Walden Pond
Walden Pond
Walden Pond
BSC Group:
Engineering & Permitting
Consultant Team
Purpose
Present and obtain public input on:
• Thoreau House Site Trail Accessibility Improvement Project
• Main Beach Accessibility Improvement Project, including the
proposed Boardwalk and Bathhouse
• Proposed project schedules
Agenda
• Overview of Project process and history
• Presentation of the Thoreau House Site Trail Accessibility
Project
• Design progress on the Main Beach Accessibility Improvement
Project
• Open comment period
Tonight’s Meeting
• 2013 DCR Resource Management Plan (RMP) / Visitor Services Master Plan
were prepared to initiate visitor center planning, and make priority
management recommendations for the Reservation.
• The Walden Pond Main Beach, including the existing bathhouse, does not
comply with state and federal accessibility codes. Prior to the Visitor Center
project, DCR made the commitment to bring the Main Beach and bathhouse
up to these standards.
• January 30, 2019 public meeting reviewed bathhouse and boardwalk concept.
Project Goals
Thoreau House Site Trail Accessibility Improvements
• The project will improve access for all to the Thoreau House Site, from the
Visitor Center crosswalk.
• Three alternatives were assessed. The Woods Path Trail alignment was
selected, primarily due to reduced disturbance to natural and cultural resources.
• The trail will restore the surface of the existing Woods Path trail, and in some
places reduce the overall width.
• The trail will be built to U.S. Forest Service Trail Accessibility Guidelines, with
90% of the trail being 5% longitudinal slope or less.
• Restored areas will be hand-raked to loosen compaction, reseeded with native
understory species and stabilized with on-site woodland duff.
• The restored trail will end at a level landing near the House Site and will provide
interpretive signage.
Process
Thoreau House Site Trail Accessibility Improvements
Site Plan
Thoreau House Site Trail Accessibility Improvements
Schedule
Permitting: November - December 2019
Bid Documents: January 2020
Project Award: End of March 2020
Project Construction: Spring 2020
Trail Opening: Late Summer 2020
Construction Estimate
$450,000 (anticipated construction cost)
1924
1933
• Minimize the visibility of the new pathway from the pond and trails around
Walden Pond.
Project Goals
Main Beach Universal Accessibility Improvements
Existing Accessibility Issues
Main Beach Universal Accessibility Improvements
The existing entrance is very steeply The cross-slope on the existing plaza Existing stairs are
pitched and not accessible does not meet accessibility requirements unusable
Single accessible bathroom doesn’t conform Main bathrooms do not contain any
to current accessibility code in configuration accessible toilet stalls
or quantity
Project Benefits
Main Beach Universal Accessibility Improvements
• Includes 150 new trees to help stabilize the slope, infill open
canopy opportunity areas, and provide a great diversity of tree maturity for
sustained canopy development over time.
• Removes over 2,500 square feet of impervious cover within the natural
resource buffer zone.
Project Benefits
Main Beach Universal Accessibility Improvements
Environmental/Historic
• Wetlands Protection Act (Concord)
• Massachusetts Historical Commission Review
• Massachusetts Endangered Species Act (Natural Heritage &
Endangered Species Program)
• National Pollutant Discharge Elimination System (U.S. EPA)
Construction
• Building Permit (State Building Inspector)
• Plumbing Permit (State Plumbing Inspector)
• Water Connection (Concord Water and Sewer)
• Electrical Permit (Concord)
• Fire Inspection (Concord Fire Department)
• Access Board review (Massachusetts Architectural Access Board)
• Emergency Access (Concord and Lincoln Fire Departments)
Anticipated Permits
Main Beach Universal Accessibility Improvements
Phase I Construction (New Bathhouse, Associated Landscaping)
Bathhouse Construction: $ 2,350,000
Landscaping: $ 1,475,000
Total: $ 3,825,000
• Permitting
Additional Information