Metode Erection Girder
Metode Erection Girder
Metode Erection Girder
A1
A2 Arah Pandaan
Arah Malang
2. DESKRIPSI PEKERJAAN
Stressing Girder
Pengangkatan Girder No 1
Selesai
3. DAFTAR PERALATAN
II ERECTION LOAD
1 Erection Weight (t) 27,00
2 Weight of Shackle/ Sling (t) 0,20
3 Weight of Hook Block (t) 0,80
4 Weight of Spreader Bar/ Chain Block/ Level Block (t) -
TOTAL LOAD 28,00
III CRANE DATA'S
1 Crane Capacity (t) 180,00
2 Crane Condition (t) 90% 75% to 100%
3 Existing Boom Length (m) 30,50
4 Hook Block capacity/ SWL (t) 180,00
5 Working radius (Max in m) 7,00
6 Lifting Capacity (t) 102,50
7 Dynamic Factors 1,10 1.05 - 1.25
II ERECTION LOAD
1 Erection Weight (t) 27,00
2 Weight of Shackle/ Sling (t) 0,20
3 Weight of Hook Block (t) 0,80
4 Weight of Spreader Bar/ Chain Block/ Level Block (t) -
TOTAL LOAD 28,00
III CRANE DATA'S
1 Crane Capacity (t) 150,00
2 Crane Condition (t) 90% 75% to 100%
3 Existing Boom Length (m) 27,45
4 Hook Block capacity/ SWL (t) 150,00
5 Working radius (Max in m) 7,00
6 Lifting Capacity (t) 102,50
7 Dynamic Factors 1,10 1.05 - 1.25
II ERECTION LOAD
1 Erection Weight (t) 27,00
2 Weight of Shackle/ Sling (t) 0,20
3 Weight of Hook Block (t) 0,80
4 Weight of Spreader Bar/ Chain Block/ Level Block (t) -
TOTAL LOAD 28,00
III CRANE DATA'S
1 Crane Capacity (t) 100,00
2 Crane Condition (t) 90% 75% to 100%
3 Existing Boom Length (m) 19,00
4 Hook Block capacity/ SWL (t) 100,00
5 Working radius (Max in m) 7,00
6 Lifting Capacity (t) 75,10
7 Dynamic Factors 1,10 1.05 - 1.25
II ERECTION LOAD
1 Erection Weight (t) 27,00
2 Weight of Shackle/ Sling (t) 0,20
3 Weight of Hook Block (t) 0,80
4 Weight of Spreader Bar/ Chain Block/ Level Block (t) -
TOTAL LOAD 28,00
III CRANE DATA'S
1 Crane Capacity (t) 100,00
2 Crane Condition (t) 90% 75% to 100%
3 Existing Boom Length (m) 15,20
4 Hook Block capacity/ SWL (t) 100,00
5 Working radius (Max in m) 7,00
6 Lifting Capacity (t) 59,70
7 Dynamic Factors 1,10 1.05 - 1.25
START
Selesai
4. METODE PELAKSANAAN
1. Traffic Management
1
2
3
4
TRUCK BOGIE
PERALATAN UTAMA
1. Crane Kapasitas 180 ton = 1 unit
2. Crane Kapasitas 150 ton = 1 unit
3. Crane Kapasitas 100 ton = 2 unit
4. Bogie = 1 unit
4. METODE PELAKSANAAN
3. Denah Rencana Penempatan Lampu Penerangan
A2 5
10 11
6 7 8 9
A1 15
12 14
PERALATAN UTAMA
1. Jumlah Lampu Penerangan pada Lokasi Erection = 15 unit
4. METODE PELAKSANAAN
4.2 ERECTION GIRDER
START
Loading Test
Pengangkatan girder
no.1
Pengangkatan girder
no.2
Pemasangan Bracing
Selesai
4. METODE PELAKSANAAN
INSPEKSI
1. Loading Test & Pengangkatan Girder ke Bogie • Titik Angkat Girder
• Seling Pengangkat
• Posisi/dudukan alat berat
CRANE 150 TON • Loading Test
A2
TRUCK BOGIE
PERALATAN UTAMA
1. Crane Kapasitas 180 ton = 1 unit
2. Crane Kapasitas 150 ton = 1 unit
3. Crane Kapasitas 100 ton = 2 unit
4. Bogie = 1 unit
4. METODE PELAKSANAAN
INSPEKSI
2. Pengangkutan dari Stockyard ke Lokasi Erection • Titik Angkat Girder
• Seling Pengangkat
• Posisi/dudukan alat berat
CRANE 150 TON • Loading Test
TRUCK BOOGIE
MUNDUR UNTUK
MENGAMBIL HALUAN
A2
PERALATAN UTAMA
1. Crane Kapasitas 180 ton = 1 unit
2. Crane Kapasitas 150 ton = 1 unit
3. Crane Kapasitas 100 ton = 2 unit
4. Bogie = 1 unit
4. METODE PELAKSANAAN
INSPEKSI
2. Pengangkutan dari Stockyard ke Lokasi Erection • Titik Angkat Girder
• Seling Pengangkat
• Posisi/dudukan alat berat
TRUCK BOOGIE MAJU CRANE 150 TON • Loading Test
KE ARAH LOKASI
ERECTION GIRDER
A2
A2
PERALATAN UTAMA
1. Crane Kapasitas 180 ton = 1 unit
2. Crane Kapasitas 150 ton = 1 unit
3. Crane Kapasitas 100 ton = 2 unit
4. Bogie = 1 unit
4. METODE PELAKSANAAN
INSPEKSI
4. Pengangkatan Girder No. 1-16 • Posisi Titik Angkat Girder
• Check Kondisi Seling Sudah Terkunci
Kuat
CRANE 150 TON • Check Dudukan Bearing Pad
• Clearance Area Crane
PERALATAN UTAMA
1. Crane Kapasitas 180 ton = 1 unit
2. Crane Kapasitas 150 ton = 1 unit
3. Crane Kapasitas 100 ton = 2 unit
4. Bogie = 1 unit
4. METODE PELAKSANAAN
INSPEKSI
4. Pengangkatan Girder No. 1-16 • Posisi Titik Angkat Girder
• Check Kondisi Seling Sudah Terkunci
Kuat
CRANE 150 TON • Check Dudukan Bearing Pad
• Clearance Area Crane
PERALATAN UTAMA
1. Crane Kapasitas 180 ton = 1 unit
2. Crane Kapasitas 150 ton = 1 unit
3. Crane Kapasitas 100 ton = 2 unit
4. Bogie = 1 unit
4. METODE PELAKSANAAN
INSPEKSI
4. Pengangkatan Girder No. 1-16 • Posisi Titik Angkat Girder
• Check Kondisi Seling Sudah Terkunci
Kuat
CRANE 150 TON BRACING RANTAI , BESI &
• Check Dudukan Bearing Pad
UNP DIPASANG DAN
• Clearance Area Crane
DIPASTIKAN TERPASANG
DENGAN BAIK & BENAR
A2
PERALATAN UTAMA
1. Crane Kapasitas 180 ton = 1 unit
2. Crane Kapasitas 150 ton = 1 unit
3. Crane Kapasitas 100 ton = 2 unit
4. Bogie = 1 unit
4. METODE PELAKSANAAN
INSPEKSI
4. Pengangkatan Girder No. 1-16 • Posisi Titik Angkat Girder
• Check Kondisi Seling Sudah Terkunci
Kuat
BRACING RANTAI , BESI &
• Check Dudukan Bearing Pad
UNP DIPASANG DAN
• Clearance Area Crane
DIPASTIKAN TERPASANG
DENGAN BAIK & BENAR
CRANE 150 TON
A2
PERALATAN UTAMA
1. Crane Kapasitas 180 ton = 1 unit
2. Crane Kapasitas 150 ton = 1 unit
3. Crane Kapasitas 100 ton = 2 unit
4. Bogie = 1 unit
4. METODE PELAKSANAAN
INSPEKSI
4. Pengangkatan Girder No. 17-18 • Posisi Titik Angkat Girder
• Check Kondisi Seling Sudah Terkunci
Kuat
• Check Dudukan Bearing Pad
• Clearance Area Crane
TRUCK BOGIE
PERALATAN UTAMA
1. Crane Kapasitas 180 ton = 1 unit
2. Crane Kapasitas 150 ton = 1 unit
3. Crane Kapasitas 100 ton = 2 unit
4. Bogie = 1 unit
4. METODE PELAKSANAAN
INSPEKSI
4. Pengangkatan Girder No. 17-18 • Posisi Titik Angkat Girder
• Check Kondisi Seling Sudah Terkunci
Kuat
TRUCK BOOGIE MAJU CRANE 150 TON • Check Dudukan Bearing Pad
MELEWATI BAWAH • Clearance Area Crane
GIRDER YANG SUDAH
TERPASANG
A2
A1
CRANE 180 TON
PERALATAN UTAMA
1. Crane Kapasitas 180 ton = 1 unit
2. Crane Kapasitas 150 ton = 1 unit
3. Crane Kapasitas 100 ton = 2 unit
4. Bogie = 1 unit
4. METODE PELAKSANAAN
INSPEKSI
4. Pengangkatan Girder No. 17-18 • Posisi Titik Angkat Girder
• Check Kondisi Seling Sudah Terkunci
Kuat
TRUCK BOOGIE MAJU CRANE 150 TON • Check Dudukan Bearing Pad
MELEWATI BAWAH • Clearance Area Crane
GIRDER YANG SUDAH
TERPASANG
A2
A1
CRANE 180 TON
PERALATAN UTAMA
1. Crane Kapasitas 180 ton = 1 unit
2. Crane Kapasitas 150 ton = 1 unit
3. Crane Kapasitas 100 ton = 2 unit
4. Bogie = 1 unit
4. METODE PELAKSANAAN
INSPEKSI
4. Pengangkatan Girder No. 17-18 • Titik Angkat Girder
• Seling Pengangkat
• Posisi/dudukan alat berat
TRUCK BOOGIE CRANE 150 TON • Loading Test
MEMPOSISIKAN SESUAI
TITIK ANGKAT CRANE
A2
A1
CRANE 180 TON
PERALATAN UTAMA
1. Crane Kapasitas 180 ton = 1 unit
2. Crane Kapasitas 150 ton = 1 unit
3. Crane Kapasitas 100 ton = 2 unit
4. Bogie = 1 unit
4. METODE PELAKSANAAN
INSPEKSI
4. Pengangkatan Girder No. 1-16 • Posisi Titik Angkat Girder
• Check Kondisi Seling Sudah Terkunci
Kuat
CRANE 150 TON • Check Dudukan Bearing Pad
• Clearance Area Crane
A1
CRANE 180 TON
PERALATAN UTAMA
1. Crane Kapasitas 180 ton = 1 unit
2. Crane Kapasitas 150 ton = 1 unit
3. Crane Kapasitas 100 ton = 2 unit
4. Bogie = 1 unit
4. METODE PELAKSANAAN
INSPEKSI
4. Pengangkatan Girder No. 17-18 • Posisi Titik Angkat Girder
• Check Kondisi Seling Sudah Terkunci
Kuat
CRANE 150 TON • Check Dudukan Bearing Pad
• Clearance Area Crane
A1
CRANE 180 TON
PERALATAN UTAMA
1. Crane Kapasitas 180 ton = 1 unit
2. Crane Kapasitas 150 ton = 1 unit
3. Crane Kapasitas 100 ton = 2 unit
4. Bogie = 1 unit
4. METODE PELAKSANAAN
INSPEKSI
4. Pengangkatan Girder No. 17-18 • Posisi Titik Angkat Girder
• Check Kondisi Seling Sudah Terkunci
BRACING RANTAI , BESI & Kuat
UNP DIPASANG DAN CRANE 150 TON • Check Dudukan Bearing Pad
DIPASTIKAN TERPASANG • Clearance Area Crane
DENGAN BAIK & BENAR
A1
CRANE 180 TON
PERALATAN UTAMA
1. Crane Kapasitas 180 ton = 1 unit
2. Crane Kapasitas 150 ton = 1 unit
3. Crane Kapasitas 100 ton = 2 unit
4. Bogie = 1 unit
4. METODE PELAKSANAAN
INSPEKSI
4. Pengangkatan Girder No. 17-18 • Posisi Titik Angkat Girder
• Check Kondisi Seling Sudah Terkunci
BRACING RANTAI , BESI & Kuat
UNP DIPASANG DAN CRANE 150 TON • Check Dudukan Bearing Pad
DIPASTIKAN TERPASANG • Clearance Area Crane
DENGAN BAIK & BENAR
A2
A1
CRANE 180 TON
PERALATAN UTAMA
1. Crane Kapasitas 180 ton = 1 unit
2. Crane Kapasitas 150 ton = 1 unit
3. Crane Kapasitas 100 ton = 2 unit
4. Bogie = 1 unit
4. METODE PELAKSANAAN
PELAKSANAAN ERECTION GIRDER :
a. Crane nomor 3 dan 4 (100 & 100 Ton), mengangkat girder L : 30.6 m (berat girder 54
ton), dari stock yard, maju ke atas truk bogie. Titik angkat berada pada ujung penampang
girder.
b. Girder L : 40.8 m, diletakkan di truk boogie, kemudian diberi perkuatan dengan sling baja
c. Setelah terpasang perkuatannya, truk boogie maju ke lokasi erection.
d. Setelah truk boogie pada posisi yang sesuai, sling crane nomor 1 dan 2 (180 & 150 ton)
diikatkan pada titik angkat girder L: 30.6 m
e. Kemudian, truk boogie, bergerak mundur ke arah stockyard, sampai keluar dari area
erection dengan bantuan excavator
4. METODE PELAKSANAAN
PELAKSANAAN ERECTION GIRDER :
f. Setelah itu, crane nomor 1 dan 2 mengangkat girder L : 30,6 m setinggi 1 m
(disesuaikan kondisi lapangan) untuk loading test diatas elevasi jalan dan perlahan
girdr diangkat dan crane maju ke arah dudukan girder bearing pad nomor 1 ( waktu
travel ± 15 menit )
g. Kemudian setelah posisi girder tepat berada diatas lokasi perletakan, team survey cek
elevasi dan ketepatan titik perletakan
h. Setelah sesuai dengan titik koordinat perletakan, girder diturunkan perlahan, sampai
menyentuh bearing pad tersebut, kemudian segera dipasang bracing rantai pada
perletakan girder, dan bracing antar girder berupa profil kanal dan besi tulangan D25
untuk setiap jarak 6 meter.
i. Cek kekuatan bracing, dan lepas sling crane nomor 1 dan 2 tersebut
j. Selanjutnya secara berurutan, tahapan metode di atas diulangi hingga 18 girder
terpasang dengan sempurna.