Lafarge DEC Presentation December 2010
Lafarge DEC Presentation December 2010
Lafarge DEC Presentation December 2010
slide 1 of 16
Agenda
Introductions
Project Description
Facilities Retained
Wet to Dry Process
Key Areas Examined
in DEIS
Schedule
www.lafargeravenafacts.com
2
slide 2 of 16
Lafarge Team
3
slide 3 of 16
The Ravena Process
Today: Wet Process
Wet Process
(1950-60’s Technology)
Raw materials are mixed with water and
ground in slurry mills. Slurry is stored and
homogenized in large slurry basins.
Slurry mixture is fed directly to the kiln
without preheating.
A large amount of extra fuel is used in
evaporating the water.
A larger kiln is needed, because much of the
kiln’s length is used up for the drying proces.
In 1962, the Ravena cement plant’s nearly
600-foot long kiln was the largest piece of
moving industrial equipment in the world.
4
slide 4 of 16
The Ravena Process
Tomorrow: Dry Process
Dry Process
Pre-heater/pre-calciner kiln line
(State-of-the-art Technology)
Raw materials are ground, mixed, and fed to a
kiln in a dry state. Ground dry material is
preheated in a preheater tower.
The preheater tower is a tall vertical structure in Reduced process waste.
which the dry kiln feed enters at the top of the
tower and is heated by kiln exhaust gas entering ZERO process wastewater discharges through
at the bottom of the tower. re-use and recycling.
Preheating of the ground dry material prior to Minimization of Impacts to Hudson River:
entering the kiln results in substantial energy • Achieves objectives of Hudson River
savings compared to the energy required to heat Estuary Program.
the wet slurry mixture.
• Flow minimization through reuse/recycle
The Rotary kiln length of approximately 200 ft. is of wastewater and use of non-Hudson
much shorter than the wet kilns. River water sources.
New emissions control technology includes: • DEC approved best technology available
scrubber, SNCR, state-of-the-art dust collectors for water intake from the Hudson River
and CEMS. to minimize impacts to
aquatic organisms.
5
slide 5 of 16
Facilities
6
slide 6 of 16
New Facilities
Phase l
Secondary crusher Scrubber
Raw mill storage bins SNCR—selective non-
Raw mill catalytic reduction
Alkali bypass Baghouse dust collectors
Coal mill Fans, drives and ancillary equipment
Prehemogenization silo Continuous Emissions Monitors
(CEMs): NOx, SO2, PM, Hg, CO/CO2,
Kiln
THC and HCl
Preheater precalciner tower
Clinker cooler
Phase ll
Power generating system
Finish mill
Clinker storage Ravena’s Quarry
Preblending system
7
slide 7 of 16
Wet vs. Dry
Raw Milling
Horizontal configuration to vertical
Same raw materials except water
8
slide 8 of 16
Wet vs. Dry
9
slide 9 of 16
Wet vs. Dry
10
slide 10 of 16
Lafarge Ravena Plant
Proposed Plant Modernization Project
11
slide 11 of 16
DEIS: Water, Energy & Waste
Comparison: Modernized Facility & Existing Plant
12
slide 12 of 16
Existing vs. New Plant
Emissions from modernized plant compared to existing plant
13
slide 13 of 16
The Future
Modernization Project Timeline
14
slide 14 of 16
Modernization Benefits
15
slide 15 of 16
Lafarge Ravena Plant Modernization Project
Information and Updates
16
slide 16 of 16