Nigeria LNG Limited Construction / Commissioning

Natural Gas Liquefaction Complex Punch Lists & Exception Lists


Bonny Island, Nigeria Page: 1 of

Form No / Form Rev :


CONSTRUCTION
QUALITY CONTROL PROCEDURE PR834-06 /

“RSO” REINSTATEMENT PUNCH LIST SYSTEM NUMBER:

Subcontract Number: Subcontractor (Company Name) : Date Issued / Rev No : DISCIPLINE:


/ Rev
Location / Area: Unit No : Issued By (Name) :
Sheet: : 1 of
CONTRACTOR /
ITEM Item or DWG PRIORITY COMPLETED
No NUMBER DESCRIPTION OF WORK
COMMISSIONING COMPANY
(A/B/c) CONTRACTOR (Date/Initials)
(Date/Initials)

ALL PRIORITY A ITEMS ABOVE HAVE BEEN VERIFIED AND ARE COMPLETE. INCOMPLETE PRIORITY B ITEMS WILL BE
TRANSFERRED TO THE MECHANICAL/RFU EXCEPTION LIST.

COMMISSIONING CONTRACTOR :

Name: (Print) Signature: Date:

COMPANY :

Name (Print): Signature: Date:

PRIORITY A ITEMS SHALL BE COMPLETED BEFORE MECHANICAL COMPLETION (MC).


PRIORITY B ITEMS MAY BE COMPLETED AFTER (MC).
PRIORITY C ITEMS WILL BE COMPLETED BY COMMISSIONING GROUP

JP 1000 NLG