Tutorial Exercise CPM

This document provides instructions for two tutorial exercises on calculating the critical path for projects using the Critical Path Method (CPM). For each problem, students are asked to: 1) construct an activity arrow network and precedence diagram based on provided activity descriptions and durations, 2) determine the early start (ES), early finish (EF), late start (LS), late finish (LF), and float/slack for each activity, and 3) summarize the results in a matrix format including identifying the critical and non-critical paths. Problem A provides one set of 10 project activities and Problem B provides a second set of 11 project activities for analysis using CPM.

Uploaded by

alex
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
202 views

Tutorial Exercise CPM

This document provides instructions for two tutorial exercises on calculating the critical path for projects using the Critical Path Method (CPM). For each problem, students are asked to: 1) construct an activity arrow network and precedence diagram based on provided activity descriptions and durations, 2) determine the early start (ES), early finish (EF), late start (LS), late finish (LF), and float/slack for each activity, and 3) summarize the results in a matrix format including identifying the critical and non-critical paths. Problem A provides one set of 10 project activities and Problem B provides a second set of 11 project activities for analysis using CPM.

Uploaded by

alex
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

PEB 702 Engineering & Society

Tutorial Exercises: CPM (7 MARKS)

Date: 23 /4/2019

Problem A.

1. Construct an activity arrow network based on the activity descriptions. Show all your work.
Label activities by their activity letters.
2. Construct a precedence network diagram based on the activity descriptions using your key
box.
3. DETERMINE THE ES, EF, LS, LF AND FLOAT/SLACK
4. SUMMARIZE ALL RESULTS IN MATRIX FORMAT
a. ES
b. EF
c. LS
d. LF
e. SLACK
f. IDENTIFY THE CRITICAL PATH AND UNCRITICAL PATHS

Activity IMMEDIATE PREDECESSOR DURATION


A - 6
B A 6
C A 3
D C 10
E B 6
F C 4
G D,E 3
H B 8
I H 4
J G, I 4

Problem B.

1. Construct an activity arrow network based on the activity descriptions. Show all your work.
Label activities by their activity letters.
2. Construct a precedence network diagram based on the activity descriptions using your key
box.
3. DETERMINE THE ES, EF, LS, LF AND FLOAT/SLACK
4. SUMMARIZE ALL RESULTS IN MATRIX FORMAT
a. ES
b. EF
c. LS
d. LF
e. SLACK
f. Identify the critical path and uncritical paths

Tutorial exercise CPM Page 1 of 2


Activity IMMEDIATE PREDECESSOR DURATION
A - 6
B - 4
C A 3
D A 5
E A 1
F B,C 4
G B,C 2
H E,F 6
I E,F 5
J D, H 3
K G,I 5

Tutorial exercise CPM Page 2 of 2