UltimateCertificationSuccess - PMBOK Guide Summary 1-5
UltimateCertificationSuccess - PMBOK Guide Summary 1-5
UltimateCertificationSuccess - PMBOK Guide Summary 1-5
Program is defined as a group of related projects, subsidiary programs, and program activities
managed in a coordinated manner to obtain benefits not available from managing them individually.
Programs are not large projects. A very large project may be referred to as a megaproject. As a
guideline, megaprojects cost US$1billion or more, affect 1 million or more people, and run for years.
Program and project management focus on doing programs and projects the “right” way. And
Portfolio management focuses on doing the “right” programs and projects
1
Organizational Project Management (OPM) is defined as a framework in which portfolio, program, and
project management are integrated with organizational enablers in order to achieve strategic objectives.
The purpose of OPM is to ensure that the organization undertakes the right projects and allocates critical
resources appropriately and ensure that all levels in the organization understand the strategic vision.
Project life cycle is the series of phases that a project passes through from its start to its completion. It
provides the basic framework for managing the project. The phases may be sequential, iterative, or
overlapping
Project life cycles can be predictive or adaptive, within a project life cycle, there are generally one or more
phases that are associated with the development of the product, service, or result. These are called a
development life cycle (they can be predictive, iterative, incremental, adaptive, or a hybrid model).
Predictive life cycle (Waterfall): the project scope, time, and cost are determined in the early
phases of the life
Iterative life cycle: project scope is generally determined early in the project life cycle, but time and
cost estimates are routinely modified
Incremental life cycle deliverable is produced through a series of iterations that successively add
functionality within a predetermined time frame and it’s considered complete only after the final
iteration
Adaptive life cycles are agile, iterative, or incremental. The detailed scope is defined and approved
before the start of an iteration. Adaptive life cycles are also referred to as agile or change-driven
life cycles
Hybrid life cycle is a combination of a predictive and an adaptive life cycle. Those elements of the
project that are well known or have fixed requirements follow a predictive development life cycle,
and those elements that are still evolving follow an adaptive development life cycle
Project life cycles are independent of product life cycles, which may be produced by a project. A product
life cycle is the series of phases that represent the evolution of a product, from concept through delivery,
growth, maturity, and to retirement.
Project Phase: Collection of logically related project activities that culminates in the completion of one or
more deliverables. The phases in a life cycle can be described by a variety of attributes
Phase gate: is held at the end of a phase. The project’s performance and progress are compared to project
and business documents. Also Called (phase review, stage gate, kill point, and phase entrance or phase
exit)
2
PROJECT MANAGEMENT PROCESSES
Processes used once or at predefined points in the project: (Develop Project Charter, Develop Project
Management Plan, Close Project/Phase, Plan Scope Management, Collect Requirements, Create WBS,
Plan Schedule Management, Plan Cost Management, Determine Budget, Plan Quality Management, Plan
Resource Management, Plan Risk Management, Plan Procurement Management)
Processes that are performed periodically as needed: (Validate Scope, Estimate Costs, Estimate
Activity Resources, Acquire Resources, Plan Communication Management, Conduct Procurement, Identify
Stakeholders, Plan Stakeholder Management)
Processes that are performed continuously throughout the project: (All other remaining process such
as define activities)
Project Management is divided into 5 Process Groups (Initiating, Planning, Executing, Monitoring &
Controlling and Closing Process Group)
Project Management Divided into 10 Knowledge Areas (Integration, Scope, Schedule, Cost, Quality,
Resource, Communication, Risk, Procurement and Stakeholder Management)
Project data are regularly collected and analyzed throughout the project life cycle. The following definitions
identify key terminology regarding project data and information
Work performance data: The raw observations and measurements identified during activities performed to
carry out the project work, such as (Percent of finished work, Start and finish dates, number of change
requests, actual costs and durations). Project data are usually recorded in a Project Management
Information System (PMIS)
Work performance information: Performance data collected from various controlling processes, analyzed
in context and integrated based on relationships across areas, such as (status of deliverables,
implementation status for change requests, and forecast estimates to complete)
Work performance reports. The physical or electronic representation of work performance information
compiled in project documents, which is intended to generate decisions or raise issues, actions, or
awareness, such as (status reports, memos, justifications, information notes, electronic dashboards,
recommendations, and updates)
3
4
Methodology is a system of practices, techniques, procedures, and rules used by those who work in a
discipline which project manager apply in their management. (PMBOK is NOT a methodology, but a
recommended reference for tailoring). Tailoring is necessary because each project is unique.
Project sponsor is generally accountable for the development and maintenance of the project business
case document. The project manager is responsible for providing recommendations and oversight
Project managers should appropriately tailor the noted project management documents, In some
organizations, the business case and benefits management plan are maintained at the program level
Business case is a documented economic feasibility study used to establish the validity of the benefits
of a selected component lacking sufficient definition and that is used as a basis for the authorization of
further project management activities it lists the objectives and reasons for project initiation.
It helps measure the project success at the end of the project against the project objectives The
business case may be used before the project initiation and may result in a go/no-go decision for the
project.
A business case may include (Business Needs, Analysis of the situation (Required, Desired, Optional),
Evaluation)
Project benefits management plan is the document that describes how and when the benefits of the
project will be delivered, and describes the mechanisms that should be in place to measure those benefits.
Development and maintenance of the project benefits management plan is an iterative activity
Development of the benefits management plan begins early in the project life cycle with the definition of the
target benefits to be realized and it may include (Target benefits, Strategic alignment, Timeframe for
realizing benefits, benefits owner, metrics, assumptions, risks)
Developing the benefits management plan makes use of the data and information documented in the
business case and needs assessment.
It is possible for a project to be successful from a scope/schedule/budget viewpoint, and to be unsuccessful
from a business viewpoint. This can occur when there is a change in the business needs or the market
environment
5
Chapter 2 (Environment in Which Projects Operate)
Projects exist and operate in environments that may have an influence on them. These influences can have
a favorable or unfavorable impact on the project. Two major categories of influences are enterprise
environmental factors (EEFs) and organizational process assets (OPAs).
EEFs originate from the environment outside of the project and often outside of the enterprise. EEFs may
have an impact at the organizational, portfolio, program, or project level. EEFs refers to conditions not
under the control of the project team and it could Internal and External.
OPAs are internal to the organization. These may arise from the organization itself, a portfolio, a program,
another project, or a combination of these. Organizational process assets (OPAs) are the plans,
processes, policies, procedures, and knowledge bases.
Processes, policies, and procedures are not updated as part of the project work and usually established
by the project management office (PMO). However, these can be updated only by following the appropriate
organizational policies associated with updating processes.
Organizational knowledge bases are updated throughout the project with project information
6
Examples of OPA’s (Organizational Knowledge Repositories)
Configuration Financial data Historical information
management repositories and lessons learned
Issue and defect repositories for metrics Project files from previous
management data projects
A system is a collection of various components that together can produce results not obtainable by the
individual components alone. A component is an identifiable element within the project or organization that
provides a particular function or group of related functions
Systems are Dynamic, can be optimized, but can’t be optimized with components at same time, Systems
are nonlinear in responsiveness. Systems are typically the responsibility of an organization’s
management
Project governance refers to the framework, functions, and processes that guide project management
activities in order to create a unique product
A project management office (PMO) is an organizational structure that standardizes the project-related
governance processes and facilitates the sharing of resources, methodologies, tools, and techniques.
Supportive PMOs provide a consultative role to projects by supplying templates, best practices,
training, access to information, and lessons learned from other projects. This type of PMO serves as a
project repository. The degree of control provided by the PMO is low.
Controlling PMOs provide support and require compliance through various means. The degree of
control provided by the PMO is moderate. Compliance may include (Adoption of project management
frameworks or methodologies, use of specific templates, forms, and tools, conformance to governance
frameworks)
Directive PMOs take control of the projects by directly managing the projects. Project managers are
assigned by and report to the PMO. The degree of control provided by the PMO is high
PMO is the natural liaison between the organization’s portfolios, programs, projects, and the organizational
measurement systems
7
8
Chapter 4 (Project Integration Management)
Project Integration Management includes the processes and activities to identify, define, combine, unify,
and coordinate the various processes and project management activities within the Project Management
Process
Iterative and agile approaches promote the engagement of team members as local domain experts in
integration management. The team members determine how plans and components should integrate.
team. The project manager’s focus is on building a collaborative decision-making environment and
ensuring the team has the ability to respond to changes.
Develop Project Charter is the process of developing a document that formally authorizes the existence
of a project and provides the project manager with the authority to apply organizational resources to
project activities.
Key benefits of this process are that it provides a direct link between the project and the strategic
objectives of the organization, creates a formal record of the project, and shows the organizational
commitment to the project
9
Develop Project Charter Inputs:
2- Agreements
It may take the form of contracts, memorandums of understanding (MOUs), service level agreements
(SLA), letters of agreement, letters of intent, verbal agreements, email, or other written agreements
Typically, a contract is used when a project is being performed for an external customer
1- Expert Judgment
Provided by any group or person with specialized education, knowledge, skill, experience, or training.
Expertise can be from (Organizational strategy, Benefits management, Technical knowledge of the
industry, Duration and budget estimation, Risk identification)
2- Data Gathering
Brainstorming: technique is used to identify a list of ideas in a short period of time. It is conducted in
a group environment and is led by a facilitator. Brainstorming comprises two parts: idea generation
and analysis. Brainstorming can be used to gather data and solutions or ideas from stakeholders,
subject matter experts (SME), and team members when developing the project charter.
Focus Groups: bring together stakeholders and subject matter experts to learn about the perceived
project risk, success criteria, and other topics in a more conversational way than a one-on-one
interview. A trained moderator guides through an interactive discussion.
Interviews: used to obtain information on high-level requirements, assumptions or constraints,
approval criteria, and other information from stakeholders by talking directly to them.
10
3- Interpersonal and Team Skills
Conflict Management: Conflict management can be used to help bring stakeholders into alignment on
the objectives, success criteria, high-level requirements, project description, summary milestones, and
other elements of the charter.
Facilitation: ability to effectively guide a group event to a successful decision, solution, or conclusion. A
facilitator ensures that there is effective participation, that participants achieve a mutual
understanding, that all contributions are considered, that conclusions or results have full buy-in
according to the decision process established for the project, and that the actions and agreements
achieved are appropriately dealt with afterward.
Meeting Management: includes preparing the agenda, ensuring that a representative for each key
stakeholder group is invited, and preparing and sending the follow-up minutes and actions.
4- Meetings
Meetings are held with key stakeholders to identify the project objectives, success criteria, key
deliverables, high-level requirements, summary milestones, and other summary information
2- Assumption Log
High level strategic and operational assumptions and constraints are normally identified in the
business case before the project is initiated and will flow into the project charter.
Lower-level activity and task assumptions are generated throughout the project such as defining
technical specifications, estimates, the schedule, risks, etc.
The assumption log is used to record all assumptions and constraints throughout the project life
cycle.
11
Develop Project Management Plan (Planning Process Group)
Develop Project Management Plan is the process of defining, preparing, and coordinating all plan
components and consolidating them into an integrated project management plan.
Key benefit of this process is the production of a comprehensive document that defines the basis of all
project work and how the work will be performed
1- Project Charter
Project team uses the project charter as a starting point for initial project planning
Project charter should define the high-level information that will be elaborated.
1- Expert Judgment
individuals or groups with specialized knowledge of or training such as (Tailoring, develop additional
components, determine resources and skill level, define Configuration Management, prioritize work on
the project and ensure resources are appropriately allocated)
2- Data Gathering
Brain Storming: Attendees include the project team members although other subject matter experts
(SMEs) or stakeholders may also participate
12
Checklists: May guide the project manager to develop the plan or may help to verify that all the
required information is included in the project management plan
Focus Groups: bring together stakeholders to discuss the project management approach and the
integration of the different components of the project management plan
Interviews: Interviews are used to obtain specific information from stakeholders to develop the project
management plan or any component plan or project document
Conflict Management
Facilitation
Meeting Management
4- Meetings
Meetings are used to discuss the project approach, determine how work will be executed to accomplish
the project objectives, and establish the way the project will be monitored and controlled
kick-off meeting is usually associated with the end of planning and the start of executing. Its
purpose is to communicate the objectives of the project, gain the commitment of the team for the
project, and explain the roles and responsibilities of each stakeholder
For small projects, there is usually only one team that performs the planning and the execution. In this
case, the kick-off occurs shortly after initiation, in the Planning Process Group, because the team is
involved in planning
For large projects, a project management team normally does the majority of the planning, and the
remainder of the project team is brought on when the initial planning is complete, at the start of the
development/implementation. In this instance, the kick-off meeting takes place with processes in the
Executing Process Group
Multiphase projects will typically include a kick-off meeting at the beginning of each phase
.
Develop Project Management Plan Outputs:
Subsidiary management plans: (Scope Management plan, Requirements management plan, Schedule
management plan, Cost management plan, Quality management plan, Resource management plan,
Communications management plan, Risk management plan, Procurement management plan, Stakeholder
engagement plan.)
13
Baselines
Scope Baseline: approved version of a scope statement, work breakdown structure (WBS), and its
associated WBS dictionary, which is used as a basis for comparison
Schedule Baseline: The approved version of the schedule model that is used as a basis for
comparison to the actual results.
Cost Baseline: The approved version of the time-phased project budget that is used as a basis for
comparison to the actual results.
Additional components
Change management plan: Describes how the change requests throughout the project will be
formally authorized and incorporated.
Configuration management plan: Describes how the information about the items of the project
(and which items) will be recorded and updated so that the product, service, or result of the project
remains consistent and/or operative.
Performance measurement baseline: An integrated scope-schedule-cost plan for the project work
against which project execution is compared to measure and manage performance.
Project life cycle: Describes the series of phases that a project passes through from its initiation to
its closure.
Development approach: Describes the product, service, or result development approach, such as
predictive, iterative, agile, or a hybrid model.
Management reviews: Identifies the points in the project when the project manager and relevant
stakeholders will review the project progress to determine if performance is as expected, or if
preventive or corrective actions are necessary.
Project management plan is one of the primary documents used to manage the project, other project
documents are also used. These other documents are not part of the project management plan;
however, they are necessary to manage the project effectively
14
Direct and Manage Project Work (Executing Process Group)
Direct and Manage Project Work is the process of leading and performing the work defined in the project
management plan and implementing approved changes to achieve the project’s objectives
Key benefit of this process is that it provides overall management of the project work and deliverables,
thus improving the probability of project success
2- Project Documents
15
The approved change request may be a corrective action, a preventive action, or a defect repair.
Approved change requests are scheduled and implemented by the project team and can impact any
area of the project or project management plan.
The approved change requests can also modify the formally controlled project management plan
components or project documents.
1- Expert Judgment
2- Project Management Information System (PMIS)
PMIS provides access to information technology (IT) software tools, such as scheduling software,
work authorization systems, configuration management systems, information collection and
distribution systems.
Automated gathering and reporting on key performance indicators (KPI) can be part of this
system.
3- Meetings
Type of meetings (Kick-off, technical, sprint, iteration planning, Scrum daily standups, steering
group, problem solving, progress update and retrospective meetings)
1- Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that is
required to be produced to complete a process, phase, or project
Deliverables are typically the outcomes of the project and can include components of the project
management plan
Change control should be applied once the first version of a deliverable has been completed
The control of multiple deliverable versions is supported by configuration management tools.
16
3- Issue Log
Project document where all the issues are recorded and tracked. Data on issues may include
Issue log is created for the first time as an output of this process
Issue log is updated as a result of the monitoring and control activities throughout the project’s life
cycle.
4- Change Requests
Any project stakeholder may request a change
Change requests can be initiated from inside or outside the project and they can be optional or
legally/contractually mandated
Change Requests can be (Corrective, Preventive, Defect repair (modify nonconforming product),
Updates)
5- Project Management Plans Updates
6- Project Document Updates
Activity list, Assumption log, Lessons learned register, Requirements documentation, Risk register,
Stakeholder register
17
Mange Project Knowledge (Executing Process Group)
Manage Project Knowledge is the process of using existing knowledge and creating new knowledge to
achieve the project’s objectives and contribute to organizational learning
Key benefits of this process are that prior organizational knowledge is leveraged to produce or improve the
project outcomes, and knowledge created by the project is available to support organizational operations
and future projects or phases
3- Deliverables
4- Enterprise Environmental Factors
5- Organizational Process Assets
1- Expert Judgment
2- Knowledge Management
Knowledge Management tools can be applied face-to-face or virtually, or both. However Face-to-
face interaction is usually the most effective way to build the trusting relationships.
18
3- Information Management
Information management tools and techniques are used to create and connect people to
information. Such as (PMIS, Lessons learned register)
Tools and techniques that connect people to information can be enhanced by adding an element of
interaction
Communities of practice (called communities of interest) & SME’s may generate insights that lead to
improved control processes
19
Monitor and Control Project Work (Monitor & Control
Process Group)
Monitor and Control Project Work is the process of tracking, reviewing, and reporting the overall
progress to meet the performance objectives defined in the project management plan.
Key benefits of this process are that it allows stakeholders to understand the current state of the
project, to recognize the actions taken to address any performance issues, and to have visibility into
the future project status with cost and schedule forecasts
4- Agreements
Procurement agreement includes terms and conditions, and may incorporate other items that the
buyer specifies regarding what the seller is to perform or provide. Project manager needs to oversee
contractor’s work to make sure all agreements are met
20
Monitor and Control Project Work Tools and Techniques:
1- Expert Judgment
Earned Value analysis, techniques to estimate durations and costs, trend analysis, risk
management, contract management, technical knowledge on industry focus area.
2- Data Analysis
Alternative analysis: Used to select the corrective actions or a combination of corrective and
preventive actions to implement when a deviation occurs.
Cost-benefit analysis: Helps to determine the best corrective action in terms of cost in case of
project deviations.
Earned value analysis: Provides an integrated perspective on scope schedule, and cost
performance.
Root cause analysis: Focuses on identifying the main reasons of a problem
Trend analysis: Used to forecast future performance based on past results. looks ahead in the
project for expected slippages and warns the project manager ahead of time. This information is
made available early enough in the project timeline. The results of trend analysis can be used to
recommend preventive actions if necessary.
Variance analysis: reviews the differences (or variance) between planned and actual performance,
such as (cost estimates, resources utilization, resources rates, technical performance). Variance
analysis may be conducted in each Knowledge Area. This allows for the appropriate preventive or
corrective actions to be initiated
3- Decision Making
Voting: making decisions based on unanimity, majority, or plurality.
4- Meetings
Meetings may be face-to-face, virtual, formal, or informal. Example groups and review meetings
21
Perform Integrated Change Control (Monitor & Control
Process Group)
Perform Integrated Change Control is the process of reviewing all change requests; approving changes
and managing changes to deliverables, project documents, and the project management plan. This process
reviews all requests for changes to project documents, deliverables, or the project management plan and
determines the resolution of the change requests
Key Benefit it allows for documented changes within the project to be considered in an integrated manner
while addressing overall project risk
22
2- Project Documents
Basis of estimates: how the duration, cost, and resources estimates were derived and can be
used to calculate the impact of the change in time, budget, and resources.
Requirements traceability matrix: helps assess the impact of the change on the project scope
Risk report: presents information on sources of overall and individual project risks involved by the
change requested
3- Work Performance Reports
include resource availability, schedule and cost data, earned value reports, and burnup or burndown
charts
4- Change requests
All Monitoring and controlling processes and some of executing processes produce change request.
Change requests include
Corrective action: realigns the performance of project work with project management plan
Preventive action: ensures the future performance of the work aligned with project
management plan
Defect repair: modify a nonconforming product or product component
Updates: changes to formally controlled project documents to reflect modified ideas
3- Data Analysis
Alternative Analysis: assess the requested changes and decide which are accepted, rejected, or
need to be modified to be finally accepted.
Cost-benefit analysis: determine if the requested change is worth its associated cost.
23
4- Decision Making
Voting: take the form of unanimity, majority, or plurality to decide on whether to accept, defer or
reject the change request
Autocratic decision making: One individual takes the responsibility for making the decision for the
entire group.
Multicriteria decision analysis: uses a decision matrix to provide systematic analytical approach
to evaluate the requested changes according to a set of predefined criteria
5- Meetings
CCB may review configuration management activities
24
Close Project or Phase (Closing Process Group)
Close Project or Phase is the process of finalizing all activities for the project, phase, or contract.
Key benefits of this process are the project or phase information is archived, the planned work is
completed, and organizational team resources are released to pursue new endeavors
25
Close Project or Phase Inputs:
1- Project Charter
2- Project Management Plan
3- Project Documents
Such as (Assumption log, Basis of estimates, Change log, Issue log, Lessons learned register,
Milestone list, Project communications, Quality control measurements, Quality reports, Requirements
documentation, Risk register and Risk report)
4- Accepted Deliverables
Approved product specifications, delivery receipts and work performance documents.
Partial or interim deliverables may also be included for phased or cancelled projects
5- Business Documents
Business Case: justify the project and determines if the expected outcomes from the economic
feasibility study used to justify the project occurred
Benefits management plan: used to measure whether the benefits of the project were achieved as
planned.
6- Agreements
Requirements for formal procurement closure are usually defined in the terms and conditions of the
contract and are included in the procurement management plan
complex project may involve managing multiple contracts simultaneously or in sequence.
7- Procurement Documentation
To close the contract, all procurement documentation is collected, indexed, and filed.
“As-built” plans/drawing or “as-developed” documents, manuals and troubleshooting considered as
part of the procurement documents
This information can be used for lessons learned and as a basis for evaluating future contracts
1- Expert Judgment
Management control, Audit, Legal and procurement and Legislation and regulations.
2- Data Analysis
Document analysis: Assessing available documentation will allow identifying lessons learned and
knowledge sharing for future projects
26
Regression analysis: analyzes the interrelationships between different project variables that
contributed to the project outcomes to improve performance on future projects.
Trend analysis: validate the models used in the organization and to implement adjustments for
future projects
Variance analysis: Variance analysis can be used to improve the metrics of the organization by
comparing what was initially planned and the end result
3- Meetings
Examples: close-out reporting meetings, customer wrap-up meetings, lessons learned meetings and
celebration meetings.
3- Final Report
Includes information such as (description of the project/phase, scope objectives, quality objectives,
Cost objectives, summary of validation information for the final product, Schedule objectives,
summary how the project achieved business needs and summary for any risks)
27
Chapter 5 (Project Scope Management)
Project Scope Management includes the processes required to ensure that the project includes all the
work required, and only the work required. And it’s concerned with defining and controlling what is and is
not included in the project
Product Scope: features and functions that characterize a product, service, or result.
Project Scope: work performed to deliver a product, service, or result with the specified features and
functions
The term “project scope” is sometimes viewed as including product scope
Project Scope is measured against the Project Management Plan
Product Scope is measured against the Product Requirements
Project life cycles can range along a continuum from predictive approaches at one end to adaptive or
agile approaches at the other
In predictive life cycle the deliverables are defined at the beginning of the project and any changes to
the scope are progressively managed
In adaptive/agile life cycle the deliverables are developed over multiple iterations where detailed scope
is defined and approved for each iteration when it begins.
Projects with adaptive life cycles are intended to respond to high levels of change and require ongoing
stakeholder engagement
Overall scope of an adaptive project will be decomposed into a set of requirements and work to be
performed, sometimes referred to as a product backlog
At beginning of each iteration the team determine how many of highest priority item on backlog can be
delivered on next iteration. Three Process are repeated each iteration (Collect Requirements, Define
Scope and Create WBS)
In predictive life cycle Collect Requirements, Define Scope and Create WBS are performed at the
beginning of the project and updated as necessary using change control process
In adaptive/agile the sponsor and customer representatives should be continuously engaged with
the project to provide feedback on deliverables
In predictive projects, the scope baseline for the project is the approved version of the project scope
statement, work breakdown structure (WBS), and its associated WBS dictionary
Business Analysis are used in some organizations to defining, managing, and controlling
requirements activities
Activities of business analysis may start before a project is initiated and a project manager is assigned
Project manager is responsible for ensuring that requirements-related work is accounted
The relationship between a project manager and a business analyst should be a collaborative
partnership
Agile methods deliberately spend less time trying to define and agree on scope in the early stage of the
project and spend more time establishing the process for its ongoing discovery and refinement
In agile approaches, the requirements constitute the backlog.
28
Plan Scope Management (Planning Process Group)
Plan Scope Management is the process of creating a scope management plan that documents how the
project and product scope will be defined, validated, and controlled
Key benefit of this process is that it provides guidance and direction on how scope will be managed
throughout the project
1- Project Charter
High-level project description assumptions, constraints, and high-level requirements.
1- Expert Judgment
Previous similar projects and information in the industry, discipline and application area
2- Data Analysis
Alternative Analysis: Various ways of collecting requirements, create, validate and control scope.
3- Meetings
May include (Sponsor, project manager, team members and selected stakeholder)
29
Plan Scope Management Outputs:
Component of the project management plan that describes how the scope will be defined,
developed, monitored, controlled, and validated
Components includes processes that help (Preparing project scope statement, create WBS, how
the baseline will be approved and maintained and how formal acceptance will be obtained)
The scope management plan can be formal or informal, broadly framed or highly detailed
The requirements management plan is a component of the project management plan that describes
how project and product requirements will be analyzed, documented, and managed
It’s also referred as Business Analysis Plan according to Business analysis
Components may include (Configuration management activities, Requirements prioritization,
Metrics, Traceability structure and how requirements will be planned, tracked and reported)
Traceability structure reflects the requirement attributes captured on the traceability matrix.
Configuration management shows how changes will be initiated, how impacts will be
analyzed, how they will be traced and reported and authorization levels to approve changes
30
Collect Requirements (Planning Process Group)
Collect Requirements is the process of determining, documenting, and managing stakeholder needs and
requirements to meet objectives
Key benefit of this process is that it provides the basis for defining the product scope and project scope.
3- Project Documents
Includes (Assumption Log, Lessons learned register and Stakeholder register)
Stakeholder Register: used to identify stakeholders who can provide information on the
requirements also captures requirements and expectations that stakeholders have for the project.
4- Business Documents
Business Case influence this process as it describes required, desired, and optional criteria for
meeting the business needs
5- Agreements
contain project and product requirements.
31
Collect Requirements Tools & Techniques:
1- Expert Judgment
Experts specialized in (Business analysis, Requirements elicitation, Requirements analysis
Requirements documentation, Project requirements in previous similar projects, Diagramming
techniques, Facilitation, and Conflict management)
2- Data Gathering
Brainstorming: used to generate and collect multiple ideas related to project/product requirements
Interviews: Can be formal & informal to elicit information by talking directly to them, and is usually
performed by asked prepared or spontaneous questions and recording the responses. Interviews
are useful for obtaining confidential information. It may include individual/multiple
interviewers/interviewees
Focus Groups: Bring together prequalified stakeholders and subject matter experts to learn about
their expectations and attitudes about proposed product/service. A trained moderator guides the
group through interactive discussion to be more conversational than one-on-one interview
Questionnaires and surveys: written set of questions designed to quickly accumulate information
of large number of respondents. It’s most appropriate with varied audiences, geographically
dispersed for quick turnaround where statistical analysis could be appropriate.
Benchmarking: Comparing actual or planned products and processes to those of comparable
organizations (internal or external) to identify best practices, generate ideas for improvement and
provide a basis for measuring performance
3- Data Analysis
Document analysis which consists of reviewing and assessing any relevant documented information
to elicit requirements by analyzing existing documentation and identifying information relevant to
the requirements
4- Decision making
Voting: Used to classify and prioritize product requirements. (unanimity, majority and plurality)
Autocratic decision making: one individual takes responsibility for making the decision
Multicriteria decision analysis: decision matrix to provide a systematic analytical approach for
establishing criteria, such as risk levels, uncertainty, and valuation, to evaluate and rank many ideas
5- Data Presentation
Affinity diagrams: allow large numbers of ideas to be classified into groups for review and
analysis.
Mind mapping: consolidates ideas created through individual brainstorming sessions into a single
map to reflect commonality and differences in understanding and to generate new ideas.
32
6- Interpersonal and Team Skills
Nominal group technique: Enhances brainstorming with a voting process used to rank the most
useful ideas for further brainstorming or for prioritization. It includes four steps
Question is posed to the group. Each person silently generates and writes down their ideas
Moderator writes down the ideas on a flip chart until all ideas are recorded
Each recorded idea is discussed until all group members have a clear understanding
Individuals vote privately to prioritize the ideas. (Voting may take place in many rounds)
Observation and conversation (Job Shadowing): Direct way of viewing individuals in their
environment and how they perform their jobs. Usually used when people have difficulty or reluctant
to articulate their requirements. Usually it’s done externally by an observer viewing business expert
performing the job. Also can be done by a participant observer who actually performs a process to
experience how it’s done and uncover hidden requirements
Facilitation: Used with focused sessions that bring key stakeholders together to define product
requirements. Workshops can be used to quickly define cross-functional requirements and
reconcile stakeholder differences. This may increase stakeholder consensus and issues can be
discovered earlier and resolved more quickly than in individual sessions. Examples
Joint application design/development (JAD) used in software development industry
Quality function deployment (QFD): using in manufacturing industry. It collects customer
needs known as Voice of the Customer (VOC)
User stories: short, textual descriptions of required functionality developed during workshops
7- Context Diagram
Example of Scope model. Context diagrams visually depict the product scope by showing a
business system and how people and other systems (actors) interact with it. They show inputs to
the business system, the actor(s) providing the input, the outputs from the business system, and the
actor(s) receiving the output
Actor Business System Output Actor
8- Prototypes
Method of obtaining early feedback on requirements by providing a model of the expected product.
Examples (computer generated 2D, 3D models, mock-ups and simulations)
Prototypes support the concept of progressive elaboration
Storyboarding is a prototyping technique showing sequence or navigation through a series of
images or illustrations. Used in films, advertising
33
Collect Requirements Outputs:
1- Requirements Documentation
Describes how individual requirements meet the business need for the project.
Requirements may start out at a high level and become progressively more detailed as more
information about the requirements is known.
Requirements should be unambiguous (measurable and testable, traceable complete, consistent,
and acceptable to key stakeholders)
34
Define Scope (Planning Process Group)
Define Scope is the process of developing a detailed description of the project and product
key benefit of this process is that it describes the product, service, or result boundaries and acceptance
criteria
Since all the requirements identified in Collect Requirements may not be included in the project, the
Define Scope process selects the final project requirements from the requirements documentation
developed during the Collect Requirements process
Develops a detailed description of the project and product, service, or result.
The preparation of a detailed project scope statement builds upon the major deliverables,
assumptions, and constraints that are documented during project initiation.
Define Scope process can be highly iterative
In iterative life cycle projects, a high-level vision will be developed for the overall project, but the
detailed scope is determined one iteration at a time
3- Project Documents
Includes (Assumption log, Requirements documentation and Risk register)
2- Data Analysis
Alternatives Analysis: to meet the requirements and the objectives identified in the charter
3- Decision Making
Multicriteria decision analysis
4- Interpersonal and Team Skills
Facilitation:
35
5- Product Analysis
Used to define products and services. It includes asking questions about a product or service
Requirements are captured at a high level and decomposed to the level of detail needed to design
the final product
Examples include (Product breakdown, Requirements analysis, Systems analysis and engineering
and value analysis and engineering)
Project Scope Statement include (Product scope description, deliverables, acceptance criteria and
project exclusions)
36
Create WBS (Planning Process Group)
Create WBS is the process of subdividing project deliverables and project work into smaller, more
manageable components.
Key benefit of this process is that it provides a framework of what has to be delivered
2- Project Documents
Includes (Project scope statement and Requirements documentation)
1- Expert Judgment
2- Decomposition
Technique used for dividing and subdividing the project scope and project deliverables into smaller,
more manageable parts.
The work package is the work defined at the lowest level of the WBS for which cost and duration
can be estimated and managed.
Popular methods to create WBS structure: top-down approach, the use of organization-specific
guidelines, and the use of WBS templates
Bottom-up approach can be used to group subcomponents
37
Decomposition of the upper-level WBS components requires subdividing the work for each of the
deliverables or subcomponents into its most fundamental components
Agile approaches decompose epics to user stories
Decomposition may not be possible for a deliverable or subcomponent that will be accomplished far
into the future The project team usually waits until the deliverable or subcomponent is agreed on,
so the details of the WBS can be developed. This technique called rolling wave planning.
The total of the work at the lowest levels should roll up to the higher levels so that nothing is left out
and no extra work is performed. This is sometimes called the 100 percent rule.
1- Scope Baseline
The scope baseline is the approved version of a scope statement, WBS, and its associated WBS
dictionary and it’s component of the project management plan. Scope baseline includes
Project scope statement: description of the project scope, major deliverables and constraint.
WBS: Hierarchical decomposition of the total scope of work to be carried out by the project team
to accomplish the project objectives and create the required deliverables. Each descending
level of the WBS represents an increasingly detailed definition of the project work.
Work package: The lowest level of the WBS is work package with a unique identifier. Each
work package is part of a control account which is a management control point where scope,
budget, and schedule are integrated and compared to the earned value for performance
measurement. Each control account has two or more work packages. But work package is
associated with a single control account
Planning package: Include one or more planning packages. A planning package is a WBS
component below the control account and above the work package with known work content
but without detailed schedule activities
WBS dictionary: document that provides detailed deliverable, activity, and scheduling
information about each component in the WBS. It’s a document that support the WBS because
you can’t include all the information in the WBS. It contains (Codes, work description,
assumption, milestones, associated activities, resources, cost, quality requirement, references)
38
39
Validate Scope (Monitor and Controlling Process Group)
Validate Scope is the process of formalizing acceptance of the completed project deliverables
Key benefit of this process is that it brings objectivity to the acceptance process and increases the
probability of final product, service, or result acceptance by validating each deliverable
2- Project Documents
Includes (Lessons learned register, Quality reports, Requirements documentation and Requirements
traceability matrix)
3- Verified deliverables
Project deliverables that are completed and checked for correctness through Control Quality.
1- Inspection
Includes activities such as measuring, examining, and validating to determine whether work/deliverables
meet requirements and product acceptance criteria. They might be called “reviews and walkthroughs)
2- Decision Making
Voting
40
Validate Scope Outputs:
1- Accepted Deliverables
Deliverables that meet the acceptance criteria are formally signed and approved by customer/sponsor
3- Change Requests
The completed deliverables that have not been formally accepted are documented, along with the
reasons for non-acceptance of those deliverables Those deliverables may require a change request
for defect repair.
41
Control Scope (Monitor and Controlling Process Group)
Control Scope is the process of monitoring the status of the project and product scope and managing
changes to the scope baseline.
Key benefit of this process is that the scope baseline is maintained throughout the project.
Performance measurement baseline When using earned value analysis, the performance
measurement baseline is compared to actual results to determine if a change, corrective action, or
preventive action is necessary
2- Project Documents
Includes (Lessons learned register, Quality reports, Requirements documentation and
Requirements traceability matrix)
42
Control Scope Tools & Techniques:
1- Data Analysis
Variance analysis: compare the baseline to the actual results and determine if the variance is
within the threshold amount (Variance = Planned – Actual)
Trend analysis: examines project performance over time to determine if performance is improving
or deteriorating
Important aspects of project scope control include determining the cause and degree of variance relative
to the scope baseline and deciding whether corrective or preventive action is required.
2- Change Requests
Analysis of project performance may result in a change request to the scope and schedule
baselines
43