Work Method Statement
Work Method Statement
Work Method Statement
WTC III
Initials
Initials
Page 2 of 6
Contents
1. Introduction 4
3. Test Procedures 4
4. Test Execution 5
Page 3 of 6
1. Introduction
1.1 The following test procedure has been prepared as a guideline for ;
1.3 The objective of this procedure is to verify that the correct air flow rate is
available at each unit and the overall air flow rate is correct.
2.2 The contractor undertaking the test capacity air flow for each unit, static
pressure and temperature measurement.
2.3 All instrumentation used for the testing, shall come with complete tools.
3. Test Procedures
3.1 Pre-Commissioning
Carry out the following prior to starting any testing and record the results:
3.1.1 Prior to commencing any testing on air flow AC, ensure that the air flow
AC have full speed running with approved method statements.
3.1.3 Identify all the unit AC existing confirm designed air flow rate.
Page 4 of 6
4. Test Execution
Once all pre-commissioning activities are completed, the following procedure will
be carried out for each system.
4.1.1 Monitor status of the AHU unit from Building Monitoring System (BMS) of
the building to see unit condition and setting and check function then take
the sreenshot from the BMS Screen as the record to confirm the damper
open or close.
4.1.2 Random check for VAV airflow by measuring the diffuser. Check the total
capacity air flow rate of VAV unit matches with the measurement with
Alnor. The two air flow rates should be approximately equal. (If the results
do not match, investigation shall be undertaken to verify the cause and
remedial works carried out).
4.1.3 Calculate the percentage of the design air flow rate being supplied to each
unit.
4.1.4 Record all results, make sure use the same parameter ( cfm, m/s. cmh)
4.1.5 If at any point during the air flow measurement the results do not match,
investigation shall be undertaken to verify the cause and remedial works
carried out.
Page 5 of 6
Page 6 of 6