Report PDF
Report PDF
Report PDF
March 2018
Subsea Engineering Opportunity: International Market Insights March 2018
Contents
1. Introduction .................................................................................................................... 3
2. Subsector overview ........................................................................................................ 5
2.1. Decommissioning activities ..................................................................................... 5
2.2. Well plugging and abandonment ............................................................................. 7
2.3. International regulations .......................................................................................... 9
2.4. Financing O&G decommissioning ......................................................................... 10
3. Subsea engineering synergies ..................................................................................... 12
3.1. Operator project management .............................................................................. 12
3.2. Well plugging and abandonment ........................................................................... 13
3.3. Facilities / Pipelines making safe .......................................................................... 14
3.4. Sub-structure removal ........................................................................................... 14
3.5. Subsea infrastructure ............................................................................................ 15
3.6. Site remediation .................................................................................................... 15
3.7. Monitoring ............................................................................................................. 16
3.8. Areas for innovation .............................................................................................. 16
4. Global market with locations of interest ........................................................................ 17
4.1. Europe .................................................................................................................. 18
4.2. North and Central America.................................................................................... 22
4.3. South America ...................................................................................................... 24
4.4. Africa .................................................................................................................... 25
4.5. Asia and Pacific .................................................................................................... 26
Appendix: List of Acronyms ................................................................................................. 29
1. Introduction
This report is part of a series of ten reports considering the opportunities for the Scottish oil
and gas (O&G) subsea supply chain in other subsea and related markets. The report is a
desk review considering the international activity of each of the sectors including where there
is current activity and where there is the potential for activity based on published targets and
available resource and opportunity. The report also considers the particular synergies of the
given sector and the subsea oil and gas supply chain. These opportunities cover areas
where there is a direct cross over and also where there are opportunities for collaboration to
provide innovative solutions.
Decommissioning overall
The aim of O&G decommissioning is to seal off a well permanently from any possible
escapes of hydrocarbon or water, or cross-flows into other formations, and clearing the
seabed and water column from any O&G infrastructure. Decommissioning is a relatively new
sector, but is the final stage in the lifecycle of oil and gas (O&G) operations. The programme
of activity includes the removal, where applicable, of a fixed platform or floating vessel e.g.
FPSOs; any moorings, risers, umbilicals or conductors; subsea infrastructure; the plugging
and abandonment (P&A) of subsea wells and subsequent onshore dismantling and disposal.
Onshore wells are not being considered as part of this report. There is a significant
crossover between the O&G subsea supply chain and O&G decommissioning both in terms
of technology requirements, but also in terms of business practices and ‘language’.
Current good practice in the O&G sector is to have a decommissioning plan in place when a
well is being drilled. However, this has not always been the case and where no plans were
considered during drilling the resulting decommissioning programme is likely to be more
complex and include more investigatory activities within the schedule. Companies can often
view it as economically beneficial to put off decommissioning as estimating decommissioning
costs is difficult (every well is different) and there is no financial return on the expenditure.
However, as time passes the installation will degrade; the understanding of the well
decreases; and regulations may become more onerous all resulting in increased costs for
the decommissioning programme.
Subsea decommissioning
The visible part of decommissioning is the removal of infrastructure and their transport to
shore followed by dismantling and recycling, this accounts for approximately 1.2 percent of
the spend on decommissioning. However, there is a larger unseen portion that occurs in the
subsea environment. All activity that occurs below sea level will be covered in this report –
the preparation and removal of infrastructure, particularly in subsea fields, and the plugging
and abandonment of subsea wells.
Global activity
O&G decommissioning is a growing area as offshore infrastructure, particularly in the North
Sea and the Gulf of Mexico, ages and moves beyond its operational life and fields become
uneconomic. Decommissioning in the GOM has so far been predominately in shallow
waters, but decommissioning activity is now occurring in deep water as well.
Decommissioning of the infrastructure and permanent sealing of associated subsea wells is
the next stage in the O&G lifecycle. Table 1 below gives an overview of decommissioning
expenditure globally, highlighting where most of the activity will be in the next 10 years. In
the mid-term markets, for example West Africa and Asia Pacific, work is needed on the
development of appropriate and efficient regulation and guidelines for decommissioning.
These regions can learn from Scotland, particularly for the deeper water fields as well as
provide potential collaboration opportunities for deploying Scottish technologies and
expertise.
2. Subsector overview
Offshore oil and gas production first began in the 1940s in the Gulf of Mexico 1 and in the
1960s in the North Sea 2 with activity now happening globally and new fields still being
discovered and developed.
Oil and gas producing fields employ either fixed or floating structures (e.g. steel jackets,
semi-submersibles or spars, amongst others) connected to multiple wells. Subsea wells
(those with the wellhead and associated infrastructure on the seabed) were first used in the
early 1960s and tend to be used in deep water situations. Many subsea wells can be tied-
back to a single fixed or floating platform, or even exporting the oil and gas straight to shore.
For example, the Perdido oil field in the Gulf of Mexico has approximately 30 wells from
three fields tied-back to a single spar platform and the Orman Lange field in the Norwegian
Continental Shelf (NCS) has 50 subsea wells that are grouped at production stations and the
gas pumped directly to the shore. The Brent field in the UKCS had four platforms with 154
wells which are currently undergoing decommissioning.
Given the age of oil and gas development globally, particularly in the North Sea, Gulf of
Mexico and West Africa, with many fields exceeding 40 years of operation, combined with
tightening regulations on offshore structures, decommissioning is a rapidly growing sector.
Cessation of production (CoP) mostly occurs at a point where a field becomes uneconomic,
such that it costs more to extract the hydrocarbons than they can be sold for. A CoP decision
is therefore impacted by oil prices and trends as well as the available hydrocarbons
remaining in the reservoir. A CoP decision may also be made where there has been a
significant issue, e.g. with the reservoir or infrastructure, that would be uneconomic to rectify
based on the likely amount of hydrocarbon that could still be extracted.
The following sub-sections cover the activities associated with decommissioning in a subsea
context and the international regulations that cover this area.
The chart in Figure 1 shows the stages of work involved in a decommissioning programme
as well as key milestones such as CoP, when the asset is hydrocarbon free and when
materials are delivered to shore for recycling.
Figure 1: Chart showing the decommissioning stages. Source: Scottish Enterprise Oil and Gas
Decommissioning Action Plan.
These activities will be considered in greater detail in Section 3 where the synergies with the
subsea oil and gas supply chain will be analysed. As can be seen in Figure 2 well plugging
and abandonment (P&A) is the biggest cost in a decommissioning programme, at 49
percent, based on UK figures, and it will therefore be the main focus of this report. The other
subsea elements such as the planning and preparation as well as the cleaning,
disconnection and removal of subsea infrastructure will also be considered.
Well P&A
Well plugging and abandonment (P&A) includes, platform wells (those that are operated
from a fixed platform); subsea wells (those where the wellhead is on the seabed, and
hydrocarbons are removed to a floating vessel, or tied-back to platform infrastructure); and
suspended exploration and appraisal (E&A) wells.
The cost of P&A across the three types of well varies, as well as cost variations from water
depth, weather, reservoir type, age, condition and complexity of operations. 3 An overview of
P&A costs (in 2016 money) in the UK North Sea regions (Table 2) and in the Gulf of Mexico
(GOM), USA (Table 3) are below. The UK industry set itself a target to reduce the cost of
well P&A by 35% from 2015 levels, these targets are included in Table 2 below. 4
Table 2: Average and cost range of well P&A in the UKCS, including industry cost reduction target.
Source: Oil & Gas UK, Decommissioning Insights 2017; OGA.
Location Well P&A 2017 average 2017 range 35% cost
(per well) (per well) reduction from
2015.
Central and Platform wells £4.9 million £0.6 - £14.8 £2.6 million
Northern million
North Sea Subsea wells £10.1 million £2.9 – £24.9 £6.4 million
and West of million
Shetland Suspended E&A £6.9 million £0.6 - £36.8 £5.1 million
wells million
Southern Platform wells £2.8 million £1.3 – £7.6 £2.0 million
North Sea million
and Irish Subsea wells £7.8 million £3.3 – £11.4 £6.2 million
Sea million
Suspended E&A £3.4 million £0.2 – £14.4 £5.7 million
wells million
Table 3: Cost estimates for the decommissioning of different well types in the GOM, USA. Source:
Bureau of Safety and Environmental Enforcement (BSEE) 5
Type of well Water depth Cost estimate by BSEE
Platform well (fixed) ≤ 400 ft (≤122m) $450,000 (£318,000)
Platform well (fixed) where ≤ 400 ft (≤122m) $150,000 (£106,000)
well has been temporarily
abandoned
Platform well (fixed) >400 ft (>122m) $565,000 (£399,000) at 401 ft
(122m) to $770,000 (£544,000) at
1400 ft (426m)
Platform well (floating) All $2,056,000 (£1.5m)
Platform well (floating) All $1,325,000 (£936,000)
where well has been
temporarily abandoned
Subsea well ≤ 400 ft (≤122m) $2,500,000 (£1.8m)
Subsea well >400 ft (>122m) $13,250,000 (£9.4m)
Workshop, 2016
One of the largest impacts on cost of well P&A is the length of time the campaign takes, due
to the day-rates of the vessels and rigs required. An average well P&A in the North Sea will
take approximately 45 days, with examples ranging from 21 - 125 days. Understanding the
condition of the well, in addition to information on the design of the well, allows work to be
planned in advance, rather than time lost through having to tackle situations on an ad hoc
basis rather than as a programme, during the P&A process. 6 Examples of cost breakdowns
from other oil and gas basins, namely the Pacific Outer Continental Shelf (OCS) in the USA,
have much lower P&A costs, this can be in part attributed to a difference in classification of
tasks within a work breakdown structure, but also, and more significantly, the time taken to
perform P&A. Well P&A is calculated as being approximately 18 percent of the cost in the
Pacific OCS Region (POCSR), with P&A activities for a well taking 3-5 days, compared to
the 45 days seen in the North Sea. The difference in these figures are due to shallower
waters, less complex wells and more predictable metocean conditions. 7
Costs have been coming down in P&A due to learning and new techniques. Further cost
reduction can be achieved and Oil & Gas UK have identified the following areas of potential3:
- Using a campaign approach. This would involve multiple well P&A’s in an area being
combined into one campaign to allow the mobilisation costs to be spread across a
number of wells. This could also be combined with cross-operator collaboration to
increase the number of wells in a single campaign. Part of the campaign should be
ensuring that the activity schedule is optimised, e.g. minimising the distance the
drilling rig must travel between wells.
- Development of innovative solutions through investment in technology, particular
themes being explored through an OGTC call are new barriers including placement
and materials, verification of permanent barriers and optimising P&A scope.
- Where possible using rigless methods, or once the topside is removed using a
workover rig. Rigless technologies could enable savings of up to 50% on the overall
P&A costs. 8
- Early removal of subsea infrastructure to reduce congestion near the well head.
- Adopting a risk-based approach to allow the scope to be determined based on the
risk profile of the well. A risk-based approach can also be used to help encourage the
uptake of new technology.
- Assessment of the well condition can be done through using a light well intervention
vessel to log well conditions prior to the start of a campaign.
Wells are classified by their condition and therefore the level of intervention required for P&A
activities. In the UK, there are guidelines that have categories, with increasing levels of
intervention. These are summarized in Table 4 below:
6 Handel, C., Abandonment of obsolete wells and installations on the Norwegian Continental Shelf,
University of Stavanger, 2014.
7 BSEE, Presentation of the 2015 decommissioning cost estimate for the POCSR platforms, 2015.
8 BCG, Preparing for the Next Wave of Offshore Decommissioning, 2018
2004
12 Campbell, D., and Twomey, B., Decommissioning of Large Offshore Installations Effect of L&R and
Major Risk Identification, Decommissioning & Abandonment Summit, 2017.
13 Offshore installations, OSPAR website, accessed April 2017, https://www.ospar.org/work-
areas/oic/installations
14 ASCOPE website, accessed April 2018, http://www.ascope.org/Projects/Detail/1061
project, for example during exploration they are with the operator; during production they are
shared through a Production Sharing Agreement; and often in the final stages, including
decommissioning, liabilities are returned to the NOC. 15
Decommissioning is often supported by the state through tax breaks for operators which
indirectly pays for the decommissioning. Depending on the country, this can be for example
in Europe, between 50 and 80 percent of the decommissioning cost. This level of support is
a push for ensuring value for money in decommissioning and reducing costs as far as
possible as the burden for the cost is largely placed upon the taxpayer. In some countries,
e.g. Denmark, the security that is provided as part of the licence conditions also includes
covering the decommissioning phase. 16,17
In the USA, there have been recent changes which are still in discussion, around the
provision of additional securities for Outer Continental Shelf (OCS) leases, pipeline rights of
way and rights of use and easement. Previously decommissioning was excluded from the
additional securities calculation where there was a sufficiently financially secure leasee or
co-leasee (whereby they could self-insure), however, the Bureau of Ocean Energy
Management (BOEM) now considers that the previous calculations are outdated and
insufficient. The new Notice to Leasees and Operators, published by BOEM in 2016, ‘NTL
No. 2016-N01’ now supersedes NTL No. 2008-N07. 18
15 World Bank, World Bank Multitaskholder Initiative, Towards Sustainable Decommissioning and
Closure of Oil Fields and Mines: A Toolkit to Assist Government Agencies, 2010.
16 BCG, The North Sea’s $100 Billion Decommissioning Challenge, 2017
17 Getting the Deal Through, Oil Regulation, Denmark, 2018
18 BOEM, Notice to lessees and operators of federal oil and gas, and sulfur leases, and holders of
pipeline right-of-way and right-of-use and easement grants in the outer continental shelf, 2016
The programme preparation will have to justify the decommissioning activities specified,
such as what will be removed, decontaminated, ‘reefed’ and/or repaired. It is therefore
important to know the condition of the wells and infrastructure during the programme
preparation period. Gathering of baseline data about the project, includes information such
as:
- Environmental surveys
- Technical engineering surveys
There are particular synergies with the oil and gas subsea supply chain in this stage of
decommissioning through:
- Project management
The O&G subsea supply chain has plentiful experience of managing complex subsea
operations. This is a skill set that will cross over directly with the project management
of decommissioning activities. Although a move to decommissioning projects is a
change in emphasis in the type of project, many areas such as health and safety
practices, offshore operations and personnel management are all common
considerations. Experience in O&G projects which will include work practices and
shared technical language is a benefit here. Decommissioning has an added push for
showing value for money throughout the programme.
- Environmental services
Environmental studies will be used to establish the baseline for the economic and
environmental impact assessments. These impact assessments will describe the
case for removal (including method) or leaving in-situ (including trenching or rock
dumping) of offshore pipelines. These studies have synergies with the early work in
O&G exploration where studies are completed to understand the benthic
environment.
19 ICF International, Decommissioning methodology and cost evaluation, prepared for BSEE.
These studies also include metocean studies to establish sea conditions for
operations, and geological studies to understand reservoir conditions in the wells to
be abandoned.
- Technical engineering studies
These studies are used to determine the structural integrity of the installations that
are to be decommissioned to allow a suitable method to be designed for their
removal. This will also allow plans to be made to tackle hard to reach parts of the
installation that may need cleaning, disconnecting or dismantling as well as making
areas safe to work.
These surveys are a part of all O&G work and therefore have a strong synergy.
- Well P&A
This covers the actual plugging and abandonment of the well. The activities include using a
rig, or rigless solutions depending on the complexity of the well, see Table 4; any repair work
to the annular cement, which could also include milling and the removal of casing and
tubing; the placement of barriers to plug the well; and finally, the verification of these barriers
to ensure they are creating a permanent seal.
Many technologies will be used in this, including those with similarities to the drilling process,
including those with cementing capabilities, as well as the skills to deal with casings. New
technologies are being developed in terms of new barriers, e.g. using resins instead of
cement or lasers to melt the casing and rock forming a permanent seal; and new techniques
e.g. thermal for cutting casings.
20 Oil & Gas UK, Guidelines on decommissioning cost estimation, Issue 3, 2013
- Conductor recovery
Conductor recovery is an element of the P&A process that can be done with a rig, or in a
complex rigless operation. There may be a requirement for milling, cutting and/or lifting as
part of these activities.
GOM 2017
lines and anchors will need to be considered as part of the sub-structure removal.
Considering steel jackets, these may be removed or, in some cases, the footings or whole
structures left in place. In the case of the latter, sometimes known as ‘rigs to reefs’ the sub-
structure is toppled so as to ensure that there is no impedance to vessel movement, etc. the
regulations on toppling vary between countries. Where a sub-structure is to be removed the
structure may be removed in a single lift, or through dismantling into smaller pieces for
multiple lifts. The decision as to which route to take will depend on the weight of the sub-
structure to be removed, and the availability of the appropriate class of crane to carry out the
lift.
Where the sub-structure is being dismantled divers and/or ROVs will be used for inspection
and for carrying out the cutting operations. Preparation work including making the structure
safe to work on, including removing other subsea infrastructure to avoid having to operate in
congested areas could be carried out. These tasks all have similarities with inspection, repair
and maintenance (IRM) techniques where divers and/or ROVs are used for inspection and
cutting. Currently cutting tools include diamond wire cutting and high-pressure water jets.
Laser cutting is an area of development in subsea engineering. There are also synergies
with installation techniques, where companies have expertise in heavy lifting and the
associated equipment.
Flexible pipeline and risers which have previously been attached to floating structures are,
once flushed and cleaned, laid onto the seabed before being cut-up and removed. In-field
pipelines will also be cleaned, cut and removed. These tasks will involve ROVs and/or divers
for the cutting and lifting equipment for the removal. Both tasks have synergies with
operational or installation activities.
Subsea infrastructure such as manifolds, blowout preventers and Christmas trees, once
cleaned and isolated are cut and removed through lifting, often in a ‘reverse installation’
manner. A drive towards standardization for subsea infrastructure could see an increase in
reuse of this equipment rather than recycling. This could increase the emphasis on the
removal technique as any procedure would need to minimize damage to the equipment. The
disconnection and isolation of these systems would be completed with ROVs and/or divers.
Where items are not removed, such as export pipelines, they are either trenched or rock-
piled to bury them, to remove them as an obstruction on the seabed. Such activities involve
techniques that are used during pipeline installation.
Over-trawl surveys may need to be completed, depending on local regulations, to check that
there is nothing that will cause an obstruction to trawling left in place.
3.7. Monitoring
Decommissioned fields will have a monitoring programme for any facilities that remain on
the seabed. This will include monitoring for e.g. leaching of hydrocarbons from wells and
cutting piles. Surveys carried out at the completion of the decommissioning are compared
with the original environmental surveys and a monitoring programme is agreed based on the
findings. An example programme would be an initial requirement for two surveys, one within
five years of the completion of decommissioning and a second within ten years. The analysis
of these results will determine future monitoring requirements. Environmental surveys can be
carried out by companies that perform these surveys during the exploration, appraisal and
operational activities of oil fields.
Any navigational aides that are deployed to mark the location of installations that have not
been removed will need to be maintained. There is a crossover here with companies
involved in IRM as well as those providing navigational aids during installation and
operational activities.
Below are areas that the industry has identified as research and development (R&D)
challenges for P&A 22,23:
- Plugging and sealing – ensuring that it is cost effective, the use of novel barrier
materials, barrier verification and ensuring the longevity of metal-to-metal seals.
- Cost effective P&A, e.g. exploring rigless options for more complex P&A wells.
- Subsurface cutting, milling and removal – including removal of equipment, debris and
collapsed casings and/or screens; entire casing removal; and multiple casing milling
- Monitoring of abandoned wells for leakage/possible leak paths
- Remediation of poor P&A
Decommissioning in the North Sea alone is expected to cost $150 billion (£106bn); in the
Gulf of Mexico approximately $38 billion of decommissioning liabilities is expected (£26.7bn);
and in the Asia Pacific region costs are anticipated in the $30-60 billion (£21-42bn). IHS
Markit estimate a $13 billion (£9bn) per year spend on decommissioning by 2040, a more
than five-fold increase from 2015 levels of $2.4 billion (£1.7bn) meaning a predicted global
figure of $210 billion expenditure between 2010 and 2040.16,27,28
Table 5 below shows a summary of the decommissioning activity that is expected to occur in
the short and medium term, along with estimates of the decommissioning liabilities in the
country where available. The following sections provide more information on these
decommissioning markets. The report has aimed to include the largest and most near-term
markets, but information on all decommissioning markets globally was not available.
from published figures from 7 countries) assumed to be an underestimate as will not include e.g.
subsea fields that are exported straight to shore, or E&A wells that have been temporarily suspended.
27 World Oil, Over 600 offshore projects to be decommissioned over the next five years, 2016.
28 SE O&G diversification toolkit, 2017
4.1. Europe
The North Sea includes the continental shelves of the UK, Norway, the Netherlands and
Denmark. Collectively the North Sea accounts for a significant proportion of global
decommissioning spend due to the age of infrastructure, the water depth, weather conditions
and types of assets deployed. In the period from 2017 to 2025 it is forecast that over 200
platforms will be partially or completely removed, almost 2,500 wells will be P&A’d and
nearly 7,800 km of pipeline will be decommissioned.3 This represents approximately a
quarter of the infrastructure that will need to be removed and wells permanently sealed
based on current installation figures (500 fixed platforms, 500 susbea production systems
and 10,000 wells).16
The combined spend on decommissioning in the North Sea is anticipated to be at least $100
billion (£69.8bn), where although the area does not have the biggest concentration of
platforms and wells, the complexity of the operations, metocean conditions and water depth
In the UK, the Oil and Gas Authority (OGA) has estimated the mid-point for the total cost of
decommissioning in the UKCS to be £59.7 billion. The estimate ranges from a low (P10)
point of £44.5 billion, to a high point (P90) of £82.7 billion. In addition to the figures, based
on current (2016) decommissioning cost from 34 operators, the industry has committed to a
cost reduction target of 35 percent from the mid-point figure. This means that the industry is
aiming for a total decommissioning cost for the UKCS of £39 billion. Achieving this cost
reduction will require the adoption of new techniques and technology; industry collaboration,
including for example multi-operator P&A campaigns; and new strategies, e.g. contracting
strategies. 30 These figures relate to an expected annual expenditure on decommissioning of
£1.8-2 billion over the next five years.3
Figure 3 below, shows the anticipated breakdown of spend between the UKCS regions.
Almost half (£7.9 billion, 46%) of the total figure of £17.1 billion is expected to be spent in the
central North Sea where deeper water (ranges from 45 to 143 m) and more complex
installations will add to the decommissioning expense. In the southern North Sea, although
there are a greater number of installations, the shallower water (18 – 73 m deep) and
simpler projects will only account for 19 percent (£3.2 billion) of the spend.3
Over the period from 2017-2025, 1624 wells and 98 platforms are expected to be
decommissioned with activity starting at approximately 50 wells per year and ramping up
towards the end of the period with a planned 153 wells to be P&A’d in 2023.3
29 Worldwide Oil and Gas, Over 600 offshore projects to be decommissioned over the next five years,
2016
30 Oil and Gas Authority, UKCS Decommissioning Estimate - 2017
In NORWAY the decommissioning sector is at an earlier stage than that in the UK, although
there will eventually be significant activity on the Norwegian Continental Shelf (NCS). There
is therefore a potential for learning, expertise and technology to be exported from the
Scottish supply chain to the NCS, with the benefit of extensive North Sea knowledge from
the UKCS. The Norwegian Petroleum Directorate’s estimate for decommissioning on the
NCS is around NOK160 billion ($19 billion).16 The Norwegian decommissioning market is
predicted to be between £400-800 million per year over the next five years.3
The NCS includes the Norwegian North Sea, the Norwegian Sea and the Barents Sea, with
oil and gas activity happening in all areas, although the Barents Sea is less well explored at
present. The NCS has had 5306 wells drilled, of which 1469 are exploration wells. Of the
remaining 3837 wells, approximately 800 have already been P&A’d. leaving a pipeline of
approximately 3000 wells for future P&A campaigns, as well as a pipeline of future wells
which could, through some estimates, more than double the number of wells that will require
decommissioning to 7000. 32 In the next five years there are plans for the P&A of
approximately 300 wells, as well as the removal of 14 platforms, 2 floating structures, 2,555
tonnes of subsea infrastructure and 222 km of pipeline this activity is almost exclusively in
the Norwegian North Sea.3,33
Financing of decommissioning on the NCS is indirectly partially covered by the state through
tax deductions, 78 percent of the cost associated with termination and the disposal of
facilities are accounted in this way. Where the Norwegian state directly owns a field an even
31 BEIS, Guidance Notes (Draft), Decommissioning of Offshore Oil and Gas Installations and
Pipelines, 2017
32 Handel, C., Abandonment of obsolete wells and installations on the Norwegian Continental Shelf,
http://www.npd.no/en/news/news/2003/the-npds-responsibilities-and-tasks-after-separation-of-the-
petroleum-safety-authority-norway--/
35 NORSOK D-010 Well integrity in drilling and well operations, Rev 4, 2013.
According to the Netherlands’ Energie Beheer Nederland (EBN), the state energy company,
the current estimate for decommissioning onshore and offshore infrastructure in the country
is €6.7 billion (£5.8 bn), of which 55 percent (€3.7 billion, £3.2 bn) is related to offshore
infrastructure. The Dutch state contributes approximately 75 percent of the cost of
decommissioning both directly and through EBN.16,37
The Netherlands has approximately 3,800 wells, of which 1,400 are offshore, in an industry
which began in 1959. It is expected that much of the Dutch oil and gas infrastructure will be
uneconomic and therefore ready for decommissioning in the next two decades. So far,
2,000, both onshore and offshore, wells have been P&A’d in the Netherlands. Roughly 150
platforms and 3,500 km of pipeline remain in the Dutch North Sea to be removed.37 In the
period 2017 to 2025 it is anticipated that 410 wells will require P&A, 17 platforms, 1,385
tonnes of subsea infrastructure and 1,827 km of pipeline to be decommissioned, with an
annual spend of £650-800 million.3
In 2017 EBN published a decommissioning masterplan for the Netherlands which has ten-
point plan encompassing near and mid-term objectives. The ten-point plan includes short-
term aims around developing effective and efficient regulation; establish a national
decommissioning database; ensure learning from projects is captured and establishing a
National Platform for decommissioning. The longer-term objectives cover collaboration;
standardisation; innovation in technology and approaches; international learning and
communication.37 This presents opportunities for the Scottish O&G supply chain through the
sharing of learning, international collaboration and innovative technology and approach
solutions.
Regulation of decommissioning is covered by the Subsoil Act and Offshore Safety Act as
well as the Environmental Protection Act for the Sea (Havmiljøloven) which has prohibited
dumping at sea since 1993. 38 Licensees must agree terms of abandonment with the Danish
Energy Authority (DEA) prior to submitting the decommissioning programme, such terms
include the securities that each party provides for the decommissioning. Licence holders are
then responsible for carrying out decommissioning in accordance with the DEA approved
decommissioning programme.17
In addition to the North Sea, Europe also has other oil reserves including the Italian sector in
36 Norwegian Petroleum Directorate, Responsible removal of old facilities. Accessed April 2018.
http://www.npd.no/en/Topics/Shutdown-and-removal/Temaartikler/Responsible-removal-of-old-
facilities/
37 EBN, Netherlands masterplan for decommissioning and re-use, 2016
38 Danish Environmental Protection Agency, Offshore Decommissioning.
the Adriatic Sea. ITALY is seen as a future decommissioning area of interest with 395
producing offshore wells (1100 including onshore wells) which will start to become
uneconomic in the next 20 years.8,39 The regulatory authority is the General Directorate for
Mineral Resources and Energy and is part of the Ministry of Economic Development (DSG-
UNMIG). All technical issues on hydrocarbons require the opinion of the Technical
Commission for Hydrocarbons. 40
The licence holder is responsible for decommissioning of any disused installations, including
the removal of equipment, such as well infrastructure and pipelines, and the remediation of
the area within two years. A decommissioning programme must be prepared by the licensee
which sets out the detail of the work to be performed. During the licence application process
the applicant must be able to provide a guarantee that the estimated decommissioning cost
can be covered, except where the net worth of the company, or a formal guarantee is given
by a group of companies having a net worth of over €10 million. 41
The Scottish supply chain is already active in this sector with Aberdeen-based Zenith Energy
completing a P&A job on the Italian Ombrina Mare development well in 2016. 42
Shelf (OCS).
There are approximately 3,700 active platforms in the OCS, and over 40 percent of these
are more than 25 years old. Decommissioning is ongoing in the US and there was an
average of 130 platforms removed annually in the last ten years. 44
Considering specifically the GOM, this is where offshore oil and gas production started and
there are now in excess of 5,000 oil and gas installations, many of which are now required to
be decommissioned. It is also the biggest decommissioning market in the world, based on
number of projects, with over 4,000 platforms decommissioned since the 1980s. The activity
that has happened so far has tended to be in shallower waters (<100m) and with smaller
steel structures (approx. 600 tonnes). However, future activity will start to happen in deeper
waters.29,45
Regulations in the USA allow for the disposal of platforms at sea in the Rigs to Reef
programme. In 2015 there were 470 platforms that had been converted into artificial reefs.
The relevant coastal state and BSEE are responsible for approving a platform to become an
artificial reef and conditions about the suitability of the structure for a reef will be taken into
consideration as well as local environmental impacts. 46 Even if a platform is to be left in
place, any wells associated with the platform must be plugged and abandoned. The
regulatory framework for decommissioning is robust with technical standards and financial
security requirements. There are ongoing changes to the requirements for security for
decommissioning, NTL No 2016-N01, see also section 2.4 for more information.
Decommissioning regulation is the responsibility of the US Bureau of Safety and
Environmental Enforcement (BSEE). BSEE have the final approval of decommissioning
programmes and are responsible for enforcing safety and environmental regulations. This
authority is given through the Outer Continental Shelf Lands Act, amongst others.45,47
NTL No. 2010-G05, issued by BOEM in 2010, states that all disused wells and platforms,
those that have been out of use for five years, including E&A and development wells, must,
within three years, be permanently or temporarily plugged and abandoned (in compliance
with existing guidance) or zonally isolated. In the last case, within two years the well must be
permanently or temporarily P&A’d. For platforms, they must be removed within five years.
This notice was issued to minimise the number of idle infrastructure that could cause a
safety or environmental concern as well as reducing decommissioning liabilities by
decommissioning infrastructure whilst it is still in reasonable condition. 48
holders in the outer continental shelf, Gulf of Mexico OCS region, 2010.
In addition to the GOM, the Pacific OCS Region (POCSR) has decommissioning liabilities
which are estimated to be $1.46 billion (£1bn). There are a significantly smaller number of
installations in the POCSR, than in the GOM, with only 11 fields in the POCSR. The
platforms were all installed between the 1960s and 1980s, meaning that they will be
approaching the decommissioning phase. The platforms are in water depths between 95 ft
(30 m) and 1,198 ft (365 m) although mostly in shallow waters. This explains the lower cost
estimate than in the GOM region, although the BSEE estimates have increased by over 16
percent from 2010 to 2014 based on assumptions about the decommissioning process.47
In MEXICO there are 30,000 wells in the National Hydrocarbons Commission (CNH)
database, these include onshore and offshore wells, as well as E&A wells. 49
Decommissioning is not yet a significant part of the Mexican oil and gas industry, as many of
its 50+ fields are not going to be depleted until after 2022, and there are new fields still being
developed. Some decommissioning activity is taking place, with 10 platforms expected to be
removed by 2020. 50 Until 2013 all O&G activity in Mexico was through the NOC, PEMEX,
but licences can now be awarded to private operators. The relevant authorities for
decommissioning in Mexico are CNH, the Energy Ministry (SENER) and ASEA, the
regulatory authority of the Environmental Ministry. Financially, a decommissioning trust is set
up and managed by the government and the contractor, to provide a guarantee that the
decommissioning activities will be carried out by the contractor. 51
Studies suggest that 60 structures and 165 wells need to be decommissioned in the coming
49 https://www.gob.mx/cnh/articulos/centro-nacional-de-informacion-de-hidrocarburos-cnih-64831
50 Scottish Enterprise, Spends and Trends report 2008-2017, South America
51 Getting the deal through, Oil regulation: Mexico, 2017
52 SubseaUK, Decommissioning opportunities in Brazil, 2018
53 Export.gov, Decommissioning Opportunities in Brazil’s Oil and Gas Horizon, 2016
54 Petrus, Brazil faces decommissioning challenge, 2017
years, with at least 20 of the structures (and their associated subsea infrastructure) being
decommissioned by 2020.53
4.4. Africa
There has yet to be significant decommissioning activity in Africa, and as such regulation
and guidance on decommissioning requirements has yet to be fully developed. Regulations
so far rely on international legislation (such as that described in section 2.3), national oil and
gas laws and Production Sharing Agreements (PSAs). Lessons can therefore be learned
from international partners who have a stronger experience in decommissioning.8 There are
over 200 wells in sub-Saharan Africa that were drilled pre-1980, which shows that there will
be an imminent focus on decommissioning here.55 Decommissioning spend in Africa,
although it is too early to predict estimated costs, is expected to be driven by Angola and
Nigeria.29
There has been no significant offshore decommissioning in NIGERIA, Africa’s biggest oil
producer, and also limited regulation developed for decommissioning. 56 The Environmental
Guidelines and Standards for the Petroleum Industry in Nigeria (EGASPIN), say that all
abandoned installations in less than 100 m of water and with a weight less than 400 tonnes
(without the topside) must be entirely removed. EGASPIN, also states that any installation
placed on the Nigerian seabed must be designed for total removal at the end of its life. 57 For
all oil and gas activity the Department of Petroleum Resources (DPR) is the official regulator.
For decommissioning a decommissioning programme must be submitted to the DPR, there
are no requirements for decommissioning funds in the legislation, although this can be
included in the submitted decommissioning programme. 58
Nigeria has an NOC, the Nigerian National Petroleum Company (NNPC), who have
approximately a 60 percent participating interest in PSAs with international oil companies
(IOCs), other NOCs and indigenous oil companies.58 There are 170 structures56 in Nigerian
waters almost exclusively in the Niger Delta area, although exploration has turned up
reserves elsewhere as well. Nigeria has shallow, approximately two-thirds of current
production, and deep water, first discovered in the mid-1990s and with some fields in a
depth in excess of 2,000 m and an increasing amount of the capex expenditure, with
exploration and drilling happening in both. The industry started in the country early in the last
century, with significant discoveries being made since the 1960s. 59
ANGOLA is the second largest oil producer in Africa. There are 1770 wells in Angola of
which 1093 are offshore. The wells range in drilling date from 1974 to the present day,
although the largest amount of activity has been since the 1990s. 60 Angola is known for it’s
deep water with fields often in 300 m to 1,200 m and beyond. The oldest wells are in the
continental shelf in comparably shallower water, but the overall decommissioning challenge
will include these deepwater, subsea wells. No significant decommissioning activity has
occurred yet in Angola, there is therefore an opportunity of export of Scottish subsea
expertise to help develop this sector. Sonangol, is the Angolan NOC, and partners in all oil
and gas projects in the country.
The biggest decommissioning challenge facing the region at the moment is a lack of
regulation and guidance around the decommissioning process, with limited experience and
technical guidance the cost of decommissioning is likely to be much higher than it could be
due to inefficiencies. Indonesia, Malaysia and China are the closest to decommissioning,
and therefore are the markets most in need of developing appropriate regulations.63,65
Acknowledging this provides an opportunity for countries further ahead to share their
learning and for Asia Pacific to benefit from it as well as providing an international market for
technology export. Work has begun with the Asean Council on Petroluem (ASCOPE)
publishing their Decommissioning Guidelines. These regional decommissioning guidelines
are tailored to the ASCOPE countries whilst abiding by international and national legislation,
and have been discussed and approved by the relevant NOCs. 66 ‘Rigs to Reef’ style
Journal, 2018.
64 Wood Mackenzie, Decommissioning Asia-Pacific: 600 fields on the front-line, 2016.
65 Pinsent Masons, Decommissioning in Southeast Asia, 2017
66 ASCOPE Decommissioning Guideline for Oil and Gas Facilities, 2015
disposal is permitted in Asia, with Malaysia’s first structure ‘reefed’ in 2004. The Baram-8, a
three-legged steel jacket that had been storm damaged in 1975 was cut into two sections
and transported to it’s reefing site 8 nautical miles from its original location and placed on the
seabed, along with the conductor, Christmas tree and braces in 2004. 67
The biggest markets are potentially Malaysia and Indonesia, with spend being driven by
shallow-water Australia29,62
Figure 5: Chart showing situation for countries comparing number of fields that have ceased
production versus the development to decommissioning regulation. Source: Wood Mackenzie
AUSTRALIA has different rules for state and territorial waters, those within 3 nautical miles
of the coast and the commonwealth waters, beyond this limit. State and territory waters are
governed by state regulations and these can differ by state. The Western Australia
government issued guidance on decommissioning which applies within its borders. The
national government, in 2018, released guidance for commonwealth waters. This guidance
promotes the early planning of decommissioning; states that decommissioning is the
responsibility of the title holder; works on the baseline of total removal of infrastructure and
states that decommissioning must be completed before the title ends. 68,69
Decommissioning in Australia is estimated to cost US$21 billion (£15 bn) over the next 50
years, due to a lack of decommissioning experience estimated costs are higher than
average, and the National Energy Resources Australia benchmarking report put Australia at
below the worldwide median when in its analysis of decommissioning. Alongside better
regulation and guidance, and the development of new technology the conclusions included
learning from other countries that have more experience in decommissioning, such as the
UK. 70,71
THAILAND is at the start of its decommissioning phase, with some of its infrastructure
reaching 40 years of operation. In the Gulf of Thailand, the main oil and gas producing area,
80 of the 450 platforms are at least 20 years old. There are also a number of licences that
are due to expire in the period 2021-23. 72 Platforms operated by PTT Exploration and
Production Public Co. Ltd. (PTTEP), Thailand’s NOC, which account for approximately 60
percent of the infrastructure, have between six and 16 wells associated with each platform,
suggesting a total well count of between 2700 and 7200. 73,74
Regulation for decommissioning in Thailand is based on the national Petroleum Act which
highlights that responsibility for decommissioning is on the ‘concessionaire(s)’ as well as the
provision of a security deposit to cover decommissioning. The government is reviewing
decommissioning guidance through an initiative known as ‘Decommissioning 2.0’ which aims
to provide a one-stop-shop for licences, etc, where approval would be entirely through the
Ministry of Energy’s Department of Mineral Fuels (DMF).8,75 Decommissioning in Thailand is
estimated to cost approximately $3 - $5 billion (£2.2 - £3.6 bn). 76 Currently decommissioning
should occur when one of the following criteria are met, although exemptions can be made
based on other development within the relevant concession block. The criteria include:
installations that have not been in use for more than a year; petroleum reserves falling to
less than 40 percent; remaining production period will be less than 5 years and
concessionaires seeking to decommission their installations.76
INDONESIA has over 450 offshore platforms, three-quarters of which are now over 20 years
old, and 65 percent are over 30 years old highlighting the potential start of the
decommissioning phase of the industry. Infrastructure older than 30 years, includes: 500
platforms, 100,000 km of pipelines and 15,000 onshore and offshore wells. Hindering the
development of the decommissioning sector is a lack of clarity about who is responsible for
decommissioning activities and liabilities, as until 2008 it was not part of PSAs. Since 2008,
the PSA template has included ‘abandonment and site restoration’ costs, which are held in a
fund by SKK Migas. Offshore infrastructure however, is the responsibility of the NOC,
Pertamina Energy, and it is therefore likely that decommissioning will fall to them.8,75,77,78
MALAYSIA has 349 Platforms, 20 Floating structures, 4,154 wells and 10,105 km of pipeline
offshore. Decommissioning however is yet to begin and there are no national guidelines for
decommissioning currently. The NOC, Petronas, as the owner of offshore assets is
responsible for decommissioning. 79
70 Deloitte, Decommissioning has potential to be Australia’s next oil and gas boom, 2017
71 National Energy Resources Australia, Oil & Gas Industry Competitiveness Assessment Report on
the Framework, Baseline Score, Insights and Opportunities, 2016
72 Barron, M., Reversal of Fortune: Thailand’s Oil and Gas Sector, Natural Resource Guidance
Council, 2016.
73 Rigzone, Thailand Looks Ahead: Gears Up for Oil, Gas Decommissioning Work, 2016
74 Saadawi, H., Offshore Production in the Gulf of Thailand, Society of Petroleum Engineers, 2017
75 Pinsent Masons, Decommissioning in Southeast Asia, 2017
76 Rigzone, Thailand Looks Ahead: Gears Up for Oil, Gas Decommissioning Work, 2016
77 Offshore Technology, Decommissioning Indonesia’s oil rigs: a vast but challenging market, 2015.
78 Gulf Oil and Gas, Indonesia Decommissioning in Oil & Gas Conference 2015, 2015.
79 Hashim, A., Upstream Decommissioning in Malaysia, LinkedIn, 2016