Morana, Christian D.: As-Built Plan
Morana, Christian D.: As-Built Plan
Morana, Christian D.: As-Built Plan
1. Implementing Offices simply use the approved _________ Plan as the reason for the approval
of Final Variation Order
a. Construction Plan
b. Built-in Plan
c. As-Built Plan
d. Site Development Plan
2. All works under a variation order declares that pursuant to Section 3 Annex "E" of the
Revised IRR of RA ______.
a. 9184
b. 9814
c. 9418
d. 9408
3. Under no circumstances shall a ______ proceed to commence work under any Change Order
or Extra Work Order unless it has been approved.
a. Designer
b. Owner
c. Laborer
d. Contractor
4. Under any of the following conditions, the procuring entity's representative/Project Engineer
may, subject to the availability of funds and within the limits of his delegated authority, allow
the immediate start of work under __________.
5. The cumulative increase in value of work does not exceed ____ of the adjusted original
contract price.
a. 5%
b. 8%
c. 10%
d. 12%
6. With the condition for undertaking works, works which are urgent, completed without prior
approval of __________ and incorporated in the “As-Built” plan.
a. Changer Order
b. Variation Order
c. Suspension Order
d. Extension Order
a. Not acceptable
b. Somehow Acceptable
c. Acceptable
d. Either Acceptable or Not Acceptable
8. The “Conditions as to When "As-Built" Plan can be Used as Reason for Final Variation Order”
is under the Department Order No. ______.
a. 12
b.144
c. 28
d. 66
9. Under any of the following conditions, the procuring entity's representative/Project Engineer
may, subject to the availability of funds and within the limits of his delegated authority, allow
the immediate start of work under any Change Order or Extra Work Order:
10. Conditions as to When "As-Built" Plan can be Used as Reason for Final Variation Order is
signed by
a. Sanny A. Castillo
b. Reginand B. Lazo
c. Dexter A. Tangpep
d. Rafael C. Yabut
DPWH Department Order No. 60, Series of 2017
1. Government Procurement Reform Act (GPRA) – Prescribes the necessary rules and
regulations for the modernization, standardization, and regularization of the procurement of
the procurement activities of the government and for the other purposes.
a. RA 9714
b. RA 9180
c. RA 9517
d. RA 9841
a. Salary Demand
b. Salary Request
c. Money Claim
d. Money Demand
3. ACEL provides solutions to the problems that beset the construction industry and introduced
the system of equipment leasing and standardization of rental rates. ACEL stands for
a. Associative Carriers and Equipment Lessor, Inc.
b. Association of Carriers and Equipment Lessor, Inc.
c. Association of Contractors and Equipment Lessor, Inc.
d. Associative Contractors and Equipment Lessor, Inc.
4. The applicable Equipment Rental Rates (less operator, cost of fuel, lubricants, maintenance,
insurance and repair).
a. Bill of Lading
b. Bar Chart
c. Bare Rental
d. Appraisal
5. The proportion of the estimated time that a piece of equipment or a system is operating up
to the completion of the project.
a. Economic Life
b. Extra Ordinary Circumstances
c. Critical Path Method
d. Equipment Utilization Schedule
6. The value which badly depreciated improvements, machines, or equipment would have if
dismantled and sold in separate parts or pieces; the value of an asset at the end its actual
results.
a. Salvage Value
b. Equipment Value
c. Money Value
d. Time Value
7. The following actions must be brought within ten years from the time the right action
accrues:
I. Upon a written contract
II. Upon an obligation created by law
III. Upon judgement
What is/ are true.
a. I only
b. III only
c. I, II and III
d. Nothing is true
8. Formulation of an objective mechanism with definite and measurable criteria to obviate and
open-ended interpretation of the occurrence of extraordinary circumstances.
a. Technical Parameters
b. S-Curve
c. Reglementary Period
d. Legal Parameters
9. The Identification of legal bases for events that will trigger/result to extraordinary
circumstances within the bound of the civil code of the Philippines.
a. Legal Parameter
b. Technical Parameter
c. Legal Document
d. Technical Document
10. A value calculated by multiplying the proportion of an individual adjustable element by the
percentage change in the current index figure when compared with the base index figure.
a. Rational Value
b. Fluctuation Factor
c. Fortuitous Event
d. Index Factor
a. Resumption Order
b. Work Suspended Order
c. Work Resumption
d. Work Suspension Order
3. A written authority issued by the 10 granting the contractor additional time beyond the
approved completion date in order to carry out additional work or on account of other special
circumstances that warrant such additional contract time.
4. Suspension due to unworkable rainy days which usually occur intermittently, where approval
by the authorized officials for suspension/resumption order for each occurrence may not be
necessary, the DPWH Project Engineer/ Engineer's Representative may issue, for documentary
purposes, a monthly Time Suspension Report, using the format in Annex "0", duly approved by
the Head of the 10 concerned, to support the corresponding time extension, provided that
proper documentation compliant to Document Tracking System (DoTS) documentary
requirements
5. The request shall be made prior to the expiration of the contract time within thirty (30)
calendar days after such work has been commenced or after the circumstances leading to such
claim have arisen, and notices delivered to the procuring entity in order that it could have
investigated them at the time. Failure to provide such notices shall constitute a waiver by the
contractor of any claim.
6. Who is the signatory from DPWH for Department Order No. 144, series of 2016?
a. Series of 2003
b. Series of 2006
c. Series of 2016
d. Series of 2012
8. Time Extension shall be made prior to the expiration of the contract time within ________
calendar days after such work has been commenced or after the circumstances leading to such
claim have arisen
a. 40 c.d
b. 35 c.d
c 30 c.d
d. 25 c.d
a. Project Logbook
b. Project Output
c. Project Files
d. Project Document
10. Which of the following D.O is/are not supersedes by D.O No. 144, Series of 2016?
a. 3-5 percent
b. 5-10 percent
c. 10-15 percent
d. 15-20 percent
2. Before procurement, the _______ shall ensure that the detailed engineering plans for the
contract, especially if prepared more than 1 year ago, are properly updated to reflect current
physical conditions.
a. Implementing Office
b. Executive Office
c. Judicial Office
d. Secretariat
3. Who will provide the electronic copy of the approved plans upon the issuance by the DPWH
of the Notice to Proceed?
a. Implementing Office
b. Executive Office
c. Contractor
d. Secretariat
4. The processing by the IO of VOs from its preparation to approval shall not exceed _____.
a. 22 Working Days
b. 10 Banking Days
c. 30 Calendar Days
d. 2 Weeks
5. 1st offense penalty for the failure to implement the provisions of this order.
a. Reprimand
b. Suspension for 1-30 days
c. Dismissal
d. None of the Above
6. 2nd offense penalty for the failure to implement the provisions of this order.
a. Reprimand
b. Suspension for 1-30 days
c. Dismissal
d. None of the Above
7. 3rd offense penalty for the failure to implement the provisions of this order.
a. Reprimand
b. Suspension for 1-30 days
c. Dismissal
d. None of the Above
8. Department Order No. 28 Subject: Specific Guidelines to Manage and Control _________ for
DPWH Infrastructure Contracts.
a. Variation Orders
b. Bid Bulletins
c. Construction Plans
d. Bid Documents
9. The IO shall see to it that, within _____ after emergency work under a proposed VO has
commenced, the contractor must deliver a notice for the claim of a VO.
a. 5 Calendar Days
b. 7 Calendar Days
c. 24 Hours
d. 72 Hours
10. Who is the signatory for the Department Order No. 28, Series of 2015?
a. Rogelio Singson
b. Roberto Singson
c. Roberto Simpson
d. Roger Singson
1. A "request for prior clearance" should only be a/an __________ for an approving official to
establish the need for additional works/ variation.
a. anuncio
b. commando
c. libretto
d. adaggio
2. Which office should all Requests for Prior Clearance to Issue Variation Order on Civil Works
and/or Consultancy Services Contracts for the approval/disapproval of the secretary be
submitted?
a. Assessor's Office
b. Office of the Vice Mayor
c. Office of the Undersecretary for Operations
d. Engineering and Planning Office
3. To facilitate the review process, the Implementing Office concerned shall provide the
corresponding _______, Routing Slip and Checklist of required supporting documents.
a. Abstract
b. Executive Summary
c. Introduction
d. Structural Analysis
4. Who is responsible for assessment and recommendation as to funding availability and NEDA-
ICC requirements (if warranted)?
5. Who is the signatory from DPWH for Department Order No. 12, series of 2009?
a. Auditor
b. Head Civil Engineer
c. Assistant Secretary
d. Secretary
7. Which of the following is not listed in the basic documents to be submitted for the Prior
Clearance for a Variation Order?
a. Memorandum Request
b. Request for Information
c. Project Profile
d. Implementing Schedule and Financial Program
8. What is the Form No. required for Implementation Schedule and Financial Program?
a. Series of 2003
b. Series of 2006
c. Series of 2009
d. Series of 2012
10. D.O. 12 Subject: Revised Procedures in Seeking _______________ from the Secretary for
Variation Orders on Civil Works and Consultancy Services Contracts.
a. Prior Clearance
b. Zoning Clearance
c. Vertical Clearance
d. Priority Clearance