National Highways Authority of India
(Ministry of Road Transport and Highways)
‘Fi-5 UH 6, Baet-10, TH, FE Ree-110075,
6-5 & 6, Sector-10, Dwarka, New Delhi-110075
No.11041/218/2007-Admn, Date! 19.09.2016
Policy Mat
[Decision taken on file No.
“Technical (215/2016)
HAVCGM(TechY Planning/2016]
Sub: Procedure for processing of cases of Utility Shifting.
NHAI has to award and construct a large number of projects in the current and upcoming
years to meet targets, It has been observed that there are delays in requisition and preparation of
utility shifting estimates, and subsequent review and approval by the implementation agencies,
which delays both the award and the construction process. In order to speed up the overall process,
modifications are being made to the process,
Preparation of estimates.
2. The delegation of powers and procedure to be followed in matters relating to Utility Shifting
work have been circulated vide following policy circulars
Policy Matters“Technical (148/2014) dated 27.01.2014
ii) Policy Matters-Technical (17/2014) dated 30.12.2014
iii) Policy Matters-Technical (127/2013) dated 07.03.2013
iv) Policy Matters-Technical (14/2012) dated 05.10.2012
v) Policy Matters-Technical (109/2012) dated 18.07.2012
vi) Policy Matters-Technical (108/2012) dated 09.07.2012
vii) Policy Matters-Technical (34/2009) dated 27.07.2009
viii) Policy Matters-Technical (28/2008) dated 19.02.2008
ix) Policy Matters-Technical (07/2007) dated 29.01.2007
x) Policy Matters-Technical (62/2006) dated 10.01.2006
xi) Policy Matters-Technical (87/2004) dated 12.07.2004
3. _ In supersession of earlier instructions issued by NHAI for preparation of utility estimates for
shifting of utilities, following guidelines are hereby laid down’
It is the responsibility of DPR consultant to procure utility shifting estimates from the
concerned utility agencies. The estimate shall be prepared with engineering map detailing
existing utilities and proposed utility shifting along with offsets in the entire stretch,
certifying the essentiality of shifting for development of Project Highway.
il) The DPR consultant shall verify the estimates received from the utility agency based on
current applicable Schedule of Rates of the agency and market rates for items not present in
the Schedule of Rates. A certification of verification from the DPR consultant shall be
included with remarks on variations if any when the utility estimate is submitted to NHAI
HQIRO for approval
{ii) Cost of utility estimates of DPR shall be included in the cost of project at the time of
approval. Any change in the project cost on approval of estimate along with reasons of
variations shall be informed to HQ.
iv) For proper assessment of utility estimates, DPR consultant shall appoint an utility expert at
a sub-professional level for 3 months, with relevant technical expertise in utilities shifting
4process. Suitable retired officials of Utility in State Govt. may also be deployed. In future
these provisions shall be included in DPR RFP.
v) In case any utility infrastructure is identified during execution phase of the project which
was not included in the Detailed Project Report. the estimate shall be verified by PD/RO and
the IE/ AE following the same procedure as above.
Upgradation of utility infrastructure
4. Currently, a no upgradation undertaking is required to be submitted by the utility agency
and vetted by the PD/RO andIB/AE if appointed. It is noted that there are cases when technical
specification of the existing utility infrastructure is deemed obsolete as per current notified
technical standard specification of the utility agency. In these cases, the agency may propose utility
infrastructure in accordance with latest technical specification standards of the utility agency. Such
a change may not be categorized as upgrdation of utility infrastructure. Also, cases such as increase
in height of poles, requirement of laying underground cables, casing of pipelines, etc. that are
deemed necessary as per technical standard specifications of the utility ageney, PD and DPR
consultant /IB/AE may not categorize it as upgradatioin of infrastructure. In such cases the DPR
consultant/PD/IBIAE shall verify and RO/CGM (Tech) shall ensure that the changes are necessary as
per the latest standards of the utility agency and State.
Completeness of documents for approval
5 __ It has been observed that certain documents such as undertaking for essentiality of utility
shifting in development of highway: no up gradation; strip plan mapping utilities duly signed by
utility agency, all consultants, DPR/E/AE, Concessionaire, PD, ete. are not being submitted along
with estimates, hence leading to resubmissions of these estimates. To reduce estimates resubmission
due to missing or incomplete documents and ensure collection of all documents, a checklist has been
developed. This checklist shall be duly filled by the DPR consultant or IB/AE, verified by the PIU
and submitted along with all the supporting documents to the RO. The format for the checklist is
enclosed herewith in Annexure-1.Approval of Estimates
6__It has been decided to delegate additional powers for approval of utility estimates to Regional
officers, with verification of site conditions and bill of quantities in the estimate.
In additional, rates are in most cases as per the standard rate card of the agency, and hence
can be verified at field level. In modification of Policy Circular (Tech) No. 14/2012 dated 05.10.2012
and Policy Circular (Tech) No. 172/2014 dated 30.12.2014, ROs and CGMs will henceforth have the
following powers of approval:
SI. Particular ‘To whom delegated | Extent of Delegation
No. (Cumulative)
@ | Transmission line/electric line | Regional Officer Rs 15 crore for each
shifting concerned division for user
agency
CGM = (Tech)-HQ] Rs 30 crore for each
jointly with | concerned division for user
| concerned Regional | agency
_ Officer _
[Water pipelines and other [Regional Officer | Rs. 10 crore for each |
utilities other than electric concerned division of user
lines agency
| CGM Cech) jointly | Rs. 20 crore for each
| with concerned | concerned division of user
| Regional Officer | agen
‘The estimates of higher value would be processed and sanctioned as per existing procedures,
Ww7. Regional Officers shall ensure inspection and verification of submitted estimates and provide
their approval within 10 days. Approval of higher estimates shall similarly be accorded within 2
weeks of receipt of estimate in HQ after joint inspection and approval of RO and CGM (Tech) H@. It
shall be ensured that detailed onsite verification is carried out before approval in accorded.
8. _A copy of letter of sanction of estimate along with entire utility map and estimate details
shall invariably be sent to HQ,
9. This issues with the approval of Competent Authority. ud
(A.K"Sadhu)
CGM (Coord.)
To:
All Officers & Employees of HQ/ROs/ PIUs/ CMUs/ Site OfficesAnnexure 1: Check-lists for Utility Shifting Estimate submission
Utility Agency Name |
Division Name
Work details
PIU
cary
SECTION OF THE CHECKLIST YES/NO/NA See
5
14 | Schedule of Rates Yes NoO NAG NA
t
SoR for all relevant items in the utility |
1-1 | estimates has been attached eee oiNG ENE NA
4,2. | SOR has approval of the competent | Yes 1 No 0) NAO NA i
2 | authority of agency
1.3 | Year of SoR : |
1.4. | SoR is for the current year Yes 0 NoO NAG NA
2 | No upgradation Yes NoO NAG NA |
Undertaking submitted in format Yes ONoO NAQ
2.1. | specified in Circular No. 127/2013 NA
dated 7.3.2013 by utility agency
| No upgradation undertaking has been | Yes (No O NAQ
2.2 | Signed by PD or a separate een |
2 | undertaking has been submitted by
PD for no upgradation
3._| Utility Strip Plan Yes .NoO NAQ NA
3.1. | Strip plan is attached Yes CNoO NAQ NA |
3.2. | Strip plan shows details of all existing | Yes 7. No. NAO |
| 32 | utilities with chainage and offsets |Ey
SECTION OF THE CHECKLIST
Strip plan shows details of proposed
utilities with chainage and offsets
Estimates mapped with locations for
utility shifting in strip plan and verified
by Utility owner, PD, IE/AE,
Concessionaire/Executing Agency
during site inspection
Yes ONoG
Yes O NoO
NAO
NAG
NA
NA
Estimate verification
Essentiality Certificate based on
SI.No.3 by PD, IE
Certificate signed by PD
Yes ONoO.
Yes ONoO
NAg
NAG
NA
NA
42
Estimates verified by PD/IE as per
Plan S.No.3 against latest SoR of the
agency where available.
Yes O NoO
NAO
NA
Estimates verified against market
values in cases where SoR is not
applicable
Yes ONoO
NAg.
NA
44
Joint on-site verification of quantities
has been done by DPR Consultant,
utility agency and PD, IE/AE of the
PIU
Yes 0 NoO
NAG
NA
45
46
47
Only existing utilities within project
ROW have been included in estimate
Estimates submitted division wise
with relevant chainage details in each
division
No splitting of Scope Division wise is
caused
Yes ONoO
Yes NoO.
NAO
NAQ
NA
NA
48
Estimated time for completing utility
shifting is mentioned and verified by
the PD
Yes ONoO.
NAGRAs) [e]NLN
FS.No_ SECTION OF THE CHECKLIST
| If any utility is to be dismantled, YesONoO NAD
49 | salvage value for dismantled utility NA
attached and verified in the estimate
| _|
| All items along with their relevant YesCNoC)} NAD |
4.10 | technical specifications to be shifted NA |
listed in the estimates
4.11 | Unit rates for items mentioned inthe | Yes No NAD) - |
= estimates
Quantities for items mentioned in the | Yes No NAQ fl
412 | estimates Ls
Items along with their unit rates, Yes NoO NAD
4.43. | quantities and amount are given in nA
13 | tabular format, including relevant
category subtotals and totals
Supervision charges mentioned in | Yes ONoO) NAO)
444 NA
Z estimates
44g | Ovethead charges if necessary are | Yes Not] NAO 7
“15 | included in estimates
Security deposit if necessary is Yes ONoO NAO)
416 NA
18 | included in estimates
4.17 | Allthe relevant taxes are included | YesONOO NAC) | NA
4.tg_| Contingency charges if necessary are | Yes 0. No NACI NA
| *"° | included
Work will be executed by utility Agency 0 |
4.19 | agency / concessionaire /specialized | Concessionaire 0 NA
| agency Specialized agency 0 |
Designated Signatory
PD/Concessionaire/DPR ConsultanvAE/IE,