What Are The Objectives of APDRP?: Answer
What Are The Objectives of APDRP?: Answer
What Are The Objectives of APDRP?: Answer
Question: 2. Who will fund the power sector projects under APDRP?
Answer: Power sector projects are funded by Ministry of Finance, Government of India under the
advice from Ministry of Power. The payment would be Channelized through a designated agency as
identified by MOP for smooth implementation of the programme.
Question: 3. What are the six level intervention strategies in power sector under
Distribution Reforms?
Answer: Ministry of power has formulated a six level intervention strategy to rejuvenate the power
sector, primarily to make it viable. Efforts are to focus on reforms in the distribution sector to improve
accountability & revenue realization in the form of increased metering conversion of un metered
connections to metered connections, addition of fresh connections, higher billing and collection
efficiency.
Technical, commercial, financial, IT, organizational interventions have been devised as part of the six
level intervention strategy. These strategy for Distribution reforms would envisage interventions at the
following levels:
Increase in income: Increasing the billing, reduction of pilferage, more remunerative pricing of the
commodity (energy) and optimum utilization of physical assets and brand value of the supplier.
Reducing the Expenditure:
Sourcing of the least cost energy and reducing the energy management or energy Handling cost. In
order to achieve the objectives of a retail business model it is proposed to convert the circle as a
independent identifiable business unit of the DISCOM.
FEEDER Level Intervention
11 kV Feeders are the basic source of income to an electricity utility. The issues confronting it are
Metering and Billing, Bill collection, Abnormal Voltage, segregation of losses and over all ensuring
quality of power supply.
1) A scheme was launched in 2000-01 with initial provision of Rs.1000 cr., for reoriented with
introduction of reforms element.
2) The Govt. has approved the proposal of Ministry of power for the six level intervention strategies
for distribution reforms. The approval envisages an expenditure of Rs.40,000 crore during tenth five
year plan under APDRP scheme.
3) An outlay of Rs.20,000 cr has been provided as central plan assistance under APDRP to state
governments for implementing the up gradation and modernization of sub transmission and
distribution scheme under investment component.
4) Rs. 20,000 cr has been provided for incentive to the performing states by way of reduction in cash
losses.
· 25% of the APDRP amount- up front on approval of project under APDRP and on issue of sanction
letter by the Financial Institutions.
· After Spending 25% of the project cost (i.e 25% APDRP + 25% of loan component from Fis), 50% of
the APDRP amount would be released.
. After spending 75% of the project cost (i.e 75% APDRP + 75% of loan component from FIs) balance
25% of the APDRP amount will be released.
Question: 6. What is the role of NTPC & Power Grid under APDRP?
Answer: The roles of NTPC & POWER GRID under APDRP are:
1) Advise and help SEBs/Utilities in preparation of DPRs and wherever requested specifically by utility,
they shall prepare DPR for states as consultant.
2) Assist SEBs/Utilities in prioritization of schemes for urban areas in distribution circles and ranking of
projects for improvement in revenue collection and increase in customer satisfation.
3) Assist Monitoring committee for review of techno economic appraisal of the DPR prepared by
utilities
5) Monitor periodically the physical and financial progress of various distribution circles for which
APDRP funds have been allocated and disbursed.
6) Advise MOP in devising guidelines for uniformity of approach in preparation and evaluation of
project proposals and disseminating information on best practices under APDRP scheme.
-As the gap or loss reduction has to be macro and over-all basis, the sum total of the losses for all
entities will be compared with the base year·he cash loss reduction shall be calculated without the
subsidy support of the state government both in the base year as well as the subsequent years.
-Once an incentive has been drawn for improvement that would become the benchmark to compare
for future improvements and therefore any deterioration thereafter, in the performance would be
ignored to incentivise the steady improvement.
-Only cash sales are to be considered for the calculation of cash loss reduction. Thus any deterioration
in the amount of sundry debtors will have to be taken out from the purview of loss/profit·
-The accounts should be audited and C&AG should certify this account.
-The head of the business units will be empowered to act and be held accountable for their actions &
performance.
-A sense of ownership and competition is created The segregation of business units of utilities is done
on business accounting basis and financial practices adopted on the following lines?
-Revenue realized from sales and cost incurred on purchase of input energy.
Question: 10. Who are the Accredited agencies for project formulation, project evaluation,
project monitoring, Implementation, energy audit under APDRP?
Answer: A committee is formed with members from NTPC, PGCIL, PFC, CEA, SEB/Utilities, Credit
rating agencies, FIs etc will constitute to accredit reputed agencies for the purpose of project
evaluation, project monitoring, Implementation, energy audit & accounting.
-Making the SEB officials collect relevant data from each 11 KV feeder in the identified circles.
-Analyzing of the data using computer tools to prepare feeder wise computer aided least cost project
report.
-Supervision of Implementation.
Question: 12. Who will formulate the Detailed Project Report-DPR, assist in technical &
managerial skills, and conduct capacity building exercise for SEBs/Utilities under APDRP?
Answer: The Ministry of Power identified NTPC & Power Grid Corporation Limited as the lead Advisor-
cum-consultants and brought CPRI, MECON under the charge of NTPC & WAPCOS,NPC,ERDA under the
charge of Power Grid.
Question: 14.What are the measures taken to reduce the technical loss reduction under
APDRP?
Answer: The following are the measure
-Installation of capacitors at all levels.
-Re-confifuration of feeder lines & distribution transformers so as to reduce the length of LT lines.
-Make the system less LT oriented by installation of smaller size energy efficient distribution
transformers so that each transformer supplies power to 10 to 15 house holds only.
-Computerized load flow studies so that investments could be undertaken for long-term strengthening
of the distribution system.
Question: 16. What is the action plans accepted under Chief Ministers National Action
plan (CMNAP) for power sectors?
Answer: The action plan under CMNAP identified and accepted are
-Establishing independent regulatory commissions at Central and state levels.
Question: 17. What are the factors involved in analyzing the load factor?
Answer: Load forecast is extremely important in planning, distribution network and capacity
addition.
-System load forecast viz. forecasts of load for the entire study area
-Spatial or small area load forecast (Division of Utility service 1area into sufficiently large number of
small areas and forecast for each small area)
-Promotion of efficient & environmentally policies constituted by Central Electricity Authority (CEA),
Regulatory commissions & establishment of Appellate tribunal.
-Overhead lines·
-Service lines·
-Works
Question: 27. Who will prepare & publish National Electricity Policy and tariff policy
Plan?
Answer: The Central Government shall, from time to time, prepare & publish the national electricity
policy and tariff policy plan, in consultation with the State Governments and the Authority for
development of the power system based on optimal utilization of resources such as coal, natural gas,
nuclear substances or materials, hydro and renewable sources of energy.
Question: 28. How does any person transmit or distribution or under take trading in
electricity?
Answer: Any person is allowed to transmit or distribute or under take trading in electricity provided
he has authorized license issued under section-14 or is exempted under section-13.
-The National Load Dispatch Centre shall be operated by a Government company or any authority or
corporation established or constituted by or under any Central Act, as may be notified by the Central
Government·
-The Central Government shall establish a centre for each region to be known as the Regional Load
Dispatch Centre having territorial jurisdiction as determined by the Central Government for the
purposes of exercising the Powers, and discharging the functions under this Part.
-All directions issued by the Regional Load Dispatch Centres to any transmission licensee of State
transmission lines or any other licensee of the State or generating company (other than those
connected to inter State Transmission system) or sub-station in the State shall be issued through the
State Load Dispatch Centre.
-Keep accounts of the quantity of electricity transmitted through the regional grid;
-Responsible for carrying out real time operations for grid control and dispatch of electricity within the
region through secure and economic operation of the regional grid in accordance with the Grid
Standards and the Grid Code.
-Responsible for optimum scheduling and dispatch of electricity within a State, in accordance with the
contracts entered into with the licensees or the generating companies operating in that State.
-Keep accounts of the quantity of electricity transmitted through the State grid;
Question: 32.What are the features available under Electricity Act-2003 for Electricity Bill-
2003?
Answer: Following are the features under Electricity Act-2003 for Electricity Bill-2003.
-The central Government to prepare a National Electricity Policy in consultation with state
governments·
-Trust to complete the rural electrification and provide for management of rural distribution by
panchayats, cooperative societies, non-government organizations, franchisees, etc.
-Provision for license free generation & distribution in the rural areas. Generation, being de-licensed
and captive generation being freely permitted.
-Provision for private licensee in transmission & entry in distribution through an independent network.
-Open accesses in distribution to be introduced in phases with surcharge for current level of cross
subsidy to be gradually phased out along with cross subsidies and obligation to supply. SERs to frame
regulations within oneyear regarding phasing of open access.
-Distribution licensees would be free to undertake generation and generating companies would be free
to take up distribution licensees.
-Trading, a distinct activity is being recognized with the safeguard of the Regulatory commissions
being authorized to fix ceilings on trading margins, if necessary.
-An Appellate Tribunal to hear appeals against the decision of the CERC and SERC.