Autodesk BIM Implementation Plan
Autodesk BIM Implementation Plan
Autodesk BIM Implementation Plan
Implementation Plan
September 2015
Contents
Executive Summary 2-3
4.0 Horizon 4 – Development of Scottish Government Guidance
1.0 Horizon 1 – Assess BIM Maturity & Define BIM thresholds 4.1 Review of BIM Level 2 Components for Scotland 21
1.1 BIM strategy 4 4.2 Development of Guidance 21-22
1.2 Implementation Plan 4-5
1.3 Assessment of BIM Maturity 6-7
1.4 Project Launch 7 5.0 Horizon 5 - Launch of BIM Level 2
1.5 Define BIM Level 2 Component 8-9 5.1 Communications Prior to Launch 23
1.6 Define Qualifying BIM Projects 10-11 5.2 Support For Launch 23
5.3 Monitoring BIM Level 2 Implementation 23
E-mail - bimdeliverygroup@scottishfuturestrust.org.uk
1
Building Information Modelling Implementation Plan -Sep 15
Executive Summary
This implementation plan sets out how the public sector within Scotland, should adopt BIM level 2, where appropriate, within construction by April 2017.
This is in response to the recommendations of the Review of Public Sector Procurement in Construction. As Scotland moves towards a digital built
environment, BIM is seen as a key tool for the Scottish construction industry going forward. BIM uses digital technology to improve the sharing and analysis
of data within both the construction and operational phases of projects. By improving data management and collaboration within projects, the industry will
be supported in delivering greater efficiencies through the design, construction and operational stages of a project.
In order to implement BIM Level 2, the plan considers the current BIM maturity of the Scottish public sector, the criteria to establish which projects should
adopt BIM level 2 by April 2017 and finally how this will be implemented through a combination of focused actions including: pathfinder projects, guidance,
awareness and training. The plan adopts the approach that the implementation of BIM within Scotland should align and build upon the existing British
Standards and draw from work already undertaken nationally and internationally..
The plan has been divided into 5 horizons which encompass specific workstreams and is summarised below:
Provide a roadmap to the implementation of BIM Level 2 by April 2017 on Public Sector Projects.
Address the recommendations of the Review of Procurement in Construction report in relation to BIM.
Support the public sector and demonstrate the benefits of adopting BIM .
Provide experienced leadership and direction nationally, in the adoption of BIM for public sector projects within Scotland.
Prepare and publish guidance for procuring authorities to better equip them in adopting BIM Level 2.
Demonstrate to procuring authorities the benefits of adopting BIM.
In considering the key horizons to deliver BIM, the diagram below outlines the high level programme.
3
Building Information Modelling Implementation Plan -Sep 15
The BIM strategy – High level strategy approved by the Construction Review Delivery Group.
Scottish BIM Implementation Plan – Detailed approach to implementation of BIM Level 2.
Assessment of Current BIM Maturity – Assess current BIM capability within Scottish public sector through capability questionnaire.
Project Launch – Publicise BIM implementation and deliver launch forums.
Define BIM Level 2 Requirements – Launch BIM Level 2 definition aligned to the Scottish public sector.
Define Qualifying Projects – Clarify which projects will adopt BIM Level 2 by April 17.
The BIM Implementation Strategy provides an overarching approach for the implementation of BIM Level 2. The strategy also sets out how the BIM
recommendations within the Review of Public Sector Procurement in Construction will be addressed. The strategy has been approved by the
Construction Review Delivery Group who report to the Ministerial Strategic Group on Procurement.
Horizons Date
Concluding Planning Stage – Horizon 1 Oct 2015
Conclude Mobilisation – Horizon 2 Dec 2015
Commence Pathfinder Project(s) – Horizon 3 Nov 2016
Publish Draft Guidance – Horizon 4 Jun 2016
Consultation on Draft Guidance Complete Aug 2016
Publish Final Guidance Oct 2016
Launch Level 2 BIM to Public Sector Projects – Horizon 5 30 April 2017.
th
Progress against the delivery of the plan will be monitored by the Scottish BIM Delivery Group who report to the Construction Review Delivery Group.
Refer to section 2.1 for a summary of the governance arrangements.
4
Building Information Modelling Implementation Plan -Sep 15
Open: The implementation plan should encourage all stakeholders to participate irrespective of size or experience.
Benefits: The implementation plan should support the public sector to identify the benefits on BIM adoption and the value added.
Understandable: The Scottish BIM implementation plan will be mobilised and communicated in an understandable manner for both the asset procurer
and the supply chain community.
Non Proprietary: All requirements will be non-proprietary as to software applications and as to the required formats of deliverables. It is imperative
that the supply chain be allowed to innovate and make their own technology choices that best suit their business.
Adaptable: The implementation plan will provide a solution which can be adapted to different procurement routes, funding solutions, sectors and
types of projects across the public sector.
Competitive: Wherever possible there are at least two solutions or methods available as to minimise market influence in terms of anti-competitive
behaviour.
Clear Purpose: Early within Horizon 1, the plan should clearly set out the criteria for projects which should adopt BIM Level 2 by April 2017. By doing
this we will provide clear direction to industry to develop working practices to embrace this change.
Innovation: In the delivery of the implementation plan, the BIM Delivery Group will consider opportunities for innovation which may include
awareness and alignment of the plan to the long term objective of achieving BIM Level 3. Remain mindful of linkages of BIM to other
recommendations within the procurement review including whole life costing.
5
Building Information Modelling Implementation Plan -Sep 15
Consultations
The BIM Delivery Group will consult with key stakeholders to further inform the current BIM capability within the Scottish public sector. This will include
but not limited to:-
Engagement with a number of professional and trade bodies.
Liaison with BIM 4 Groups
Hold launch forums with key procuring authorities.
6
Building Information Modelling Implementation Plan -Sep 15
Early analysis should be undertaken to understand the typical information needs and data exchange points plotted against key development stages.
7
Building Information Modelling Implementation Plan -Sep 15
This definition has been taken from the UK BIM Task group and
reflects a definition consistent with the intentions of Scottish BIM
Implementation.
As of August 2015 the Level 2 BIM components will be complete and will Diagram 5: BIM Levels of Maturity
comprise of the following elements which can be configured to suit a project’s
data requirements:-
The above packaging, supported by the British Standards Institute (B/555 roadmap) is being used both nationally and internationally and forms the
basis for a forthcoming ISO standard. The Scottish Implementation Plan will review, build upon and ensure alignment to these standards.
8
Building Information Modelling Implementation Plan -Sep 15
These International draft standards derived from the BSI Public Available Specifications (PAS) 1192-2 and 3, will emphasize how the briefed employer’s
information requirements (or conditions), should be configured and specified by the clients.
European Parliament voted to modernize European public procurement rules by recommending the use of electronic tools such as building information
electronic modelling, or BIM, for public works contracts and design contests. The EU asked their member states to consider the use of technology to
modernise and improve the public procurement processes. The article that refers to BIM is Article 22(4) below:
“4. For public works contracts and design contests, Member States may require the use of specific electronic tools, such as of building
information electronic modelling tools or similar….”
Scotland has not adopted this EU directive and will not place BIM adoption within statutory regulation. However the directive was a significant footstep
for the EU and its member states to widen the adoption of BIM across the European construction sector and increase EU industry’s global effectiveness
especially in securing international contracts. The BIM Delivery Group intends to work closely with and participate in the European BIM working group to
draw on a variety of sources and ensure that the plan is compatible with the ISO development and international best practice.
9
Building Information Modelling Implementation Plan -Sep 15
In October 2012, the Scottish Government launched a review of public sector construction procurement. The review, led by Robin Crawford and Ken
Lewandowski, published its report the Review of Scottish Public Sector Procurement in Construction on 22 October 2013. The review identified the
benefits in adopting BIM and made the following recommendations in how the Scottish Government and procuring authorities should adopt BIM. These
recommendations included:-
57 -BIM should be introduced in
central government with a view to 66 - The industry needs to be
encouraging adoption across the ready to embrace modern
public sector. The objective should methods of construction, and new
be that, where appropriate, and emerging technologies such as
projects across the public sector Building Information Modelling.
adopt BIM level 2 by April 2017.
57.2 - When
57.1 - Resources deciding if BIM will
add value to a 57.4 - Suitable trial 57.5 - Baseline
should be identified projects should be information should
and a programme project public sector 57.3 - Guidelines
clients should identified ahead of be established to
plan for Scottish BIM and advice on the
undertake an the 2017 target date allow proper
implementation by use of BIM should be
assessment of the and their evaluation of the
2017 established. developed.
likely return on management co- impact of BIM
investment from its ordinated centrally. implementation.
use.
10
Building Information Modelling Implementation Plan -Sep 15
The recommendation endorsed by Scottish Ministers was that public sector projects where appropriate should adopt BIM level 2 by April 2017. When
deciding if a project is appropriate for BIM adoption, procuring authorities should consider multiple criteria including value of project, data requirements
and return on investment. To address this, the BIM Delivery Group will develop a BIM decision matrix which procuring authorities will utilise to
understand if their project would benefit in adopting BIM.
This decision matrix will be included within the Scottish BIM guidance and will be included within the Scottish Construction Procurement manual for use
by relevant procuring authorities.
The draft assumptions that will inform this decision matrix are as follows:-
Assessing projects for BIM Level 2 adoption will be a requirement for relevant procuring authorities on or after the 30th April 2017.
The decision matrix will recommend BIM level 2 for all projects above the OJEU threshold (currently £4.32m).
Projects below the OJEU threshold (£4.32m) will be subject to an assessment of the project specific criteria to determine whether BIM will
offer benefits to that project.
These draft assumptions are initial proposals and will be tested against the feedback provided through the capability questionnaire and consultation
process during Horizon 1. The BIM Delivery Group within Horizon 1 will communicate clearly the ongoing adoption of BIM to industry and support this
with a considered and proportionate decision matrix for BIM adoption by April 2017.
11
Building Information Modelling Implementation Plan -Sep 15
2.1 Governance
2.1.1 Monitoring & Reporting
Monitoring Of Progress
The progress in delivering the implementation plan will be monitored by the Construction Review Delivery Group. At the end of each Horizon, the BIM
Delivery Group will report and attend the Construction Review Delivery Group. The BIM Delivery Group will seek endorsement for the outputs delivered for
that Horizon. The BIM Delivery group will liaise with the Construction Procurement Review Core Team prior to submission to the Construction Review
Delivery Group.
Risk Management
The BIM Delivery Group will develop, manage and update a project wide risk register. This will consider all key risks for the implementation of BIM and
shall ensure these risks are monitored and managed during the development process.
Programme Reporting
The BIM Delivery Group will develop, manage and update a project programme. This will be updated and monitored to assess progress on a monthly
basis.
Reporting
The BIM delivery Group will report to the Construction Procurement Review Core Team on a monthly basis. This will include updates in relation to
progress, key issues, risk management, forthcoming communications and activities.
12
Building Information Modelling Implementation Plan -Sep 15
13
Building Information Modelling Implementation Plan -Sep 15
14
Building Information Modelling Implementation Plan -Sep 15
The BIM PSBG is a collaboration of public sector procuring organisations who will champion the Scottish BIM strategy in their respective organisations.
Their purpose is to raise awareness of the BIM strategy, promote a shared understanding of its value proposition and raise potential issues affecting the
implementation of the BIM strategy in their respective areas of interests.
15
Building Information Modelling Implementation Plan -Sep 15
BIM 4 Academia
Building Information Modelling (BIM) 4 Academia Group (BIM4 AG) is a forum of Scottish academic providers and training boards. The BIM4AG is a
forum to share knowledge, guidance and feedback as to how BIM can be pragmatically implemented in a structured manner at apprentice, undergraduate
and post-graduate level. The group will explore opportunities for research and sharing of knowledge. The group should also consider and respond to
skill requirements for BIM adoption and opportunities within the implementation programme to promote learning within construction institutions and
schools.
In addtion to the identified groups above, the BIM Delivery Group will also consult with various bodies, organisations and institutes as is required to
deliver this implementaion plan.
16
Building Information Modelling Implementation Plan -Sep 15
2.3 Research
During Horizon 2, the BIM Delivery Group will engage with organisations who are conducting research on current BIM practice national and internationally.
With most countries looking towards a digitised construction sector all over the globe, there are recent examples of BIM adoption and new methods of
working. The BIM Delivery Group will review various programmes and link any good practice to the outcomes of the Scotland wide BIM delivery
programme.
17
Building Information Modelling Implementation Plan -Sep 15
The aspiration of this work-stream is that a minimum of three pathfinder projects are delivered. A Pathfinder Project Delivery Group will be formed to
manage, monitor, and report on the progress and lessons learnt from the projects. In deciding upon the pathfinder projects the following considerations
should be made:-
Project Status – As well as new projects, partly developed BIM projects moving into a construction phase could be adopted to test certain data
exchanges?
Type of projects – New build, infrastructure and refurbishment contracts to be considered.
Project Value – Consideration as to value of projects and ability to demonstrate BIM is deliverable on smaller value projects would be
advantageous.
Project Sector – Consider projects against pipeline value and sector. (Education, Transport, Health, Water).Supply chain involvement.
Consider opportunities for adopting outcome based digital data aligned with COBIE for interim (pre-handover) data exchanges?
Consider opportunities for adopting Industry Foundation Classes (IFC) model, in lieu of COBIE for operation the asset model?
Consider level of dimension deliverables within the pathfinders and case studies. (3D parametric modelling, 4D-time simulation and 5D-cost
dimension?)
Propose one refurbishment project to demonstrate the benefits of laser scanning and reality data capture of existing buildings into the model
environment.
Project programme – consider any projects proposed programme timescales.
Early discussions, has identified willing procuring authorities, who would volunteer projects as pathfinders. The final decision on pathfinder projects, will
be restricted by the projects available at the time of delivery. Through regular reporting by the Pathfinder Project Delivery Group, the pathfinders will
inform the development of the Scottish Government BIM guidance and provide suitable case studies.
18
Building Information Modelling Implementation Plan -Sep 15
The associated monitoring and management should be completed by a Pathfinder Project Delivery Group.
Where possible, the pathfinder should also identify any dis-benefits associated with the project to inform future BIM guidance and approaches.
Consideration should be given to the pathfinder projects and their results being validated by outside parties such as Construction Excellence or academic
partners.
19
Building Information Modelling Implementation Plan -Sep 15
All lessons are to be captured and shared with the BIM Delivery Group to inform the Scottish Government BIM Guidance for future work practices. The
pathfinder projects can also be adopted as case studies within the finalised guidance.
20
Building Information Modelling Implementation Plan -Sep 15
The guidance will be accessible to all and will be published in the updated Scottish Government’s Construction Procurement Manual.
21
Building Information Modelling Implementation Plan -Sep 15
1. Stage 1 – Early document to inform ways or working on pathfinder. To include existing UK BIM Task Group BIM Level 2 components.
2. Stage 2 – Draft Scottish Government BIM Guidance addressing objectives above and informed by research, pathfinders and consultations.
3. Stage 3 – Final Scottish Government BIM Guidance. Refined further by consultations, pathfinder feedback and incorporating case studies.
22
Building Information Modelling Implementation Plan -Sep 15
Through effective ongoing communication to industry and the public sector, the level of communication prior to launch will be assessed at that point.
Completion of the above represents the required position by January 2017. Ahead of the launch it is recommended that a BIM Champion network should
be set up to offer a forum for procuring authorities to share knowledge and expertise in the delivery of BIM within projects. This group should continue to
drive adoption and knowledge share across the procuring authorities.
Once BIM Level 2 has been implemented, a comprehensive lesson learned exercise should be completed and this should address:
Lessons in the implementation of BIM.
Review of actual benefits either achieved or demonstrated.
Identify areas not achieved/implemented and assess reasons for this and future actions required.
Consider areas of further education and training going forward.
Discussion and recommendation on if/how the public sector continue to develop their BIM maturity. Consider next steps to BIM Level 3.
The lessons learned exercise should be managed by the BIM delivery Group with involvement of key stakeholders as required. This should be submitted
to the Construction Review Delivery Group for approval.
23
Building Information Modelling Implementation Plan -Sep 15