K Faid - Master PDVSA - Module 12 - 2009
K Faid - Master PDVSA - Module 12 - 2009
K Faid - Master PDVSA - Module 12 - 2009
Module 12
Investment Profitability
Investment Profitability Studies
Studies
in the
in the Petroleum
Petroleum Industry
Industry
Karim Faïd
Contents
Contents
Introduction
Introduction
Fundamentals of
Fundamentals of general
general methodology
methodology 33
Value creation
Value
creation and
and profitability
profitability analysis
analysis 16
16
Principles of
Principles
of risk
risk analysis
analysis methodology
methodology 68
68
Conclusion
Conclusion
From projects’
From projects’ value
value to
to corporate
corporate financial
financial performance
performance 84
84
Value creation and performance
StrategicManagement
Strategic Managementaimsaimsat
atValue
ValueCreation
Creation
ititis
isaasystem
systemfor
forallocating
allocatingresources whichallows
resourceswhich allows
thecompany
the companyto
toimprove
improveperformance.
performance.
Value
Value
Valueisiscreated
¾¾Value createdthrough
throughinvestment
investmentprojects.
projects.
Profitability studies
¾¾Profitability studies allow
allow one
one to
to evaluate
evaluate the
the value
value that
that could
could be
be
createdby
created byananinvestment
investmentproject.
project.
Performance
Performance
Analysts and
¾¾Analysts and shareholders
shareholders want
want to
to compare
compare companies,
companies, follow
follow their
their
evolutionand
evolution andanticipate
anticipatetheir
theirfuture
futureperformance.
performance.
Economic Evaluations
the communication tool
TECHNICAL
TECHNICAL MANAGEMENT
MANAGEMENT
STAFF
STAFF
Most of the investment decisions are based on the overall financial impact
of an investment opportunity rather than on specific technical considerations.
Exchange
of sufficient and appropriate
Evaluating information / data Recommending
the data a course of action
© 2009 IFP Training
Today’s Actions
6
Decision process
Studies
Studies PROJECT
PROJECT Operations
Operations
Preliminary
Preliminary Basic
Basic
Studies Engineering Start-Up
Start-Up
Studies Engineering
Conceptual
Conceptual
Studies
Studies
Detailed Field
Field
Pre-Project Detailed
Pre-Project Engineering Operations
Operations
Engineering
GO
GO/ /NOT
NOTGOGO Contractor
Contractor Provisional
for Advanced
for Advanced Provisional
Selection
Selection Acceptance
Studies
Studies Acceptance
GO
GO/ /NOT
NOTGO
GO
To Launch
To Launch
Pre-Project
Pre-Project Final
Final
GO End
Endof
GO/ /NOT
NOTGO GO of Acceptance
Project
Project Sanction
Sanction
AA long
long and
and complex
complex process
process requiring
requiring operator,
operator, partners
partners and
and authorities
authorities approval.
approval.
Economic
Economic studies
studies with
with risk
risk evaluation
evaluation and
and sensitivity
sensitivity analysis
analysis have
have to
to be
be provided
provided as
as part
part of
of the
the
recommendation
recommendation to to approve
approve the
the Project.
Project.
The
The sanction
sanction may
may take
take place
place before
before or
or after
after the
the Basic
Basic Engineering
Engineering phase
phase depending
depending on
on the
the type
type of
of
project.
project.
Feasibility and,
Pre-Project Studies Contracts
Awards Transfer
Start-up
Detailed Studies
Contracts Negotiations
Manufacturing
and Construction
Exploitation Phase
Equipment
9MainEquipment
9Main
9Bulk
9Bulk DirectCosts
Direct Costs
9Construction
9Construction Technical Costs
+
9Transportation
9Transportation
9Temporary Facilities
9TemporaryFacilities IndirectCosts
Indirect Costs
Camps
9ConstructionCamps
9Construction
+
Services
9EngineeringServices
9Engineering
9Management&&Supervision
9Management Supervision GeneralExpenses
General Expenses
9Surveys
9Surveys
+
9Insurance
9Insurance AssociatedExpenses
Associated Expenses
9Commissioning
9Commissioning
+
© 2009 IFP Training
FacilitiesCost
Facilities CostEstimate
Estimate = Contingencies
Contingencies
10
The investment project’s magic triangle
AAproject
projectisisaaglobal
globalapproach
approachto
toachieve
achieveaadefined
definedobjective
objective
AAproject
projectisisaamethod
methodand
andaatool
tooldesigned
designedtotocontrol
controlan
anindustrial
industrialinvestment
investment
AAproject
projectis
isbased
basedupon
uponan
aneconomic
economicreality
reality
Schedule Cost
Schedule means VALUE Cost means
Forecast and Anticipation CREATION Budget Control and Forecast
Quality
Quality also means Safety
Discount Rate
© 2009 IFP Training
PROJECT
PROJECT Operating Revenues
Gvt Take
ECONOMICINDICATORS
ECONOMIC INDICATORS
NetPresent
Net PresentValue
Value
InternalRate
Internal Rateof
ofReturn
Return
Pay-OutTime
Pay-Out Time
FinancialExposure
Financial Exposure
Profitability Index
Profitability Index
EconomicCost
Economic Cost
BASICRISK
BASIC RISKANALYSIS
ANALYSIS
SpiderCharts
Spider Chartsor
orTornado
TornadoDiagrams
Diagrams
Dependent projects
CommonResource
Common Resource
Project A Project B
Competition
or
Complementarity
Competing
Value(A+B)
Value(A+B) << Value(A)
Value(A) ++ Value(B)
Value(B)
Projects
Complementary
Value(A+B)
Value(A+B) >> Value(A)
Value(A) ++ Value(B)
Value(B)
© 2009 IFP Training
Projects
14
InvestmentProfitability
Investment ProfitabilityStudies
Studies
inthe
in thePetroleum
PetroleumIndustry
Industry
Contents
Contents
Introduction
Introduction
Fundamentals of
Fundamentals of general
general methodology
methodology 33
Value creation
Value
creation and
and profitability
profitability analysis
analysis 16
16
Principles of
Principles
of risk
risk analysis
analysis methodology
methodology 68
68
Conclusion
Conclusion
From projects’
From projects’ value
value to
to corporate
corporate financial
financial performance
performance 84
84
Capital
Employed
Shareholders Lenders
Capital Employed
is to be remunerated from the return on investment projects
© 2009 IFP Training
aa project
project will
will be
be financed
financed by
by aa fraction
fraction of
of the
the total
total capital
capital available.
available.
16
Cost of capital and value creation in the absence of risk
All
All funds
funds make
make up
up total
total capital
capital employed
employed to
to which
which one
one must
must associate
associate aa single
single cost
cost
WEIGHTED
WEIGHTED AVERAGE
AVERAGE COST
COST OF
OF CAPITAL
CAPITAL
WeightedAverage
Weighted AverageCost
Costof
ofCapital
Capital
Equity Capital Debt Capital
ii==ααee++(1
(1––αα))CCp
p
(1-α)% α%
Cost Cp Cost e
Remuneration Remuneration
Total Capital
expected by contracted with
shareholders lenders
Example
α= 25% Debt 1–α = 75% Equity
cost e = 4% cost Cp = 12%
© 2009 IFP Training
18
Cost of debt capital
• The cost of debt capital corresponds to the market interest rate, plus a premium
for the lender. The premium depends on the quality of the company, on the
guaranties of the parent-company when the borrower is an affiliate, and on the
country risk.
• Notation of companies
– The notation is the evaluation by a specialized independent agency of the
risk of non-payment of loans.
– This notation condition the access to loans from financial markets and
bankers: amount of further loans, interest rates charged…
• A number of ratios are computed by financial analysts and if those ratios are
beyond some given limits, the lenders will be very reluctant to agree to further
loans:
• Gearing = Debt Capital / Equity Capital
19
• The cost of equity capital for the company is the rate of return expected by the
shareholders.
20
Cost of equity capital / Gordon Shapiro model
Cost
Cost of Capital
Cost
EquityCapital
Equity Capital WeightedAverage
Weighted AverageCost
Costof
ofCapital
Capital
Cost
Cost
Debt Capital
Debt Capital
Debt Ratio
23
PROJECT
PROJECT Revenues
Capex Opex
Gvt Take
Cash
Cash Flow
Flow == Cash
Cash Inflow
Inflow –– Cash
Cash Outflow
Outflow
Operating period
Present
years
Investment
One must “bring” all cash flows from the future to the present,
that is
discount all the project’s cash flows.
24
Time value of money and discount rate
FutureValue
Future Valuein
inyear
yearnnof
ofaaPresent
PresentCash
CashFlow
FlowCF
CF0
0
compounding
CF0 CFn = CF0 . (1+i)n
PresentValue
Present Valueof
ofaaFuture
FutureCash
CashFlow
FlowCF
CFnfrom
fromyear
yearnn
n
CFn discounting
CF0 = CFn
(1+i)n
Amount that can be borrowed today and paid back,
with an annual interest i, in n years with the future cash flow CFn
25
FutureNet
Future NetCash
CashFlows
Flows
i = 10%
Year 0 1 2 3 4 5 6 Sum
0 20 30 50 50 50 50 250
Acc.
18 18
43 25
@10%»»
81 38
Value@10%
115 34
PresentValue
146 31
««Present
174 28
© 2009 IFP Training
DiscountedCash
Discounted CashFlows
Flows
26
Concept of net present value
FutureNet
Future NetCash
CashFlows
Flows
i = 10%
Year 0 1 2 3 4 5 6 Sum
-100 20 30 50 50 50 50 150
Loan»»
««Loan
Acc.
18
««Net
-82
NetPresent
-57 25
PresentValue
@10%»»
Value@10%
-19 38
Value@0%
PresentValue
15 34
@0%»»
NetPresent
46 31
74 28
««Net
27
Financing
Financing Decision
Decision Investment
Investment Decision
Decision
(selecting
(selecting financial
financial sources)
sources) (selecting
(selecting investment
investment projects)
projects)
FinancialTheory
Financial Theoryexcludes
excludesRiskRisk
Company’sDiscount
Company’s DiscountRate
Rate==Weighted
WeightedAverage
AverageCost
Costof
ofCapital
Capital
i i==ααee++(1
(1––αα) )CCp
p
Forthe
For themanagement
managementof
ofthe
thecompany
companyfacing
facingtechnical,
technical,economic,
economic,and
andcontractual
contractualrisks,
risks,
Company’sDiscount
Company’s DiscountRate
Rate==Weighted
WeightedAverage
AverageCost
CostofofCapital
Capital++Risk
RiskPremium
Premium
28
Discount rate and value creation in the presence of risk
Project’s
the company’s discount rate Value
RiskPremium
Premium
Company’s Discount Rate (%) ii
Risk
introduced by
introduced by thethemanagement
management
to mitigate the overall risk
to mitigate the overall risk
Company’s Cost of Capital (%)
29
Condition11
Condition
Thesize
The sizeof
ofthe
theproject
projectdoes
doesnot
notchange
changesignificantly
significantly
thefinancial
the financialstructure
structureof
ofthe
thefirm.
firm.
Therelative
The
relativeweight
weightof
ofthe
thefirm’s
firm’svarious
varioussources
sourcesof
offinancing
financingshould
shouldnot
not
bemodified.
be modified.
IfIfthat
thatis
isnot
notthe
thecase,
case,the
theaverage
averagecost
costof
ofcapital
capitalis
isdetermined
determinedfrom
fromthe
the
newfinancial
new financialstructure
structurewhich
whichincorporates
incorporatesthe
thefinancing
financingofofthe
theproject.
project.
Condition22
Condition
Thereis
There isno
nocapital
capitalrationing.
rationing.
Atthe
At
thelimit
limitofofthe
thebudget
budgetconstraint,
constraint,each
eachselected
selectedproject
projectlimits
limitsfurther
further
accessto
access toloans.
loans.
© 2009 IFP Training
Thiswould
This
wouldthen
thenchange
changethe
theaverage
averagecost
costof
ofcapital.
capital.
30
Nominal money and constant money : «inflate» / «deflate»
1$0 = * (1+d)
n
1$n Monetary depreciation is summarized
in the annual inflation rate
“Inflate”
* (1+d)
n
/ (1+d)n “Deflate”
Nominal
Nominal Money
Money
31
Inflation = d = 5% a year
Priceof
Price ofaaSpecific
Specific
Goodor
Good orService
Service
Nominal Money
P’
Nominal Money Basket
δ’ = +7% a year P
Constant Money
δ = +1.9% a year
Constant Money
© 2009 IFP Training
years
1+δδ’’==(1+
1+ (1+δδ))..(1+d)
(1+d)
δδ’’≈≈δδ++dd
32
Interest rates in nominal money and constant money
Without Inflation
Lenders
Lenders
Sn = S0 * (1+e)n
S0 Sn
eeinterest
interestrate
rate
Loan (in real terms)
Payoff
With Inflation
Lenders
Lenders
S’n = S0 * (1+e’)n = Sn * (1+d)n
S0 e’interest
interestrate
rate S’n
e’ Payoff
Loan
(1+e’)==(1+e)
(1+e’) (1+e) *(1+d)
(1+d)
*
e’≈≈ee++dd
e’
33
NominalMoney
Money OR Constant
ConstantMoney
Money
Nominal
Project’s
Value
CF’n discounting
CF0 = CF’n
(1+i’)n
PresentValue
Present Valueof
ofaaFuture
FutureCash
CashFlow
FlowCF
CFnfrom
fromyear
yearnn
Without Inflation
CFn discounting
CF0 = CFn
(1+i)n
Amount that can be borrowed today and paid back,
with an annual interest rate i, in n years with the future cash flow CFn
PROJECT
PROJECT Revenues
Capex Opex
Gvt Take
Year 0 … to ... N
Revenues (1)
Capex (2)
Opex (3)
36
Economic indicators of profitability studies
ECONOMICINDICATORS
ECONOMIC INDICATORS
NetPresent
Net PresentValue
Value
InternalRate
Internal Rateof
ofReturn
Return
Pay-OutTime
Pay-Out Time
FinancialExposure
Financial Exposure
ProfitabilityIndex
Profitability Index
EconomicCost
Economic Cost
NetPresent
Net PresentValue
Valueof
ofaaCash
CashFlows
FlowsSchedule
Schedule
Year 0 1 … C … N
n
Discounting at a rate i 1 (1+i) (1+i) (1+i)N
Cash Flows CF0 CF1 … CFn … CFN
Discounted Cash Flows CF0 CF1/(1+i) … CFn/(1+i)n … CFN/(1+i)N
Net Present Value = Sum of Discounted Cash Flows
N
CFn
NPV = ∑
n = 0 (1 + i )
n
i = Discount Rate
© 2009 IFP Training
38
Economic criteria / Net Present Value
N
CFn
NPV = ∑
n = 0 (1 + i )
n
IfIfNPV
NPV==00
Therevenues
The revenuesof ofthe
theproject
projectarearesufficient
sufficientto:
to:
payall
¾¾pay alltypes
typesofofexpenses
expenses
repaythe
¾¾repay thecapital
capitalinvested
invested
remunerateititat
¾¾remunerate ataarate
ratejust
justequal
equaltotothe
thediscount
discountrate
rate
The
The value
value of
of the
the discount
discount rate
rate which
which takes
takes NPV
NPV to
to zero
zero
measures
measures the
the rate
rate of
of return
return from
from the
the investment
investment project
project
NPV
IRR
Discount Rate
Company’s
Discount Rate
Project’s
Project’s IRR
IRR == Return
Return on
on Capital
Capital Invested
Invested
Value
Value Creation
Creation if
if and
and only
only if
if NPV
NPV >> 00
© 2009 IFP Training
Internal
Internal Rate
Rate of
of Return
Return >> Discount
Discount Rate
Rate
40
Computing NPV and the IRRs
Discount
Discount Rate
Rate i’i’ Discount
Discount Rate
Rate ii
Nominal
Nominal Money
Money Constant
Constant Money
Money
Cash
Cash Flow
Flow CF'
CF'nn Cash
Cash Flow
Flow CF
CFnn
Nominal
Nominal Money
Money
NPV
NPV Constant
Constant Money
Money
CF ' n CFn
NPV = ∑ NPV = ∑
(1 + i ' ) n (1 + i ) n
CF ' n = CF n (1 + d ) n
n n
IRRA
IRR A
IRRB
IRR B
Discount Rate
(A)
CF0A
(B)
CF0B
IncrementalRate
Incremental Rateof
ofReturn
Return
© 2009 IFP Training
42
Economic criteria / Pay-Out Time - Financial Exposure
NPV
NPV
POT
M$
0 1 2 3 4 5 6 7 8 9 10 11 12
Financial
Financial
Exposure
Exposure
Cash Flows Acc. Cash Flows
PI NPV PI NPV
PI = PI =
Investment Financial Exposure
PROFITABILITYINDEX
PROFITABILITY INDEX
AAMEASURE
MEASUREOF
OFVALUE
VALUECREATED
CREATEDPERPERDOLLAR
DOLLARINVESTED
INVESTED
45
Capital rationing
To select between various investment projects with the constraint of a limited budget,
there are two simple methods:
Profitability
Profitabilityindex
indexmethod
method
Choosing
ChoosingIndependent
IndependentProjects:
Projects:Projects,
Projects,ranked
rankedaccording
accordingtotodecreasing
decreasing
profitability
profitabilityindex,
index,are
arepicked,
picked,one
oneafter
afterthe
theother,
other,up
upto
tothe
thepoint
pointwhere
where
««Total
TotalCAPEX
CAPEX==Capital
CapitalAvailable
Available»»
Scarcity
Scarcitycost
costofofcapital
capital
Choosing
ChoosingIndependent
IndependentProjects:
Projects:Projects,
Projects,ranked
rankedaccording
accordingtotodecreasing
decreasing
internal
internalrate
rateof
ofreturn,
return,are
arepicked,
picked,one
oneafter
afterthe
theother,
other,up
upto
tothe
thepoint
pointwhere
where
««Total
TotalCAPEX
CAPEX==Capital
CapitalAvailable
Available»»
© 2009 IFP Training
46
Economic criteria / Unit Economic Cost
Break-EvenPrice
Break-Even Price
UnitSelling
Unit SellingPrice
Pricesuch
suchthat
thatNPV
NPV==00
NoProfit,
No Profit,No
NoLoss
Loss
Break-EvenPrice
Break-Even Price==Unit
UnitEconomic
EconomicCost
Cost
Project’s
Value
Unit Economic Cost ($/t)
NPV>>00ififand
NPV andonly
onlyifif
47
Break-EvenAnnual
Break-Even AnnualRevenues
Revenues
AnnualRevenues
Annual Revenuessuch
suchthat
thatNPV
NPV==00
NoProfit,
No Profit,No
NoLoss
Loss
Break-EvenAnnual
Break-Even AnnualRevenues
Revenues==Annual
AnnualEconomic
EconomicCost
Cost
Project’s
Value
Annual Economic Cost (M$)
NPV>>00ififand
NPV andonly
onlyifif
© 2009 IFP Training
AnnualRevenues
Annual Revenues>>Project’s
Project’sAnnual
AnnualEconomic
EconomicCost
Cost
48
Costs vs profits
49
PROJECT
PROJECT Revenues
Capex Opex
Gvt Take
i i i==ααee++(1
(1––αα) )CCp
p
Equity
Equity Capital
Capital e
StandardFinancial
Standard FinancialStructure
Structure
of company’s portfolio Finance
of company’s portfolio
ratioα,α,cost
(debtratio costofofdebt
debte)e)
Finance Division
Division OperationalDivision
Division
(debt Operational
Debt
Debt Capital
Capital Cp
FinancialTheory
Financial Theoryexcludes
excludesRisk
Risk
Company’sDiscount
Company’s DiscountRate
Rate==i i==Weighted
WeightedAverage
AverageCost
Costof
ofCapital
Capital
independent of any fiscal regime
independent of any fiscal regime
© 2009 IFP Training
Practical
Practical experience
experience incorporating
incorporating management’s
management’s assessment
assessment of of risk:
risk:
Discount
Discount Rate
Rate == Weighted
Weighted Average
Average Cost
Cost of
of Capital
Capital ++ Risk
Risk Premium
Premium
50
Global profitability analysis / Summary
Technical
Technical Data
Data in
in Constant
Constant Money
Money Economic
Economic Assumptions
Assumptions & & Fiscal
Fiscal Regime
Regime
Capex,
Capex, Opex, Production profile
Opex, Production Price,
Price, Inflation d, Discount rate
Inflation d, Discount rate ii
Inflate
profile
x(1+d)n Fiscal
Fiscal Terms
Terms
Company’s
Company’s Cash
Cash Flows
Flows Schedule
Schedule
Year 0 … to ... N
Revenues (1)
Duties (2)
Capex (3) Project’s
Project’s
Fiscal Depreciation (4) Economic Indicators
Economic Indicators
Opex (5) N
CFn
NPV = ∑
Others (6) n =0 (1 + i )
n
(interests, carry, provisions, etc.)
Fiscal Depreciation
3spreads the investment cost over the depreciation period.
3rules are set in the petroleum contract, depending on type of investment.
3depreciation is generally charged starting the first year of exploitation.
3 Σ depreciation charges = nominal value of asset, except when there is an uplift.
3straight-line depreciation: constant depreciation charges = Capex / Nbre years
Consolidation
3a negative taxable income of a project is consolidated at the level of the
company’s result in the country. Provided the latter is positive, this will induce
tax savings (or tax shield) which must be credited to the project.
Ringfencing
3a negative taxable income of a project is a fiscal loss which is carried forward
© 2009 IFP Training
to the following fiscal year. It is then a charge which can de deduced in the
computation of the taxable income.
52
Consolidation and Ringfencing
CONSOLIDATION Year 0 1 2 3 4 5
Revenues (1) 40 70 70 70 70
Capex (2) 140
Depreciation (3) 35 35 35 35
Opex (4) 20 25 25 25 25
Income (5)=(1-3-4) -15 10 10 10 45
Tax (6)=(5) * t -6 4 4 4 18
Cash Flows (7)=(1-2-4-6) -140 26 41 41 41 27
Year 0 1 2 3 4 5
RINGFENCING (1)
Revenues 40 70 70 70 70
Capex (2) 140
Depreciation (3) 35 35 35 35
Opex (4) 20 25 25 25 25
Carry Forward (5) -15 -5 0 0
53
AAschedule
scheduleforforaastandard
standardfinancing
financingplan
planisisbuilt
builtin
inorder
orderto
tocompute
compute
thefinancial
the financialcharges
chargesassociated
associatedwith
withthe
theproject,
project,and
anddeduce
deducethem
themin
in
the taxable income if this is allowed for by the fiscal rules
the taxable income if this is allowed for by the fiscal rules of theof the
countrywhere
country wherethetheproject
projectwill
willbe
becarried.
carried.
ConstantAnnuity
Constant Annuity
Year 0 1 2 3 4 5
Loan 100.0
Outstanding Debt (end year) 100.0 83.6 65.6 45.8 24.0 0.0
Capital Repayments 16.4 18.0 19.8 21.8 24.0
Interests 10.0 8.4 6.6 4.6 2.4
Annuities 26.4 26.4 26.4 26.4 26.4
Interest Rate 10%
ConstantCapital
Constant CapitalRepayment
Repayment
Year 0 1 2 3 4 5
Loan 100.0
Outstanding Debt (end year) 100.0 80.0 60.0 40.0 20.0 0.0
Capital Repayments 20.0 20.0 20.0 20.0 20.0
© 2009 IFP Training
AAschedule
scheduleforforaastandard
standardfinancing
financingplan
planisisbuilt
builtin
inorder
orderto
tocompute
compute
thefinancial
the financialcharges
chargesassociated
associatedwith
withthe
theproject,
project,and
anddeduce
deducethem
themin
in
the taxable income if this is allowed for by the fiscal rules
the taxable income if this is allowed for by the fiscal rules of theof the
countrywhere
country wherethetheproject
projectwill
willbe
becarried.
carried.
ConstantAnnuity
Constant Annuity
Year 0 1 2 3 4 5
Loan 100.0
Outstanding Debt (end year) 100.0 83.6 65.6 45.8 24.0 0.0
Capital Repayments 16.4 18.0 19.8 21.8 24.0
Interests 10.0 8.4 6.6 4.6 2.4
Annuities 26.4 26.4 26.4 26.4 26.4
Interest Rate 10%
Year 0 1 2 3 4 5 6
Loan 60.0 40.0
Outstanding Debt (end year) 60.0 106.0 88.6 69.5 48.5 25.4 0.0
Capitalized Interests 6.0
Capital Repayments 17.4 19.1 21.0 23.1 25.4
the
Practical
Practical experience
experience incorporating
incorporating management’s
management’s assessment
assessment ofof risk:
risk:
Discount Rate = After-Tax Weighted Average Cost of Capital + Risk Premium
Discount Rate = After-Tax Weighted Average Cost of Capital + Risk Premium
56
Classical global profitability analysis:
a simple, particular case of one simple fiscal regime
Technical
Technical Data
Data in
in Constant
Constant Money
Money Economic
Economic Assumptions
Assumptions & & Fiscal
Fiscal Regime
Regime
Capex,
Capex, Opex,
Opex, Production
Production profile Price,
Price, Inflation d, Discount
Inflation d, Discount rate
rate ii
Inflate
profile
x(1+d)n Corporate
Corporate Income
Income Tax
Tax
Company’s
Company’s Cash
Cash Flows
Flows Schedule
Schedule
Year 0 … to ... N
Revenues (1) Project’s
Project’s
Economic Indicators
Economic Indicators
Capex (2)
Fiscal Depreciation (3) N
CFn
NPV = ∑
n = 0 (1 + i )
n
Opex (4)
Others (5) IRR = i
(carry, provisions, etc.)
such that NPV = 0
Corporate Taxable Income (6) = (1-3-4-5)
Corporate Income Tax (7) = (6) x tax rate
57
After-TaxWeighted
After-Tax WeightedAverage
AverageCost
Costof
ofCapital
Capital
Equity Capital Debt Capital
i’i’==ααê’ê’++(1(1––αα))C’
C’p
p
with ê’
with ê’==(1–t)
(1–t)e’
e’
α%
(1-α)%
Example
α = 25% Debt 1–α = 75% Equity
© 2009 IFP Training
Questionin
Question inthe
thefinal
finalphase
phaseof
ofaalarge
largeinvestment
investmentproject
projecteconomic
economicevaluation
evaluation: :
what is the return on equity capital invested in the project with a given financingplan?
what is the return on equity capital invested in the project with a given financing plan?
Dividends Reimbursements
PROJECT
PROJECT
Company Bank
59
Investment
Project finance
In the preparation of the project finance, the banks will have two main
objectives:
¾ determine the viability of the project, and
¾ eliminate as much as possible the specific risks of the project.
60
Advantages of project finance
PROJECT
PROJECT Revenues
Capex Opex
Gvt Take
OperationalDivision
Operational Division
Company’s Cash Flows Schedule
Year 0 … to ... N
Revenues (1)
Capex (2)
Opex (3)
P
PRRO
O JJ E
ECCT
T Revenues
Bank Loan
Opex
Repayments
Debt Capital
Interests
Shareholders
Shareholders
Equity Capital
Equity Capital
63
Minimum remuneration expected by shareholders
profile
x(1+d)n Fiscal
Fiscal Terms
Terms
Equity
Equity Cash
Cash Flows
Flows Schedule
Schedule 0 … to ... N
Year
Revenues (1)
Operating Cycle
Interests (7)
Deflate
IRR≈≈(1
IRR (1––αα))ROE
ROE++ααee
Rateof
Rate ofReturn
Returnon
onEquity
EquityCapital
Capital>>Rate
Rateof
ofReturn
Returnon
onCapital
CapitalInvested
Invested
Financial Leverage
Return on equity capital can be raised by increasing the debt ratio.
65
Onlyaaglobal
Only globalprofitability
profitabilityanalysis
analysisisiscarried
carriedout
outin
inpreliminary
preliminarystudies
studiestotoevaluate
evaluate
thereal
the realprofitability
profitabilityof
ofthe
theproject,
project,and
anddecide
decidetotocarry
carryon
onor
ornot.
not.
Only
Only aa global
global profitability
profitability analysis
analysis is
is justified
justified
ifif the
the company's
company's debt
debt ratio
ratio is
is fixed
fixed for
for the
the whole
whole portfolio
portfolio of
of projects.
projects.
According
According toto the
the principle
principle of
of corporate finance of
corporate finance of non
non allocation
allocation of
of funds
funds toto
uses,
uses, aa project
project will
will be
be financed
financed byby aa fraction
fraction of
of the
the overall
overall capital
capital available
available to
to
which
which is
is associated
associated one
one single
single cost,
cost, the
the average
average cost
cost of
of capital.
capital.
Even
Even for
for aa project
project for
for which
which the
the company
company could
could borrow
borrow more
more than
than for
for the
the
average
average of of its
its portfolio,
portfolio, the
the economic
economic benefit
benefit of
of financial leverage cannot
financial leverage cannot be be
allocated to this project since the
allocated to this project since the debt ratio is imposed upon all projects and
debt ratio is imposed upon all projects and
© 2009 IFP Training
this
this will
will force
force the
the company
company to to use
use aa smaller
smaller part
part of
of debt
debt in
in the
the other
other projects.
projects.
66
InvestmentProfitability
Investment ProfitabilityStudies
Studies
inthe
in thePetroleum
PetroleumIndustry
Industry
Contents
Contents
Introduction
Introduction
Fundamentals of
Fundamentals of general
general methodology
methodology 33
Value creation
Value
creation and
and profitability
profitability analysis
analysis 16
16
Principles of
Principles
of risk
risk analysis
analysis methodology
methodology 68
68
Conclusion
Conclusion
From projects’
From projects’ value
value to
to corporate
corporate financial
financial performance
performance 84
84
Reasons of failure
Technical reasons
Delay in completion
Management problems
Cost overruns
Price volatility
© 2009 IFP Training
68
What is risk analysis?
69
Economic Evaluation
NPV
NPV IRR
IRR
Scenario
Scenario
Development
Development Plan
Plan && Economic
Economic Assumptions
Assumptions
Sensitivityanalysis
Sensitivity analysis
Production
Price
Capex
50 100 150
M$
71
500
400
300
200
100
-100
-40% -30% -20% -10% Base 10% 20% 30% 40%
© 2009 IFP Training
Variation
72
Sensitivity analysis in investment decision
73
Identify key variables which contribute most to the project’s risk and
examine them more in detail.
74
Methodology of quantitative risk analysis
Methods
Methods
Decision
DecisionTree
TreeAnalysis
Analysis
Monte
MonteCarlo
CarloSimulation
Simulation
Scenarios
ScenariosApproach
Approach
The decision criteria becomes the NPV expected value which is the probability
weighted average of the branchs' NPV's. The result can be significantly different
from the most likely outcome.
© 2009 IFP Training
However event trees become rapidly over complicated when they include
several parameters (price, volume, costs). They have to be simplified or one has
to revert to simulation techniques.
76
Discrete probabilistic approach: decision trees
MANAGEMENT
MANAGEMENT
78
Probability distributions and risk profiles
Probability
Probability
Probability
x x x
Probability
Probability
Probability
Probability
x
79
Log-normal distribution
•1.0 •P99
•P95
•0.9 Min(P95):
Min (P95):48
48 Mode
Mode: :86
86 Max(P5):
Max (P5):265
265
•0.8
•0.7 •mode
•0.6
•0.5 •median
•0.4 •mean
•0.3
•0.2
•0.1
•P5
•0.0 •P1
•0 •50 •100 •150 •200 •250 •300 •350 •400 •450
•Variable
Swanson’sLaw
Swanson’s Law
Mean≈≈0.30
Mean 0.30xxMin
Min++0.40
0.40xxMode
Mode++0.30
0.30xxMax
Max
80
Continuous probabilistic approach: Monte Carlo
Monte-Carlo simulation, aa purely
Monte-Carlo simulation, purely probabilistic
probabilistic approach:
approach:
¾¾ each
each risk factor: one
risk factor: one distribution
distribution of
of subjective
subjective probabilities.
probabilities.
¾
¾ aa simulation run: picks,
simulation run: picks, at
at random,
random, aa value
value for
for each
each variable,
variable,
and
and computes
computes the
the project’s
project’s NPV
NPV value.
value.
¾ repeat the
¾ repeat the process
process aa great
great number
number of
of times
times in
in order
order to
to
obtain a histogram of present values.
obtain a histogram of present values.
TECHNICAL
TECHNICAL
STAFF
STAFF
Difficult
ItIt is
is very
very difficult
difficult to
to account
account forfor all
all the dependencies between
the dependencies between variables.
variables. Communication
It is impossible to the technical options
It is impossible to optimize the technical options for the development
optimize for the development
architecture
architecture and and production
production profiles.
profiles.
It is
It is impossible
impossible to identify the
to identify the contribution
contribution ofof aa given
given input
input to
to the
the output
output
value:
value: itit isis called
called the
the black box effect.
black box effect.
DECISIONTHEORY
DECISION THEORY
ExpectedNet
Expected NetPresent
PresentValue
Value
ENPV <NPV>≅≅0.3
ENPV==<NPV> NPVmin++0.4
0.3NPV 0.4NPV
NPVmode++0.3
0.3NPV
NPVmax
min mode max
(Swanson’s Rule)
(Swanson’s Rule)
withaameasure
with measureof
ofthe
therisk
riskprovided
providedby
bythe
thestandard
standarddeviation
deviation
© 2009 IFP Training
σσ≅≅1/3 (Vmax––VVmin))
1/3(V
max min
82
InvestmentProfitability
Investment ProfitabilityStudies
Studies
inthe
in thePetroleum
PetroleumIndustry
Industry
Contents
Contents
Introduction
Introduction
Fundamentals of
Fundamentals of general
general methodology
methodology 33
Value creation
Value
creation and
and profitability
profitability analysis
analysis 16
16
Principles of
Principles
of risk
risk analysis
analysis methodology
methodology 68
68
Conclusion
Conclusion
From projects’
From projects’ value
value to
to corporate
corporate financial
financial performance
performance 84
84
Capital
Employed
Shareholders Lenders
Company’s
Company’s Annual
Annual Financial
Financial Results
Results
These
These indicators
indicators measure
measure
the
the financial
financial performance
performance
Return on Equity of
of the
the company.
company.
84
Balance sheet
ASSETS LIABILITIES
Provisions
Current Liabilities
Cash (trade payables)
Provisions or Allowances
85
Balance sheet
ASSETS LIABILITIES
Provisions
Capital Employed
Capital Invested
Debt Capital
Operating Working Capital - Cash
86
Financial indicators
(Accounting)Result
(Accounting) ResultBefore-Tax
Before-Tax==Taxable Income==
TaxableIncome
OperatingRevenues
Operating Revenues--Operating
OperatingExpenses
Expenses
Operating --Depreciation
DepreciationCharges
Charges--Financial
FinancialCharges
Charges
Expenses Corporate Tax==
CorporateTax
TaxableIncome
Taxable Income xxIncome
IncomeTax
TaxRate
Rate
Depreciation
Charges
Operating
Revenues
EBITDA Corporate Tax
or
Gross EBIT Financial
Operating Profit or Charges
Operating After-Tax
Income Operating
Income Net Income
CashFlow
Cash Flow==FFO
FFO==
NetIncome
Net Income++Depreciation
DepreciationCharges
Charges
Investments
Cash Flow Cash Flow
© 2009 IFP Training
Operating Income =
Operating Revenues
Operating - Operating Expenses
Expenses - Depreciation Charges
Operating Income, or
Depreciation EBIT, Earnings Before Interest and Tax,
Charges or operating profit, or operating result, or trading profit:
Operating
Revenues represents the earnings generated by investment cycle
and operating cycle for a given period.
89
Depreciation
Charges Tax ==t txx(R
CorporateTax
Corporate (R- -DD- -MM- -FC)
FC)
Operating
Revenues Corporate Tax
RR- -DD- -MM- -FC
FC==Taxable
TaxableIncome
Income
RR==Operating
OperatingRevenues
Revenues
After-Tax DD==Operating
OperatingExpenses
Expenses
Operating M = Depreciation Charges
M = Depreciation Charges
FC==Financial
FC FinancialCharges
Charges
Income
© 2009 IFP Training
t t==income
incometax
taxrate
rate
90
Net operating income
Operating
Expenses Net Operating Income =
Operating Income
- Corporate Tax - Tax Shield
Depreciation
Charges Tax ==t txx(R
CorporateTax (R- -DD- -MM- -FC)
FC)
Operating Corporate
Revenues Theoretical Tax Shield ==t tFC
TaxShield FC
(without financial charges)
Tax
TheoreticalTax
Theoretical Tax==
CorporateTax
Corporate Tax++Tax
TaxShield
Shield==
Net t x (R - D - M)
t x (R - D - M)
Operating
Income
Depreciation Debt
Charges ROACE Capital
Operating ROACE
Net
Revenues
Theoretical Tax Fixed Assets
Equity
Net Capital
Operating
Income Operating
Working Capital
ROACE==NET
ROACE NETOPERATING
OPERATINGINCOME
INCOME/ /AVERAGE
AVERAGECAPITAL
CAPITALEMPLOYED
EMPLOYED
© 2009 IFP Training
Return on capital employed can also be considered as the return on equity if net debt is zero.
It is the most important indicator of value creation used in financial management.
92
Net income
Operating
Expenses
Net Income =
Depreciation Operating Income
Charges - Corporate Tax – Financial Charges
Operating
Revenues = Net Operating Income - (1-t) FC
Corporate Tax
= Before-Tax (Accounting) Result
Financial Charges - Corporate Tax
Depreciation Debt
Charges Capital
Operating
Net
Revenues Corporate Tax Fixed Assets
ROE
ROE
Financial Charges
Equity
Capital
Net Income Operating
Working Capital
© 2009 IFP Training
ROE==NET
ROE NETINCOME
INCOME/ /EQUITY
EQUITYCAPITAL
CAPITAL
94
Cost of debt and return on equity
ROCE
Cost of Debt Return On Equity
10 % = 0 .5 * 8 % + 0 .5 * 12 %
ROCE
Cost of Debt Return On Equity
10 % = 0 .5 * 6 % + 0 .5 * 14 %
10 % = 0 .5 * 8 % + 0 .5 * 12 %
10 % = 0 .8 * 8 % + 0 .2 * 18 %
Financial Leverage
Return On Equity increases when Weight of Debt increases
96
Conclusion
Return on equity
is equal to return on capital employed plus a leverage effect.
If the use of debt allows one to reach a return on equity much higher
than the return on capital employed, it increases also the financial risk
of the shareholders.
In the long term, only a high return on capital employed will really create
value for the shareholders.
Valuecreation
Value creation