Project Planning & Control
Project Planning & Control
Project Planning & Control
Chapter Coverage
• What is a project?
• The project planning and control process
• Network planning – Critical Path Method (CPM)
Projects:
A project is a set of activities with a define start
point and a define end state, which pursues a
defined goal and uses a define set of resources.
Stages in project management
Stage 1
Understanding
the project
environment
Stage 2
Project Changes
definition
Stage 3
Project Corrective action
planning
Stage 4 Stage 5
Technical Project
execution control
Stage 1: Understanding project environment
The project environment comprises the
factors which may affect the project during
its life. See next slide ……………
Geo-social environment Econo-political environment
• Geography • Economy
• National culture • Government
The Project
Quality
New aircraft
project
Adjust as necessary
1 2 3 4 5
1. Identify activities: Work breakdown structure
1. Serve
breakfast in bed
Accuracy of estimates
comes with experience!
Probability
3 5 6 Activity duration 13
Optimistic time Expected time
Most likely time Pessimistic time
3. Identify relationship and dependencies
Orange
Activities requiring
operator time
Bread Toast Butter
Tray
4
Staff required
3
2
1
0
0 1 2 3 4 5 6 7 8 9
Time (mins)
“Making breakfast” – Minimizing staff
requirements
Time (mins)
0 1 2 3 4 5 6 7 8 9
Orange
Tray
4
Staff required
3
2
1
0
0 1 2 3 4 5 6 7 8 9
Time (mins)
5. Fix the schedule
“Making breakfast” – Maximizing toast
quality
Time (mins)
0 1 2 3 4 5 6 7 8 9
Orange
4 Tray
Staff required
3
2
1
0
0 1 2 3 4 5 6 7 8 9
Time (mins)
Stage 5: Project control
1. Project monitoring: current expenditure to date, amount of
overtime authorized, inspection failure, progress of activities
etc.
m Pa
r oo int
bed b ed
ar e ro
p om
e
Pr
Remove furniture Replace furniture
Pr
ep en
are c h
kit it
ch intk
en Pa
Network diagram for simple decorating project
EET – the very earliest the event could possibly
Activity reference a occur if all preceding activities are completed as
early as possible.
Activity duration 1
LET – the latest time that the event could possibly
1 take place without delaying the whole project
Event number
3
An Event
b c
2 3
1 a 2 5 f 6
1 1
d e
Earliest Event Latest Event
1 2
Time (EET) Time (LET) 4
Activity on arrow – Using “dummy”
activities
2
x
x
1 2 1 3
y
1 3 5
2 4 6
Critical Path
– Network diagrams have more that one sequence of
activities which will lead from the start to the end of the
project – these sequence are called paths.
– Each path has a total duration which is the sum of all its
activities.
3
3 3
b c
2 3
1 a 2 5 f 6
0 0 1 1 1 6 6 1 7 7
d e
1 2
4
2 4
Chapter 16, Page 575
Worked Example
18 20 G
A
H 3
5 D
8 7
B E L
0 0 10 10 27 27 35 35
10 10 8
F I
9
C 4
K M
1 19 19 5
4
3 J
22 22
The End