possible, but will because it was too narrow.
always induce some drag. Since the mirrors are
The finished mirrors seen both before and after beeing mounted in the car
3.2.5.6 Production and Finished Product The finished product is an anonymus mirror, that
Concept 3 was the chosen concept. It would is almost invisible from the outside. It has a satis-
create the best view and not interfere with the fying view range to the back, and does not block
aerodynamics. The fact that the adjustment the front view.
mechanismen would be so easy to produce, did
remain fairly constant, or rather it should at least With the car as reference frame, the negative
not become positive. camber change can lead to unwanted effects
regarding suspension.
With a positive camber angle less lateral force
than required may be developed, with the The chosen solution was to optimize the camber
possibility of slipping. The cornering stability angle change for minimizing the ground-to-cam-
is reduced because the contact point is moved ber-angle during cornering action. With an axle
towards the center of gravity. width of 100 cm, and a maximum delta change of
±2 cm, the car’s roll angle and the corresponding
A negative camber angle would rather increase
the stability, but could also lead to over steer.
Wishbone Angles
Seen from above, the links form triangles that,
coupled with the rod ends and clevis mount
points as hinges, define the vertical swinging
motion of the knuckles, and otherwise complete-
ly lock the knuckles from moving sideways or Figure 3.3.5: Viewed from beneath, front right sus-
forward or backwards. The angle subtended by pensions
the links in the horizontal plane determines the
force absorbed during braking and cornering.
The angles can be optimized for reducing stress
during braking or cornering. The middle ground
is 90º. However, to avoid the links interfering with
the wheels turning about the steer axis, and
because the car will corner harder and more
frequently than braking, this angle was reduced
to 80º.
Figure 3.3.6: Rear view of front left suspension links
This setup can also be reused when the effects of Figure 3.3.11: Constraint model for top arms during
the cornering force are calculated. The system is braking
then expressed as the following linear equations:
The top arms must thus exert a backwards force Solving for the support forces in the beams can
of 495 N and the lower arms a forwards force of be done with the followingg equation:
1060 N. To decompose these reaction forces into
the arising axial forces in the top and lower links,
the following model and equations are derived:
3.3.1.1 Hubs FEM simulations were only done for braking and
The hubs were made for easy installation of bear- cornering, since the car’s weight is transferred
ings, held in place by retaining rings. directly from the rims, through the hub, to the
bearings.
3.3.1.2 Axles
If the axles deform during operation they might
interfere with the brakes. Sufficient stiffness is
therefore required.
Low weight
5 4 20 5 25
Adjustability
4 1 4 1 4
Manufacturability
3 4 12 4 12
Reliability
4 5 20 4 16
Low cost
4 2 8 3 12
Maintainability
3 4 12 3 9
Weighted sum
76 76
necessary: They discovered that in a Ferrari F40 the sharpest, and 20 m in most other corners. The
only 40% of theoretical full ackerman was used. ackerman test model was thus used to optimize
the position of the toes on the steering knuck-
With purely mechanical passive steering it is les to achieve optimal ackerman on these curve
not possible to achieve full ackerman steering radii.
throughout all wanted turning radii. A test setup
in NX showed that the steering appears fully ack- As seen in figure 3.3.25, the grid marks the posi-
erman compliant the first few degrees, and then tion of the different turning radii from 2 to 25 m,
the difference increases progressively until the in- with the most important ones annotated. The
ner wheel massively over-steers. This over steer of red bar is an extension of the right axle, and the
the inner wheel is thought to be good, since the white of the left axle, so that the turning center
lateral acceleration of the car (at higher speeds) can be observed as the drag link is moved in the
transfers weight to the outer wheels, but as there CAD assembly, exploiting the constraints on all
will be some scrubbing it may waste energy. Still, the suspension parts.
given that we have been provided with a map of
the race track with annotations of the corners, we
know that the corners are no less than 15 m at
Figure 3.3.27: Verification of 6 m turning radius HPC provided 15 mm thick samples of massive
requirement carbon fiber for testing. The tests revealed that
the bolt connections would require reinforce-
ment to avoid delamination. This reinforcement
was made using unidirectional carbon fiber
wrapping as illustrated in figure 3.3.31. Tests
showed that a bolted connection could with-
stand as much as 9 kN, far exceeding the required
780 N.
Wishbone Connectors
For the lower control arms, two solutions were
considered. While a single-piece solid wishbone
(figure 3.4.35) is simpler, it is not adjustable like
the connector with rod links (figure 3.4.36). The
connector solution is also easier to manufacture.
Figure 3.3.37: 3D view of the left wishbone connec-
tor
The wishbones for the left and right sides are With an expected vertical load of 780 N it can
symmetrical. be verified that 10 mm bore rod ends should be
chosen over the other.
Rod ends from SKF are primarily meant for radial
loads (relative to the eye). The size of the lower
rod ends was decided to be Ø10 mm.
where
Using a strut bar was also considered, but the Figure 3.3.42: Front left wheel well on the final body
stiffness of the monocoque was so high that this shell
would be unnecessary weight.
Knuckle
Coilover assembly
Brake caliper
Hub assembly
Connector
Lower mounting point
Figure 3.3.46: 3D CAD model of the rear suspension developed during the spring 2012
3.3.2 REAR SUSPENSION The knuckle connects the axle, the hub and the
wheel to the rest of the suspension. The forces
3.3.2.1 Introduction acting on the wheel will be transmitted through
The most suitable solution for the rear suspen- the knuckle, to the rest of the suspension and
sion was the double wishbone. This would pro- to the monocoque. It needs to be designed to
vide light weight, proper adjustability and a de- withstand the forces acting upon it, and provide
sirable change of camber angle during cornering. sufficient ride qualities such as suitable camber
A suggestion for a fully damped rear suspension change and optimal roll center height.
was presented in the project period (Endresen, et
al., 2011), and was further developed during the Geometric Optimization
Eco-marathon master project in the spring 2012. The design developed during the project phase
had a problem with the angular displacement of
3.3.2.2 Knuckle the rod ends being exceeded (Endresen, et al.,
2011). This was due to changes done in the
geometry of the monocoque at a late stage of
the project phase.
ΔZ - rear
ΔZ - front
Clamps
Clevis assembly
Axle
Brake disc
Figure 3.3.49: Distance between the lower rod ends • Find the virtual reaction point of the suspen-
and the brake disc increased on the new design sion links (A)
• Draw a line from the tires contact patch with
The geometric design of the knuckle was the ground (C) to the virtual reaction point
changed, tilting it 23° inwards at the bottom. This • The roll center (R) is located where this line
also increased the distance between the lower crosses the centerline of the body.
rod ends and the brake disc which was too short (Gillespie, 1992)
on the old design.
The rear roll center is typically positioned 200-
A 2D-model of the rear suspensions front-to-back 250 mm above the ground on a race car. On the
view was made (figure 3.3.52). The geometry of DNVFF2 the rear roll center height is 293 mm
the suspension as a whole was included when when the suspension is in ride height, and 256
mm when it is fully compressed.
ECO-MARATHON 2012 217
Centerline
C
Figure 3.3.50: How to determine the roll center of an
independent suspension Figure 3.3.51: Mounting points for A-arm connector
and toe link on the same horizontal line to prevent
The geometry of the knuckle will also affect the bump- and roll steer
bump- and roll steer, which are small changes
in the suspension’s toe angle when the wheel is
moved relative to the body in bump and droop.
Bump- and roll steer causes poor straight-line
stability, unpleasant vehicle behavior and high
energy losses on lighter cars (Dixon, 1996). The change of camber angle for the rear suspen-
sion is 2.1° during compression. A larger camber
The change in camber angle during cornering is angle change would lead to too much lateral
configured based on the wheels maximum movement between the tire and the ground.
vertical travel of ±20 mm. Approximately it Then the wheel would be outside of the cars
should be equal to the body roll to ensure good body during spring compression, violating the
handling abilities. SEM rules.
Figure 3.3.52: 2D-model of the suspensions front-to-back geometry in UGS NX 7.5. The most important dimensions
218 ECO-MARATHON 2012
are shown in the illustration.
Weight Optimization and Strength Analysis rect distance in relation to the knuckle. To apply
The knuckle was made in massive carbon fiber constraints and forces as close to the reality as
to save weight. A proper strength analysis of possible was emphasized, but the reader must be
the knuckle was done in UGS NX 7.5 Advanced aware that some compromises have been made.
Simulation with estimated material properties The mounting points for the brake caliper have
for the carbon fiber Appendix B. The reader must been neglected to simplify the simulations. This
be aware that the uncertainties regarding the is assumed to have little influence on the final re-
material properties may have lead to small errors sult. The forces applied are based on the calcula-
in the result. tions done in the project report from the autumn
2011 (Endresen, et al., 2011).
1D RBE2 beam elements were used to make
models of the axle and the wheel. This was done
to apply the loads and constraints in the cor-
A
B
y x
F3
F1
F2
Figure 3.3.53: FE analysis setup for the knuckle Figure 3.3.54: Test result from the final analysis of
the knuckle
A B C Value Unit
DOF 1 1 1 1 F1 510 [N]
DOF 2 1 0 1
F2 550 [N]
DOF 3 1 0 0
DOF 4 0 0 0 F3 960 [N]
DOF 5 0 0 0 σmax 233 [MPa]
DOF 6 0 0 0
Table 3.3.3: FE analysis set up for the knuckle. DOF Table 3.3.4: FE analysis set up and result for the
1-3 is displacement in x-, y-, and z-direction, respec- knuckle
tively. DOF 4-6 is rotation about x-, y-, and z-axis,
respectively
Production
A mold for producing the knuckle was milled out
from ebaboard at the IPM prototype lab. Bjarne
Stolpnessæter was very helpful during this pro- Figure 3.4.56: 3D model of the mold and the
cess. The mold was sanded down and painted knuckle
with polyurethane paint to ensure a smooth
surface. The layup of the carbon fiber was done The side of the carbon fiber that had been facing
by HPC in Fredrikstad. Due to the asymmetric up from the mold during casting had an uneven
shape of the rear suspension system it was only surface; at most there was a variance of ±1.0 mm
necessary to produce one mold. in the thickness. The design of the knuckle re-
quired both sides to be perfectly even in order to
Three blocks of massive carbon fiber were or- achieve maximum stability between the axle and
dered from HPC. The milling of the knuckles was the knuckle. A 2.5 mm thick layer of Araldite 2031
done at the IPM prototype lab. A STEP - model glue was applied on this side and after hardening
of the knuckle was imported into NX IDEAS 5.0, it was face milled down to create an even surface.
which generated the code needed to mill the
knuckle in the CNC milling machine. A diamond The engine knuckle was milled with a larger
mill with high rotation speed was used to pre- thorough hole for the axle due to the hexagonal
vent delamination and splintering of the carbon shape of the engine axle. An additional insert
fiber. One knuckle was kept as a spare. was required to make it compatible with the
engine axle. The insert was produced by Nomek
The connection points between the knuckle and in Alumec 89 which is a type of aluminum that
the rest of suspension system were constructed has excellent machinability, high strength, low
of threaded metal bars screwed into threaded weight and good stability during machining
holes in the carbon fiber. Araldite 2031 and alu- (Korea Nonferrous metals Co, 2005). It was glued
minum clamps were added to ensure sufficient to the knuckle with Araldite 2031.
strength. For more detailed information, see
Appendix F.
L2
Forces acting on the connection joint between It is assumed that the lateral force from corner-
the knuckle and the lower A-arm generated by ing, F1, is equally distributed over the upper and
the vertical force F4 acting on the contact path lower connection joints on the knuckle, hence:
between the tire and the ground:
This yield:
F5 α
F9
F6Y
F6
F6X
Figure 3.3.59: Forces acting on the connector
C
If added up, this will yield:
A
F8
F10 z
F9
y x
Upper spring
holder Steel washer
Spring
Containing ring
Value Unit Lower spring holder
F8 1900 [N]
F9 2700 [N] Piston Upper elastomer
stopper
F10 275 [N]
σmax 467 [MPa] Lower POM rings
Table 3.3.6: FE analysis set up and result for the Lower elastomer
connector stopper
Cylinder
3.3.2.4 Coilover
Coilover is short for “coil over shock”, which Lower rod end
means that the spring and the shock is com-
bined in a single, compact package. The main
purpose of the coilover is to absorb the vertical
forces acting on the contact patch between the
tire and the ground, ensuring a smooth ride Figure 3.3.62: Coilover cross section overview
and good handling abilities. The design of the
coilover started very late in the autumn 2011, There are mainly three different types of
and a lot of changes were done during the coilovers, these are the “remote reservoir”, “pig-
spring 2012. See figure 3.3.62. gyback” and “emulsion”. The most common type
is the remote reservoir coilover shock, which is
Theory a mono-tube shock charged with nitrogen. The
A coilover shock is a mono-tube shock with high use of a remote reservoir to house the nitro-
quality that includes provisions to mount coil gen and the floating piston allows the use of a
springs on the shock, which offers a number of shorter tube than would otherwise be necessary.
advantages: The pressure tube is connected to the reservoir
with a short flexible hydraulic hose.
• Completely rebuildable.
• Good tune ability. The coilover allows the A piggyback coilover shock is very similar to the
designer to choose between a vast array of remote reservoir, but instead of the reservoir
spring lengths and spring rates. This makes it being connected to the shock with a flexible
possible to select the perfect spring rate for hose, it is mounted directly on the shock with a
a desired suspension frequency. bracket that incorporates the necessary hydrau-
• The built in spring seat gives the designer lic passage between the cylinder and the reser-
the opportunity to adjust the suspension voir.
height, ride height and preload. It gives
ability to vary between springs of different In an emulsion coilover shock there is no reser-
lengths, hence obtaining different amount voir and no floating piston. The nitrogen charge
of spring travel. is contained in the tube along with the oil in an
emulsion. It is best suited to lightweight and/
or low-speed use, and is also the most compact
(Ansell, 2008)
Δz3
Δz2 β
α
L3 L2
Δz
Δz1 L1
FZ3
A
FZ2
FZ
(Gillespie, 1992)
Strength Analysis
The most stressed components in the coilover
are the upper and lower spring holder. They are
A wheel travel of ±20 mm implied a spring travel transferring all the vertical force from the wheel
of ±9 mm and the weight of the driver and car to the spring. The design of the coilover requires
would result in a spring force of 390 N. This lead the piston to be able to withstand the verti-
to a required spring rate of 40 N/mm for the cal forces from the wheel if the coilover is fully
spring to be adequate compressed. The spring compressed.
also had to be able to withstand the vertical
force generated by the wheel driving over a A 2.0 mm thick steel washer was added to the
bump (Endresen, et al., 2011) without hitting the upper spring holders design as reinforcement.
top of the wheel well. This implied a necessary A
spring rate of 120 N/mm. A compromise was
made to fulfill these properties. Elastomer
dampers were added in the bottom of the
coilover to help the spring absorb the shock if
the compression force became too high, and a
spring rate slightly higher than 40 N/mm was
chosen.
Property Value Unit
Wire diameter 5 [mm]
F1
Inner diameter 20 [mm]
Unloaded length 70 [mm]
Number of coils 9.8 [-]
Figure 3.3.64: FE analysis of the upper spring
Permitted loaded length for holder.
52.8 [mm]
dynamic load
A Value Unit
Rate 47 [N/mm]
DOF 1 1 F1 1200 [N]
DOF 2 1 δmax 9.3E-04 [mm]
Table 3.3.8: Properties of the SF-TF 1901 compres-
DOF 3 1
sion spring ordered from Lesjöfors (Lesjöfors, 2012) DOF 4 1
σmax 17 [MPa]
DOF 5 1
The static deflection rate of the suspension DOF 6 1
determines its natural frequency. This is the rate
at which the suspension compresses in response Table 3.3.9: FE analysis of the upper spring holder
to weight. The natural frequency can be deter-
mined by a simple formula: The force from the spring on the lower spring
holder will be absorbed by the M18 threads con-
necting it to the cylinder. This was simulated as a
plain inner cylinder wall to simplify the analysis.
A Value Unit
DOF 1 1 F1 1200 [N]
DOF 2 1 δmax 3.2E-03 [mm]
DOF 3 1
σmax 29 [MPa]
DOF 4 1
DOF 5 1
DOF 6 1
3.3.2.7 Assembly
Holes were drilled for the mounting points in
the rear wheel well wall. A printed template was
used to find the exact placement of the holes.
A special designed hole-tool was used to make
sure the holes were drilled with the correct angle
relative to the wheel well wall.
One of the lower A-arm connectors milled out in the Makino CNC milling machine
further into the wheel well. One small block of in the wheel wells. Following the lower A-arm,
aluminum was inserted behind each of the two upper A-arm, coilover and the knuckle was
suspension clevises in the mounting points for mounted, respectively. After assembly the
the lower A-arm to adjust the suspension system coilover needed to be adjusted. This meant ad-
to fit the new motor. The engine was mounted justing the upper and lower stoppers inside the
on the left side of the body since most of the coilover so that the wheels vertical travel was
turns on the race track were left turns. Added restricted to ±20 mm. A wheel made out of card-
weight on the left side would help preventing board was used to do the final adjustments of
the car from rolling over. the rear suspension before the axle, hub, brake
discs and brake calipers were mounted.
The clevises with the belonging wedges and
polyurethane vibration dampers were mounted
From the left: Knuckle with hub assembly, lower A-arm assembly, coilover assembly
3.3.2.8 Further Recommendations Next year’s team should look into the possibility
The rear suspension system worked perfect dur- of making the suspension system as a flexible
ing testing and the race in Rotterdam. However, mechanism, as proposed in the Project Report
there is some play causing small misalignments from the autumn of 2011 (Endresen, et al., 2011).
in the toe angle while driving. Due to time issues The coilover in the existing suspension system
the problem has not been further investigated, is heavy due to the weight of the steel spring. A
but it is believed the cause of the problem is play flexible solution would decrease the weight and
in the Ø10 mm rod end connecting the knuckle reduce the number of moving parts, hence de-
to the lower A-arm. If the suspension system is to crease the mechanical complexity of the suspen-
be used next year, the team should find a solu- sion system.
tion to this problem
Top pulley
Steering colum
Drag link
PU bearing
Bottom pulleys
3.4 STEERING
This is a continuation of the work done on the The chosen concept was a cable based system.
steering in the autumn of 2011. A requirement When the steering column is rotated a cable
had to be added to the requirements list from that is spooled around it pulls the drag link. The
last semester. It was important to have the most chosen cable was made from Kevlar, as a backup
amount of adjustability available for the front solution this cable could be exchanged with one
suspension and steering. This made it necessary made from steel.
to vary the length of the drag link in addition to
having adjustable tie rods (Endresen, et al., 2011).
mn
Tie rod clevis
Length adjustment
Cable mount
Figure 3.4.7: 3D model of the steering column, with sub parts assembled
2 237
The solution was to make the second section The dashboard and steering wheel mount con-
of the column quite small and slide a “thread sisted of two cross beams mounted between the
house” onto it. This unit would be of the needed wheel wells. Plastic cylinders were inserted in the
diameter and have two holes in which the cable core material of the cross beams during produc-
could be threaded into. The housing had an open tion. Holes could easily be cut out afterwards for
end that allowed access to the cable inside. The the steering column. Another set of plastic bush-
cable could be tied around the steering column ings were inserted to form plastic glide bearings.
and the housing could be slid over the knots. The steering column was supported by these two
The housing was fastened with two M5 screws to bearings. Two aluminum stoppers were made for
the column. The cable would be in two lengths, the column. These would press against the bear-
one going to each side of the drag link. If one of ings and stop the column from moving in or out.
the cables should snap it would still be possible One of the stoppers also limited the rotation to
to steer to one side and maintain some level of the 120° specified.
control.
3.4.2.1 Analysis
The maximum force exerted on the drag link by
the front suspension would be 150 N. Friction
in the steering system could double this force.
The pre tensioning of the cable did not affect the
steering column as the forces were in equilib-
rium.
Figure 3.4.8: Thread house The results showed that the steering column
would have no problems handling the 300N load.
For the steering wheel mount it was important The maximum stress was 69 MPa and very small
to make a precise connection, to keep overall deformations.
play in the steering low. This was done by mak-
ing an aluminum socket that would fit perfectly 3.4.3 PULLEYS AND KEVLAR CABLE
into the steering column. The steering wheel was
attached to this socket. A reinforcement ring was
made to support the four attachment bolts on One of the goals for the new steering was to min-
the inside of the steering wheel. The socket was imize friction to improve the feel of the steering,
secured to the column with an 8mm aluminum and enable self-centering. Pulleys would be used
locking pin. together with the Kevlar thread to achieve this.
Figure 3.4.11: Strength analysis of the steering column, maximum stress of 69 MPa.
Left: Drag link with length adjustment, cable mounts and physical stoppers. Kevlar thread in yellow.
Right: Upper pulley assembly glued to the wheel well. Visible section of the steering column.
On the final attempt of the competition the
steering failed. The car crashed into the barrier at
the start/stop lane. This was right before the car
should stop for the lap, so the speed was low. The
car was returned to the paddock and inspected.
It was discovered that the left cable had snapped
at the exit of the thread house. The driver had
complained during the run that the steering felt
“hard”. It was harder than usual to turn the steer-
ing wheel. Several things had been overlooked
in the inter race checks that could have caused
this. The track at Ahoy was very dusty. Filth had
collected in the grease applied to the drag link
during the competition. It made the drag link
harder to move. The rear brake hose and electri-
cal wires ran under the drag link on the right side
of the car. They had changed position causing
the physical stopper to catch hold of them.
Straightening the car after a left turn would have
been harder than usual. It is unknown how much
strain this caused on the cable. The mechanism
used to limit the steering columns rotation had
come undone during the attempt. This meant
that the steering column could be rotated further
even though the drag link could not be moved.
The last corner did not require full steering lock
however, so this was probably not a contribut-
ing cause. Finally, the modification done to the
tie rod had one serious side effect. When the left
suspension was compressed the wheel would
get a toe in angle. This would have made the car
harder to steer. All these factors lead to the steer-
ing failure.
Pedal box
Mounting plate
3.5 BRAKES
The work presented in this chapter is a continu- car and driver. Testing the driver’s maximum
ation of the work done in the autumn of 2011 strength would not necessarily reflect real force
(Endresen et al, 2011). The main challenge for the he or she would exert under emergency brak-
brake system has been to design and produce a ing. A brake failure in an emergency situation
new pedal box and all its sub parts. The rest of could be very serious for the driver, car and other
the brake system is composed of standard, of the contenders. The brake system was therefore
shelves parts (brakelines, calipers and discs). designed with a safety factor of 2 for worst case
scenario.
The brake system is crucial for the safety of both
Pivot point
travel and how hard it is to operate the brakes. Arms of different lengths were connected to the
This component is experiencing the highest piston arm of each cylinder. The cylinder at-
stress in the whole brake system. The master tached to the shortest arm would receive a high-
cylinders had to be pressed with a force of 360 er force due to force equilibrium (see picture).
N, to hold the car stationary on a 20 % slope. The brake balance could easily be fine tuned
For a dynamic case with the car running in wet between the front and rear circuit by altering the
conditions, a higher force is needed to stop the length of the pivot arms.
vehicle safely. With a mechanical advantage of
4/1, 200 N input force from the driver would yield
800 N force to the cylinders. The final mechanical
advantage achieved in the design was 4,4/1.
The car should have more brake force on the For the strenght analysis, NX7.5 was used. The
front wheels to stop the back from sliding, (En- material properties were set to aluminum 6061,
dresen et al, 2011). By having a pivot point in the as Alumec was not available. A force of 600N
middle of the pedal arm, the master cylinders (emergency braking) and constrains was applied
were given different mechanical advantages. in the mounting points.
The pedal arm was produced from a 10mm thick be as upright as possible in its resting position.
Alumec plate. Due to problems fastening the This minimizes vertical travel of the pedal, which
work piece in the hydraulic press, the part moved could lead to the driver’s foot slipping off.
slightly during production. This resulted in a
difference in thickness of 0.4mm over the pedal
arm. The performance of the pedal arm will not
be affected by this unevenness. Holes for the
pivot point, mount and foot plate were drilled
out. The hole for the pivot was made to a H7 fit
specification. This way the GE 8 spherical bearing
would not need any external support after being
inserted. 8x10mm aluminum spacers mounted
on a M8 steel bolt were used to adjust the force
arm for each master cylinder. SI 8 E rod ends were
used to connect the cylinders and pivot point
arms. Spacers and rod ends were secured in place
by fitting a nut to the end of the bolt.
Underneath the box 2 mm deep grooves simi- 2011). Alterations had to be made to the master
lar to those on top were subtracted to reduce cylinders for them to be compatible with the rest
weight. Two 6 mm bolts going across all four of the system. An adapter solution was made for
walls would hold the master cylinders in place. the hydraulic hoses going to the calipers. Bicycles
The pedal arm was held in place with an 8 mm use 6 mm hoses and banjo plugs for the brake
steel locking pin. Two mount points were left in system, while motorcycles use 10 mm. The solu-
the floor of the box near the pedal mount. Two tion was to produce a M10 bolt with internal M6
bolts would be used in these points to fix the box threads. This bolt could be secured and sealed
to the car. with a gasket in the master cylinder. The original
6 mm banjo screws could then be used without
The analysis was performed on an earlier revi- modifications. To reduce weight the M10 screw
sion of the part. Another brace would be added was machined out of aluminum, and the piston
to the design before production. The results of arms were cut to half their original length.
the analysis were conservative and still valid.
Aluminum 6061 was assigned as the material. To further reduce weight the cylinders were fas-
Forces acting on the master cylinder does not tened in the milling machine and excess material
act directly on the holes supporting the cylinder was removed. This saved 35 g per cylinder, but
cross bolts. This was simulated by adding 1D con- it was discovered that they had been damaged
nectors, as seen in figure xx. To simulate brake by the hydraulic press. Some deformation and
balance, 1700 N and 900 N force vectors were set cracks had occurred on top of the cylinder at the
on the two master cylinder points. For the pedal connection of the brake fluid reservoir. The cylin-
arm supports the reaction forces were simulated ders were fixed by filling the cracks with Araldite
by bearing forces of 2000 N. The pedal box was and machining the hole circular. After the re-
held in place by a fixed constraint on the contact pairs the cylinders were tested and found to be
area of the two mounting bolts. A simple support in working order. The other area for potential
from below simulated the floor of the car. weight savings was exchanging steel parts with
aluminum. Both the piston arms and hydraulic
The brake pedal box was machined out from a connection bolts were made from steel. Remak-
single block of Alumec, in the Makino milling ing these parts in aluminum saved about 100 g.
machine at IPM. According to volume calcula- A total of 170 g was trimmed from the master
tions done in NX the finished part would weigh cylinders.
approximately 120 g. The Alumec block had a
mass of 1 kg before production started. Holes for 3.5.2 OTHER BRAKE CIRCUIT PARTS
the master cylinders and pedal arm were made
with H7 specifications. The front most bolt would
The rest of the brake system consisted of stand-
carry most of the load from the master cylinders.
ardized, off the shelves parts. Some were pur-
A steel bolt was used for the front mount, while
chased and some were reused from the old car.
an aluminum bolt would suffice for the rear. The
As the products for bicycle brakes already have a
pedal arm locking pin was made from steel in the
low weight, very little can be gained by making
turning machine. The final piece had a weight of
custom parts. The only area where a significant
116 g (without bolts), a very satisfactory result.
weight reduction could have been made was the
steel brake discs. These could have been replaced
3.5.1.3 Master Cylinders
with discs of carbon fiber, but this was not prior-
More detailed descriptions and calculations
itized.
performed on the new master cylinders can
The hoses reused from the old car were of a steel
be found in the autumn report (Endresen et al,
reinforced type. This reinforcement stops them spaced out to solve this problem. Because the
expanding under load, giving a firmer feel to discs are attached to the hub they had to be
the brakes. DOT fluid used in the brake circuit spaced an equal amount. Spacing the discs was
required o-rings made from a special rubber. The done by stacking three M5 washers per bolt
reused calipers were from two different brands, (each disc had six bolts). To do this accurately a
Formula Oro and Avid Elexir 5. The Formula micrometer had to be used.
calipers were the lighter of the two, and there-
fore placed in the back. They both had the same Hydraulic hoses were connected from the
piston size of 22 mm. calipers to the master cylinders and the system
was filled with DOT 5.1 brake fluid. Bleeding
A more detailed description about the status of the brakes was a simple process that could be
the parts reused can be found the report from performed by two people. One had to actuate
previous semester (Endresen et al, 2011). the fluid syringe connected to the brake caliper.
The other would tell when the level in the fluid
3.5.3 ASSEMBLY AND TESTING reservoirs started to rise. When this happened
the circuit should be air free and full of fluid. The
bleed kit was purchased by an earlier SEM team.
After the brakes had been assembled a quick
function test was performed. Because the mount-
When working on the suspension the calipers
ing holes on the master cylinders were elongated
were often taken off. To stop any fluid leaking
they could be moved back and forth about 5mm.
they were fitted with bleed stoppers. These stop-
This presented a solution for the brake sensor for
pers compress the caliper piston fully, to stop
the electrical system. A bracket for the sensor was
movement if the brake pedal is pressed. The cali-
made and fastened using a hole made for weight
pers needed to be fine adjusted to stop the discs
savings. This positioned the sensor directly in
from rubbing the brake pads. Using a bright light
front of the cylinder mount. By fitting the pedal
underneath the suspension made fine tuning
arm with a powerful spring it would pull both
easier. It was possible to visually determine which
master cylinders towards it, thus trigging the
way the caliper had to be moved in order for the
sensor.
disc to rotate freely. Two of the discs were slightly
bent making it impossible to eliminate scrubbing
When mounting the calipers and discs a prob-
completely. This was only crucial for the race, so
lem was discovered. The wheel hubs were not
the old discs were used in the testing period.
designed big enough in the axial direction. This
was exaggerated by the fact that the backside of
During the test day at Dragvoll several test were
the rims was rough and uneven, so the wheels
done on the brake system. Two team members
touched the brake calipers. The hubs had to be
were needed to test the car. One person pushed
Brake pedal assembly with reservoir holder and brake sensor. Mouting plate glued to the floor of the car.
3.6
WHEELS
Outer CF layer
Massive CF core
Valve
Rim ring
Inner CF layer
Tyre Foam core
3.6 WHEELS
The development of the rim design started in the An internal pressure of 5 bars was applied on the
project phase executed in the autumn 2011. It rim rings surface.
was finalized during the spring 2012. A
DOF 1 1
3.6.1 STRENGTH ANALYSIS DOF 2 1
Table 3.6.1: FE analysis set up for
DOF 3 1
DOF 4 1
the rims.
The strength analysis of the carbon fiber layup
DOF 5 1
was performed in UGS NX Nastran. The carbon
DOF 6 1
fiber type used was DB 420.
B
The hole for the valve was drilled on the rim rings
The mold in ebaboard was milled at To-mo
inner surface, which had the most free space due
Modeller og Interiør AS in Fredrikstad. This was a
to the rims asymmetric shape. It was placed there
positive plug which was used to produce a nega-
to prevent the valve from coming in conflict with
tive mold in fiberglass. The result was an accurate
the tire. A special jig was made to secure the rim
and durable negative mold that could be used to
while the hole for the valve was made in the drill
produce a large amount of rims before its condi-
press, and to make sure the hole was drilled with
tion would be exacerbated.
the correct angle relative to the rim rings surface.
The hole was drilled with a Ø4.0 mm bore, fol-
The rims were produced at HPC by using the
lowed by Ø8.0, Ø10.0 and Ø11.5 mm which is the
same layup method as in 2011 (Qviller, Stock-
specified bore size for the valve. This was done
fleth, Bleie, & Hoel, 2011). 8 layers were applied,
to avoid delamination and rough edges in the
giving the rim an overall thickness of 4.0 mm.
carbon fiber.
Three regular rims and one engine rim was made,
plus one spare of each.
Small cracks and irregularities in the rim rings
inner surface were filled with Araldite 2031. After
The center hole and the bolt circle on the regu-
applying the glue and sanding it down with
lar rims were made by HPC, but the 45° chamfer
fine sand paper the rim rings inner surface was
around the center hole had been left out from
smooth and without any visible cracks or irregu-
the production. This was a crucial part of the rims
larities.
design, and without it the rims would not fit onto
the hubs. The chamfer was made by Finmekanisk
Drilling of hole in the rim ring for the TR-414 tubeless snap in valve
Left: Araldite 2031 to cover up small cracks and irregularities on the rim rings inner surface
Right: Sikaflex and PVC tape to prevent leakage
3.6.3 PERFORMANCE The rims produced in 2011 are each 200 grams
than lighter the ones produced in 2012. Therefore
the rims from 2011 were modified to fit the new
Testing revealed that the rims were not as good as
hubs, and were used on the two last attempts in
first predicted. The unevenness on the rim ring was
Rotterdam. They performed well and could also be
the main problem, causing the wheel to wobble
used next year. However, it is recommended to use
in the lateral direction when rotated. This lead to
them as spare rims only.
reduced handling abilities and loss of energy while
driving.
3.6.4 FURTHER RECOMMENDATIONS
One rime cracked after the first outdoor testing
day at Dragvoll. It happened after the car had been Next years team should make new rims. It is highly
transported back to the workshop, and the tire recommended to produce them in another mate-
had an internal pressure of 5 bars. It was reason to rial than carbon fiber. Several of the teams in Rot-
believe that something had gone wrong during terdam had rims milled out of aluminum. Produc-
the production process of this rim since the rim did ing rims in carbon fiber is a complicated job and
not explode, but air was leaking slowly through several risks will be eliminated by producing them
a visible crack in the rim ring. The damaged rim in a more durable material.
was sent to Paal Fediuk at HPC who repaired it for
3.7
PROPULSION
Figure 3.7.1: Exploded view of comlpeted motor assembly
3.7 PROPULSION
3.7.1 MOTOR DESIGN Design of the stator, magnet arrays and air gaps
are based on project report of Endresen (2011).
This section summarizes the work done on the The stator is a resin cast with Litz wire windings
motor parts. It is an improvement of last year’s cast inside. Torque is trasferred to the rim tho-
motor based on the specifications from last se- rugh the rotors.
mester (Endresen, 2011).
3.7.1.3 Hub and Axle
3.7.1.1 Requirements The new magnet array, with the removal of the
The motor was given a budget of 100 000 NOK. In iron core rings used in previouse years, the motor
addition to service hours, SmartMotor sponsored can be made much more compact.
the purchase of the magnets, which were ex-
pensive and had a lead time of many months. A The diameter of the axle is designed to accomo-
significant improvement over the previouse iron date easy insertion of wires for the three-phase
ring motor is the use of a Hallbach array which drive current. It is, however, kept reasonably thin
eliminates the need for steel cores to conduct to avoid oversized and heavy bearings.
the magnetic flux and reduces the weight of the
engine considerably – if the magnets are glued Larger diameters enables a octagonal section
directly onto the rotors. that mates with the suspension. This will make it
simpler to attach the motor wheel to the car as it
Due to the efficiency of the motor, combined does away with the key that easily fell out
with the low nominal output (around 100 W) al- (Bleie et al., 2011).
leviates the need for cooling, it is therefore not a
requirement.
Weight < 10 kg X
Weight < 7 kg X
Since the outer rim adapter will be exposed to tip, which can be inserted into an normal power
sunlight, it must be from a UV-resistant polymer, drill.
or else be coated with a UV-blocking paint. Dur-
ing competition the rear wheels will be occluded
by aerodynamic covers anyway, but experience
from testing shows that the car is tested a lot
without wheel covers.
3.7.2.1 Rotor
The rotor consists of carbon fiber plates and per-
manent magnets. Magnets were glued on with
a two component Araldite. The glue was recom-
mended by one of our major sponsors with a
wide experience within composites. Before the
magnets were glued, the Araldite was tested
for tensile strenght. Four tests were performed.
Three of these showed acceptable results, the last
showed insufficient glue in the necessary area.
Figure 3.7.12: Magnets in a Hallbach array, arrows The successful tests showed that the carbon fiber
showing direction of magnetization delaminated before the glue failed. This makes
the carbon fiber the limiting factor.
The magnets used were NdFeB N42 magnets.
These were selected because of their magnetic
strength and their thermal abilities. The mag-
nets were assembled in a Hallbach array before
they were attached to the rotor plates. Several
attempts were made in order to find the right
technique for doing this. The first attempt was to
use a circular wooden plate with another wood-
en plate of a smaller diameter centered on top of
the first. Shape and diameter of the array can be
Figure 3.7.13: Magnets and iron ring, arrows show-
controlled this way. This procedure was however
ing direction of magnetization
unsuccessful as the magnetic field caused the
magnets to turn out of position. By adding a third
wooden plate on top of the center plate, the
problem was fixed.
important challenge was to keep all metals in ment had to be constructed. This was particularly
a safe distance. Since the plates were fastened important when gluing the magnets as the forces
with a bolt and nut, wrenches were necessary. here would be especially high. When the mag-
Careless handling of these caused the magnet nets were assembled in the Hallbach array, glue
arrangement to collapse. was put on the carbon fiber plates. The plates
were then lowered onto the Hallbach arrays. In
The rotor plates were made of carbon fiber. These order to get the magnets centered on the ro-
were milled out to the correct thickness and with tor plates, wide shafts were designed to exactly
the proper flange to support the spacer ring and match the attachment holes in the rotor plates.
magnets. The necessary thickness was found by These shafts were then put on the bolts in the
first calculating the forces that the plates would center of the wooden plates used for the magnet
be exposed to. HPC suggested a thickness of assembly. This ensured a right possition of the
2 mm would be sufficient. To increase safety, a magnets. In addition its kept the carbon fiber
thickness of 4 mm was chosen. plates horizontal while lowering. This led to a suc-
cessful distribution of Araldite 2021 glue.
To assemble the rotors properly, special equip-
Rotor production
Welding of stator mold
3.7.2.2 Stator Production air, epoxy and wires. In the bottom plate, four
The stator consists of litz wire and epoxy. The bolts were attached. These ran through holes in
wire was wound on a wooden board. To ensure the remaining pieces. Bolts were intended for
a clear layout of the wires a technical drawing tightening the plates together during the vac-
was printed and stapled onto the wooden board. uum process. In order to get the cast out of the
Nails were used to keep the wires in place. With mold after casting the mold needed to be cov-
three phases and 24 pole pairs, 288 nails were ered with release agent. This was smeared on the
needed. Another wooden board was used to pieces which were then baked at curing tempera-
make an outer radius guideline. This was neces- ture for 10 minutes, three times. The pieces were
sary to ensure the correct size of the coils. A mar- baked so the release agent would set properly to
gin of 1 mm was added to the diameter. Six wires the steel and to prevent it from reacting with the
were then wound in a double layer wave wind- epoxy.
ing. The winding was then tied up with 288 knots
to replace the nails. Cotton string was used to tie The second mold was of a simpler design, con-
the winding as this is not magnetically conduc- sisting of Ebaboard with a stator sized hole milled
tive. Steel wire was also considered as this would out. This was then covered with spray paint and
have an easier assembly but this was discarded wax. Spray paint was used to fill the pores in the
as it would lead to a higher leakage flux. The nails material and the wax was a release agent suitable
were then removed. for low temperatures. The same lid was used for
When the wires were wound, tied and properly this mold to squeeze the wires.
fitted in the circumference ring, the wires were
placed in the mold. 3.7.2.4 Open Casting
The open casting technique used the ebaboard
3.7.2.3 Mold Production mold. Windings is placed in the mold with wire
For the different stators two different molds were ends coming out of the top lid. Epoxy is poured
made. The first mold was made for vacuum cast- in and the lid is pressed down. This causes some
ing. This was a four piece mold made of steel. The of the epoxy to overflow the mold. Before pro-
mold consisted of a plane bottom plate with an duction, too little epoxy was prepared, resulting
entry hole for the epoxy, two semi-circle shaped in shortage of epoxy. Still, this stator had many of
side plates and a plane top lid with exit hole for the desired properties.
ECO-MARATHON 2012 271
Open casting of the second stator
3.7.2.5 Vacuum Casting with sealing tape, but the mold was particularly
The method of vacuum casting was recommend- challenging to seal. This might have been due
ed by professor Nils Petter Vedvik at IPM, as a to the welding done when making the mold, as
casting method suitable for electrical equipment. this may have created an air canal from the side
This method will, if performed successfully, give of the mold. The distance between the pressure
great dielectric properties and prevent partial bolts was too long for supplying the right pres-
discharges. In this design partial discharges is not sure in between the bolts. This problem was
an issue and it would therefore be acceptable solved using clamps along the circumference of
with minor imperfections in the cast. However, the mold. In order to check the cast procedure
casting the stator was quite challenging. several test stators were made. When the first test
stator was made it included three wires coming
A vacumm pump was connected with tubes to out of the mold for simulating the power cables
two safety chambers in series, before it was con- and a bundle of litz wire was also tied tightly and
nected to the topside of the mold. The mold was put in the mold. This was done in order to exam-
slanted so the outlet tube was position higher ine how the epoxy would surround the litz wire.
than the inlet tube. This configuration enabled
the mold to be filled with epoxy in a controlled 3.7.2.6 Spacer Ring
manner. The epoxy would flow into the mold and To keep the rotor discs at a desired distance, a
it was easy to see when the epoxy would come spacer ring was constructed. The ring was sup-
out of the topside. When this happened the ported by a flange in the rotor discs. In order to
outlet tube was blocked and the epoxy would achieve the right mechanical strength polyoxy-
continue to fill the mold until the pressure inside methylene (POM) was selected as material. The
the mold was equal to the atmospheric pres- flanges in the rotor discs were highly necessary
sure. One major challenge here was to keep all as there was a very small margin for misplace-
interfaces airtight. All connections were covered ment. Any mispalcement of the space ring would
lead to rubbing between the spacer ring and reduce the wear on the outer plate, an aluminum
stator. ring was glued to the outer plate were the rods
would come in contact. With all this equipment
3.7.2.7 Assembly of the Motor in place the inner plate could be lowered onto
The stator was to be fitted on an aluminum axle the rest of the motor.
made especially for this project. Necessary holes
needed for fitting and securing the stator on the 3.7.2.8 Problems Regarding the Construction
axle were milled out. When the motor was assembled the axle was
spun. Clear cogging force was experienced, simi-
The stator was mounted on the axle and the lar to that one may find in iron based machines.
three power wires were lead through the hollow Since the motor is completely ironless, this indi-
axle. Wires would then come out on the inner cated a short circuit in the stator. The motor was
side of the engine, the side facing the car. then brought to Smart Motor for testing. Using a
Rotor plates were fitted with ball bearings in the separate engine, the motor was spun as a gen-
center holes. The axle was then put through the erator and torque was measued. Even with open
ball bearing in the outer plate and the spacer wires the machine still needed 7 Nm just to spin
ring was then put on, surrounding the stator. at rated speed. Since there was no mechanical is-
Last, the inner rotor plate was to be lowered onto sus regarding the motor, the motor was disasem-
the remaining parts. Since the magnetic forces bled and the stator removed. The motor now
are very strong, this process needed special tools. spun freely. This showed that the problem was
Five holes were made in the inner rotor plate and stator related. The stator was inspected visully
fitted with threaded inserts of aluminum. These and by loading it with a high current while exam-
inserts would allow assembly of the motor plates ining it with a thermal camera. Still, no problem
with threaded rods. The rods went through holes were found.
in the stator and down to the outer rotor plate. To
Figure 3.7.20: Efficiency as a function of torque of the new engine at 257,5 rpm, 26
km/h with the smallest obtainable air gap
The efficiency of the drive train is limited by had an air gap adjusted for the first battery pack
two factors, air gap and back induced voltage. with a high voltage drop, the air gap was reduced
Lowering the maximum speed will increase total to better match the second battery pack with
efficency. a more stabile voltage. This was done by first
reducing the air gap, then using a drill to spin
3.7.2.10 Conclusion the engine at nominal speed, measure the back
The car had not been tested under windy condi- induced voltage and implement the new param-
tions. When the car was accelerating facing the eters in the engine controller. No more changes
wind, this required more current than the battery were made to the engine for the rest of the
was able to deliver. The battery management competition.
system shut down and the car stopped. This was
solved by rewriting the code in the acceleration The Hallback array motor is operational but it is
program to have a lower acceleration. not as energy efficient as it should. This could be
greatly improved by making a new stator. Experi-
The engine was also modified. Since the engine ence shows that the stator width could probably
Garcı´a-Fornieles, J. M., Fan, I. S., Perez, A., Wain- Kolisch, R., & Padman, R. (2001). An Integrated
wright, C., & Sehdev, K. (2003). A Work Breakdown Survey of Deterministic Project Scheduling. Omega-
Structure that Integrates Different Views in Aircraft The International Journal of Science , 249-272.
Modification Projects. Concurrent Engineering ,
47-54. Tonning, O. (2012). Implementing Lean System
Engineering in the DNV Fuel Fighter project. Trond-
Gillespie, T. (1992). Fundamentals of Vehicle Dy- heim, Norway: Norwegian University of Science
namics. USA: Society of Automotive Engineers, and Technology.
Inc.
PMI. (2008). A Guide to the Project Management
I would like to thank the following people for their support, either directly or indirectly, to the progress and
success of this project:
• Kristina Dalberg
Det Norske Veritas (DNV)
Main sponsor contact person
• Bjarne Stolpnessæter
IPM staff, NTNU
For all the CNC milling of moulds, suspension knuckles and a lot more, for always being open to new ma-
chining requests and short delivery times
• Børge Holen
IPM workshop, NTNU
For machining assistance
• Office Adminstration
IPM staff, NTNU
For handling all the purchasing orders and payments
• Arne Gellein
SINTEF Materialer og Kjemi
For free metal cutting
NB: DB420 er en strikket armering bestående av 2 distinkte lag, det er IKKE en vev. Altså gir en ammering en
layup [45/-45]. Tykkelse på hvert lag er jo gitt av tettheter og volumfraksjoner, så det finner du greit.
Angående volumfraksjon, vil en rimelig range være 0.50-0.55 med godt vakuum. Slurv og fanteri forøvrig kan
gi lavere, f.eks. 0.45.
Program: Main
O0150 ; Main program for milling front left wishbone
S3000 M03 F1400 G17 G90 ;
M08 ; Coolant on
M21 ; Optional: Mirror X-axis, for right wishbone
M22 ; Optional: Mirror Y-axis, for right wishbone
M23 ; Optional: Mirror OFF
G00 X-15. Y0. ; Move outside material block
Z-90. ;
G01 Z-103. ; Prepare cut depth for first cut
M98 P151 L7 ; Cut seven times with 3mm cuts
G90 ; Switch back to absolute coordinates just in case
G01 Z-123. ; Prepare height for final planar cut
M98 P151 L1 ; Last planar cut
N11 G90 ; Labeled for graph plot
G01 X-15. ;
G00 Z-90. ;
X40. Y-28.8 ;
G01 Z-106. ;
X35. ;
M98 P152 L21 ; Mill north ear profile
G90 ;
G00 Z-90. ;
X40. Y-45.8 ;
G01 Z-106. ;
X35. ;
M98 P152 L21 ; Mill south ear profile
G90 ;
G00 Z-90. ;
X-15. ;
Y-59.1 ;
G01 Z-125. ;
M98 P153 L8 ; Cut out the bottom angles
G90 ;
G01 Z-90. ; Begin safe return to origin
M09 ; Coolant off
M05 ; Spindle stop
G00 Z0. ; To origin
X0. Y0. ;
M30 ; Program end/all reset
%
O0152 ; Program for milling ear profiles, operates only in ZX-plane, caller must modify
Y-axis
Assumes starting in position X35. Z-106. and Y depending on which is being
milled
G18 G90 ; Select ZX-plane for circular interpolation and abs. coords.
G02 X26.5 Z-100. R9.021 ; East radius
G01 X16.2 ;
G02 X8.586 Z-104.739 R8.501 ; West radius
G01 X0. Z-121.910 ; West slope
G91 ;
G01 Y-0.2 ; Strafe for next cut
G90 ;
G01 X8.586 Z-104.739 ; West slope
G03 X16.2 Z-100. R8.501 ; West radius
G01 X26.5 ;
G03 X35. Z-106. R9.021 ; East radius
G91
G01 Y-0.2 ; Strafe for next cut
G90 ;
M99 ;
%
Program: Main
O0150 ; Main program for milling front left wishbone
S3000 M03 F1400 G17 G90 ;
M08 ; Coolant on
M21 ; Optional: Mirror X-axis, for right wishbone
M22 ; Optional: Mirror Y-axis, for right wishbone
M23 ; Optional: Mirror OFF
G00 X-15. Y0. ; Move outside material block
Z-90. ;
G01 Z-103. ; Prepare cut depth for first cut
M98 P151 L7 ; Cut seven times with 3mm cuts
G90 ; Switch back to absolute coordinates just in case
G01 Z-123. ; Prepare height for final planar cut
M98 P151 L1 ; Last planar cut
N11 G90 ; Labeled for graph plot
G01 X-15. ;
G00 Z-90. ;
X40. Y-28.8 ;
G01 Z-106. ;
X35. ;
M98 P152 L21 ; Mill north ear profile
G90 ;
G00 Z-90. ;
X40. Y-45.8 ;
G01 Z-106. ;
X35. ;
M98 P152 L21 ; Mill south ear profile
G90 ;
G00 Z-90. ;
X-15. ;
Y-59.1 ;
G01 Z-125. ;
M98 P153 L8 ; Cut out the bottom angles
G90 ;
G01 Z-90. ; Begin safe return to origin
M09 ; Coolant off
M05 ; Spindle stop
G00 Z0. ; To origin
X0. Y0. ;
M30 ; Program end/all reset
%
The goal of the testing was to verify the viability of using a bolted connection to massive carbon fiber
for our car’s suspension. The size of the bolt was dictated by the size of the end rods that we were
aiming to use. The test setup therefore consisted of a short rod of massive carbon fiber with two M8
bolts inserted into either end. The end holes were carefully drilled to Ø6.8 mm and thread-tapped to
M8. Two bolts were inserted through connectors and screwed into the CF test piece, then pulled
until failure in a tensile testing machine.
We proposed to reinforce the ends with layers of CF UD wrapped around. For these tests, this would
be unpractical, so we used two clamps from aluminum and M4 bolts. These were tightened to
simulate the additional stiffness provided by wrapping UD layers around the ends of the CF rod.
Additionally, we tried to glue the bolts into the holes using Araldite 2031, both with and without
threads in the hole of the CF piece.
The results from the different tests, although few, were consistent and is summarized as follows:
ECO-MARATHON 2012
Appendix G: K-brief example
Specifications:
- sponsor: Altitec
- battery charger included
- nom voltage 48V
- nom discharge current 24A
- capacity 5800mAh Specifications:
- sponsor: Gylling
- battery charger NOT included
- nom voltage 46,2V
Problems : - max discharge current 19A
- for power drawing >300W depending on discharge capacity very high voltage drop - capacity 4400mAh
- voltage drop often triggers the BMSs under voltage protection and shuts down battery
- battery is likely to get warm which triggered BMSs temperature protection one time while testing Battery is charged by a power source (rating: 60V/10A) from the Electrical department.
Conclusion:
- battery is not suitable for race conditions in combination with the 2012 drive drain
Problems:
Charger: - limited current discharge ability
- BMS over current prtection triggers latest at 19A
- SmartMotor engine controllers fly start routine at high torque (>12Nm) not possible
- Limited torque for drive train due to limited current
Conclusion:
- battery is of limited suitability for the 2012 drive drain
ASSEMBLY TEST:
Subsystem: S.8 Brake circuit Responsible:H.J.S Test Date: 19.04.2012 Place: Dragvoll Sport center
Test Test ID. Procedure Requirement for passing the Personnel Material/ Performance Comments Status Correcting
no. test Tools (measures) Pass/No actions
pass
1 Effectiveness of Place the car on a The vehicle must remain Driver and team member The car must remain The car remained Pass
the braking circuit 20%slope. stationary. pushing the car stationary stationary and then it was
also pushed while the
Appendix G: Assembly test example
braking.
2 Braking Move the vehicle and test Enough brake force Driver and team member Pass
capabilities the brakes pushing the car
3 Leaks Press hard on brake pedal No visible leaks Driver and team member Entire No visible leaks have Pass
to check if there are some Brake to appear
leaks system
4 Brake pedal Measure the dimensions Minimum surface area of brake One team member to The Brake pedal is Pass
dimensions pedal: 25 cm2. measure it approximately 49 cm2
5 Braking Combinations of weak, The brakes must be strong Driver and another team The brake systems Pass
effectiveness gradual, hard and instant enough and have to stop the car member to push the car must be reliable and
braking as soon as the driver steps on and to measure the able to perform
the pedal distance
with low and higher
speed, as well as during
turning at different radius.
Braking:
Initial braking should be cautious to listen to how the brake pads attack the discs, and the vibrations that are transferred to the chassis and amplified.
We should try combinations of weak, gradual, hard and instant braking with low and higher speed, as well as during turning at different radius.
We will also need to check whether the rear wheels begin to skid (if allowed by the gym center) - if they do, too much force is routed to the rear brakes.
ECO-MARATHON 2012
313