Control House
Control House
Control House
Control house
Nowadays, the control house is one of the main parts in every modern HV
switchyard and substation. Why? Simply, because substations have grown in
complexity and equipment such as circuit breakers, switch disconnectors, CT,
VTs and others must be controlled, monitored and protected from some
common point in the field.
1.1 Foundation
The control house foundation typically consists of a spread footing with either
masonry blocks or cast-inplace walls. The footing is designed for an allowable
bearing capacity based on soil data. If soil data is not available, a maximum
bearing of 48 kPa can be used.
The footings are installed below frost depth and in accordance with local
building codes and practices.
Drilled piers are an alternative to spread footings. Drilled piers are especially
applicable for pre-engineered metal buildings with structural supporting bases
that can rest directly on the piers without requiring a concrete floor slab. Soil
data is necessary for determining the required depth, diameter, and reinforcing
of the piers.
Damp-proofing of foundation walls is desirable, especially if concrete block is
used. If a basement level is constructed, damp-proofing should be provided.
SUBSTATION CONTROL HOUSE
Footing drains are usually provided when a basement level is constructed. All
foundation walls should be insulated with a 5.1-cm (2-inch) thickness of rigid
insulation for energy conservation.
It is preferable to install the insulation on the inside of the walls, although the
outside is acceptable.
Figure 2 –
New control house piers poured and cables installed before the control house arrives
Go back to contents ↑
1.2 Floor
SUBSTATION CONTROL HOUSE
The control house floor is typically a floating concrete slab 12 to 16 cm thick
reinforced with welded wire fabric, deformed steel bars, or a combination of
both.
The base beneath the floor slab should be 10-12 cm of compacted sand or
gravel, thoroughly mixed and compacted sand or gravel, or thoroughly mixed
and compacted natural soil. A 0.15 mm thick plastic film vapor barrier should be
installed between the floor slab and the base.
The method for cable routing in the control house has to be considered before
finalization of the floor slab design. Cable trenches can be formed into the floor
slab, or false floors can be installed providing access to large areas below the
finished floor.
Go back to contents ↑
The pre-engineered metal building is the easiest to procure and erect. The
manufacturer can design and fabricate the required building components when
given the building size; wind, snow, and ice loads; and any special
requirements such as additional roof loads for suspended cable trays or other
equipment.
Masonry buildings constructed of block masonry are most economical when
masonry module dimensions are used to size the building and the building
openings.
SUBSTATION CONTROL HOUSE
Figure 3 –
Control house on the left
Two types of roof systems are commonly used for masonry buildings: pre-cast,
pre-stressed concrete panels; and steel joists and steel decks. A sloping roof is
recommended for both systems and can be obtained by pitching the roof deck
or installing tapered roof insulation.
The roof membrane has to be compatible with the slope. For the slopes of 8.3
cm/m (1 in./ft) and less, built-up pitch and slab is commonly used. For greater
slopes, gravel is used.
The control house should be equipped with at least one double door, possibly
with a removable transom, conveniently located to facilitate equipment entry
and removal. In certain circumstances a second exit needs to be installed in the
control house.
If the plan of the room or space and the character and arrangement of equipment are such that
an accident would be likely to close or make inaccessible a single exit, a second exit shall be
provided.
SUBSTATION CONTROL HOUSE
The National Electrical Code (NEC) also defines specific requirements for a
second exit. The doors should include locking devices, astragals to prevent
water from entering, and adequate weatherstripping and hardware to permit a
rapid exit from the control house.
Consider adequate methods for building insulation. These methods include use
of insulated wall panels, ceiling insulation, storm doors, and windows, and
weatherstripping around all openings.
Metal buildings are shop painted and require only minor field touch-up after
erection. Masonry buildings may be left unpainted or may be painted with
portland cement or latex paint. Tint all prime coats to match the finished coat.
Go back to contents ↑
Double or duplex panels are commonly used for higher voltage circuits,
necessitating additional space for equipment mounting. Normally, these panels
are arranged in two parallel rows with the panel backs facing each other . In
this configuration, operating, instrumentation, and control equipment for a circuit
is installed on the front of one panel, and the corresponding relaying equipment
for the same circuit is installed on the front of the panel directly to the rear.
In some instances, two circuits may share the same control and relaying
panels.
SUBSTATION CONTROL HOUSE
Some equipment such as static relaying systems and communications
equipment is available mounted in racks. Consequently, separate relay and/or
control panels are not required for this equipment.
Compact relay and programmable logic controller designs can be mounted on 48.26-cm (19-
inch) racks.
SUBSTATION CONTROL HOUSE
Figure 6 – Relay protection panels in control room (photo credit: Protection Installation Services
Ltd)
Figure 7 – Mimic diagram in protection relay panel (photo credit: Edvard Csanyi)
Locate relays beginning at the tops of the relay panels and working downward.
Relays with glass covers should not be located within 12 inches of the floor to
avoid inadvertent breaking of the glass. Locate operating switches at
convenient heights near the center of the boards. Require nameplates for all
devices.
Provide ample space for relay installation, removal, operation, and
testing. Panel construction can include removable front plates for device
mounting.
SUBSTATION CONTROL HOUSE
Panels may also include 19-inch rack mounting facilities. Many of the newer
relays and items of accessory equipment are designed to fit into 19-inch racks.
Cover plates may cover space reserved for future use. In this way, only a new
predrilled plate is required when changing out a device or modifying the
configuration.
Figure 8 – 19-inch rack-mounted protection relay type MICOM and test sockets (photo credit:
Edvard Csanyi)
SUBSTATION CONTROL HOUSE
Panel wiring is accomplished on the backs of the panels. Devices are
interconnected and wired to terminal blocks, as required, for operation and
connection to devices on other panels.
Panels can include small sections perpendicular to the main section at each
end for installation of terminal blocks, fuse blocks, or small auxiliary
devices.
Cable connections from the equipment in the substation yard can be made
directly to terminal blocks mounted on the panels or to strategically placed
terminal cabinets. Interconnections between the terminal cabinets and the
panels can then be made with single conductor wire.
Panel arrangement in the control house should permit ready accessibility to the
backs of the panels. Some vendors of pre-engineered buildings can provide
completely wired and tested control and relay panels and auxiliary AC/DC
power systems as part of the building package.
Go back to contents ↑
2.2 DC Equipment
Substation DC equipment located in the control house normally consists of the
battery, battery charger, monitoring and control devices, and distribution
panelboard.
Detailed design requirements and procedures for the substation DC system can be found
Go back to contents ↑
2.3 AC Equipment
A low-voltage AC system is provided in the substation for lighting, convenience
outlets, heating, ventilating, air conditioning (HVAC) equipment and
miscellaneous control functions.
For greater reliability, two separate sources may be provided for the AC system
service. These sources are often fed through a manual or automatic transfer
switch so that ac system power can be restored if one source fails.
SUBSTATION CONTROL HOUSE
Figure 11 –
Substation AC Auxiliary Supply For Inessential Loads (on photo: AC auxiliary switchgear
400/230 V; credit: ZPAS Group – zpasgroup.co.uk)
Go back to contents ↑
2.4 Cableways
Cable routing can be accomplished by using any of several methods.
The sizes and locations of the cable trenches are based on the quantities of
cables and locations of panels and equipment to be interconnected .
Usually, a cable trench is located adjacent to the backs of the control and relay
panels to facilitate panel interconnections.
With duplex panels, it may be desirable to use the entire space between the
front and rear panels as cable trench, depending on circuit quantities.
SUBSTATION CONTROL HOUSE
Figure 12 –
Concrete cable trenches in control house
Go back to contents ↑
The top of the removable panels should be flush with the finished floor.
When cables are mounted under false floors, establish routes and paths in
which cables should be routed. This will allow the separation of circuits as
required to maintain system reliability based on duplicate circuits.
If circuits in one area are damaged, other undamaged circuits in the other parts
of the building are likely to keep the substation in service.
SUBSTATION CONTROL HOUSE
Go back to contents ↑
2.4.3 Conduits
Conduits can be used for cable routing in floors, along walls, and for cable
entrance into the control house. Conduits are available in plastic, aluminum,
and steel. Each of these types may be used in control houses for wire
containment to convenience outlets, lighting fixtures, and other control house
auxiliary power equipment.
Plastic conduit is easily installed and is available in a variety of sizes. Take
adequate physical and thermal precautions when using plastic conduit to
ensure safe operation.
Metallic conduits of aluminum and steel are widely used as control house
cableways. Intermediate- and heavy-walled steel conduit provide excellent
physical protection.
Figure 13 –
Cables in false floor of a substation control house
SUBSTATION CONTROL HOUSE
The installed costs, however, may be relatively high because of the extensive
labor required for installation. The installed cost of rigid aluminum conduit may
be somewhat less than that for steel.
A lower installed cost may be realized by using thin-walled steel conduit (i.e.,
electrical metallic tubing) since it is less expensive and easier to install.
Go back to contents ↑
2.4.4 Wireways
Wireways are sheet-metal troughs used for routing groups of power circuits
around a control house to feed various branch circuits. Conduit is used between
the wireway and the devices.
Wireway offers the advantage of laying rather than pulling the cable into
position and the ability to change or reroute circuits easily . Wireway is
available with hinged or removable covers in a variety of lengths and sizes.
Select and install wireway in accordance with the National Electrical Code.
Figure 14 –
Cables laid on metallic wireways in false floor
SUBSTATION CONTROL HOUSE
Go back to contents ↑
An advantage of cable trays is the ability to lay rather than pull in the
conductors. Suspended cable trays, however, prevent extensive use of this
technique because of support locations.
A large variety of types, sizes, and fittings is available to suit individual
requirements. Cable tray should be selected and installed in accordance with
the NEC and NEMA Standards.
Go back to contents ↑
SUBSTATION CONTROL HOUSE
Pitch the sleeves to drain out of the building. Provide covers over the cables.
Install spare sleeves during initial construction.
Figure 16 –
Cables entries in control house
Go back to contents ↑
2.6 Lighting
Fluorescent lamps are generally used for lighting in control houses. The trend is
toward energy-saving lamps and energy-saving electromagnetic or electronic
ballasts.
houses. This system can be operated in case of failure of the ac system. It can be operated
Go back to contents ↑
In areas requiring heat only, unit electric space heaters are positioned
throughout the control house for balanced heating. If both heating and cooling
are required, electric heat pumps can be used. Several small units, or one large
unit with a duct system for air distribution, can be used. Supplemental electric
resistance heating coils may be required for heating in colder areas.
In some cases baseboard radiation heating units can be used in rooms not
reached by the main heating system. These rooms include offices, lavatories,
and storage rooms.
Figure 17 –
Louvers to achieve good air circulation
Most stations will be unattended and, therefore, a normal personal comfort level
is not required. However, for maintenance reasons, comfort levels are
necessary.
SUBSTATION CONTROL HOUSE
If the control house is to be heated only, it is usually desirable to install power
ventilation equipment for air circulation. Size the system for three to five air
changes per hour. Place power-operated, thermostatically controlled roof
ventilators and manually operated wall louvers to achieve good air circulation.
Position wall louvers so that equipment does not interfere with air circulation. Provide
If control house air conditioning is used to provide positive air pressure, then
the vent should remain open and fan should run continuously . This also
applies if the unit is a heat pump.
The isolated battery room should be equipped with a gravity roof ventilator to
remove corrosive and combustible gases. Do not use power-operated roof
ventilators.
Go back to contents ↑
Most substations with toilet facilities will require septic tank and drain field
systems.
Go back to contents ↑
SUBSTATION CONTROL HOUSE
2.9 Communications
A commercial telephone is usually installed in the control house for external
communications. Additionally, system telephones or voice channels over carrier
systems may be used for system communications.
Go back to contents ↑
References:
1. Design Guide for Rural Substations by United States Department of
Agriculture
2. Drop-In Control House for a Large 230 kV Transmission Substation: A
Case Study in Implementation by Douglas M. Arcure (Shaw Group) and
Chris Clippinger (Schweitzer Engineering Laboratories, Inc.)