Line Sizing Design Guide, Rev 1
Line Sizing Design Guide, Rev 1
Line Sizing Design Guide, Rev 1
Design Guide
SYNOPSIS
This Design Guide addresses the design guidelines to be used in sizing of all process and utility lines on
the Bayu-Undan Platforms.
Calculation methods and general sizing criteria are presented for the common types of lines required to
be sized during the course of detailed design.
CONTENTS
1 GENERAL............................................................................................................................... 1
1.1 Piping Sizes............................................................................................................................. 1
1.2 Piping Valves and Fittings....................................................................................................... 2
2 DESIGN CRITERIA - LIQUIDS............................................................................................... 3
2.1 Single Phase Liquid Lines....................................................................................................... 3
2.2 Liquids Flowing By Pressure (Pressure Letdown)...................................................................6
2.3 Gravity Flowlines..................................................................................................................... 6
2.4 Vertical Downflow (Liquids from Drain Boxes)........................................................................6
1.5 Static Accumulation................................................................................................................. 7
1.6 Seawater / Firewater............................................................................................................... 7
1.7 Drains...................................................................................................................................... 7
1.8 Tank Overflows........................................................................................................................ 8
3 DESIGN CRITERIA - SINGLE PHASE VAPOUR LINES........................................................9
4 DESIGN CRITERIA - GAS/LIQUID TWO PHASE LINES.....................................................11
4.1 Flow Patterns......................................................................................................................... 11
4.2 Erosion................................................................................................................................... 11
1.3 Line Sizing............................................................................................................................. 12
5 DESIGN CRITERIA - RELIEF AND DEPRESSURING LINES.............................................13
5.1 Relief Valve Inlet Lines.......................................................................................................... 13
5.2 Relief Valve Outlet Lines....................................................................................................... 13
5.3 Flare Headers and Sub-Headers........................................................................................... 14
5.4 Flare Stacks.......................................................................................................................... 14
5.5 Blowdown Inlet Lines............................................................................................................. 14
5.6 Blowdown Outlet Lines.......................................................................................................... 14
5.7 High Pressure Vents.............................................................................................................. 14
5.8 Atmospheric Tank Vents........................................................................................................ 14
6 CALCULATION METHODS................................................................................................... 16
6.1 Valves and Fittings Equivalent Lengths.................................................................................16
7 DESIGN MARGINS............................................................................................................... 18
ATTACHMENTS
1 GENERAL
This guide presents pressure drop and velocity criteria for the sizing of lines on offshore platforms and
other similar facilities (eg. FPSO). Engineers are expected to use the criteria presented in this guide
tempered with judgement when selecting line sizes.
Lines shall be sized such that process pressure drop requirements are satisfied. In general, when both
allowable pressure drop and allowable maximum velocity are shown, the more stringent of the two
should control.
Piping is to be sized for the controlling operating case determined by analysis of the flowrates, operating
pressures and temperatures for all identified operating modes according to the guidelines below.
Consideration is also given to start-up and shutdown conditions and other off-design operations where
these significantly impact on line sizing. For gas and two phase lines, particular attention is to be given
to the effects of changes in operating pressures, temperatures and gas composition with time.
A 20% design margin is applied to pressure drops for the purposes of comparison with the guidelines
for pressure drop per 100 m. If 1.2 times the calculated pressure drop only marginally exceeds the
guideline then engineering judgement is to be used in selecting the line size (this criteria shall not be
applied to flare system pressure drop calculations).
No provision for future increased capacity is made.
Sizing criteria is based on pressure drop, recommended velocity, erosion and noise constraints in
accordance with the guidelines given below. Critical lines, eg pump suctions, relief, vent and blowdown
lines, are recorded as ‘critical’ on the linelist. The Process Department will approve layout isometrics of
critical lines based on rigorous pressure drop calculations.
Long pipelines are excluded from the scope of this philosophy. These are to be sized rigorously.
For initial calculations where the number and type of fittings are unknown, the equivalent length of
piping shall be obtained by multiplying the piping run obtained from a preliminary layout drawing by
the factors in Table 1.1.
Table 1.1
Multiplying Factor For Piping Length
Approximate Pipe Length (m) 30 60 150
Pipe NB (mm)
75 and smaller 1.9 1.6 1.2
100 2.2 1.8 1.3
150 2.7 2.1 1.4
200 and greater 3.4 2.4 1.6
Table 2.1
Recommended Velocity and Maximum P for Carbon Steel Liquid Lines
HYDROCARBONS
Type of Service Velocity m/s Maximum P bar/100m
General Recommendation
Liquid Density, kg/m3
1600 1.5-2.4 1.1
800 2-3 0.9
320 3-5 0.3
Pump Suction See Table 2.2 See Table 2.2
Pump Discharge See Table 2.2 See Table 2.2
Liquid from condenser 1-2 0.1
Refrigeration Lines 0.6-1.2 0.09
Gravity Rundown Lines 1-2.5 0.033
Liquid Feed to Towers 1.2-2 0.06 - 0.1
Liquids to Reboilers 0.9 - 1.8 0.02 - 0.06
WATER LINES
General Recommendation 0.6-4.8 0.06-0.45
Service Diameter, mm
25 0.6-1
50 1-1.5
100 1.5-2.1
150 2.1-2.7
200 2.5-3
250 3-3.7
300 3.7-4.3
400 3.7-4.6
500+ 3.7-4.9
Pump Suction See Table 2.2 See Table 2.2
Pump Discharge 1.5-3, refer also to Table 4.2 See Table 2.2
Boiler Feed 2.5-4.5
Cooling Water 3.6-4.8 0.45
Table 2.2
Allowable Pressure Drops and Velocities in Piping for Centrifugal Pumps
Table 2.3
Allowable Velocities in Piping for Salt and Produced Water
l g
gu = g
l
Size the line for all expected flow rates such that frictional forces offset gravitational forces thus
avoiding sub-atmospheric pressures at the top of the pipe.
Install a back-pressure control near the base of the line.
Size the line as self venting as above.
2.7 Drains
To avoid deposits of solid particles sewage, closed and open drains shall be designed for the minimum
fluid velocities given below:
Table 2.4
Minimum Velocities for Drain Lines
Service Min Velocity (m/s)
Sanitary Drains 0.8
Oily Water Drains (Open Drains) 0.9
Other Drains 1.1
However a minimum size of NB 100mm shall be used for the header and NB 75mm for the sub-headers.
Q K * D* H 1.5
Q = flowrate (m3/hr)
Notes:
1. Reciprocating compressor lines should be sized on a conservative basis with maximum velocities of
12 m/s.
2. The velocity of gases containing wet carbon dioxide is not to exceed 18 m/s where film-forming
corrosion inhibitor is being used. At velocities above this limit corrosion inhibitor loses its
effectiveness.
3. Friction drop criteria need not be considered for a line with a control valve having a large pressure
drop e.g. compressor recycle, vent to flare, etc.
4. For continuous flow (including lines in flare systems) the vapour velocity should not exceed the
erosional velocity as calculated in section 4.0 below. The calculated velocity shall not exceed either
the maximum recommended velocity or the erosional velocity. For intermittent flow where pressure
drop is not a consideration (eg. Compressor capacity control recycle lines) the velocity should not
exceed 40 m/s.
In addition to the velocity and pressure drop criteria, the maximum allowable vapour velocity relating to
the acceptable noise levels should not normally be exceeded. This velocity is calculated by the formula:
Vmax = 198.5 ( )-0.506
where Vmax = Maximum allowable vapour velocity (m/s) based on
a noise limit of 85 dBA @ 1m
= Gas density at flowing conditions (kg/m3)
When the vapour velocity exceeds Vmax for noise limits, consideration should be given to the routing of
the pipework, and addition of acoustic insulation on the piping, before significantly increasing the line
size.
4.2 Erosion
High velocities in 2 phase lines can cause rapid wear by erosion. The velocity at which erosion may
occur is calculated by the formula given in API RP14E, i.e.
C
Ve =
m
m can be calculated from the equation in API RP14E, or estimated by the following:
m = g (1-) + l
C = 400 (intermittent)
For Bayu-Undan, wellstream fluids shall be assumed as nominally solids free and the above “C” values
shall be used.
For absolutely solids free conditions:
Non-corrosive gas/condensate C = 400 (continuous) (Note 1)
C = 450 (intermittent)
Notes:
1. “C” values recommended by EEMUA (Publication No. 194 – “Guidelines for Material Selection
and Corrosion Control for Subsea Oil and Gas Production Equipment”).
a. Calculate the erosional velocity and determine the minimum pipe size required to avoid fluid
erosion.
b. Check the flow pattern to ensure that slug flow is avoided - annular mist flow is preferred.
However, if slug flow cannot be avoided due to erosional velocity constraints, then the slug flow
regime has to be accepted.
c. Calculate the pressure drop either using the method outlined in API RP14E or by use of
proprietory software (ESI, HYSYS, PIPESIM).
Wellhead flowlines, production manifolds and other lines transporting gas and liquid in two phase flow
where significant pressure drop is available, are generally sized on the basis of flowline velocity. This
velocity shall not exceed the erosional velocity as calculated in Section 4.2.
Calculation of static head resistance in two phase systems should consider the fluid to be all liquid since
this is likely to occur at some stage of platform operation. Static gain should be treated with caution
since flashed vapour present may not necessarily recondense in the downcomer pipe.
Slug flow with resultant pressure pulsation and vibration is to be avoided. Problems are most likely in
lines from exchangers where partial vaporisation or condensation has occurred. In comparison,
equilibrium fluids which are continuously flashing with vapour expansion are usually relatively stable.
Where slug flow is expected to be a problem, consideration should be given to equipment layout, e.g.
locate exchanger near terminus so that the liquid vapour line is as short as possible. In all cases
however it is good engineering practice to layout piping so that it is self venting to the terminus (i.e. no
pockets).
Where there are a number of valves discharging into the same manifold, caution should be exercised to
ensure that the backpressure in the manifold allows all relief valves to discharge properly.
The recommended maximum Mach number is 0.75 calculated at rated flowrate and downstream
junction with header conditions. Back pressure based on installed critical area shall be checked to
confirm it is below the system design pressure.
Note that Mach number for vapour lines is calculated from the following equation :
vs RT
Caisson vent line is sized to suit total displaced air flow rate while conforming to the velocity/pressure
drop criteria in Section 3.0.
6 CALCULATION METHODS
For the purposes of calculating line sizes and pressure drops the following calculation methods shall be
used:
Single Phase Lines - In-house validated spreadsheets
- ESI Software
Liquid Network/Pump - FLUIDFLO
Circuits (seawater, cooling
medium, heating medium
pumps)
Two Phase Lines - In-house validated spreadsheets
- ESI (horizontal lines only)
- PIPESIM where applicable.
Firewater Systems - HYENA or equivalent.
Flare Networks - FLARENET or equivalent.
Copper-Nickel lines will be sized using the Hazen-Williams formula. In this case, a Hazen-Williams
‘C’ value of 140 is used in calculations as recommended in the NFPA Handbook.
The roughness of Coflexip flexible pipes is calculated as follows:
E = D
250 D in mm - for roughbore flexible pipe with a stainless steel carcass.
For smooth flexible pipe (thermoplastic lined) E = 0.0048 mm.
7 DESIGN MARGINS
In view of the space and weight limitations on the Bayu-Undan facilities, line sizes must be kept to a
minimum consistent with the correct operation of the platform. Care should be taken to ensure that
design margins are not ‘doubled up’, thus unnecessarily increasing line sizes.
All pressure drop calculations shall include a 20% design margin on pressure drop to allow for
manufacturing tolerances and deterioration of the new pipe with scale, rust etc. (This criterion shall not
be applied to flare system pressure drop calculations).
ATTACHMEN T (A)
Enlarger Reducer
Short Long Hard Soft 90 º miter bends Sudden Std red. Sudden Std red.
45 º Ell Rad Ell Rad Ell T T Equivalent Length in terms of small d
Globe Valve or Ball Check
Nominal Pipe Size (mm)
Threaded
Plug Cock
Threaded
Threaded
Threaded
Threaded
d/D = 1/4
d/D = 1/2
d/D = 3/4
d/D = 1/2
d/D = 3/4
d/D = 1/4
d/D = 1/2
d/D = 3/4
d/D = 1/2
d/D = 3/4
Welded
Welded
Welded
Welded
Welded
3 miter
4 miter
2 miter
Valve
40 16.8 7.9 4.0 2.1 0.3 0.3 0.6 0.9 1.5 0.6 0.9 2.4 2.7 0.6 0.9 1.5 0.9 0.3 1.2 0.3 0.9 0.6 0.3 0.3
50 21.3 10.1 5.2 4.3 0.6 0.6 0.9 1.2 1.5 0.9 1.2 3.0 3.4 0.9 1.2 2.1 1.2 0.3 1.5 0.3 0.9 0.9 0.3 0.3
65 24.4 12.2 6.1 3.4 0.6 0.6 1.5 0.9 3.7 0.9 2.4 1.5 0.6 1.8 0.6 1.2 0.9 0.6 0.6
75 30.5 15.2 7.6 5.2 0.6 0.6 1.8 1.2 4.3 1.2 3.0 1.8 0.6 2.4 0.6 1.5 1.2 0.6 0.6
100 39.6 19.8 9.8 9.1 0.9 0.9 2.1 1.5 5.8 1.5 3.7 2.4 0.9 3.0 0.9 1.8 1.5 0.9 0.9
150 61.0 30.5 14.6 21.3 1.2 1.2 3.4 2.4 8.5 2.4 5.5 3.7 1.2 4.3 1.2 2.7 2.1 1.2 1.2 0.3
200 79.2 38.1 19.5 36.6 1.8 1.8 4.6 2.7 11.3 2.7 7.6 4.9 1.5 5.8 1.5 3.7 2.7 1.5 1.5 0.6
250 100.6 48.8 24.4 51.8 2.1 2.1 5.5 3.7 14.3 3.7 9.4 6.1 2.1 7.3 2.1 4.6 3.7 1.8 1.8 0.6
300 121.9 57.9 29.0 51.8 2.7 2.7 6.7 4.3 16.8 4.3 8.5 6.4 6.1 11.3 7.3 2.4 8.5 2.4 5.5 4.3 2.1 2.1 0.6
350 137.2 64.0 32.0 24.4 3.0 3.0 7.9 4.9 18.9 4.9 9.8 7.3 6.7 12.8 7.9 2.7 6.1 4.9 2.4
400 152.4 73.2 36.6 44.2 3.4 3.4 8.8 5.5 21.9 5.5 11.6 8.2 7.3 14.3 9.1 3.0 7.3 5.5 2.7
450 167.6 85.3 42.7 48.8 3.7 3.7 10.1 6.1 25.0 6.1 12.8 9.1 8.5 16.2 10.7 3.4 7.9 6.1 3.0
500 198.1 91.4 47.2 64.0 4.3 4.3 11.0 7.0 27.4 7.0 14.0 10.1 9.8 18.3 11.6 4.0 9.1 7.0 3.4
550 209.7 102.1 51.8 68.6 4.6 4.6 12.2 7.6 30.5 7.6 15.8 11.0 10.4 19.8 12.8 4.3 9.8 7.6 3.7
600 228.6 112.8 56.4 77.4 4.9 4.9 13.4 8.2 33.5 8.2 17.1 11.9 11.0 21.3 14.0 4.6 10.7 8.2 4.0
750 95.1 6.4 6.4 16.8 12.2 42.7 12.2 21.3 15.5 13.4
910 7.6 7.6 20.1 14.3 51.8 14.3 25.6 18.3 15.8
1067 9.1 9.1 23.5 16.8 61.0 16.8 29.9 21.0 19.5
1220 10.7 10.7 26.8 19.8 67.1 19.8 34.1 24.7 21.9
1375 12.2 12.2 30.2 21.3 76.2 21.3 38.4 27.4 24.4
1525 13.7 13.7 33.5 24.4 79.2 24.4 57.9 30.2 28.0
ATTACHMENT (B)
Rev 1
/conversion/tmp/scratch/462273052.doc
February 2000
BAYU-UNDAN UPSTREAMGAS RECYCLE PROJECT - PRELIMINARY ENGINEERING
ATTACHMENT (C)
Rev 1
/conversion/tmp/scratch/462273052.doc
February 2000