12/20/2018 Aconex

Peter Ghicu Final (WF-016285) TD Re-submittal Review - (2 Reviewers) 8:55 AM


EGIS INTERNATIONAL WORKFLOW TRANSMITTAL EGIS_INT-WTRAN-069754

MAIL TYPE MAIL NUMBER REFERENCE NUMBER


Workflow Transmittal EGIS_Int-WTRAN-069754 EGIS_Int-WTRAN-069754

Final (WF-016285) TD Re-submittal Review - (2 Reviewers)

From Mr Peter Ghicu - EGIS International

To (4) Mr Allan Marasigan - EGIS International

Mr Manuj Kumar - EGIS International

Mr Sarfraz Ulhaque - EGIS International

Mr Peter Ghicu - EGIS International

Cc (2) Mr Alaa Elbashbishy - EGIS International

Mr Harish Akula - EGIS International

Sent Thursday, 20 December 2018 8:55:48 AM AST (GMT +03:00)

Status N/A

DOCUMENT ATTACHMENTS (1)

(0 selected)

Planned
Revision
File Document No Revision Title Status Submission
Date
Date

MATERIAL SUBMITTAL FOR


EZ03-CW02-LCQ- For
2 01/12/2018 CONCRETE HOLLOW BLOCKS
ARC-MAS-020021 Approval
(SMEET PRECAST)

MESSAGE

Workflow Review History

The attached documents have completed the "TD Re-submittal Review - (2 Reviewers)" workflow with the following results :

This transmittal was automatically generated.

https://mea.aconex.com/Logon 1/2
12/20/2018 Aconex

Doc No Step Participant Review Outcome Comments

EZ03-CW02-LCQ-ARC-MAS-020021 Co-Reviewer 1 M Kumar A - Proceed - No Comment

Co-Reviewer 2 S Ulhaque A - Proceed - No Comment

SRE Final Review P Ghicu A - Proceed - No Comment