Economic Analysis of Gas Pipeline Projec
Economic Analysis of Gas Pipeline Projec
Economic Analysis of Gas Pipeline Projec
net/publication/332530981
CITATIONS READS
0 874
2 authors:
Some of the authors of this publication are also working on these related projects:
Development of Sustainable Poverty Reduction Strategy for Northeast Nigeria: Challenges and Islamic Solution View project
All content following this page was uploaded by Ahmed Adamu on 19 April 2019.
Abstract
Nigeria has the largest gas reserves in Africa and Gas pipeline industry has been in operation in the country since
the gas discovery in the country in late 1960s. Lack of sufficient gas development infrastructure has caused
energy imbalance in the country, and making the country rely heavily on the few existing pipelines, which makes
the country’s energy sector vulnerable to any shock on these pipelines. Recently, the Nigerian government
resolved to build new gas pipelines as part of its plan to maximise gas utilization. As such, this research analysed
the economics of these possible gas pipelines options so as to assess if investment in new gas pipelines is viable
in Nigeria and which of the pipeline route option is more viable. The research used gas pipeline models that
already exist in literature to analyse the investment cost, gas deliveries as well as costs and benefits of six
possible gas pipeline routes options in the country. The BSRO pipelines route option was found to be more
viable and estimated to have an annual gas delivery of 37.25 bcm, investment cost of $1.15 billion, NPV of
$2.43 billion, IRR of 50.38%, payback period of 2.60 years for forty years of operation. However, in terms of
coverage and ability to supply more gas to more locations, the all gas pipeline route option is more
recommendable. Other gas pipeline routes options are also viable except the NRO gas pipelines, and it is
recommended not to consider this option alone, even in the future, the best recommendation is to combine it with
the BRO pipelines option.
Keywords: Gas Pipeline Routes, BNRO, BSRO, BNRO, NRO, SRO, NRO, NPV, IRR, payback period
List of Abbreviation
BRO: Base Route Option
BCM: Billion Cubic Metres
BNRO: BRO+NRO
BSRO: BRO+SRO
E (CCMS): Estimated Cost of Compressor Stations
E (CCP): Expected Cost of Constructing Pipeline
BWRO: First Alternative System
HP: Horsepower
IEA: International Energy Agency
IIC: Initial Investment costs
IRR: Internal Rate of Return
KM: Kilometre
LC: Labour Cost
MCM: Million cubic metres
IEA: International Energy Agency
NPV: Net Present Value
N: Nigerian Naira
NRO: Northern Route Option
NR: Not recoverable
PCW: Pipe Coating and Wrapping
PMC: Pipe Material Costs
SV: Salvage Value
SLD: Straight Line Depreciation
WACC: Weighted Average Cost of Capital
1. Introduction
It was reported that the domination of oil and gas resources in total energy mix will continue up to 2040 in
Africa as reported in the IEA Africa Energy outlook, due to the slow growth of their potential replacements
and/or alternatives [2]. However, the span of global proven conventional gas reserves was estimated to be around
54.1 years and that of oil around 52.53 years in 2014 by British Petroleum (BP) [3]. Accounting for recent
discoveries of the Shale oil and gas reserves, the future longevity and domination of the oil and gas might be
39
Journal of Economics and Sustainable Development www.iiste.org
ISSN 2222-1700 (Paper) ISSN 2222-2855 (Online)
Vol.8, No.2, 2017
extended [4]. With the fear of oil production peaking and its higher CO2 emission than natural gas, the natural
gas may take the lead and become more favourable in the future. Though, natural gas has long been dumped (or
flared) due to the abundance and relative low cost of oil production. With the promising future for the natural gas
especially in developing countries, where the demand for natural gas is very low, different sorts of natural gas
uses can be developed to trigger its demand [5] [6].
Nigeria, being the most populous country in Africa and having the largest gas reserves in the continent,
the need to invest and diversify the use of natural gas in imperative [7]. It was estimated that, by the year 2040,
around 50 million people will still live without access to electricity [2]. Ibitoye (2007) estimated that electricity
supply from gas will continue to dominate energy supply mix and will constitute 70% of the total electricity
generation in Nigeria by 2030 [8]. Going by this estimate, we will witness additional 7% increase in the share of
sources of electricity from natural gas in 2030 from 2011. IEA (2014) estimated that natural gas will dominate
the future energy balance with 23% in 2040, which higher than 18% for oil and 5% for coal. Hydro and
bioenergy were estimated to have a share of 2% and 50% respectively in 2040 [2].
The total final energy consumption in Nigeria as at 2012 was 121 Million tons of oil equivalent (Mtoe),
which will increase by 64% in year 2040. This signifies significant increase in energy demand in the country in
the future, which justifies the need for more investment and diversification of energy sources in the country.
Lack of sufficient gas development infrastructure has caused energy imbalance in the country, and making the
country rely heavily on the few existing pipelines, which makes the country’s energy sector vulnerable to any
shock on these pipelines. This is the reason why the Nigerian government developed a gas master plan, that
enumerate intended investment projects that will help in diversify gas supply options, which will stimulate
development of natural gas in the country to become the major energy source in the country [9] [1] [10].
Therefore, this research is aimed to provide economic framework of the key gas development project i.e. gas
pipeline that can be implemented to achieve the objective of the plan. The research will also serve as an
academic guide toward actualizing and extending the objective of the plan in the country.
Considering the large gas reserves and the persistent gas flaring in the country, the research is motivated
to identify the gas development projects that can be implemented to use gas as a means of improving access to
energy and making the gas reserves useful for the economic growth in the country. The research is motivated by
the need to have estimation of the viability of these gas development projects so that investors would understand
the viability of these gas development projects, which could motivate them to invest in the country. The research
is also motivated by the need to have recommendation on the optimal and viable projects, and the need to
provide recommendations for incentives to encourage investment in other non-viable projects in the country (if
any).
In line with achieving the objective of the gas master plan in Nigeria of sufficient domestic gas supply,
the research identified that gas pipelines are major and significant infrastructure necessary to utilizing the natural
gas [11], and this is clearly outlined in the gas master plan. The research then asks: What are the optimal
combination of the proposed gas pipeline route options? And what are the costs and benefits of each of the gas
pipelines route combinations? This will help inform the government and prospective investors on the best
combination of the gas pipeline route options, and the resulting costs and benefits of each of the gas pipelines
routes so as to make optimal, informed and reliable investment decisions.
The research aims to identify and analyse the economics of the relevant gas development project (Gas
Pipelines) that can help enhance domestic gas consumption. In other word, the aim of this research is to identify
the different gas pipeline route options and analyse the economics of each of the options so as to stimulate latent
demand for natural gas in the country in line with achieving the objective of the gas master plan of eliminating
gas flaring and expanding domestic gas utilization in the country.
The objective of the research is to analyse the capital investment requirements for six different possible
gas pipeline routes as well as their respective costs and benefits .An assessment will be carried out between these
gas pipeline options in terms of its capital cost requirement, potential of gas delivery, and returns on investments.
The research will use the NPV, IRR, Payback period and investment cost models already established in the
literature to analyse the costs and benefits of the gas pipeline projects. Gas pipeline investment cost models as
identified in Shahi (2013) will be used to estimate the Nigerian-specific capital cost requirements and gas
delivery of the proposed gas pipeline routes [12].
The research is significant as it will analyse the key possible gas pipeline projects that Nigeria can
develop to improve domestic gas utilization so as to reduce gas flaring, improve electricity generation, improve
welfare of the people, facilitate more job opportunities, enhance productivity and efficiency in the productive
sectors of the economy. As the research will provide empirical and analytical analysis of these gas development
projects, it will serve as viability indicative framework of these projects for government and prospective
investors in the gas sector in the country. The research will serve as the academic supporting document to the
Nigerian gas master plan, as it aims to further provide economic assessment of gas development projects aimed
at achieving domestic gas consumption as outlined in the plan. It serves as academic guide toward actualising the
40
Journal of Economics and Sustainable Development www.iiste.org
ISSN 2222-1700 (Paper) ISSN 2222-2855 (Online)
Vol.8, No.2, 2017
41
Journal of Economics and Sustainable Development www.iiste.org
ISSN 2222-1700 (Paper) ISSN 2222-2855 (Online)
Vol.8, No.2, 2017
42
Journal of Economics and Sustainable Development www.iiste.org
ISSN 2222-1700 (Paper) ISSN 2222-2855 (Online)
Vol.8, No.2, 2017
Figure 3: West African Gas Pipeline. Sourced: West African Gas Pipeline Company [21]
43
Journal of Economics and Sustainable Development www.iiste.org
ISSN 2222-1700 (Paper) ISSN 2222-2855 (Online)
Vol.8, No.2, 2017
As at May 2008, there are more than 1000 kilometres connected gas pipelines within the Nigerian
territory, which are concentrated in the Niger Delta region. Other pipelines beyond the gas-producing region are
the Ajaokuta gas pipeline and the main Nigerian Escravos-Lagos Pipeline system that links the pipelines to the
Lagos beach, which links to the West African gas pipeline and for further transportation via LNG or extended
pipeline. The following table represents a summary of the existing major gas pipeline networks in the country.
The map of the major gas networks is presented in figure 4 [22].
Table 1: Major Gas Pipeline Networks within Nigerian Border
Project Name Start Point End Point Diameter Length
(inches) (Kilometres)
Transmitting System Banga Field Bonny Terminal 32 268
Escarvos-Lagos Pipeline System Escravos Lagos 36 340
(ELPS)
Aladja System Pipeline Oben Ajaokuta 24 294
Greater Ughelli System Ughelli Warri - 90.3
Figure 4: Map of major gas pipelines in Nigeria: gas pipelines indicated by the bold red lines. [23]
The four major gas transmitting pipelines in Nigeria covering slightly more than 1000 kilometres of
land, supply gas to few power, cements and fertilizer plants. Nigerian Gas Company further expanded the chart
of the Nigerian gas pipeline systems by considering other small distant pipelines and by looking at their
destinations to various industrial companies and power stations as follows [24]:
1. The Aladja Gas Pipeline System which supplies the Delta Steel Company, Aladja.
2. The Oben-Ajaokuta-Geregu Gas Pipeline System, supplies Gas to Ajaokuta Steel Company, Dangote’s
Obajana Cement Company and PHCN Geregu Power Plant.
3. The Sapele Gas Supply Systems which supplies gas to PHCN Power Station at Ogorode, Sapele.
4. The Imo-River-Aba System for gas supply to the International Glass Industry Limited PZ, Aba Textile Mills
and Aba Equitable Industry.
5. The Obigbo North -Afam system caters for PHCN Power Station at Afam,
6. The Alakiri to Onne Gas pipeline system supplies gas to the National Fertiliser Company (NAFCON) now
Notore Chemicals for fertilizer production;
7. The Alakiri -Obigbo North -lkot Abasi system for gas supply to the former Aluminum Smelting Company of
Nigeria (ALSCON) Plant now Rusal Industries in Ikot Abasi.
44
Journal of Economics and Sustainable Development www.iiste.org
ISSN 2222-1700 (Paper) ISSN 2222-2855 (Online)
Vol.8, No.2, 2017
8. The Escravos-Lagos Pipeline (ELP), which supplies gas to NEPA's Egbin Power Plant near Lagos.
Subsequent spur lines from the ELP supply the West African Portland Cement (WAPCO) Plants at Shagamu and
Ewekoro, PZ Industries at Ikorodu, City Gate in lkeja Lagos, PHCN Delta IV at Ughelli, and Warri Refining and
Petrochemical Company at Warri.
9. Ibafo – Ikeja Gas Supply Pipeline System supplies gas to Ikeja City Gate from where Gaslink distributes to
the Lagos Industrial Area (LIA).
10. Ikeja – Ilupeju – Apapa Gas Pipeline System currently operated by Gaslink for Gas Supplies to Greater
Lagos Industrial Area.
11. Ajaokuta – Geregu Gas Pipeline System, which supplies gas to the Geregu PHCN Power Plant.
12. Ajaokuta – Obajana Gas Pipeline System, which supplies gas to Dangote’s Obajana Cement Plant (OCP).
“All these facilities comprise of over 1,250 kilometres of pipelines ranging from 4" to 36" in diameters
with an overall design capacity of more than 2.5 billion standard cubic feet of gas per day (bscf/d), 16
compressor stations and 18 metering stations. The facilities represent a current asset base of more than N21
Billion business contact” Nigerian Gas Company Limited (2012) [24]. There are other pipeline projects going on,
and some are being proposed. The on-going projects include the expansion of the existing pipelines and
extension of pipelines to new areas, especially the Northern part of the country, where there is no single pipeline
network despite the largeness of the region and huge human population, which comprises almost 56% of the
nation total population of more than 160million people [25].
3.2. Methodology
This research reports on the economic methodology in assessing the economics of the gas pipelines in Nigeria.
To assess the costs and benefits of the six different gas pipeline routes combinations, first, the investment cost
comprising of gas pipeline material cost, pipe coating and wrapping cost, cost of constructing the compressor
stations, and labour cost will be estimated using the models below. The gas delivery and cost of capital of each
of the pipelines will be estimated as well as the annual costs and benefits for running the gas pipeline routes
using the NPV, IRR and payback period methods. The initial investment cost of these pipelines are estimated
using equation 1 [12].
(1)
Where E (CCP) stands for the expected cost of constructing/laying down the gas pipelines and E (CCMS) is the
expected cost of installing compressor stations. Cost of constructing the pipeline consists of the fixed cost of the
45
Journal of Economics and Sustainable Development www.iiste.org
ISSN 2222-1700 (Paper) ISSN 2222-2855 (Online)
Vol.8, No.2, 2017
system including the cost of material and right of way (ROW) if applicable. It consists of the costs of process
equipment, supporting facilities, direct/indirect labour etc. The formula for pipeline construction cost is given as
follows [12]:
(2)
Where PMC is the pipe material cost and PCW is the cost of pipe coating and wrapping and LC stands
for the labour cost of installing the pipeline.
To estimate the cost of laying down a pipeline, i.e. E(CCP), we will adopt the model established by
Shahi Menon (2005) [12], which suggested that the costs of constructing a pipeline include the costs of pipe
materials, pipe coating and fittings, and the cost of labour for installation. These parameters were incorporated in
equation 2, and are defined as follows:
5% (3)
Therefore, the PCW is 5% of the pipe material cost, which is defined in equation 4
0.0246 ! " # # (4)
Where:
D is the diameter (outside) of the pipe in millimetres (mm), L stands for the length of the pipe in km, T stands for
the pipe wall thickness in mm and C is the pipe material cost in $/metric ton [14]. Estimating the labour cost
during the installation can be difficult depending on the area where the pipe will be laid down and the contractor.
It also depends on the length of the pipe and from where the pipes are brought. According to Mohitpour, et al
(2003), the labour cost for laying the gas pipeline was estimated to be $316,800 per mile, which is $196,850.39
per kilometre. However, this may vary depending on the location and nature of the environment; the contractors
normally study the nature of the work and fix cost for labour. From historical data and some gas construction
figures, a fixed amount is slated for every diameter and distance of the pipeline, which is normally $15, 000 as
average labour cost during pipe installation [26]. This is based on the external labour cost of gas pipeline
installations as the pipe installation company is expected to be a foreign company (likely from America), and the
engineers will be paid based on the international labour cost. For the purpose of this estimation we adopt the
following model [12].
$15, 000 ' ( ) * (5)
For the cost of constructing and installing the compressor stations, we still adopt the model established by Shahi
Menon (2005) which estimates the compressor cost as $2000 per Horsepower capacity of the compressor. This is
corroborated in the work of Yipeng Z. and Zhenhua R. (2014) [27]. Intervals between compressor stations are
between 40 and 60 miles (64 and 161km) [28], and the minimal intervals is adopted in order to maintain high
pressure in the gas. Therefore, the cost of compressors of a pipeline will be $2000 multiply by number of
compressors and then multiply by the Horsepower capacity of the compressors.
$2000 ∗ , ( - . ( ∗ / 0 ( 1 -( ( (6)
The pipeline thickness (t) is derived through the following equation adopted from Shahi Menon (2005).
23 425
(7)
6
Where !7 is the diameter outside, and !8 is the diameter inside.
Depreciation and taxation are also accounted. Straight-line depreciation method is used, which is an accounting
way of calculating the devaluation of an item at a fixed rate over a long period of time [29]. It is the opposite of
declining balance method, where the asset depreciates more in the first year and then depreciates less every other
year of its lifetime. Straight Line depreciation divides the total value of the asset by its operational period to
derive the annual depreciation amount, which means at the end of the business period (40 years), the book value
of the asset will be zero. However, because we will have a salvage value (SV) of the gas pipelines in our analysis,
a salvage value will be considered, which is deducted from the value of the pipelines before applying the
straight-line depreciation, and is given as follows [30] [31]:
SV ∗ 1 " '( 9:;<=:>< (8)
Where
88?
'( / 100 (9)
9:;< =:><
Where '( is the depreciation rate.
Depreciation relates to taxation, because corporate tax rate is charged against the depreciation value of
the asset to arrive at the tax benefit. Usually companies deliberately over depreciate their assets in order to pay
less of their taxes [32]. Depreciation is deducted in the cost, thereby reducing the taxable income. Therefore,
depreciation tax benefit is the relief or discount of a tax the gas pipeline operator receives for the depreciation of
the pipeline, which will be considered as a benefit not a cost [33]. The tax benefit is derived by multiplying the
tax rate by the annual depreciation value, which will then be deducted from the total tax payment to arrive at
total tax payable [34]. Since the proposed gas pipelines are within Nigerian territory, the complexity of using
different corporate tax rates will not arise.
Annual operating and maintenance costs (O and M) have to be considered even though the pipelines are
46
Journal of Economics and Sustainable Development www.iiste.org
ISSN 2222-1700 (Paper) ISSN 2222-2855 (Online)
Vol.8, No.2, 2017
not in operation, but an assumption can be made based on the existing literature, and adopt a fixed percentage of
the investment cost (equation 1) to be the annual O and M costs. However, since the Nigerian pipeline will
connect through the onshore land of the Nigerian territory, 2% of the costs of constructing the pipeline will be
assumed to be the O and M costs annually [35] [36] [37]. O and M costs consist of costs of labour, supervision,
energy, telecommunication, miscellaneous etc. The 2% was considered as a result of including the operation
costs, otherwise the cost of maintaining the pipeline would have been below the 2% of the initial investment cost
[12].
The capital structure of the gas pipelines investment will be 60% debt and 40% equity, and this is in
line with the capital structure of the proposed domestic gas pipelines [16], and it is the capital structure of an
average oil and gas listed companies in the country, with particular reference to Nigerian Oando plc [38].
However, the Nigerian government is recommended to own substantive part of the business [16].
Therefore, the cost of capital will be accounted through the cost of equity and cost of debt for all the
investments appraisal. The cost of equity will be accounted using the Capital Asset Pricing Model (CAPM), and
the after tax cost of debt will be used. To account for both cost of debt and cost of equity, the Weighted Average
Cost of Capital (WACC) will be applied, and from which all the cash flows will be discounted [39] [40]. The
WACC is used because it accounts for both costs of the two sources of capital, which are debt and equity [39]
[40].
B 2
A ∗ C< ∗ CD 1 " #E (10)
? ?
Where E is the total value of the equity, C is the total value of the capital, D is the total value of the debt,
C< is the cost of equity, CD is the cost of debt and TR is the tax rate, which is 30 percent in Nigeria [41].
Starting with the cost of debt, we will use the after tax cost of debt going by [40], which is:
CD ( ∗ 1 " #E (11)
Where, ( is the prime lending rate of the Nigerian commercial bank, which is 16.90% as at March 2015
[42], and which has been the average prime lending rate for a decade [43]. This rate is used based on the
assumption that the debt to fund these projects will be provided by a bank within Nigeria. The formula for cost
of equity using CAPM model is stated in equation 12 [31].
C< (; F (> " (; (12)
Where, C< is the cost of equity, (; is the risk free interest rate, (> is the expected market portfolio return,
and the difference between (> and (; is the equity risk premium (ERP), which measures the additional
compensation to the investor for taking the risk of investing in a riskier business, and F accounts for
responsiveness of the business to the average stock market change, hence how risky is the business. (; is usually
the interest rate of a relatively risk free investment, which the investor may wish to invest in, it is usually a
government bond, which have higher level of security, and hence low risk. The higher the risk, the higher the
expected interest rate [44]. The yield on the Nigerian government bond is used as the risk free interest rate.
According to the trending economics, the yield on the Nigerian government bonds has averaged around 13.04
percent from 2007 to 2015. The return on the bonds changes frequently, and as at July 2015, the rate was 14.81
percent. The highest it has ever being was 17.30 percent in February 2015, and lowest it has been was 6.04
percent in March 2010. Due to these erratic fluctuation of the return on the bonds, the average return on the
bonds from 2007 to 2015 will be used, which is 13.04 percent [45] [46].
The ERP as mentioned is the difference between the rate of return on a risk free investment and the
expected market rate of return of the investment [44].The Nigerian estimated average ERP as contained in
Moody’s report and the Stalwart report as at January 2015 was 11.15 percent, so we will use the latest ERP for
this analysis, which is 11.15 percent [47] [48]. Therefore, the expected market portfolio return can be assumed
to be 11.15 percent plus 13.04 percent risk free rate, and this gives 24.19 percent as the expected market
portfolio return. This will be the maximum return the investor will expect for investing in the riskier investment,
and it will be the (> in equation 12. The Risk Premium is higher compare to some other countries, and this may
suit this kind of business due to some country risk factors associated with it, which includes the potentials of gas
pipeline vandalism, which have been frequent recently causing loss of gas and extra cost of repair. There is also
security risks associated with kidnapping and killings of oil and gas personnel by the militants. There are
political and economic risks in the country, associated with changes of government and economic policies.
Now the next variable to identify is the F (Beta). Beta measures the reaction of a price of a share in a
company to the change in the overall stock market. A Beta lower than 1 shows that the stock value is less
volatile than the stock market, and if it is higher than 1, it shows that it is more volatile than the market. The
formula for the Beta is given as the covariance between the unlevered return on the business (EG and that of the
market (E> , divided by the variance of the latter, which is presented as follows [44].
?HI JK ,JL
FG (13)
MNO JL
Because there is no available data for Nigerian stock market for domestic gas pipeline investment, as
47
Journal of Economics and Sustainable Development www.iiste.org
ISSN 2222-1700 (Paper) ISSN 2222-2855 (Online)
Vol.8, No.2, 2017
there are no listed gas pipeline companies in the country, the average P of seven listed oil and gas companies
(BOC Gases Nigeria PLC, Conoil PLC, Eterna Plc, Forte Oil Plc, Mobil Oil Nigeria Plc, MRS Oil Nigeria Plc,
Oando Plc) in the country is used as the proxy Beta for the investments, which was 0.86 as at July 2015 [49] [38]
[50, 51].
Since debt is included in the capital structure, the amortization cost will be accounted using the
following formula [50]
2<R= :S=<OT= ON=<
A / ( Q W a (14)
U4V `
WXYZ[\]\^[ ]_[\
Where, N is the total number of period. To calculate the certified volume of gas/capacity of a pipeline
(where applicable), the Weymouth formula is used as provided in pipeline rules of thumb [52], which assumed
that the optimum number of compressors are in place to achieve the desired pressure level of the gas at the
destination using the lowest compressor station intervals as stated earlier, and is presented in equation 15:
e
cdU D f ghWi 4hii
b (15)
√k
Where:
Q= Cubic feet of gas per 24 hours
d= pipeline inside diameter in inches
P1= Psi (abs) at starting point
P2=Psi (abs) at ending point
L = Length of the pipeline in miles
For the annual gas delivery of the gas pipeline, equation 16 applied the availability rate and the annual gas
delivery capacity to arrive at the actual gas delivery of the pipeline. [33] [52].
n
lSoU A 0 m 1 ( / - - - m 1 (16)
The Nigerian regulated gas transportation cost of $0.80/Mcf is used [53] [54] [55]. This is almost
similar to the estimated average cost of gas transportation for the five segments of the Nord stream (Gryazovets-
Vyborg, Nord-Stream offshore, Opal, and Nel), which was estimated to have an average levelised cost of gas
transportation of $0.81/Mcf ($28.7/thousand cubic metres) [33]. The regulated tariff in the country did not
account for distance, and as such it is highly recommended to review this tariff and account for distance. For the
availability/utilization rate, 80% is applied based on the existing pipelines average availability rate in the country,
and this accounts for the number of days that the pipeline will be operational[24] [20] [21] [56]. Other non-
operational period could be due to fall or stop in supply/patronage, or for holidays, or for maintenance purposes
or as a result of vandalism etc
The Net Present Value (NPV) accounts for the difference between the initial investment cost and the
present values of all the future cash inflows and cash outflows. Therefore, NPV is the difference between the
present value of the future net cash flows and the initial investment cost. For the Internal Rate of Return (IRR), it
is the maximum allowable rate of return on the investment, it is the discount rate that brings the business to
breakeven, where NPV equals to zero. It is derived by trying so many discount rates, and the discount rate that
makes the NPV zero is the IRR. Payback period is the number of years that the investor will have to wait to get
back his/her initial investment [44].
The net present value and the IRR will be derived from these cash flows. The Net Present Value
formula is presented as follows:
?W ?i ?u
p q " r i………… u (17)
UsO UsO UsO
Where, r is the initial investment cost, s are the net cash flows of respective periods, ( is the discount
rate, and # is the end period. IRR is the discount rate at which the NPV equals to zero. The discounted payback
period is derived by dividing the absolute value of the last negative cumulative discounted cash flow by the
discounted cash flow value in the following year and then adding the period of the last negative cumulative
discounted cash flow, this is presented in equation 18 below [34].
v
! / ' - m0 C ( ' A (18)
?
Where A is the period where last negative cumulative discounted cash flow was recorded, B is the absolute value
of the last negative cumulative discounted cash flow at period A, and C is the discounted cash flow value after
the period A.
Using all the above costs and benefits inputs, an annual cash flow of these investments will be derived and
discounted to arrive at the net present value, IRR and Payback period, which will be used for comparison.
3.3. Costs and Benefits of the Combination of BSRO Pipelines (Near Future Plans)
The step by step analysis of the business option that combines the BRO and SRO will be presented. This
combination is what represents the intended near future gas pipeline plan. Other options will follow similar step
48
Journal of Economics and Sustainable Development www.iiste.org
ISSN 2222-1700 (Paper) ISSN 2222-2855 (Online)
Vol.8, No.2, 2017
by step analysis, and their IIC compositions as well as their accounting estimation results will be presented.
Now, we will present step by step analysis of the combination of the BRO and SRO, which is
abbreviated as BSRO. The equation for estimating initial investment costs (IIC) is already presented in equation
1:
First, we need to find the pipeline thickness (t), which is derived as follows following equation 7. For
the BSRO’s 3a segment, which has 42 inch diameter, the following wall thickness is calculated, which will be
used for the entire analysis, as thickness for other pipelines will be the same.
x6:S4xU:S
vwJ7W_ 0.5 12.7 (19)
6
Equation 19 calculated the wall thickness of the 3a sub-segment of the BSRO pipelines network (Warri-
Shagamu). We will adopt 0.5 inches as wall thickness on all other pipelines. We will also use the pipe material
cost of $800 per tonne as sourced from Shahi Menon (2005), Mohitpour et al (2003) and Tianjin Yuheng Steel
Co., Ltd. [26] [57] [12]. The PMC of the three segments and sub-segments of the BSRO are presented in table 2.
Table 2: Pipeline Material Cost of BSRO pipelines
Pipe PMC ($)
Length Pipeline material cost
Pipeline Diameter
(km) Thickness (mm) ($/metric
ton)
1. South-North:
1a. Calabar to Ajaokuta 56 490 12.7 800 5,302,892.11
1b Ajaokuta to Kaduna 48 495 12.7 800 4,367,256.70
2. Interconnector: Obiafu-
42 100 12.7 800 732,312.48
Oben Node
3. Four segments of West-
Escravos ext.
3a: Warri-Shagamu (offshore) 42 200 12.7 800 1,464,624.96
49
Journal of Economics and Sustainable Development www.iiste.org
ISSN 2222-1700 (Paper) ISSN 2222-2855 (Online)
Vol.8, No.2, 2017
50
Journal of Economics and Sustainable Development www.iiste.org
ISSN 2222-1700 (Paper) ISSN 2222-2855 (Online)
Vol.8, No.2, 2017
51
Journal of Economics and Sustainable Development www.iiste.org
ISSN 2222-1700 (Paper) ISSN 2222-2855 (Online)
Vol.8, No.2, 2017
52
Journal of Economics and Sustainable Development www.iiste.org
ISSN 2222-1700 (Paper) ISSN 2222-2855 (Online)
Vol.8, No.2, 2017
53
Journal of Economics and Sustainable Development www.iiste.org
ISSN 2222-1700 (Paper) ISSN 2222-2855 (Online)
Vol.8, No.2, 2017
following tables. The summary of capital cost elements of other gas pipeline options will be presented
accordingly. Analytical comparison of the costs and benefits of these gas pipelines options will be presented.
54
Journal of Economics and Sustainable Development www.iiste.org
ISSN 2222-1700 (Paper) ISSN 2222-2855 (Online)
Vol.8, No.2, 2017
and unviable option is the NRO pipelines which have the negative NPV of $479 million, which means the
pipelines are not viable. The hierarchy of the viability of these projects based on NPV are presented in figure 5
below.
NPV ($)
3,000,000,000.00
2,500,000,000.00
2,000,000,000.00
1,500,000,000.00
1,000,000,000.00
500,000,000.00
0.00
BSRO All pipelines BNRO BRO SRO NRO
-500,000,000.00 route
options
-1,000,000,000.00
60.00% IRR %
50.00%
40.00%
20.00%
10.00%
0.00%
BSRO All pipelines BNRO BRO SRO NRO
route options
55
Journal of Economics and Sustainable Development www.iiste.org
ISSN 2222-1700 (Paper) ISSN 2222-2855 (Online)
Vol.8, No.2, 2017
option and BNRO pipelines are ranked the fourth and fifth by the IRR, which have an IRR of 28.44% and 23.98%
respectively. The least viable option is the NRO pipelines, which have IRR rate of 11%. All the IRR were above
the discount rate expect the IRR of NRO pipelines.
The IRR shows the rate of return where the NPV equals to zero, this means that the BSRO and SRO has
the potential of offering higher investment return at breakeven. In other word, the IRR can be viewed as the
maximum percentage rate that can be earned on each dollar invested at a period [68]. The two methods have
discrepancy in ranking the projects, which is possible because of a possible difference in the size of the
investment, or timing of the positive net cash flows [69]. In this scenario, the discrepancy is attributed to the
differences in the size of the businesses as well as the size of the cash flows, as the NPV accounts for difference
between discounted cash flows and initial investment, which means higher initial investment might cause lower
NPV, and higher cash flows can return higher NPV, while the IRR estimates the rate of return at which the
discounted cash inflows will equate the initial cash outflows. Therefore, both techniques might have different
ranking order. However, some recommended to go by NPV method, as the IRR rate is an arbitrary rate, which
signals the maximum possible rate of rate, which might not be attainable given the business scenarios [70] [71]
[72]. IRR favours investments that return initial investment quicker, which makes it more agreeable to the
Payback period method [68].
The Payback period ranking is similar to the ranking of the IRR, BSRO pipelines have the lowest
payback period of 2.60 years, and then BRO pipelines have payback period of 4.80 years. Others have payback
period of 2.83, 5.62 and 7.49 years for SRO, all pipeline route option and BNRO pipelines respectively. NRO
pipelines are not recoverable, so their initial investment costs cannot be recovered within the operational period.
All the three accounting indicators suggest that BSRO pipelines are the most viable option
Joining the ranking outcome of NPV, IRR and Payback period, figure 7 illustrates the heights of the
ranking of these investments
50.38%
28.44% 47.00%
2.43 31.55% 0
1.95 23.98% 0.95
1.02 11.00%
1.00
BSRO
BNRO
BRO
SRO
NRO
OPTIONS
-2.60
-5.62 -2.83
-4.80 -0.48
-7.49
坐标轴标题
Figure 7: Ranking of the gas pipeline route options using the three accounting indicators
From figure 7, the top two business investments going by the top height above zero when combing the
effects of IRR and NPV together are; BSRO and all gas pipelines option. Considering the green bar, which is the
payback period and is expected to be shorter for the most viable option, the BSRO pipelines still have shorter
height of -2.60, which means it has shorter payback period and more preferred than all the other options. NPV is
largely the most considerable method compare to other techniques as explained earlier as it accounts for exact
56
Journal of Economics and Sustainable Development www.iiste.org
ISSN 2222-1700 (Paper) ISSN 2222-2855 (Online)
Vol.8, No.2, 2017
magnitude of the return and it is more precise estimate of the returns than the IRR [71] [72]. Relying on one
criteria may not reflect the effect of other criteria in the judgement, which could be influential in ranking the
projects.
Therefore, to harmonise the different ranking positions based on these criteria, the ranking positions are
added and the pipeline with the lowest ranking position will be the most viable. The lowest point matters because
lower points mean most viable, for example, the most viable option at a time is always ranked as number 1.
Table 10 shows the ranking position of each of the gas pipeline options.
Table 2: Ranking positions based on the three profit indicators
Pipelines Ranking position
BSRO
NPV 1
IRR 1
PAYBACK PREIOD (YRS) 1
Points 3
All possible pipeline routes option
NPV 2
IRR 4
PAYBACK PREIOD (YRS) 4
Points 10
BNRO
NPV 4
IRR 5
PAYBACK PREIOD (YRS) 5
Points 14
BRO
NPV 3
IRR 3
PAYBACK PREIOD (YRS) 3
Points 9
SRO
NPV 5
IRR 2
PAYBACK PREIOD (YRS) 2
Points 9
NRO
NPV 6
IRR 6
PAYBACK PREIOD (YRS) 6
Points 18
Table 10 shows the different ranking positions of each of the pipeline options as indicated by the three
accounting methods. For each method, ranking was made, with the most viable being the number 1. Summing
the ranking positions for each project, the BSRO pipelines have the lowest ranking points, which is 3. This is
because it was ranked 1st in all the three accounting indicators. This makes it the most viable option among the
six options based on the harmonised ranking positions. The second most viable options based on this ranking are
the BRO and SRO pipelines, which both have the harmonised ranking points of 9. All gas pipeline options and
BNRO are ranked 3rd and 4th respectively, with the harmonised ranking points of 10 and 14 respectively. The
Least and unviable is the NRO pipelines, which has the harmonised ranking point of 18.
Therefore, BSRO pipelines are the most viable option among the six projects. All the project options
except the NRO pipelines were viable at the base scenario. It is recommended not to consider this option (NRO)
alone, even in the future, the best recommendation is to combine it with the BRO pipelines, since BRO pipelines
are likely to be constructed soon, it is advisable to include the NRO pipelines. This academic finding justifies the
intention of the government to consider investing on the BSRO pipelines.
However, in terms of coverage and ability to supply more gas to more locations, the all gas pipeline
option is more recommendable. The all gas pipeline option covered the whole country, and this enables spread of
potentials for gas development sites and job creations. The spread of the gas power turbines can be well achieved
if all the gas pipeline options are considered. Concentration of industries in the south has caused migration from
the north, and making the northern economy less active. This is because access to industrial inputs are easier in
the south as the oil and gas production take place in the region. The electricity shortages was also partly
57
Journal of Economics and Sustainable Development www.iiste.org
ISSN 2222-1700 (Paper) ISSN 2222-2855 (Online)
Vol.8, No.2, 2017
attributed to the low transmission capacity and transmission losses. Around 20% of the existing transmission
capacities are not operational [73], and 8.05% of electricity generated is lost in the process of transmission [74].
The over reliance on the transmission networks can be highly reduced if the all gas pipeline routes option is
constructed ,and as a result, more distributed gas power turbines can be constructed, which can be connected to
the distribution lines. This will enhance sub-regional power generations and investment in distribution lines, and
will motivate establishment of industries across the country, and avoid unnecessary migration of labour forces.
This will also facilitate spread of higher productivity of the industrial, commercial and residential sectors in
every region as the access to natural gas is equally provided. The value addition as a result of the wide spread of
the gas supply, which can be achieved through all the gas pipeline route option can offset the lower viability of
the option compare to the BSRO pipelines.
The all gas pipeline route option is equally viable, and its NPV is not much lower than the BSRO
pipelines, its IRR is 28.44%, and has payback period of 5.62 years, as such, it is worth considering. Therefore,
the all gas pipeline routes option is highly recommended. If all the gas pipelines routes are considered together,
the NRO pipelines will not be singled out, which if singled out, the NRO pipelines will be unviable.
58
Journal of Economics and Sustainable Development www.iiste.org
ISSN 2222-1700 (Paper) ISSN 2222-2855 (Online)
Vol.8, No.2, 2017
Reference
1. Yar'adua, L.A., The Nigerian Gas Master-PlanEngr, Group Managing DirectorNigerian National
Petroleum Corporation, Editor. 2007.
2. International Energy Agency, Africa Energy outlook, in A Focus on Energy Prospect in Sub-Saharan
Africa. 2014, OECD/IEA, 2014.
3. BP, BP Statistical Review of World Energy 2015.
4. Lu, X., J. Salovaara, and M.B. Mcelroy, Implications of the recent reductions in natural gas prices for
emissions of CO2 from the US power sector. Environmental science & technology, 2012. 46(5): p.
3014-21
5. Russell, P.R., Global energy forecasts: Robust growth in developing countries, fueled by Coal. ENR
(Engineering News-Record), 2012. 268(6): p. 2.
6. Adamu, A. and D. Roddy. How Nigeria can convert from the leading Natural Gas Exporter to leading
Natural Gas Consumer? in 51st meeting of the EWGCFM and 1st conference of the RCEM & ICSTF.
2013. ESCP Europe Campus, London, United Kingdom. 16-18 May, 2013.
7. EIA. International Energy Statistics Electricity capacity 2014 [cited 2014 20th January]; Available
from:
http://www.eia.gov/cfapps/ipdbproject/iedindex3.cfm?tid=2&pid=alltypes&aid=7&cid=NI,&syid=2008
&eyid=2012&unit=MK.
8. Ibitoye, F.I. and A. Adenikinju, Future demand for electricity in Nigeria. Applied Energy, 2007. Vol.
84(5): p. 492-504.
9. Alokolaro, O. and F. Alghali. Gas Utilization in Nigerian Gas Master Plan (NGMP). Energy and
Natural Resources Group 2015 [cited 2015 14th January]; Available from: http://www.advocaat-
law.com/userfilesadvocaat/file/Advocaat-Gas%20Masterplan.pdf.
10. Ige, D.O., The Nigerian Gas Master Plan-Investor Road Show, N.N.P.C. Group Managing Director,
Editor. 2008.
11. Amirat, A., C. Mohamed, A., and K. Chaoui, Reliability assessment of underground pipelines under the
combined effect of active corrosion and residual stress. International Journal of Pressure Vessels and
Piping, 2006. 83(2): p. 107-117.
12. Shashi, E.M., Gas Pipeline Hydraulics. Chapter 10, ed. T.a. Francis. 2005, 6000 Broken Sound
Parkway NW, Suite 300: Tylor and Francis group.
13. Nigerian National Petroleum Corporation, History of the Nigerian Petroleum Industry B. information,
Editor. 2013, NNPC.
14. Nigerian National Petroleum Corporation, Nigerian Gas Master Plan, M. Ventures, Editor. 2013,
NNPC.
15. Awhotu Ese, Nigerian, Algerian Officials Discuss Saharan Gas Pipeline, in Leadership. 2009: Nigeria.
16. Nwaoha, C. and D.A. Wood, A review of the utilization and monetization of Nigeria's natural gas
resources: Current realities. Journal of Natural Gas Science and Engineering, 2014. 18: p. 4120-4432.
17. Ukpohor, E.T.O., Nigerian gas master plan: Strengthening the Nigeria gas infrastructure blueprint as a
base for expanding regional gas market, in 24th World Gas Conference 2009, WGC 2009, International
Gas Union World Gas Conference Papers, Editor. 2009: Buenos Aires. p. 5152-5169.
18. Ukpohor, E. and O. Theophilus, Nigerian Gas Master Plan: Strengthening the Nigeria Gas
Infrastructure Blueprint as a base for expanding regional Gas Market, in World Gas Conference. 2010,
Nigeria Liquefied Natural Gas Company: Bonny Island, Nigeria.
19. Trans-Sahara Pipeline deal sealed. Pipeline and Gas Journal, 2009. 236(8).
20. Hamer, P., West African gas pipeline. Oil and Gas Journal, 2012. 110(6).
21. WAPco, The Pipeline system. 2012, West African Gas Pipeline Company website: Nigeria.
22. Nigeria Pipelines map. Crude Oil (petroleum) pipelines - Natural Gas pipelines - Products pipelines: .
2008 [cited 2012 December]; Available from:
http://www.theodora.com/pipelines/nigeria_oil_gas_and_products_pipelines_map.html.
23. theodora.com. Nigeria Pipelines map. Natural Gas pipelines 2008 [cited 2013 21st September];
Available from: http://www.theodora.com/pipelines/nigeria_oil_gas_and_products_pipelines_map.html.
24. Nigerian Gas Company Limited. Existing pipeline System. 2012 [cited 2012 December 2012];
Available from: http://www.nnpcgroup.com/nnpcbusiness/subsidiaries/ngc.aspx.
25. Nigerian Gas Company Limited. Future and ongoing Projects. 2012 [cited 2012 16th December,
2012]; Available from: http://www.ngc-nnpcgroup.com/projects/future-projects.
26. Mohitpour, M., H. Golshan, and A. Murray, Pipeline Design and Construction. Vol. 2nd edition. 2003,
New York: ASME Press.
27. Yipeng, Z. and R. Zhenhua, Pipeline compressor station construction cost analysis. Int. J. of Oil, Gas
and Coal Technology, 2014. Vol. 8(1): p. 41-61.
59
Journal of Economics and Sustainable Development www.iiste.org
ISSN 2222-1700 (Paper) ISSN 2222-2855 (Online)
Vol.8, No.2, 2017
28. Borraz-Sánchez, C. and D. Haugland, Optimization methods for pipeline transportation of natural gas
with variable specific gravity and compressibility TOP 2013. Vol 21(3): p. 524-541.
29. Petronijevič, P., et al., Methods of calculating depreciation expenses of construction machinery. Journal
of Applied Engineering Science 2012. Vol. 10(1): p. 43-48.
30. Halit, Ü. and D. Şebnem, Optimization for design and operation of natural gas transmission networks.
Applied Energy, 2014. Vol. 133(November): p. 56-69.
31. Elliott, B. and J. Elliott, Financial accounting and reporting. 17th ed. 2015: Harlow : Pearson
32. Jackson, S.B., The effect of firms' depreciation method choice on managers' capital investment
decisions. Accounting Review, 2008. 83(2): p. 351-376.
33. Chyong, C.K.C., N. Pierre, and M. David, The Economics of the Nord Stream Pipeline System,
Electricity Policy and Research Group, Editor. 2010, University of Cambridge, 2010: Economic and
Social Research Council. p. 1-40.
34. Horngren, C.T., S.M. Datar, and G. Foster, Cost accounting: A managerial emphasis. 11th ed. 2002:
Prentice Hall.
35. Krey, W. and Y. Minullin, Modelling compeition between natural gas pipeline projects to China.
International journal of global environmental issues, 2010. 10(1): p. 143-171.
36. ECT, Gas transit tarrifs in selected energy charter treaty countries. 2006, Energy charter secretariat.:
Brussels.
37. Reinicke, K.M., New strategies for the operation and maintenance of pipeline systems. Oil and Gas
European Magazine, 2000. 26(2): p. 20.
38. Financial times. Equities. Oando PLC 2015 [cited 2015 7th July]; Available from:
http://markets.ft.com/research/Markets/Tearsheets/Financials?s=OANDO:LAG.
39. Magni, C.A., An Average-Based Accounting Approach to Capital Asset Investments: The Case of
Project Finance. European Accounting Review, 2015.
40. Buus, T., A general free cash flow theory of capital structure. Journal of Business Economics and
Management, 2015. 16(3): p. 675-695.
41. Taxrates cc. Nigeria Tax rates. 2013 [cited 2013 3rd May, 2013]; Available from:
http://www.taxrates.cc/html/nigeria-tax-rates.html.
42. Central Bank of Nigeria, Money Market Indicators (In Percentage). 2015.
43. Trending Economics. Lending interest rate (%) in Nigeria. World Bank Indicators - Nigeria - Interest
Rates 2015 [cited 2015 26th June]; Available from: http://www.tradingeconomics.com/nigeria/lending-
interest-rate-percent-wb-data.html.
44. Peterson, P.P. and F.J. Fabozzi, Capital Budgeting Theory and Practice. 2004: Hoboken : Wiley.
45. Trending Economics. Nigeria Government Bond Yield. 2015 [cited 2015 7th July]; Available from:
http://www.tradingeconomics.com/nigeria/government-bond-yield.
46. Central Bank of Nigeria. Government Securities - FGN Bonds. Government securities 2015 [cited 2015
5th June]; Available from:
http://www.cenbank.org/rates/GovtSecuritiesDrillDown.asp?beginrec=1&endrec=10&market=Bonds.
47. Stalwart report, Rising equity risk premium puts Nigerian Stock Market on the watch list, in Market
development. 2015.
48. Aswath, D. Country Default Spreads and Risk Premiums. Country Risk Premium 2015 [cited 2015
16th June]; Available from:
http://pages.stern.nyu.edu/~adamodar/New_Home_Page/datafile/ctryprem.html.
49. Financial times. Equity Screener. Fund & ETF screener 2015 [cited 2015 8th July]; Available from:
http://markets.ft.com/screener/screenerResults.asp.
50. Oke, B.O., Capital Asset Pricing Model (CAPM): Evidence from Nigeria. Research Journal of Finance
and Accounting, 2013. Vol.4, (No.9, 2013 ): p. 17-26.
51. Nwude, E.C., Is CAPM a Good Predictor Of Stock Return In The Nigerian Packaging Stocks? .
Research Journal of Finance and Accounting, 2013. Vol. 4(No.15).
52. MacAllister, E.W., Pipeline Rules of Thumb Handbook. 8th ed. Manual to quick and accurate solution
to everyday pipeline engineering problems. 2009: Elsevier.
53. Prasad V.S.N. Tallapragada, Nigeria’s Electricity Sector- Electricity and Gas Pricing Barriers. 2009:
International Association for Energy Economics.
54. Okafor, C., NGC to get $0.80/mcf transportation cost, in ThisDayLive. 2015.
55. Alike, E., New Price for Domestic Gas Takes Effect January 1, 2015, in This Day Live. 2014.
56. EIA, Natural Gas Pipeline Capacity & Utilization US energy Information Administration, Editor. 2008.
57. Tianjin Yuheng Steel Co. Ltd. price gas pipe. 2013 [cited 2013 10th May]; Available from:
http://www.alibaba.com/showroom/price-gas-pipe.html.
58. United States Agency for Internation Development, Natural Gas Value Chain: Pipeline Transportation,
60
Journal of Economics and Sustainable Development www.iiste.org
ISSN 2222-1700 (Paper) ISSN 2222-2855 (Online)
Vol.8, No.2, 2017
61
Journal of Economics and Sustainable Development www.iiste.org
ISSN 2222-1700 (Paper) ISSN 2222-2855 (Online)
Vol.8, No.2, 2017
APPENDICES
Appendix A: Base Route Option (BRO)
1b
1a
62
Journal of Economics and Sustainable Development www.iiste.org
ISSN 2222-1700 (Paper) ISSN 2222-2855 (Online)
Vol.8, No.2, 2017
63
Journal of Economics and Sustainable Development www.iiste.org
ISSN 2222-1700 (Paper) ISSN 2222-2855 (Online)
Vol.8, No.2, 2017
*NRO cannot exist without the BRO, so its business model is established on the assumption that the BRO is
already constructed.
64
Journal of Economics and Sustainable Development www.iiste.org
ISSN 2222-1700 (Paper) ISSN 2222-2855 (Online)
Vol.8, No.2, 2017
Appendix H: Specification of the combination of BRO and SRO pipelines (BSRO) [1]
Pipeline Diameter Length (km)
1. South-North:
1a Calabar to Ajaokuta 56” 490
1b Ajaokuta to Kaduna 48” 495
2. Interconnector: Obiafu-Oben Node 42” 100
3. Four segments of West-Escravos extensions
65
Journal of Economics and Sustainable Development www.iiste.org
ISSN 2222-1700 (Paper) ISSN 2222-2855 (Online)
Vol.8, No.2, 2017
4d 4c
4b
1b
4a
1a
66
Journal of Economics and Sustainable Development www.iiste.org
ISSN 2222-1700 (Paper) ISSN 2222-2855 (Online)
Vol.8, No.2, 2017
Appendix L: Specification of Combination of all the possible Pipeline routes [1] [16]
Pipeline Diameter Length
(km)
1. South-North:
1a Calabar to Ajaokuta 56” 490
1b Ajaokuta to Kaduna 48” 495
2. Interconnector: Obiafu-Oben Node 42” 100
3. Four segments of West-Escravos
extensions
3a: Warri-Shagamu 42“ 200
3b: Ore-Ondo-Ekiti 24” 125
3c:Shagamu-Ibadan-Osun-Jebba 24“ 321
3d: Shagamu -Papalantro 16“ 40
4. Future potential pipelines:
4a: Enugu-Makurdi-Yola 24” 874.8
4b:Kaduna-Jos-Gombe 24” 501.3
4c: Kano-Maiduguri 24” 593.2
4d: Zaria-Funtua(then to 24” 768.3
Katsina)-Gusau-Sokoto-Birnin Kebbi
67