S o P-Piping
S o P-Piping
S o P-Piping
Please note- points mentioned in this documents are what we follow generally but not necessary every time. Please
provide your project detail for our confirmation
A. GENERAL
1. All piping material purchased shall be supported with material test certificates and
identification mark. After piping material received at site, it shall be subjected to random
chemical and mechanical test before it is taken for use. Material not conforming to standard
shall be rejected.
2. Before installation of pipe, pipes shall be made clean from inside by light hammering. Ends
shall be closed with cloth / PVC caps to avoid foreign particle to go inside. No rags or paper
bags shall be used for the same.
3. On pump suction line reducer if any shall be of eccentric type and installed to allow full
drainage.
4. After completion of piping, each line shall be hydro tested to 1.5 times the working pressure
of the piping using clean water.
1. Machine cut bevels are preferred. however, smooth flame -cut bevels with proper
grinding are acceptable.
2. Proper gap between the joints shall be maintained during tack welding by providing
spacers. This would ensure the full penetration of welds. The recommended gaps are: 1.5
mm weld gap for pipe smaller than 150 mm diameter.
3 Tack welds should be small and should penetrate fully to the bottom of the welding
groove. The tack welds that are not fully penetrated shall be grind off. Every tack weld
1
32, Samruddhi CHS Ltd., M.G. Road, Kandivli Village, Kandivli (W) Mumbai – 67
Ph. 022 – 28610231 Fax 022 -28055758, Mail id : sales@ashishengineering.net
Website : www.ashishengineering.net
shall be cleaned of scales, slag, flux, etc before welding additional beads. Every tack
weld shall become a part of the finished weld after full welding is done.
C. BENDING
1. Completed bends shall have smooth surfaces and shall be free of spots and
wrinkles.
2. Hot bending shall be done with the pipe filled up with sand. Minimum radius shall be
three times the pipe diameter. Hot bend shall be allowed to cool naturally before the
sand is removed.
3. Cold bending is not allowed for pipe diameters of 50 mm and above. If good quality
bends with a radius of three times the pipe diameter are not possible, higher radius shall
be made with the prior approval of Consulting Engineer/ Owner.
4 Flattening at any cross-section shall not exceed 3 % of the outside radius . Also the
minimum pipe thickness after bending shall not be less by 10 % of the nominal thickness.
D. WELDING
1. Welders and welding procedures shall be qualified in accordance with the requirements
of the latest edition of ASME section IX and IS - 817 for IBR/non -IBR piping. Both horizontal
and vertical qualifications shall be shown on qualification papers.
3. After each run of welding, slag shall be removed and through inspection and rectification
of this run should be done before the next welding run is started. Welding of full thickness
penetration shall be ensured.
4. Finished welds shall project minimum 1.5 mm but not more than 3 mm from the outer
surface of the pipe.
5. After completion of the welding, slag and metal spatters shall be thoroughly removed.
8. Weld repairs must be made by removing the defective weld metal by grinding or by
other mechanical means.
9. D. P. test will be carried out in steam piping of 10 % of the total weld joints.
10. 10% radio graphic examination shall be carried out in case of IBR piping. The welder used for
IBR piping shall be IBR approved. The IBR piping drawing shall be got prepared and
approved from IBR authority by contractor.all expense for approval purpose will be by
owner.
2
32, Samruddhi CHS Ltd., M.G. Road, Kandivli Village, Kandivli (W) Mumbai – 67
Ph. 022 – 28610231 Fax 022 -28055758, Mail id : sales@ashishengineering.net
Website : www.ashishengineering.net
STAINLESS STEEL
A. GENERAL
2. All piping material purchased shall be supported with material test certificates &
identification mark. After piping material received at site, it shall be subjected to random
chemical & mechanical test before it is taken for use. Material not conforming to
standard shall be rejected.
3. All piping material shall be stored in the clean place to avoid the material to
become dirty.
4. Before installation of pipes, pipes shall be made clean from inside by light hammering. Ends
shall be closed with cloth / PVC caps to avoid foreign particle to go inside. No rags or
paper bags shall be used for the same.
5. All pipe lines shall be laid such that it should be easily drainable i.e all lines shall be provided
slope of 5 mm / meter with direction indication on pipeline.
7. Incase of SS316L loop no dead leg exceeds three pipe diameter in any end of pipe/tapping.
All valves for tapping shall have Zero dead leg.
9. Vent and filters location shall be drainable and at place where maintenance can be
carried out easily.
10. All exposed wall / rack piping in the process area has clearance for cleaning and wipe
down.
12. On pump suction line, reducer if any shall be of eccentric type & installed to allow full
drainage.
13. After completion of piping each line shall be Hydro tested using clean DM water at 1.5 times
the Design pressure of the piping, or 1.5 times the loop pump discharge pressure which
ever is higher.
a. Remove oxide films i.e discolouration by pickling solution by mixing 1000 ml HCL (Sp.gr.1.19),
100 ml Nitric ACID (Sp.gr.1.4) and 1000 ml water. A suitable inhibitor such as Hexamethylence
tetramine shall be used. The pickling solution is allowed for about 10 minutes.
b. The treated surface is then cleaned thorouly first with water and then with very dilute caustic
soda solution. final rinsing is done by water.
15. All SS-316L piping shall be electropolished to 0.4 RA and externally polished to 180 grid.
3
32, Samruddhi CHS Ltd., M.G. Road, Kandivli Village, Kandivli (W) Mumbai – 67
Ph. 022 – 28610231 Fax 022 -28055758, Mail id : sales@ashishengineering.net
Website : www.ashishengineering.net
B. FABRICATION
1. Machine cut bevels are preferred. However, edges beveled with a file or grinder
followed by cleaning with a stainless steel wire brush are acceptable.
2. Proper gap between the joints shall be maintained during tack welding by providing
spacers. This would ensure the full penetration of welds.
3. Tack welds should be small and should penetrate fully to the bottom of the welding
groove.
4. Completed bends shall have smooth surfaces and shall be free of spots and wrinkles.
6. Cold bending is not allowed for pipe diameters of 50 mm and above. If good quality bend
with a radius of three times the pipe diameter are noted possible, higher radius of five
times the pipe diameter shall be made with the prior approval of Consulting Engineer
/Owner
7. Flattening at any cross-section shall not exceed 3 % of the outside radius . Also the minimum
pipe thickness shall not be less by 10% of nominal thickness.
8. S.S. tubing work for gases shall be carried out with SS compression fittings using SS ferrules.
Tube shall be bent using tube bender machine where ever required.
2. Argon Arc welding shall be used. Electric welding shall be used only with the approval of
Consultant /Owner.
3. Pipes up to 2mm thick may be welded without any root gap. Pipes of wall thickness
between 2 and 4.76 mm may be welded with a root gap of 1/2 the wall thickness . And
pipes above 4.76 mm thick shall be bevelled.
5. Finished welds shall project minimum 1.5 mm but not more than 3 mm from the outer
surface of the pipe.
7. After completion of the welding, slag and metal spatters shall be thoroughly removed.
Only stainless steel chipping tools and wire brushes are permitted.
8. The area of 50 mm on both the sides of welding shall be cleaned with halogen -free
solvent.
10. Weld repairs must be made by removing the defective weld metal by grinding or other
mechanical means.
12. All ss-304 pipe joints shall be 10% radiographed as per ASME section IX.
All SS-316L electro polished tubes / pipes shall be welded using orbital welding m/c.
documentation should be done for all weld joint.
All joints shall be 100% Boroscopically examined where ever boroscope is not possible radio
graphy shall be carried out.
5
32, Samruddhi CHS Ltd., M.G. Road, Kandivli Village, Kandivli (W) Mumbai – 67
Ph. 022 – 28610231 Fax 022 -28055758, Mail id : sales@ashishengineering.net
Website : www.ashishengineering.net
G.I.PIPING
The following codes, standards and specifications are made a part of this specification.
All standards, specifications, codes of practices referred to herein shall be the latest
edition including all applicable amendments and revisions.
In case of discrepancy between this specification and those referred to herein, this
specification shall govern.
IS:3589 Electrically welded steel pipe for water, gas and sewage (220 mm to 2000 mm
nominal Diameter).
A.2 MATERIALS
All materials, fittings, fixtures and appliances shall be of the best quality conforming to
relevant Indian Standards and shall be procured from approved manufacturers.
Unless specifically allowed by the Engineer, the contractor shall submit samples of fittings
and fixtures which shall be retained by him for comparison when bulk supplies are
received at the site. Ultimate choice lies completely with the Engineer.
The materials brought to the site, shall be stored in a separate secured enclosure away
from the building materials. Pipe threads, sockets and similar items shall be specially
protected till final installation. Valves and other expensive items shall be kept under lock
and key. Fragile items shall be checked thoroughly when received at the site and items
found damaged shall not be retained/used at the site.
Under scope of this specification, pipes and pipe fittings may be of any or a
combination of the following Types :
B Related works
All works, like earthwork, masonry, concrete, steel work, cutting holes, chases, repairs and
rectifications associated directly with installation of piping systems shall come under the
scope of Contractor unless specifically excluded.
6
32, Samruddhi CHS Ltd., M.G. Road, Kandivli Village, Kandivli (W) Mumbai – 67
Ph. 022 – 28610231 Fax 022 -28055758, Mail id : sales@ashishengineering.net
Website : www.ashishengineering.net
Where desired by the engineer or shown on the drawings the pipes shall be concealed in
masonry or concrete of the structure. The plumbing contractor must coordinate with the
building Contractor for leaving the chases, openings, conduits as necessary. However, the
Contractor shall rectify if required the chases, openings and conduits, supplement and
make good after laying and testing of the concealed pipelines.
All concealed G.I. piping shall carry Anit corrosive treatment consisting of a coat of coal
tar and wrapping with Bitumen Impregnated hessian cloth & cover the chase in 1:3 mortar
including covering with chicken mesh.
In addition to fulfilling the functional requirements, all pipelines shall be laid true to line,
plumb and level. Any deviation shall need approval of the Engineer. Meticulous care
shall be taken to avoid chances of airlock and water hammer.
Pipes shall be laid on continuous unyielding surface or on reliable supports at least one
near each joint and spacing as directed by the Engineer. The support must be strong,
neat and shall have provisions for securing the pipes in every direction and easy
maintenance. Pipes shall be encased or concealed in masonry or concrete if shown on
drawing or directed by the Engineer. All pipe works shall be so laid, fixed and maintained as
to be and to remain completely water-tight, thereby avoiding waste of water, damage to
property and the risk of contamination of the water being conveyed.
No piping shall be laid or fixed so as to pass into or through any sewer, scour outlet or drain
or any manhole connected therewith.
Underground piping shall be laid at such a depth that it shall not be damaged by traffic
and other loads and frost, where applicable.
The size and depth of the trench shall be as approved by the Engineer. Backfilling shall be
done with selected fine earth, unless otherwise permitted, in 150mm layers and carefully
consolidated. Special care shall be taken while filling in the vicinity of the pipe to avoid
damages. Before backfilling the laid pipe shall be fully tested and approved.
Once a joint has been screwed up it shall not be backed off unless the threads are
reclined and new compound applied. G.I. union / flanges shall be used as per direction of
engineer for easy dismantling / maintenance of G.I. pipelines vent shall be provided at
suitable location to avoid air locking.
d.2) Protection
Open end of each pipe shall be protected during installation by suitable covers or
plugs so that the ends, threads, socket are not damaged and no foreign material finds
its way into the pipeline. Fitting & Fixtures liable to be misused or stolen during the
construction phase shall be fitted only before testing & handing over.
7
32, Samruddhi CHS Ltd., M.G. Road, Kandivli Village, Kandivli (W) Mumbai – 67
Ph. 022 – 28610231 Fax 022 -28055758, Mail id : sales@ashishengineering.net
Website : www.ashishengineering.net
Jointing of pipes shall be completely leak proof and durable. Instruction of the
manufacturer shall be followed unless desired otherwise by the Engineer. However,
usually recommended practices are stated below for guidance:
a) Flanged joints:
Flanged joints shall be made by jointing rings of good quality, smooth and hard compressed
fibre board of thickness not less than 1.5 mm and of such width as to fit inside the circle of
bolt. Diagonally opposite bolts shall be tightened in pairs and in stages so that degree of
all bolts in a joint are similar. Damaged gaskets shall be replaced.
b) G.I. piping shall be joined only by screwed joints. Screwed joints shall be carefully
tightened. Care shall be taken to remove any burr from the ends of the pipes. Jointing
shall be done by using PTFE (Teflon) tape or good quality sealent.
All pipes, fittings and appliances shall be inspected, before laying and shall be sounded to
disclose cracks. Any defective item shall be clearly marked as rejected and forthwith
removed from the site.
After laying and jointing, the line shall be slowly and carefully charged with water, so that all
air is expelled from the vent. Allowed to stand full of water for a few days, if time permits,
and then tested under pressure. The test pressure shall be 1.5 times design press. or double
the maximum working pressure, whichever is greater. The pressure shall be applied by
means of a manually operated test pump, or in the case of long mains or mains of a large
diameter, by a power driven test pump, provided that the pump is not left unattended.
In either case due precaution shall be taken to ensure that the required test pressure is
not exceeded. Pressure gauge shall be accurate and shall preferably have been
recalibrated before the test. The pump having been stopped, the test pressure shall
maintain itself without measurable loss for at least five minutes. The end of the main shall
be closed by fitting a water-tight expanding plug and the plug shall be secured by struts to
resist the end thrust of the water pressure in the mains.
The service pipes shall be slowly and carefully charged with water, allowing all air to
escape and avoiding all shocks or water hammer. The service pipe shall then be inspected
under working conditions of pressure and flow. When all draw-off taps are closed, the
service pipes shall be absolutely watertight. All piping, fittings and appliances shall be
checked for satisfactory support and protection from damage, corrosion and frost.
d) Trenches
Unless particular items are included in the Schedule, no separate measurement shall be
made for lead, lift, dewatering, dressing, storing, backfilling, consolidation etc. that may be
required in this connection.
e) Pipe Works
8
32, Samruddhi CHS Ltd., M.G. Road, Kandivli Village, Kandivli (W) Mumbai – 67
Ph. 022 – 28610231 Fax 022 -28055758, Mail id : sales@ashishengineering.net
Website : www.ashishengineering.net
No separate measurement shall be made for specials, supports and fixtures, cutting
chases, holes and rectification unless specially indicated in the Schedule of Items. if the
specials are separately indicated in the schedule, the measurement for these shall be over
and above the measurement of the pipe work as mentioned below.
The pipe work shall be measured in length exclusive of sockets, specials, fittings, etc. in
position.
g) Chases, holes
No measurement shall be made for cutting chases, holes etc. Unless it is specifically
indicated in the schedule of rates.
9
32, Samruddhi CHS Ltd., M.G. Road, Kandivli Village, Kandivli (W) Mumbai – 67
Ph. 022 – 28610231 Fax 022 -28055758, Mail id : sales@ashishengineering.net
Website : www.ashishengineering.net
UPVC PIPING
A. GENERAL
1. Before installation of pipes , pipes shall be made clean from inside by light hammering. Ends
shall be closed with cloth / PVC caps to avoid foreign particle to go inside. No rags or paper
bags shall be used for the same.
2. After completion of piping , each line shall be hydro tested to 1.5 times the working pressure
of the piping using clean water.
B.1 CUT PIPE : Cut pipe square. As joints are sealed at the base of the fitting socket. An angled
cut may result in joint failure. Acceptable tools include miter saw, mechanical cut off saw or
wheel cutter. Wheel type cutters must employ a blade designed for plastics.
B.2 REMOVE BURR AND BEVEL : Remove all burr from inside and outside of pipe with a knife-edge,
file, or deburring tool. Chemfer (bevel) the end of the pipe 100-150.
CLEAN : Remove surface dirt, grease, or moisture with a clean dry cloth.
B.3 DRY FIT : With light pressure, pipe should go one third to one half of the way into the fitting
socket. Pipes and fittings that are too tight or too loose should not be used.
B.4 APPLICATOR : Use an applicator that is one half the pipe diameter. Too large an applicator
will force excessive cement into the inside of small diameter fittings. Too small an applicator
will not apply sufficient cement to large diameter systems.
B.5 SOLVENT CEMENT : Apply a full even layer of solvent cement to the outside of a pipe and
medium layer of cement to the inside of a fitting.
B.6 JOIN PIPE AND FITTINGS : Assemble pipe and fitting socket till it contacts socket bottom. Give
pipe a quarter turn. Hold pipe and fitting together until the pipe does not back out. Remove
excessive cement from the exterior. A properly made joint will show a continuous bead of
cement around the perimeter.
C. TESTING PRESSURE
Prior to testing, safety precautions should be instituted to protect personnel and property in
case of test failure.
Conduct pressure testing with water. Do not use air or other gases for pressure
testing.
The piping system should be adequately anchored to limit movement. Water under pressure
exerts thrust forces in piping systems. Thrust blocking should be provided at change of
direction, change in size and at dead ends.
10
32, Samruddhi CHS Ltd., M.G. Road, Kandivli Village, Kandivli (W) Mumbai – 67
Ph. 022 – 28610231 Fax 022 -28055758, Mail id : sales@ashishengineering.net
Website : www.ashishengineering.net
A. ERECTION OF PIPING
1. All piping shall be erected as shown in the drawings and as per this specification,
applicable codes and good engineering practice.
3. Gaskets between the flanges shall be tightened uniformly by tightening the bolts
uniformly.
4. Piping to and from the equipments including rotary equipments shall be carried out only
after these equipments are leveled.
5. Valved drains and valved plugged vents shall be provided at all the lowest points and
the highest points respectively, irrespectively of whether it is shown in the drawings
or not.
6. Valves shall be installed in such a way that they are easily approachable.
7. Lift check valves shall be installed in horizontal piping only. Swing check valves can be
installed in vertical lines. All the check valves should be installed with arrow in the direction
of flow.
11. All the drain pipes shall have minimum 1 : 200 slope, unless otherwise given.
12. All lined piping such as lead lined, rubber lined, teflon lined, glass lined, etc shall be
assembled as per drawings.
13. Teflon tape or sealent shall be used for tightening of G.I. piping.
14. While basic layouts may be available in the drawings provided by the Consultant / Owner,
the detailed BOQ shall have to be made by the contractor and got approved from the
Enginner.
15. Special attention shall be given by the Contractor to economy. Summetry in layout is very
important. Fittings meant for operation shall be located and oriented to allow easy reach
and operation, Maintenance, repairs and replacements of pipes, fittings and fixtures must be
conveniently possible. All material shall be installed in most workmen like manner by skilled
workers.
11
32, Samruddhi CHS Ltd., M.G. Road, Kandivli Village, Kandivli (W) Mumbai – 67
Ph. 022 – 28610231 Fax 022 -28055758, Mail id : sales@ashishengineering.net
Website : www.ashishengineering.net
1. Outside surfaces of pipes shall be thoroughly cleaned of soil, rust, and foreign materials by
scrapping and wire brushing. Oil and grease shall then be removed by a solvent
degreaser.
2. 3 mm thick anticorrosive tape of coatek or equivalent make shall be used for wrapping &
coating of U/g pipes. Wherever asked for Tape primer quantity used shall be minimum 250
gm/sq. meter
5. Where the pipe rests on rock it may be bedded on a layer of fine selected material or
concrete to avoid local point support.
The trench shall be so treated by gradient and fitting in the area that it does not act as a
drainage channel.
2. Contractor shall carefully check the orientation of foundations, elevations , locations of the
anchor bolts, supporting structures , hole diameters, etc. well in advance so that timely
action can be taken . Minor rectifications like chipping of foundations etc. shall be carried
out by the Contractor after obtaining the Owners approval.
3. Contractor shall set- up liners for proper leveling, place the base plate on the liners and
set anchor bolts. Provisional alignment of base plate should be done and anchor bolts
should then be fixed by pouring morter in foundation pockets. Contractor shall assemble
the complete equipment and align for grouting. Alignment should be rechecked after
grouting.
4. Base plates should leveled on four corners for the directions of shaft and right angle to
shaft.
5. While aligning, adjustments shall be carried out to the coupling and not the shaft. During
alignment, the deflection and face deviation of the driving and the driven shaft shall be
separately measured and should be within allowable limits as specified by the supplier.
After completing the alignment, it should be ensured that the shaft rotates smoothly and
freely by hand.
6. Alignment should be rechecked after the connection of piping. Any misalignment induced
by the piping connections shall be corrected by adjusting the piping.
12
32, Samruddhi CHS Ltd., M.G. Road, Kandivli Village, Kandivli (W) Mumbai – 67
Ph. 022 – 28610231 Fax 022 -28055758, Mail id : sales@ashishengineering.net
Website : www.ashishengineering.net
C. PIPING SUPPORTS
1. Piping supports, anchors, guides ,etc shall be constructed as per the drawings.
2. Absolutely no welding shall be done on the lined piping such as rubber lined, leadlined,
teflon -lined, glass lined, etc. Standard bracket type supports shall be fabricated for
these lined piping.
3. Three mm rubber pad shall be used between the clamp and the non-metalic pipes such
as PVC, Polypropylene, FRP, Glass etc.
4. Adequate supports for the metallic piping shall be provided as per drawing and
depending on site conditions. Consult Site Engineer in case of clarifications or adequacy
of supports.
5. Steam piping shall be provided „ T‟ shoe supports of about 250mm. Long. T size shall be more
then insulation thickness.
1. Running test of motor , pumps, fans etc shall be performed with no load to ensure that the
vibrations , sound and temperature of equipment are not abnormal .
2. After running test of motor, the motor and the driven unit shall be coupled. Due care should
be taken to check the direction of rotation.
3. Assembled rotary unit shall then be run on no load to ensure that the vibrations, sound
and temperature are not abnormal.
4. Hydraulic test of all the stationary equipments shall be taken. . Pumps are tested running
them on water. Fans, blowers, compressors, etc are tested on air.
5. Contractor shall carry out above testing to the satisfaction of Site in charge and their
signature shall be obtained on the test certificates.
6. The work will be inspected by representative of owner. Contractor shall be responsible for all
errors of fabrication & for correct fitting of piping. Any repair shall be carried out by
Contractor free of cost.
7. All piping shall be hydraulically /pneumatically tested for the test pressure given in the
piping specification. The test pressure shall not be less than 1.5 times design press. for
hydraulic and pneumatic test.
8. The pressure gauge shall be calibrated and certified by competent party before test is
conducted.
9. Underground piping, insulated piping and inaccessible piping shall be tested before
installation.
11. Piping system may be tested in section by blanking and properly tagging. However
complete system shall also be tested for the final approval .
13
32, Samruddhi CHS Ltd., M.G. Road, Kandivli Village, Kandivli (W) Mumbai – 67
Ph. 022 – 28610231 Fax 022 -28055758, Mail id : sales@ashishengineering.net
Website : www.ashishengineering.net
12. Test reports shall be written in a separate note book and shall be certified by the site
engineer immediately after the test.
* TEST PROCEDURE
1. Before testing, the piping system shall be isolated from the equipments , in-line instruments,
etc by blank-offs. The blank offs must be of “Flagged” type , must be removed after the
test and the in-line equipments/ instruments be reinstalled.
2. During the start-up of the testing , the entrapped air must be removed from the highest
system point and the flange connections be adequately tightened.
3. Hold time of the testing shall be sufficient to allow careful inspection of all the joints and
shall not be less than ten minutes , During the hold time, if the pressure remains constant,
the tested piping section shall be approved.
E. CLEANING OF PIPING
1. All the burrs, welding slag and weld spatters shall be removed by suitable mechanical
means. After the completion of fabrication and mechanical cleaning, all the
fabricated piping shall be thoroughly flushed with water to remove all the foreign
materials such as soil, loose scales, oil film, sand, cement, etc. Adequate precaution
should be taken to avoid collection of foreign materials from main lines to smaller branch
lines during flushing.
2. Before installation, all the valves shall be properly inspected for foreign materials
contaminators. Clean the valves first by wiping with clean /dry lint less cloth and then by
clean lint less cloth moisture with clean trichloroethylene for metallic valves or dilute
sulfuric acid for polypropylene /PVC valves.
1. All the equipments, in-line instruments, steam traps, etc. shall be isolated before cleaning.
All the blank - offs shall be removed after the completion of cleaning.
2. Strainer baskets shall be removed before cleaning and replaced immediately after
cleaning.
3. Connect lower point of the system to open drain and flush with water until clean of dirt
and scale.
F. MISCELLANEOUS STEEL
All bolts, anchor bolts , nuts, lock washers, supports and other miscellaneous items not
furnished by equipment supplier or by Owner or otherwise called for in this specification shall
be supplied by the Contractor . Before installing the equipment, the Contractor shall
verify location of bolts, and if any discrepancy exits , he shall notify Owner.
14
32, Samruddhi CHS Ltd., M.G. Road, Kandivli Village, Kandivli (W) Mumbai – 67
Ph. 022 – 28610231 Fax 022 -28055758, Mail id : sales@ashishengineering.net
Website : www.ashishengineering.net
G. TEMPORARY SCREENS
Temporary screens of 20 mesh shall be installed in the suction lines of all the rotary
equipments and at the inlet of all the delicate equipments like glass
and glass lined equipments. These screens shall be removed after the operation
becomes normal and the distance pieces, if any, shall be installe
H. GROUTING
H.1 Grouting of anchor bolts, holes, pockets and under base plates or under equipments have
been broadly classified into two categories.
Non shrinking grout shall be generally used for grouting the following equipments:
Ordinary grout shall be generally used for grouting the following equipments.
The grouting material shall solidly fill the spaces to be grouted and permanently retain
original volume so that the base plates are held firmly in the set position. The amount of
water used in the mixture shall be kept to a minimum just enough to make the mixture
peaceable and for the grout to have a consistency too stiff for the grout to flow. The top of
the foundation shall be clean and free of all laitance, locate particles, oil, grease etc
shall be wetted thoroughly leaving no puddles prior to grouting. All tapped pockets
shall be repaired using ordinary grout. Under no account shall neat cement be used
for grouting.
H.2 PLACEMENT
* The finished surface shall be floated smooth and shall slope away from the base
plates. (Approx. 1:25)
15
32, Samruddhi CHS Ltd., M.G. Road, Kandivli Village, Kandivli (W) Mumbai – 67
Ph. 022 – 28610231 Fax 022 -28055758, Mail id : sales@ashishengineering.net
Website : www.ashishengineering.net
* After the initial set is over, the grout shall be kept thoroughly wet for a minimum period
of 5 days.
* During grouting , care shall be taken to ensure that the base plate level and the
alignment is not disturbed and that no honey -combing takes place in the grout.
I. MEASUREMENTS
a. All structural steel work shall be measured by Length, weights being calculated on the
basis of standard weights of sections used. No allowances shall be made for welding
or for bolts, rivets etc. The rate shall include painting of the structural steel work wherever
required with one coat of red oxide primer.
b. The size of piping for measurement shall be nominal diameter for G.I. & M.S. piping. The
length shall be measured along the centerline in running meter. Excluding all valves, fittings
and piping specials which will be paid in number as per BOQ and actual measurement.
The rate shall include painting of C.S piping with one coat of red oxide primer. For SS tubes
the diameter considered shall be outside diameter.
c. The erection weight of equipment specified are indicative and for reference only the unit
of measurement for equipments shall be item wise/ package wise. Variation in weight
shall not be considered increase or reduction in the rate.
d. All surplus material left out after completion of job will be taken back by
contractor. Payment shall be made only for actual erected material.
The payment done for supply of such a surplus material will be adjusted in the
bill/final bill.
J. HOT INSULATION SPECIFICATION FOR PIPING & TANK ( STEAM & CONDENSATE PIPING)
1. Hot insulation material shall be Lloyd / UP Twiga make compact mineral wool machine
made mattresses as per I.S 3690. The density of wool shall be 100 Kg/cum. The material shall
be suitable for 540 deg. C
2. Wool mattresses shall be backed by G.I wirechiken mess made from 22 SWG GI wire.
6. The insulation shall be cladded with 24 SWG aluminum sheeting of hard quality ASTM - B 209
alloy 1060 temper H-14.
7. Bituminous coated felt sheet shall be used with all aluminum sheeting joints, circumferential
as well as longitudinal to seal the joints to make it water proof.
8. All flanges & valves shall be provided with removable box cover of 24 SWG Aluminum sheet
11. Wooden support in two pieces shall be provided on each pipe supports. Length of wooden
block shall be minimum 100mm. or M.S. Tee section of suitable size cut from ms beam of
200x100 and 250mm. Minimum length shall be provided.
16
32, Samruddhi CHS Ltd., M.G. Road, Kandivli Village, Kandivli (W) Mumbai – 67
Ph. 022 – 28610231 Fax 022 -28055758, Mail id : sales@ashishengineering.net
Website : www.ashishengineering.net
12. Measurement of insulation shall be in running meter in case of piping.. Each valve
insulation shall be measured as equivalent to two meter of pipe insulation. Each elbow, tee
shall be measured 1.5m of pipe insulation.
K. HOT INSULTAION FOR S.S.PIPING and OTHER THEN STEAM / CONDENSATE SERVICE.
1. The insulation material used for s.s.piping shall be chloride free preferably armacell or
equivalent for temp. up to 900c. & The cladding shall be of 24swg Alu. Sheet. Cover insulation
in production area shall be SS 304 -24swg.with outer surface Matt finished and cover shall be
welded.
L. COLD INSULTAION
1. The cold insulation shall be carried out using PUF sigment coverd with 24swg Alu. Sheet. /
Armacell or equivalent material for temp. 40 to 900C with 24swg Alu. Cladding.
Prior to apply of primer on the surfaces to be paint, surface shall be cleaned properly with
wire brush, sand paper or caustic depend upon the dirty ness of surfaces.
After cleaning of surface one coat of red oxide paint shall be applied and allow the surfaces
to dry.
17