CBD Ec 4 2004 PDF
CBD Ec 4 2004 PDF
CBD Ec 4 2004 PDF
Eurocode 4-2004
Composite Beam
Design Manual
Eurocode 4-2004
For ETABS® 2013
1 Introduction
1.1 Organization 1-2
1.2 Recommended Reading/Practice 1-3
2 Design Prerequisites
2.1 Design Code 2-1
2.2 Units 2-1
2.3 Preferences 2-2
2.4 Overwrites 2-2
2.5 Composite Beam Properties 2-2
2.5.1 Beam Properties 2-2
2.5.2 Metal Deck and Slab Properties 2-4
2.5.3 Shear Stud Anchor Properties 2-5
2.5.4 Cover Plates 2-6
2.6 Beams Designed as Composite Beams 2-6
2.6.1 Frame Elements Designed by Default as
Composite Beams 2-7
2.6.2 Overwriting the Frame Design Procedure
for a Composite Beam 2-8
2.7 How the Program Optimizes Design Groups 2-9
2.8 Analysis Sections and Design Sections 2-12
2.9 Output Stations 2-13
2.10 Effective Width of the Concrete Slab 2-14
i
Composite Beam Design Eurocode 4-2004
ii
Contents
iii
Composite Beam Design Eurocode 4-2004
iv
Contents
Appendix A Preferences
Appendix B Overwrites
Bibliography
v
Chapter 1
Introduction
Initiation of the design process, along with control of various design parame-
ters, is accomplished using the Design menu. The design/check of composite
beams is seamlessly integrated within the program.
Automated design at the object level is available for any one of a number of
user-selected design codes, as long as the structures have first been modeled
and analyzed by the program. Model and analysis data, such as material prop-
erties and member forces, are recovered directly from the model database, and
no additional user input is required if the design defaults are acceptable.
1-1
Composite Beam DesignEurocode 4-2004
The program checks the requirements for strength and deflection limit states at
service and construction time conditions. It also checks vibration for service
time condition. It considers shoring-unshoring phases if shoring is used. It cal-
culates camber if it is required.
The program can determine the number of steel headed stud anchors required
to achieve the desired level of composite action. On the other hand, the pro-
gram can check the adequacy if the profile—number and distribution—of the
steel headed stud anchors is provided.
Program output can be presented graphically on the model, in tables for both
input and output data, or in calculation sheets prepared for each member. For
each presentation method, the output is in a format that allows the engineer to
quickly study the stress conditions that exist in the structure, and in the event
the member is not adequate, aid the engineer in taking appropriate remedial
measures, including altering the design member without re-running the entire
analysis.
The program supports a wide range of composite beam design codes, including
many national building codes. This manual is dedicated to the use of the menu
option “Eurocode 4-2004.” This option covers the “EN 1994-1-1:2004—
Design of composite steel and concrete structures” (Eurocode 4-2004). The
implementation covers load combinations from “EN 1990:2002 which is de-
scribed in the section Design Load Combinations in Chapter 3.
The design codes supported under “Eurocode 4-2004” are written in newton-
millimeter units. All the associated equations and requirements have been im-
plemented in the program in newton-millimeter units. The program has been
enabled with unit conversion capability. This allows the users to enjoy the flex-
ibility of choosing any set of consistent units during creating and editing mod-
els, exporting and importing the model components, and reviewing the design
results.
1.1 Organization
This manual is designed to help you quickly become productive using the Eu-
rocode 4-2004 composite beam design option. Chapter 2 addresses prerequi-
sites related to modeling and analysis for a successful design in accordance
1-2 Organization
Chapter 1 - Introduction
with the code. Chapter 3 provides detailed descriptions of the specific require-
ments as implemented in the program for the code.
In writing this manual it has been assumed that the user has an engineering
background in the general area of structural reinforced concrete design and
familiarity with Eurocode 4-2004 code.
2.2 Units
For composite beam design in this program, any set of consistent units can be
used for input. Typically, design codes are based on one specific set of units.
The documentation in this manual is presented in newton-millimeter-seconds
units unless otherwise noted. However, any system of units can be used to
define and design a building in the program.
2.3 Preferences
The Composite Beam Design Preferences are basic assignments that apply to
all composite beam members. Default values are provided for all preference
items. Thus, it is not necessary to specify or change any of the preferences.
However, at least review the default values to ensure they are acceptable. Some
of the preference items also are available as member specific overwrite items.
The Preferences are described in Appendix A. The Overwrites are described in
Appendix B. Overwritten values take precedence over the preferences.
2.4 Overwrites
The composite beam design Overwrites are basic assignments that apply only
to those elements to which they are assigned. Default values are provided for
all overwrite items. Thus, it is not necessary to specify or change any of the
overwrites. However, at least review the default values to ensure they are
acceptable. When changes are made to overwrite items, the program applies the
changes only to the elements to which they are specifically assigned.
Overwritten values take precedence over the preferences. See Appendix B for
more information about Overwrites.
The many properties associated with composite beams are defined using
various menus in the program. Other items related to the beam properties are
specified in the composite beam preferences or overwrites.
Basic steel beam properties can be user defined along with the basic geometry
of the steel section, except for the cover plate, if it exists. Cover plates are
specified in the composite beam Overwrites. When defining a beam, a material
property that includes the yield stress for that beam is also assigned. That yield
stress is assumed to apply to the beam and the cover plate unless it is revised in
the beam overwrites. The steel Material Property also includes the price or
cost-per-unit-weight that is assigned to the beam.
If the user defines a beam section by selecting it from the built-in section
database, the program assumes that it is a rolled section and applies the design
equations accordingly. If the user defines a section without selecting it from the
built-in database, the program assumes it is a welded section and revises the
design equations as necessary. The program does not check or design any of
the welding for these welded beams.
A beam designed using the Composite Beam Design postprocessor can have
composite behavior only if it supports a deck section (not a slab or wall
section).
The concrete slab over metal deck must be specified as a deck section property
(not a slab section property) if the beam is to have composite behavior. If the
slab is specified using a slab section property instead of a deck section
property, the Composite Beam Design postprocessor designs the beams
supporting that slab as noncomposite beams.
A deck section can be specified as a Filled Deck (metal deck filled with
concrete), an Unfilled Deck, or a Solid Slab (solid concrete slab with no metal
deck). In the specified metal deck geometry includes the following:
Slab Depth: The depth of concrete fill above the metal deck. This item is
labeled tc in Figure 2-1.
Deck Depth: The height of the metal deck ribs. This item is labeled hr in
Figure 2-1.
Rib Width: The average width of the metal deck ribs. This item is labeled wr
in Figure 2-1.
Rib Spacing: The center-to-center spacing of the metal deck ribs. This item
is labeled Sr in Figure 2-1.
If the deck has been specified as Filled Deck or Solid Slab (not Unfilled Deck),
a slab material must be specified for the concrete. This should be a previously
specified concrete material property. This concrete material property is used to
specify all material properties of the concrete, except in some code-specific
cases.
If the deck has been specified as Unfilled Deck, a steel material property must
be specified for the deck material, and an equivalent shear thickness must be
specified for the deck. These two items are used by the program to determine
the membrane shear stiffness of the deck.
wh
Weight-per-Unit-Area = wc r r + tc + wd
Sr
Note that the program does not check the design of the metal deck itself.
The specification of composite deck stud anchors can include the following
items:
Height: The height of the shear stud. This item is labeled Hs in Figure 2-1.
Tensile Strength, Fu: The specified tensile strength of the shear stud.
One consequence of this process is that the cover plate is not included for
overall analysis of the building. However, the cover plate is considered both for
resisting moments and deflections for design of the composite beam within the
program's Composite Beam Design postprocessor.
The properties specified for a cover plate are the width, bcp, the thickness, tcp,
and a design yield stress, Fydcp. The width and thickness dimensions are
illustrated in Figure 2-1. The program does not check or design any of the
welding between the cover plate and the beam bottom flange. It also does not
determine cutoff locations for the full length cover plate.
Note that beam sections that are defined in Section Designer are always treated
as general sections. Thus, if an I-type or channel-type section is defined using
Section Designer, the program will consider it to be a general section, not an I-
The line type associated with the frame object that represents a composite
beam must be "Beam." In other words, the beam element must lie in a
horizontal plane.
For composite beams, the beam local 2-axis must be vertical. The Local axis 2
Angle is displayed on the Geometry tab of the Beam Information form.
The frame object representing a composite beam should span from support to
support. Composite beams should not be modeled using multiple, adjacent
frame objects between supports for a single composite beam.
In the case of a cantilever beam overhang, the frame object should span from
the overhang support to the end of the beam. The cantilever beam back span
should be modeled using a separate frame object. If cantilever beams are not
modeled in this way, the analysis results for moments and shears will still be
correct but the design performed by the Composite Beam Design processor
probably will not be correct.
The beam must meet the section requirements described in the subsection
entitled Section Requirements in this chapter.
The beam must meet the material property requirement described in the
subsection entitled Material Property Requirement in this chapter.
The beam must meet the two other requirements described in the subsections
entitled Beam Orientation and Support and Extent in this chapter.
At least one side of the beam must support deck that is specified as a Deck
section (not a Slab or Wall section). The deck section can be filled, unfilled
or a solid slab. When the deck is unfilled, the beam will still go through the
Composite Beam Design postprocessor and will simply be designed as a
noncomposite beam.
The beam must not frame continuously into a column or a brace. Both ends
of the beam must be pinned for major axis bending (bending about the local
3axis).
No design
By default, steel sections are designed using either the composite beam design
procedure or the steel frame design procedure. All steel sections that meet the
requirements described in the previous subsection entitled Frame Elements
Designed by Default as Composite Beams are by default designed using the
composite beam design procedures. All other steel frame elements are by
default designed using the steel frame design procedures.
Change the default design procedure used for a beam(s) by selecting the beam(s)
and clicking the Design menu > Overwrite Frame Design Procedure command.
This change is successful only if the design procedure assigned to an element is
valid for that element. For example, if two steel beams, one an I-section and the
other a tube section, are selected and an attempt is made to change the design
procedure to Composite Beam Design, the change will be executed for the I-
section, but not for the tube section because it is not a valid section for the
composite beam design procedure. A section is valid for the composite beam
design procedure if it meets the requirements specified in the section entitled
Beams Designed as Composite Beams, earlier in this chapter.
Note that the procedures documented for composite beam design allow for
designing a beam noncompositely. One of the overwrites available for
composite beam design is to specify that selected beams are designed as
composite, noncomposite with a minimum number of shear studs specified, or
noncomposite with no shear studs. These overwrites do not affect the design
procedure. Changing the overwrite to one of the noncomposite designs does
not change the design procedure from Composite Beam Design to Steel Frame
Design. The noncomposite design in this case is still performed from within the
Composite Beam Design postprocessor.
Finally, note that the user can specify that the composite beam design
procedures are to be used for a beam even if that beam does not support any
deck, or for that matter, even if no slab is specified. In these cases, the beam
will be designed as a noncomposite beam by the Composite Beam Design
postprocessor.
When considering design groups, the program first discards any beam in the
design group that is not assigned an auto select section list.
Next, the program looks at the auto select section list assigned to each beam in
the design group and creates a new list that contains the sections that are
common to all of the auto select section lists in the design group. The program
sorts this new common section list in ascending order, from smallest section to
largest section based on section weight (area).
When designing with design groups, the program attempts to quickly eliminate
inadequate beams.
The program then finds the beam with the largest positive design moment in
the design group, or the “pseudo-critical beam.” The program then checks the
design of the pseudo-critical beam for all sections in the common section list.
Any sections in the common section list that are not adequate for the pseudo-
critical beam are discarded from the common section list, making the list
shorter. This new list is the shorter common section list. The shorter common
section list is still in ascending order based on section weight (area).
Now the program checks all beams in the design group for the first section
(smallest by weight [area]) in the shorter common section list. If the
optimization is being performed on the basis of beam weight and the section is
adequate for all beams in the design group, the optimum section has been
identified. If the section is not adequate for a beam, the next higher section in
the shorter common section list is tried until a section is found that is adequate
for all beams in the design group.
If the optimization is based on price instead of weight, the program finds the
first section in the shorter common section list (i.e., the one with the lowest
weight) that is adequate for all beams. Next it calculates the cost of this first
adequate section and then determines the theoretical heaviest section that could
still have a cost equal to the adequate section by dividing the total price of the
beam with the adequate section (steel plus camber plus shear connectors) by
the unit price of the steel. This assumes that when the cost of the steel section
alone is equal to or greater than the total cost of the adequate section, the
section could not have a total cost less than the adequate section. The program
then checks any other sections in the shorter common section list that have a
weight less than or equal to the calculated maximum weight. If any of the other
sections are also adequate, a cost is calculated for them. Finally, the section
with the lowest associated cost is selected as the optimum section for the
design group.
design each beam in the design group individually based on its own auto
section list and ignores the rest of the design group. If for a particular beam
none of the sections in the auto select section list are adequate, the program
displays results for the section in the auto select list with the smallest
controlling ratio shown in red. Note that the controlling ratio may be based on
stress or deflection.
By default, the program selects the optimum composite beam size based on
weight, not price. When a beam is optimized by weight, the program internally
optimizes the beam based on area of steel (excluding the cover plate, if it
exists). Thus, the weight density specified for the steel is irrelevant in such a
case.
By default, when auto select section lists are assigned to beams, the program
compares alternate acceptable composite beam designs based on the weight of
the steel beam (not including the cover plate, if it exists) to determine the
optimum section. The beam with the least weight is considered the optimum
section. The choice of optimum section does not consider the number of shear
connectors required or if beam camber is required.
In the Preferences, the user can request that the program use price to determine
the optimum section. If a price analysis is requested, the program compares
alternate acceptable beam designs based on their price and selects the one with
the least cost as the optimum section.
For the cost comparison, specify costs for steel, shear studs and beam camber.
The steel cost is specified as a part of the steel material property. The shear
stud and beam camber costs are specified in the composite beam preferences.
The costs for steel and cambering are specified on a unit weight of the beam
basis; for example, a cost per pound of the beam. The shear connector cost is
specified on a cost per connector. By assigning different prices for steel, shear
connectors and camber, the user can influence the choice of optimum section.
The cost of the cover plate is not included in the comparison (but it would be
the same for all beam sections if it were included).
The volume of the beam is calculated by multiplying the area of the steel beam
(plus the area of the cover plate, if used) by the length of the beam from center-
of-support to center-of-support.
It is possible for the last used analysis section and the current design section to
be different. For example, an analysis may have been run using a IPE 400
beam, and then it is determined in the design that a IPE 500 beam worked
better. In that case, the last used analysis section is the IPE 400 and the current
design section is the IPE 500. Before the design process is complete, verify that
the last used analysis section and the current design section are the same.
The program keeps track of the analysis section and the design section
separately. Note the following about analysis and design sections:
Assigning a beam a frame section property assigns the section as both the
analysis section and the design section.
Running an analysis always sets the analysis section to be the same as the
current design section.
Assigning an auto select list to a frame section initially sets the design
section to be the beam with the median weight in the auto select list.
Unlocking a model deletes the design results, but it does not delete or change
the design section.
Changing a design load combination deletes the design results, but it does not
delete or change the design section.
Changing any of the composite beam design preferences deletes the design
results, but it does not delete or change the design section.
Deleting the static nonlinear analysis results also deletes the design results
for any load combination that includes static nonlinear forces. Typically,
static nonlinear analysis and design results are deleted when one of the
following actions is taken:
Again, note that these actions delete only results for load combinations that
include static nonlinear forces.
For composite beam design, the program checks the moments, shears and
deflections at each output station along the beam. No checks are made at any
points along the beam that are not output stations.
The effective slab width on either side of the beam can be specified in the
overwrites. The effective widths are specified on the left and right sides of the
beam. As illustrated in Figure 2-2, when viewed from the I-end of the beam
toward the J-end of the beam, the program assumes the right side of the beam
to be on the right-hand side.
j-end of beam
i-end of beam
The capacity of the composite beam is approximately twice that of the steel
beam alone.
The steel beam alone is capable of resisting the entire moment in the
composite beam for the last 15% of the beam length at each end of the beam.
Note that for a uniformly loaded beam, the moment drops off to half of the
maximum moment or less in the last 15% of the beam.
Redefine this default “middle range” of 70% in the composite beam design
preferences, if desired (Appendix A).
The program checks the deck types and deck directions on each side of the
composite beam within the specified middle range (see the previous subsection).
When multiple deck types or deck directions occur on the same side of a composite
beam, the program decides which single deck section and direction to use on that
side of the beam.
The program goes through these steps in this order to choose the deck section.
1. The program calculates the product of tc * f ck for each deck where tc is the
depth of the concrete above the metal deck and f ck is the concrete slab
compressive strength. It uses the deck section that has the smallest value of
tc * f ck in the calculations for the beam.
2. If two or more deck sections have the same value of tc * f ck but the deck
spans in different directions, the program uses the deck section that spans
perpendicular to the beam.
3. If two or more deck sections span in the same direction and have the same
value of tc* f ck , the program uses the deck section with the smaller tc
value.
4. If two or more deck sections span in the same direction and have the same
values of tc and f ck , the program uses the first defined deck section.
In this program's composite beam design, the deck is assumed either parallel or
perpendicular to the span of the beam. If the deck span is exactly parallel to the
beam span or within 15 degrees of parallel to the beam span, the deck span is
assumed to be parallel to the beam span. Otherwise, the deck span is assumed
to be perpendicular to the beam span.
The assumed deck type and deck direction on each side of the beam can be
specified using the composite beam overwrites.
Refer to the floor plan shown in Figure 2-4. The typical floor in this plan
consists of 65 mm normal weight concrete over 75 mm metal deck that is
designated Deck Type A. However, the upper left-hand quadrant of the floor
consists of 90 mm normal weight concrete over 75 mm metal deck that is
designated Deck Type B. Assume that the concrete compressive strength is 30
MPa for both deck types.
Now consider the beam labeled “Girder F” in the figure. Deck Type A exists
along the entire length of the right-hand side of this beam. Thus, the program
uses Deck Type A on the right side of the beam in the calculations. Both Deck
Type A and Deck Type B exist along the left-hand side of the beam. The
program uses the following method to determine which of these deck types to
use on the left side of the beam in the calculations:
2. Use Deck Type A on the left side of the girder in the composite beam
calculations because it has the smaller value of tc * f ck .
Note that the loads applied to the beam are still based on the actual deck types.
Thus, the load applied to the upper half of Girder F in Figure 2-4 would include
the contribution from Deck Type B even though Deck Type B might not be
used in calculating the composite beam properties.
A second example is shown in Figure 2-5. In this example, the deck type is the
same throughout the floor, but the direction of the deck changes in the upper
left-hand quadrant of the floor.
Now consider the beam labeled “Girder G” in the figure. The deck ribs are
oriented parallel to the span of Girder G along the entire length of the right-
hand side of this beam. Thus, the program uses Deck Type A oriented parallel
to the span of Girder G on the right side of the beam in the calculations.
Deck ribs oriented both perpendicular and parallel to the span of Girder G exist
along the left-hand side of the beam. Because only the deck direction is
different along the left side of the beam, not the deck type (and thus tc and f ck
do not change), the program uses the deck that spans perpendicular to Girder G
on the left side of the beam.
Now consider the example shown in Plan B of Figure 2-6. Assume that the
effective width of Beam B is controlled by the distance to the centerline of the
adjacent beam. When considering the perpendicular distance from Beam B to
the adjacent beam on the upper side of Beam B, the program considers the
diagonal beam labeled Beam Z when the angle θ is less than 45 degrees. If the
angle θ is greater than or equal to 45 degrees, Beam Z is ignored when
calculating the effective slab width on the upper side of Beam B.
Plan C in Figure 2-6 shows a special case where two diagonal beams frame
into Beam C at the same point. In this special case, the program assumes that
the effective width of the slab on the side of the beam where the two diagonals
exist is zero. The user can, of course, change this in the overwrites. The
program assumes the zero effective width because, although it is checking the
effective width for Beam C, it is unable to determine whether a slab is actually
between the two diagonal beams.
LV
xD * LD
Beam D
Plan D
Figure 2-7 Example of the Effect of Openings on Composite Beam Effective Width
Assume again that the effective width of this beam is controlled by the distance
to the centerline of the adjacent beam, and also assume that the program checks
the effective width of the slab over the default center 70% of the Beam D
length. If the width of the opening, xD * LD is less than 0.15LD, the program
bases the effective width of the concrete slab on the distance to the adjacent
beams. On the other hand, if xD * LD exceeds 0.15LD, the program assumes the
effective concrete slab width for Beam D to be zero; that is, it assumes a
noncomposite beam.
By default, the program automatically determines the locations where the beam
is braced for buckling about the local 2-axis. This information is then used to
determine the unbraced length associated with any point on the beam. Instead
of using the program calculated bracing points, the user can specify in the
overwrites brace points for any beam.
For buckling about the local 2-axis, the program differentiates between bracing
of the top flange of the beam and bracing of the bottom flange of the beam. The
program automatically recognizes which flange of the beam is the compression
flange at any point along the beam for any design load combination. With this
ability and the program-determined or user-specified bracing point locations,
the program can automatically determine the unbraced length of any segment
along the beam and can apply appropriate code-specified modification factors
(e.g., C1 factor for flexure) to the flexural strength of the beam.
i-end of beam
Metal deck sections with no concrete fill are assumed to continuously brace the
top flange if the deck ribs are specified as oriented perpendicular to the beam
span. If the deck ribs are specified as oriented parallel to the beam span, the
deck is assumed to not brace the top flange.
Beam Considered
considered at an angle greater than 30 degrees, as shown in Br
ac
the sketch to the right. It is up to the user to provide ing
Be
appropriate detailing at this point to ensure that the bottom am
flange is adequately braced. If appropriate detailing is not θ > 30°
provided, the user should redefine the brace points using one
of the methods described in the next section.
When the bracing is program calculated or brace points are user specified, the
program always assumes that each end of the beam is braced at both the top
and the bottom flange. If the unbraced length of a beam is longer than the
actual beam, specify a user defined unbraced length, not user defined brace
points.
For buckling about the local 2-axis, specific bracing points can be specified
along the beam that apply to the top flange, bottom flange, or both, or one
maximum unbraced length can be specified that applies over the entire length
of the beam to both the top and bottom flanges.
As soon as the user specifies any user defined bracing points or unbraced
lengths for a beam, all of the program determined lateral bracing information
on that beam is ignored. Thus, if any bracing point is specified for a beam,
all of the bracing points for that beam should be specified.
The user can change the default bracing assumed for a beam in the composite
beam overwrites. The bracing specified can be different for construction
loading and final loading.
The point of maximum positive moment for each design load combination
used for checking the strength of the beam to carry the final design loads is a
design check location. Note that there may be more than one of these design
load combinations and thus there may be more than one point of maximum
moment to consider.
The point of maximum negative moment (if negative moment exists) for
each design load combination used for checking the strength of the beam to
carry the final design loads is a design check location.
A point load or point moment location for any design load combination used
for checking the strength of the beam to carry the final design loads is a
design check location.
The ends of a cover plate, if one is specified, are design check locations.
The end or edge of the deck. This occurs, for example, at locations where the
beam spans through an opening in the deck.
At each design check location the program checks the moment capacity of the
composite beam and determines the number of shear connectors required
between that location and the nearest point of zero moment (or in some special
cases, the end of the slab).
The program determines one set of design check locations that applies to all
design load combinations.
Consider, for example, a composite beam with two design load combinations
used for checking the strength of the beam to carry the final design loads.
Assume one of those load combinations is a uniform load over the full length
of the beam and the other is a point load at the third point of the beam. Also
assume there is positive moment only in the beam and no cover plate. In this
example, the program considers the following design check locations:
The point of maximum positive moment for the design load combination
with uniform load only.
The point of maximum positive moment for the design load combination
with point loads at the third point.
The location of the point load, that is, the third point of the beam.
The program checks the moment capacity and the number of shear connectors
required between each of these four locations and the nearest point of zero
moment for both of the design load combinations. Thus, for the design load
combination with uniform load only, the program still checks how many shear
studs are required between the location of the point load in the other design
load combination and the nearest point of zero moment. This ensures that there
is always a sufficient number of shear connectors in the appropriate location on
the beam.
For normal loading conditions involving static dead load, live load, snow load,
wind load, and earthquake load, or dynamic response spectrum earthquake
load, the program has built-in default loading combinations for each design
code. These are based on the code recommendations and are documented for
each code in the corresponding manuals.
For other loading conditions involving moving load, time history, pattern live
loads, separate consideration of roof live load, snow load, and so on, the user
must define design loading combinations either in lieu of or in addition to the
default design loading combinations.
The default load combinations assume all load cases declared as dead load to
be additive. Similarly, all cases declared as live load are assumed additive.
However, each load case declared as wind or earthquake, or response spectrum
cases, is assumed to be non additive with other similar cases and produces
multiple lateral load combinations. Also wind and static earthquake cases
produce separate loading combinations with the sense (positive or negative)
reversed. If these conditions are not correct, the user must provide the
appropriate design combinations.
The default load combinations are included in design if the user requests them
to be included or if no other user defined combination is available for
composite beam design. If any default combination is included in design, all
default combinations will automatically be updated by the program any time
the design code is changed or if static or response spectrum load cases are
modified.
Live load reduction factors can be applied to the member forces of the live load
case on an element-by-element basis to reduce the contribution of the live load
to the factored loading.
The user is cautioned that if moving load or time history results are not
requested to be recovered in the analysis for some or all of the frame members,
the effects of those loads will be assumed to be zero in any combination that
includes them.
For Composite Beam Design, three separate types of load combinations are
considered. They are:
Strength Check for Final Loads: Design load combinations for checking the
strength of the beam to carry the final design loads.
Deflection Check for Final Loads: Design load combinations for checking
the deflection of the beam under final design loads.
The design load combinations are defined separately for each of the three
conditions. The program automatically creates code-specific composite beam
design load combinations for each of the three types of design load
combinations based on the specified dead, superimposed dead, live and
reducible live load cases. The user can add additional design load combinations
and modify or delete the program-created load combinations.
None of the program default load combinations include the effect of lateral
loads. If lateral loads need to be considered, the user should specify user-
defined design load combinations. As many load combinations as needed can
be specified. In addition, the program creates special live load patterns for
cantilever beams.
Each composite beam design load combination for a cantilever has a dead load
(DL), superimposed dead load (SDL) and a live load plus reduced live load
(LL + RLL) component. There may also be other types of load components as
well. The nature of the other types of load components is not important. The
DL, SDL, (LL + RLL) and other components are shown in Figure 2-9a.
The program internally creates a simply supported model of the cantilever back
span. It applies a load to this simply supported span that is equal to a factor
times the LL + RLL applied to the span. The factor used is specified in the
composite beam design preferences as the Pattern Live Load Factor. This
internally created model and loading is illustrated in Figure 2-9b. In the figure,
PLLF is short for Pattern Live Load Factor.
Finally for strength design (final loads only) of cantilever back spans, the
program considers the following two conditions for each design load
combination:
DL + SDL (+ any other type of load if it exists) over the full length (back
span plus overhang) of the cantilever beam plus the (LL + RLL) multiplied
by the Pattern Live Load Factor applied to the simply supported back span.
LL + RLL Other
PLLF * (LL + RLL) Note: PLLF = The Pattern Live Load Factor as
specified on the Beam tab in the
composite beam preferences.
Figure 2-9 Conditions Considered for Strength Design of a Cantilever Back Span
Note that the conditions described herein are considered for strength design for
final loads only. The program does not do any special pattern loading checks
for deflection design or for construction loading design.
If load patterning different from that provided by the program is needed, the
user should create a design load combination. When creating user defined live
load patterning, it typically works best to give the specially defined pattern live
load cases an “Other” design type instead of a “Live Load” design type. That
way, the special pattern live load cases are not included in the automatically
created default design load combinations, avoiding possible double counting of
some live loads in those load combinations.
Each composite beam design load combination for a continuous span has a
DL, SDL and (LL + RLL) component. There also may be other types of load
components as well. The nature of the other types of load components is not
important. The DL, SDL, (LL + RLL) and other components are shown in
Figure 2-10a.
Finally for strength design (final loads only) of continuous spans, the program
considers the following two conditions for each design load combination:
DL SDL
LL + RLL Other
PLLF * (LL + RLL) Note: PLLF = The Pattern Live Load Factor as
specified on the Beam tab in the
composite beam preferences.
Note that the conditions described herein are considered for strength design for
final loads only. The program does not do any special pattern loading checks
for deflection design or for construction loading design.
If load patterning different from that provided by the program is needed, the
user should create a design load combination. When creating user defined live
load patterning, it typically works best to give the specially defined pattern live
load cases an “Other” design type instead of a “Live Load” design type. That
way, the special pattern live load cases are not included in the automatically
created default design load combinations, avoiding possible double counting of
some live loads in those load combinations.
2.14.1 Deflection
In Composite Beam Design, when a beam is shored, the deflection is calculated
using (a) the transformed moment of inertia, Itr, if there is full (100%)
composite connection, (b) the effective moment of inertia, Ieff, if there is partial
composite connection, or (c) the moment of inertia of the steel beam alone,
Ibare, if the beam is designed noncompositely or found to be a cantilever
overhang.
I tr= ∑A 2
tr y1 + ∑ I − (∑ A ) y
O tr
2
where,
where,
2 - 32 Deflection
Chapter 2 - Design Prerequisites
I bare
= ∑ ( Ay ) + ∑ I − ( ∑ A) y
1
2
O
2
bare
where,
∑(Ay 1
2
) = Sum of the product A times y12 for all of the elements of the
steel beam section (including the cover plate, if it exists),
mm4.
When deflection is used as a criterion for selecting the optimum beam size, the
program checks that the total load deflection minus the camber does not exceed
the specified total load deflection limit. It also checks that the live load
deflection does not exceed the specified live load deflection limit.
Deflection 2 - 33
Composite Beam Design Eurocode 4-2004
Deflections for the beam are calculated at each output station. The overall
deflected shape of the beam is drawn by connecting the computed values of
deflection at each output station with straight-line segments. Thus, the program
assumes a linear variation of M/EI between output stations.
In this program's composite beam design, the reported deflection is the vertical
displacement relative to a line drawn between the deflected position of the ends
of the beam. For example, refer to the beam shown in Figure 2-11. Figure 2-
11a shows the original undeformed beam and also shows an arbitrary point
along the beam labeled A. Figure 2-11b shows the beam in its deformed
position and illustrates the deflection that the Composite Beam Design
postprocessor reports for the beam at point A.
Figure 2-11 Deflection Results Reported by the Composite Beam Design Postprocessor
When reviewing the displacement at the end of the cantilever, the displacement
is reported relative to the undeformed position of the end of the cantilever. In
that case, the rotation at the supported end of the cantilever overhang is
correctly taken into account. However, the displacements displayed are all
based on the analysis section properties (noncomposite moment of inertias).
2.14.3 Camber
When beam camber is calculated, the amount of camber is based on a
percentage of the dead load (not including superimposed dead load) deflection.
By default, this percentage is 100%, but this value can be modified using the
composite beam design preferences.
The minimum camber that the program specifies (other than zero) is 15 mm.
The maximum camber the program specifies is 100 mm. The program specifies
the camber in 5 mm increments. Table 2-1 shows how the program assigns
camber to a beam based on the specified percentage of dead load deflection.
In the table, CP is the specified percentage of dead load deflection upon which
the camber is based. The CP * ∆DL column is broken into two subcolumns
labeled “≥” and “<”. These two subcolumns specify the range of CP * ∆DL for
which the program specifies a particular camber.
The program specifies camber for those beams for which the user requests it to
specify camber, regardless of the beam depth or length. Review the beam
Camber 2 - 35
Composite Beam Design Eurocode 4-2004
g Es I tr
f = Kf (DG11 Eqn. 3.1)
W L3
where,
2 - 36 Vibration Frequency
Chapter 2 - Design Prerequisites
1.6
L H
1.4
gEI w
f = Kc
WL3
1.2
Frequency Coefficient, Kf
1.0
0.8
0.6
0.4
0.2
0
0 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 2.2 2.4
Cantilever / Backspan Ratio, H/L
Figure 2-12 Kf Coefficient for an Overhanging Beam for Use in the Preceding Equation
See the definition of Kf on the preceding page.
Vibration Frequency 2 - 37
Composite Beam Design Eurocode 4-2004
Asb
D ≥ 35 f + 2.5 Equation 2
N eff
where,
Neff = The effective number of beams resisting the heel drop impact, unitless.
If the damping ratio, D, is greater than the right side of the preceding equation,
the beam is considered acceptable. Approximate damping ratio values for
typical building configurations are published in the literature (see, for example,
Allen 1974; Allen and Rainer 1976; Allen, Rainer and Pernica 1979; Murray
1975; and Murray 1991). The derivation of the initial displacement amplitude
is described herein.
1
=tO tan −1 (0.1π f ) Eqn. 3
πf
PO L3
Asb = (0.1 − tO ) , if tO ≤ 0.05 sec Eqn. 4a
2.4 Es I tr
PO L3 1
=Asb * * VF , if tO > 0.05 sec Eqn. 4b
2.4 Es I tr 2πf
where,
In Equation 4c, the terms sin(0.1πf) and cos(0.1πf) are evaluated in radians.
When calculating Neff using Equation 5, the program does not check or
consider the number of parallel, equally spaced identical beams.
The beam spacing used in Equation 5 is user input in the composite beam
overwrites.
If the beam considered has deck on one side, or less, the program calculated
value of Neff is always set to 1.0.
3
s −8 L
4
L
N eff 2.967 − 0.05776 b
= + 2.556 *10 + 0.00010 Eqn. 5
d
avg I tr sb
where,
davg = Average depth of concrete slab including the concrete in the metal
deck ribs, mm.
L = Center-of-support to center-of-support length of the beam, mm.
Itr = Transformed section moment of inertia for the composite beam
calculated assuming full (100%) composite connection regardless of
the actual percent composite connection, mm4. Itr is calculated using
the first equation in the section entitled Beam Deflection and Camber.
If there is no deck supported by the beam, Ibare is used for this item.
where,
tc = Depth of the concrete slab above the metal deck ribs or the depth of the
solid concrete slab, mm.
Each of the preceding quantities may be different on the left and right sides of
the beam.
A composite beam segment may span between any two of the following three
items provided that there is concrete on the beam, and the beam top flange is
available over the full length of the segment:
2. Another beam in the program model that frames into the beam being
considered.
3. The physical end of the concrete slab on top of the beam considered.
A composite beam segment cannot exist in locations where concrete is not over
the beam or where the beam top flange has been coped. Figure 2-13 shows
some examples of composite beam segments. The figure uses the following
notation:
Note that a composite beam can have more than one composite beam segment,
as shown in Figure 2-13c.
LCBS
LCBS
End of
slab
LCBS
Notes:
1. S is the support distance.
2. G is the gap distance.
3. If a beam is supported by a wall or a point support, ETABS assumes that the dimension S is 0
mm.
4. The dimension bf in Cases 1 and 2 is the top flange width of the supporting girder.
5. The dimension bf in Cases 3 and 5 is the flange width of the supporting column (dimension
parallel to the local 3-axis). If the two flanges have different widths, the larger flange width is
used.
6. The dimension d in Cases 4 and 5 is the depth of the supporting column (dimension parallel to
the local 2-axis).
When determining the location of the ends of the beam top flange, the program
begins by assuming that the top flange extends from the center of the left
support to the center of the right support. It then subtracts a support distance, S,
from each end of the beam and a gap distance, G, from each end of the beam.
The gap distance, G, is always 12 mm. The support distance varies depending
on the type of support and the angle at which the beam frames into the support.
If the end of the beam is supported by a wall or a point support, the support
distance, S, is assumed to be zero. If the end of the beam is supported by
another beam, support distance S is determined as illustrated in Cases 1 and 2
in Figure 2-14, which show the beam supported by an I-shaped beam. A
similar method is used in the unusual case of other types of support beams.
In the unusual case of some other column shape, the program draws a bounding
rectangle around the shape. The sides of the rectangle are parallel to the local 2
and 3 axes of the shape. The beam is assumed to connect to the center of the
bounding rectangle. The dimensions of the edges of the rectangle are assumed
to be bf and d, where bf is the dimension parallel to the local 3 axis, and d is the
dimension parallel to the local 2 axis.
2. Any output station with a positive moment greater than 0.999 times the
maximum positive moment.
3. Any output station that has a point load applied to it for any load case
defined in the program. Even if the load case with the point load is not
used in the design load combinations for composite beam design, the
program will still consider the output station associated with the point load
when it determines the shear stud distribution. It will not, however, in any
way explicitly consider the loads in that unused load case when
determining the shear stud distribution.
At each considered output station, the program begins by determining the
distances L1 left and L1 right. These are illustrated in Figure 2-15 for a typical
composite beam with positive moment only and with a concrete slab over
metal deck along its entire length. The following notation is used in the figure:
L = Length of composite beam measured from center-of-support to
center-of-support, mm.
L1 left = Distance from the output station considered to the closest point
of zero moment or physical end of the beam top flange, or
physical end of the concrete slab on the left side of the output
station considered, mm.
L1 right = Distance from the output station considered to the closest point
of zero moment or physical end of the beam top flange, or
physical end of the concrete slab on the right side of the output
station considered, mm.
Next, the program calculates the number of shear studs, N, required within the
lengths L1 left and L1 right. This is a code-specific calculation and is described in
the next chapter.
The program works along the beam from left to right, making calculations at
each considered output station along the way. These calculations are described
later in this section. When there is more than one composite beam segment
along the beam, the program must also work back along the beam from right to
left, again making calculations at each considered output station along the way,
after finishing the pass from left to right.
The program also checks if the number of shear studs required based on
strength considerations or minimum stud requirements actually fit on the beam.
This check is described in the section entitled Number of Shear Studs that Fit
in a Composite Beam Segment later in this chapter. If the required number of
studs does not fit on the beam, the program considers the beam to be
inadequate.
The values we are ultimately interested in are the NCBSn values. Note that the
final NCBSn values calculated are the values of interest. All other NCBSn values
are intermediate values.
Also in the equations used note that NCBSxPrev is the value of NCBSx calculated at
the previously considered output station. Finally the term Roundup used in
some of the equations means to calculate the indicated quantity and round it up
to the next integer.
When working along the beam from left to right and the output station
considered falls in composite beam segment 1, or at the right end of composite
beam segment 1, the following equation is used to determine the value of
NCBS1. Note that when there is only one composite beam segment along the
beam, the following equation is used at each considered output station.
N N
=N CBS1 Roundup Max , * LCBS1 ≥ N CBS1 Prev
L1 left L1 right
Values of NCBSn where n> 1 (i.e., values of NCBS for composite beam segments
2, 3, etc.) are not applicable and thus not calculated at these stations when
working along the beam from left to right. In the term NCBS1, the "1" denotes
composite beam segment 1.
The equations in this subsection are used when the output station considered
falls in composite beam segment n, where n > 1, and the program is working
from left to right along the beam. Note that if the output station considered
coincides with the right end of composite beam segment n, the output station is
assumed to be in composite beam segment n (when working along the beam
from left to right).
N
=N CBSi Roundup * LCBSi ≥ N CBSi Prev
L1 left
n −1
N- N CBSi ∑
=N CBSn Roundup i =1
* LCBSn ≥ N CBSn Prev
n −1
L1 left −
i =1
LCBSi
∑
Otherwise use the next equation to calculate NCBSn.
N
=N CBSn Roundup * LCBSn ≥ N CBSn Prev
L1 left
When I >n, values of NCBSi are not applicable and thus are not calculated at
those stations when working along the beam from left to right.
The equations in this subsection are used when working back along the beam
from right to left and the output station considered falls in the rightmost
composite beam segment, or at the left end of the rightmost composite beam
segment. For the rightmost composite beam segment:
N N
N CBS rightmost = Roundup Max , * LCBS rightmost ,
L1 left L1 right
N CBS rightmost ≥ N CBS rightmost prev
For other composite beam segments that are not the rightmost composite beam
segment, the following equation applies, where i represents the composite
beam segment number.
The equations in this subsection apply when working back along the beam
from right to left. (Note that this implies that there is more than one composite
beam segment along the beam.) In this section, assume that the output station
considered falls within (or at the left end of) composite beam segment n.
N
=N CBSi Roundup * LCBSi ≥ N CBSi Prev
L1 right
The following two equations apply for composite beam segment n. For
example, if the output station considered falls in composite beam segment 2,
the following two equations apply to composite beam segment 2 only.
rightmost rightmost
N
If
L1 right
* ∑
i=
n +1
LCBSi < ∑
i=
n +1
N CBSi , use the following equation to calculate
NCBSn.
rightmost
N − N CBSi ∑
=N CBSn Roundup i= n +1
* L
CBSn ≥ N CBSn Prev
rightmost
L1 right −
i= n +1
LCBSi
∑
N
=N CBSn Roundup * LCBSn ≥ N CBSn Prev
L1 right
L
MSCBS = Roundup CBS
Max LS
The program also checks that the number of studs required in a composite
beam segment does not exceed the number that can actually fit in the segment.
The section entitled Number of Shear Studs that Fit in a Composite Beam
Segment describes how the program determines the maximum number of shear
studs that can fit into a composite beam segment.
Note that the minimum number of shear studs required in a composite beam
segment is calculated based on the maximum longitudinal spacing of shear
studs specified on the Shear Studs tab in the overwrites.
combination and then uses an intelligent algorithm to determine the final stud
distribution that satisfies all design load combinations.
Figure 2-16(c) shows the final stud distribution that reports for this beam. Note
that the intelligent algorithm allows the program to shift one of the five shear
studs required in composite beam segment 2 for design load combination 1 into
composite segment 1.
The program uses the same process to determine the number of shear
connectors that can fit on a composite beam when there is a solid slab with no
metal deck and when the deck ribs span parallel to the beam span. The program
uses a different process when the deck ribs span perpendicular to the beam.
These conditions are described in the next two sections.
The number of shear studs that can fit in a row across the beam top flange may
be limited by the width of the beam top flange, by the width of the deck ribs, or
by the Max Studs per Row item specified on the Shear Studs tab in the
composite beam overwrites.
1. The program determines the number of shear studs that can fit in a single
row across the width of the top flange of the beam. When there is a solid
slab (no metal deck), the number of shear studs is limited by the width or
thickness of the beam flange (item 1a below), or by the "Max Studs per
Row" item specified on the Shear Studs tab in the composite beam
overwrites. When the deck spans parallel to the beam, the number of shear
studs may be limited by the width or thickness of the beam flange (item 1a
below), the width of the metal deck rib (item 1b below), or by the "Max
Studs per Row" item specified on the Shear Studs tab in the composite
beam overwrites. Following is a description of each of these limits:
a. When checking the number of shear studs that fit across the width of
the beam flange, the program assumes that the studs are centered about
the centerline (web) of the beam and that the center of a shear stud can
be no closer than ds or 25 mm, whichever is larger, to the edge of the
beam flange. This is illustrated in the following sketch.
b. When checking the number of shear studs that fit within a metal deck
rib, the program assumes that the studs and deck rib are centered about
the centerline (web) of the beam and that the center of a shear stud can
be no closer than ds+ hr/4 to the edge of the beam flange. This is
illustrated in the following sketch.
hr
≥ (ds + hr/4) ≥ (ds + hr/4)
wr
Regardless of the number of studs calculated to fit across the width of the
beam flange in items 1a or 1b above, the program does not use a number of
studs larger than the “Max Studs per Row” item specified on the Shear
Studs tab in the composite beam design overwrites.
2. The program determines the number of rows of shear studs that can fit
between the two considered points on the beam top flange. This number of
rows is controlled by the “Min Long Spacing” item specified on the Shear
Studs tab in the composite beam design overwrites.
Figure 2-17 is a flowchart that illustrates the details of how the program
calculates the maximum number of shear studs that fit in a composite beam
segment when there is a solid slab or when the span of the metal deck is
parallel to the beam span.
Yes
Start ds SPRmax = 1
Here
Is t f − top < ?
2.5
No
Yes
Is this a solid slab (i.e., no Temp = Minimum of (bf-top -2ds, bf-top -2)
metal deck)?
No
Temp
SPR max = Int + 1 ≤ MSPR
MTS
L − MLS L
RSmax = Int CBS + 1 = Int CBS
MLS MLS
The term "Int" in the flowchart means to calculate the indicated quantity and
round the result down to the nearest integer. The definitions of the variables
used in the flowchart are:
SPRmax = Maximum number of shear studs that can fit in one row across
the top flange of a composite beam, unitless.
MTS = Minimum transverse spacing of shear studs across the beam top
flange as specified on the Shear Studs tab in the composite beam
overwrites, mm.
MSPR = Maximum shear studs per row across the beam top flange as
specified on the Shear Studs tab in the composite beam
overwrites, unitless.
Note that in the flowchart formulation, the studs located closest to the ends of
the composite beam segment are located no closer than MLS/2 to the ends of
the composite beam segment. This helps prevent possible double-counting of
shear studs in adjacent composite beam segments.
The process used to determine the number of shear studs that can fit in a
composite beam segment when the metal deck is assumed to span
perpendicular to the beam span is described as follows.
1. The program determines the number of shear studs that can fit in a single
row across the width of the top flange of the beam. This number of shear
studs is limited by either the width or thickness of the beam flange, or by
the "Max Studs per Row" item specified on the Shear Studs tab in the
composite beam overwrites.
In the preceding paragraph and the sketch, ds is the diameter of the shear
stud. The clearance requirement means that the minimum clear distance
from the face of a shear stud to the edge of the beam flange is equal to one-
half of a shear stud diameter. For shear studs less than 25 mm in diameter
(typically they are 19 mm in diameter), the program clearance is slightly
more than one-half of a shear stud diameter. This clear distance is provided
by the program to allow for adequate welding of the shear stud.
Some codes require that if the thickness of the beam flange is less than the
diameter of the stud divided by 2.5, the shear studs must be located on top
of the beam web. This means that only one stud can fit across the width of
the beam flange if tf <ds/2.5. The program checks the top flange thickness
for this requirement when determining the number of studs that fit across
the width of the beam flange.
2. The program determines how many deck ribs are available to receive shear
studs within the length of the composite beam segment. To determine this,
the program makes several assumptions, which are described as follows:
a. The mid-height of a side of the metal deck rib is assumed to align with
one end of the composite beam segment, as shown in Figure 2-18. In
Figure 2-19 is a flowchart that illustrates the details of how the program
calculates the maximum number of shear studs that fit in a composite beam
segment when the span of the metal deck is perpendicular to the beam span.
Yes
Start ds SPRmax = 1
Here
Is t f − top < ?
2.5
No
b f − top − 2d s
No SPR max = Int + 1 ≤ MSPR
Is ds ≤ 1" ? MTS
Yes
b f − top − 2
SPR max = Int + 1 ≤ MSPR
MTS
L CBS − Sr + 0.5w r
NR = Int + 1
Int MLS + 1 S
S r
r
NSmax = SPRmax * NR
Figure 2-19 Flowchart of the Method to Determine the Maximum Number of Shear
Studs that Can Fit Within a Composite Beam Segment When the Metal Deck Ribs
Are Oriented Perpendicular to the Beam Span (The term "Int" in the flowchart means
to calculate the indicated quantity and
round the result down to the nearest integer.)
The term "Int" in the flowchart means to calculate the indicated quantity and
round the result down to the nearest integer. The definitions of the variables
used in the flowchart are the same as those used in the Figure 2-17 flowchart,
with the following additions:
The following two sections describe the two methods of specifying user defined
shear studs.
Figure 2-20 illustrates uniformly spaced user defined shear studs over the
length of the beam. These shear studs are specified by inputting the spacing for
the Uniform Spacing item on the Shear Studs tab in the composite beam
overwrites.
Greater than or equal to Shear studs are centered
MLS / 2 and less than one- along the length of the Specified uniform
half the specified uniform beam top flange shear connector
shear connector spacing spacing
plus MLS / 2
Elevation
End distance Shear studs at specified uniform spacing centered along length of beam top flange End distance
is the same is the same
at each end at each end
Figure 2-20 Uniformly Spaced User Defined Shear Connectors Over the Length of the Beam,
Specified Using the Uniform Spacing Item
on the Shear Studs Tab in the Composite Beam Overwrites
1. The shear studs are assumed to occur over the length of the top flange of
the beam. In most cases, this is shorter than the center-of-support to center-
of-support length of the beam.
2. There is assumed to be one shear stud per row. To use this option to
specify 2 studs every 300 mm, specify a spacing of 150 mm. The 150 mm
spacing gives the closest equivalent to two studs every 300 mm.
3. The program determines the exact distance from the end of the beam top
flange (or end of the concrete slab) to the first shear stud, as shown in the
following equation. In that equation the term “Int” means to calculate the
indicated quantity and round the result down to the nearest integer, and the
where,
ED = Distance from the end of the beam top flange (or end of the
concrete slab) to the first shear stud, m.
TFL = The length of the beam top flange available to receive shear studs,
mm. This length is typically determined by subtracting the support
distance and the gap distance at each end of the beam from the
center-of-support to center-of-support length of the beam. In
special cases, an additional distance can be subtracted if the slab
does not exist over some portion of the beam.
MLS = Minimum longitudinal spacing of shear studs along the length of
the beam, as specified on the Shear Studs tab in the composite
beam overwrites, mm.
After the shear studs at the end of the beam top flange (or end of the concrete
slab) have been located using the preceding equation, the program knows the
exact location of each uniformly spaced shear stud along the length of the
beam.
In the preceding equation, the studs at the ends of the beam are assumed to be
no closer than MLS/2 from the end of the beam top flange. The studs at the
ends of the beam are also assumed to be no farther than (MLS + Specified
Spacing)/2 from the end of the beam top flange. Finally, the distance from the
studs at the ends of the beam to the end of the beam top flange is assumed to be
the same at each end of the beam.
Similar to the preceding, if the concrete slab stops before the end of the beam,
the first shear stud at that end of the beam is assumed to occur at a distance not
less than MLS/2 from the end of the slab and not more than (MLS + the
specified uniform spacing)/2 from the end of the slab.
Do not confuse beam sections with composite beam segments. See the section
entitled Specifying a User Defined Shear Connector Pattern earlier in this
section for more information.
Note the following about the shear studs specified for additional beam sections:
The program assumes that the specified shear studs occur in a single line
along the beam web within the specified length of the beam section. It
further assumes that the end shear studs in the beam section are located one-
half of the equal space from the ends of the specified beam section. These
assumptions mean that the spacing of shear studs in a beam section is equal
to the length of the beam top flange available to receive shear studs in the
beam section divided by the specified number of shear studs. See Figure 2-20
for an example.
The figure shows a beam section that is 2750 mm long. Assume that 11 shear
studs have been specified for this beam section. The spacing of shear studs in
the beam section is equal to the beam section length divided by the number
of studs, that is, 2750 mm/11 studs = 250 mm/stud. The end studs are located
one-half of a space, that is, 250 mm/2 = 125 mm, from each end of the beam
section.
The program does not check shear stud spacing requirements for user defined
shear stud patterns.
Assume that a beam section is specified at the end of a beam and the beam
top flange does not exist over a portion of that beam section length. This can
often happen because, as described in the Physical End of the Beam Top
Flange of the section entitled Distribution of Shear Studs on a Composite
Beam, the program subtracts a support distance and a gap distance from the
end of the beam when computing the length of the beam top flange.
In that case, the program places all of the specified shear studs on the portion
of the top flange that does exist. See Figure 2-22 for an illustration.
The figure shows a beam section at the end of the beam that is 3000 mm
long. The end of the beam top flange starts 250 mm from the specified left
end of the beam section. Thus, the actual length of top flange available for
shear studs is 2750 mm. Assume that 11 shear studs have been specified for
this beam section.
2750 mm11 studs = 250 mm/stud. The end studs are located one-half of a
space, that is 250 mm/2 = 125 mm, from each end of the beam top flange
within the beam section.
If the beam top flange does not exist over the entire length of the specified
beam section, the program ignores the shear studs that are specified for that
beam section.
Figure 2-22b illustrates how the program interprets the stud pattern as specified
in Table 2-3. The location and spacing of shear studs is as described in the
bulleted items in the previous subsection entitled Defining Additional Beam
Sections.
Table 2-3 Specification of Beam Sections in the Example Shown in Figure 2-23
Beam Section Starting Point Ending Point Number of Studs
1 0 mm 1,000 mm 6
2 1,000 mm 2,200 mm 4
3 2,200 mm 3,200 mm 6
How the Program Checks a Beam with User Defined Shear Studs 2 - 67
Composite Beam Design Eurocode 4-2004
Note that the transformed section properties used for stress calculations for a
beam may be different from those used for deflection calculations or vibration
calculation for the same beam because of the use of Ec for long term and short
term conditions. Also for vibration, concrete is assumed to be effective in both
tension and compression; whereas for deflection calculation, the concrete is
considered effective only in compression.
The program determines the transformed section moment of inertia for three
different sets of conditions for three reasons:
(i) Deflection check: For deflection calculation, Itr is based on the following
conditions:
(ii) Vibration check: For vibration calculation, Itr is based on the following
conditions:
(iii) Stress check: For stress check or for calculating moment capacity in the
elastic range, Itr is based on the following conditions:
2 - 68 How the Program Checks a Beam with User Defined Shear Studs
Chapter 2 - Design Prerequisites
2.19.1 Background
Figure 2-24 shows a typical rolled steel composite floor beam with the metal
deck ribs running parallel to the beam. Figure 2-25 shows a typical composite
user defined steel beam with the metal deck ribs running parallel to the beam.
Note that the user defined beam may have a different top and bottom flange
size, and that no fillets are assumed in this beam.
Figure 2-24 Composite Rolled Steel Beam Shown with Metal Deck Ribs
Running Parallel to the Beam
Background 2 - 69
Composite Beam Design Eurocode 4-2004
Figure 2-25 Composite User-Defined Steel Beam Shown with Metal Deck Ribs
Running Parallel to the Beam
For each of these configurations the following items may or may not be
included when calculating the transformed section moment of inertia:
Concrete in the metal deck ribs: The concrete in the metal deck ribs is
included in the calculation when the deck ribs are oriented parallel to the beam
(typically the case for girders). It is not included when the deck ribs are
oriented perpendicular to the beam (typically the case for infill beams).
Cover plate: The cover plate is included only if one is specified by the user in
the composite beam overwrites.
Note that the deck type and deck orientation may be different on the two sides
of the beam as described in Multiple Deck Types or Directions Along the Beam
Length in the section entitled Effective Width of the Concrete Slab.
2 - 70 Background
Chapter 2 - Design Prerequisites
The first task in calculating the transformed section moment of inertia of the
composite section is to compute properties for the steel beam alone (plus the
cover plate, if it exists). The properties required are the total area, Abare, the
location of the ENA, ybare, and the moment of inertia, Is.
If the beam section is a rolled steel beam or channel chosen from the program
section database, Abare, ybare and Ibare are calculated as shown in Table 2-4 and
using the subsequent three equations (after Table 2-5). If the beam section is a
user defined (welded) beam, they are calculated using Table 2-5 and the
subsequent three equations.
Table 2-4 Section Properties for Rolled Steel Beam Plus Cover Plate
Item Area, A y1 Ay1 Ay12 IO
d
Steel beam As Ay1 Ay12 Is
2
3
tcp bcp tcp
Cover plate bcptcp − Ay1 Ay12
2 12
Sums ∑A ∑ ( Ay )1 ∑( Ay12 ) ∑I O
Table 2-5 Section Properties for User-Defined (Welded) Steel Beam Plus Cover Plate
Item Area, A y1 Ay1 Ay12 IO
t f −top b f − top t 3f − top
Top flange bf-toptf-top d− Ay1 Ay12
2 12
d tw h3
Web htw Ay1 Ay12
2 12
t f −bot b f − bot t 3f − bot
Bottom flange bf-bottf-bot Ay1 Ay12
2 12
3
tcp bcp tcp
Cover plate bcptcp − Ay1 Ay12
2 12
Sums ∑A ∑ ( Ay ) 1 ∑( Ay12 ) ∑I O
The area of the steel section (including the cover plate if it exists), Abare, is
given by the following equation
Abare = ∑ A.
The ENA of the steel section is located a distance ybare from the bottom of the
bottom flange of the steel beam section (not bottom of cover plate) where ybare
is determined from the following equation
ybare =
∑ ( Ay ) .
1
∑A
The moment of inertia of the steel section (plus cover plate, if one exists) about
its ENA, Ibare, is given by the following equation
I bare
= ∑ ( Ay ) + ∑ I − ( ∑ A) y
1
2
O
2
bare .
The following notations are used in the preceding Tables 2-4 and 2-5 and the
preceding equations:
Abare = Area of the steel beam (plus cover plate, if one exists), mm2.
As = Area of the rolled steel section alone (without the cover plate
even if one exists), mm2.
Ibare = Moment of inertia of the steel beam (plus cover plate if one
exists), mm4.
bf-bot = Width of the bottom flange of a user defined steel beam, mm.
bf-top = Width of the top flange of a user defined steel beam, mm.
d = Depth of the steel beam from the outside face of the top flange
to the outside face of the bottom flange, mm.
ybare = Distance from the bottom of the bottom flange of the steel
section to the ENA of the steel beam (plus cover plate if it
exists), mm.
∑ ( Ay ) =
1 Sum of the product A times y1 for all of the elements of the
steel beam section, mm3.
Recall that for the calculation of transformed section properties to be used for
stress and deflection calculation, concrete in tension is ignored. But concrete is
assumed effective for both tension and compression for vibration calculations.
Because of the possibility that some of the concrete may be in tension, and
because the amount of concrete that is in tension is initially unknown (if any),
the process for calculating the distance ye is iterative. After the distance ye has
been determined, the other calculations to determine the composite properties
are relatively straightforward.
The program uses the following method to calculate the properties of the
composite section.
The location of the ENA of the composite section, defined by ye (see Figure 2-
27), is calculated using the following iterative process:
a. The program assumes (guesses) that the ENA of the composite section is
within the height of the steel beam and uses the following equation to
calculate the distance ye that defines the location of the ENA for the
composite section. Note that with this assumption, all of the concrete is
above the ENA of the composite section, and thus it is all in compression
and can be considered.
ye =
∑( A
element d element )
∑A element
where,
For any element from the steel section (flange, fillet, or web), the
equivalent area is taken as its own area unmodified. Any element
delement = Distance from the ENA of the element considered to the ENA of
the steel beam alone (including cover plate, if it exists), mm.
Signs are considered for this distance. Elements located below
the ENA of the steel beam alone (including cover plate, if it
exists) have a negative distance and those above have a positive
distance.
b. If the calculated ENA is not within the height of the steel beam, as
assumed in Step a, the assumed location of the ENA is incorrect and
calculation for ye continues.
iii If the newly calculated location of the ENA is not the same as the
previously calculated zone (Step i), the most recent assumed location
of the ENA is incorrect and another iteration is made.
iv The program repeats the iterations until the location of the ENA has
been determined.
After the location of the ENA is known, the other calculations to determine the
composite section moment of inertia are non-iterative and relatively straight-
forward. The other calculation steps are as follow.
Sums ΣA tr Σ (A y ) Σ (A y
tr 1 tr 1
2
) ΣI O
a. If the deck spans perpendicular to the beam span, the concrete in the
metal deck ribs is ignored. If the deck spans parallel to the beam span,
the concrete in the metal deck ribs is considered.
b. The cover plate may or may not be present.
c. The concrete slab and metal deck may not exist on one side of the
beam or the other.
d. The top of the concrete slab may be at a different elevation on the two
sides of the beam.
e. The appropriate modulus of elasticity of concrete, Ec, should be used.
For deflection, the Ec is reduced by a factor of creep; for vibration, the
Ec is increased by an enhanced factor; and for stress based calculation,
the user specified value is used.
f. Concrete is considered effective for compression and considered
ineffective for tension, while Itr is calculated for deflection and stress
calculations. While Itr is calculated for vibration, concrete is
considered effective for both compression and tension.
Following is a list of the variables introduced in Table 2-6 that have not been
mentioned previously in this section.
hr* = Height of the metal deck ribs above the ENA used for calculating the
transformed section properties, mm. Note that this could be different
on the left and right sides of the beam.
If the deck ribs are oriented perpendicular to the beam span, hr* = 0.
If the deck ribs are oriented parallel to the beam span, one of the
following four items applies:
3. If the ENA is within the metal deck, hr* equals the height of the
metal deck above the ENA.
4. If the ENA is above the metal deck, hr* = 0.
tc* = Thickness of the concrete slab above the metal deck (or solid slab) that
lies above the ENA that is used for calculating the transformed section
properties, mm. Note that this could be different on the left and right
sides of the beam. One of the following four items applies:
2. If the ENA is below the top of the metal deck (bottom of the
concrete slab), tc* = tc.
3. If the ENA is within the concrete slab, tc* equals the height of the
concrete slab above the ENA.
4. If the ENA is above the concrete slab, tc* = 0
Abare = Area of the steel beam (plus cover plate), mm2. This area does not
include the concrete area.
Ec = Modulus of elasticity of concrete slab, MPa. Note that this could be
different on the left and right sides of the beam. Also note that this it
may be different for stress calculations and deflection calculations.
Es = Modulus of elasticity of steel, MPa.
Sr = Center-to-center spacing of metal deck ribs, mm. Note that this may be
different on the left and right sides of the beam.
beff = Effective width of the concrete flange of the composite beam, mm.
This width is code dependent. Note that this width may be different on
the left and right sides of the beam. See the section entitled Effective
Width of the Concrete Slab for additional information.
d = Depth of the steel beam from the outside face of the top flange to the
outside face of bottom flange, mm.
hr = Height of the metal deck rib, mm. Note that this may be different on
the left and right sides of the beam.
tc = Thickness of the concrete slab, mm. If there is metal deck, this is the
thickness of the concrete slab above the metal deck. Note that this may
be different on the left and right sides of the beam.
wr = Average width of a metal deck rib, mm. Note that this may be different
on the left and right sides of the beam.
ybare = Distance from the bottom of the bottom flange of the steel beam to the
ENA of the steel beam (plus cover plate, if it exists) alone, mm.
ye = The distance from the ENA of the steel beam (plus cover plate, if it
exists) alone to the ENA of the fully composite beam, mm.
z = Distance from the ENA of the steel beam (plus cover plate, if it exists)
alone to the top of the concrete slab, mm. Note that this distance may
be different on the left and right sides of the beam.
Σ(A y )
tr 1 = Sum of the product Atr times y1 for all of the elements of the
composite steel beam section, mm3.
Σ(A y tr 1
2
) = Sum of the product Atr times y12 for all of the elements of the
composite steel beam section, mm4.
y=
∑(A y )
tr 1
∑A tr
y = ybare + ye
Figure 2- 28 Illustration of y
The transformed section moment of inertia about the ENA of the composite
beam, Itr, is calculated using the following equation.
I tr= ∑A 2
tr y1 + ∑ I − (∑ A ) y
O tr
2
where,
Ibare = Moment of inertia of the steel beam alone plus cover plate, if it exists, mm4.
Ieff = Effective moment of inertia of a partially composite beam, mm4.
Itr = Transformed section moment of inertia about ENA of the composite
beam calculated as described in the section entitled Transformed
Section Moment of Inertia, mm4.
where,
I tr
Str =
(y +t ) cp
where,
Itr = Transformed section moment of inertia about the ENA of the composite
beam, calculated as described in the section entitled Transformed Section
Moment of Inertia, mm4.
y = Distance from the bottom of the beam bottom flange to the ENA of the
composite beam calculated as described in the section entitled
Transformed Section Moment of Inertia, mm.
where,
yeff = The distance from the bottom of the beam bottom flange to the ENA of
the partially composite beam. Note that the distance yeff is measured
from the bottom of the beam bottom flange even when there is a cover
plate, mm.
CSteel
Fy
Plastic neutral axis (PNA)
TSteel
Fy
Note that the concrete is stressed to 0.85fcd and the steel is stressed to Fyd. The
distance yp is measured from the bottom of the beam bottom flange (not cover
plate) to the plastic neutral axis (PNA). The distance zp is measured from the
top of the concrete slab to the PNA; it can be different on the two sides of the
beam as described later. The illustrated plastic stress distribution is the basic
distribution of stress used by the program when considering a plastic stress
distribution for positive bending. Note that if the metal deck ribs are parallel to
the beam, the concrete in the ribs is also considered.
Figure 2-32 illustrates how the program idealizes a steel beam for calculating
the plastic stress distribution.
Figure 2-32 Idealization of a Rolled Section and a User-Defined Section Used for
Calculating the Plastic Stress Distribution
Two different cases are shown, one for a rolled section and the other for a user
defined section. The idealization for the rolled section considers the fillets
whereas the idealization for the user defined section assumes there are no fillets
because none are specified in the section definition. Although not shown in
those figures, the deck type and orientation may be different on the left and
right sides of the beam as shown in Figure 2-3 of the section entitled Effective
Width of the Concrete Slab in this chapter.
For a rolled steel section, the fillets are idealized as a rectangular block of steel.
The depth of this rectangular block, kdepth, is:
kdepth = k−tf.
The basic steps in computing the positive plastic moment capacity are as
follows:
Determine the location of the PNA using the subsection Location of the
Plastic Neutral Axis.
Calculate the plastic moment capacity of the composite section using the
equation given in subsection Plastic Moment Capacity for Positive Bending
together with the appropriate equation depending on the location of the PNA.
Note that for user defined sections, the terms related to the top and bottom
fillets are ignored.
If the deck ribs are oriented parallel to the beam span, MPFconc is calculated as
follows
wr hr wr hr
=MPFconc 0.85 f cd beff tc + + 0.85 f cd beff tc + .
S r left S r right
Note that the maximum concrete force has contributions from the left and right
sides of the beam that are treated separately and may be different.
MPF
= steel (A F s yd + bcp tcp Fydcp ) .
MPFsteel
= (b t
f -top f -top Fydf -top + tw h + b f -bot t f -bot Fydf -bot + bcp tcp Fydcp ) .
When computing the location of the PNA, it is important to remember that the
concrete is assumed to take no tension. Also, the concrete in the metal deck
ribs is considered effective in compression only if the metal deck ribs are
oriented parallel to the beam span.
The maximum concrete and steel forces are compared to determine whether the
PNA is within the concrete slab or the steel section. If MPFcon c>MPFsteel, the
PNA is within the concrete slab. If MPFsteel >MPFconc, the PNA is within the
steel section. If MPFsteel = MPFconc, the PNA is at the top of the steel beam.
If the PNA is within the slab, the fact that the concrete slab can be different on
each side of the beam complicates locating the PNA. If the PNA is within the
steel section, there are several general locations for it. After the general
locations have been identified, it is a straightforward process to determine the
location of the PNA. The general locations are:
Note it is very unlikely that the PNA would be below the beam web but there is
nothing in the program to prevent it. This condition would require a very large
beam bottom flange and/or cover plate. Each of the PNA locations in the steel
section is described following the description of the PNA in the concrete slab.
Next the program adds the compressive forces of those four items, starting with
the item at the highest elevation and proceeding downward. As each item is
added into the sum, the sum of compressive forces is compared with the
maximum tension value, which is the sum of MPFsteel. As soon as the sum of
forces exceeds MPFsteel, the program recognizes that the last location
considered is below the PNA, and the second to last location considered is
above the PNA. Using this information, the program can solve directly for the
location of the PNA.
Figures 2-33 and 2-34 show the internal forces for a rolled steel section and a
user defined steel section, respectively, for the condition where the PNA is in
the concrete slab above the metal deck.
Figures 2-35 and 2-36 show the internal forces for a rolled steel section and a
user defined steel section, respectively, for the condition where the PNA is
within the height, hr, of the metal deck ribs.
p CC 1
z
CC 2
TF T
TF B
TC P
Note that in Figures 2-33 through 2-36 the concrete compression forces (CC1
and CC2) may have different magnitudes and locations (elevations) for the left
and right sides of the beam.
Also note that the program ignores the rebar area for computing composite
moment capacities.
The term y2, which is the distance from the top of the steel beam to the PNA, is
shown in these figures and is defined by the following equation
MPFsteel − MPFconc
y2 = .
2b f -top Fydf -top
Figure 2-39 Rolled Section With PNA Within the Beam Top Fillet, Positive Bending
The term y3, which is the distance from the bottom side of the beam top flange
to the PNA, is shown in Figure 2-39 and is defined by the following equation.
The last term applies only to rolled steel beams; it reduces to zero for user
defined beams.
Figure 2-40 Rolled Steel Section With PNA Within the Beam Web, Positive Bending
The term y5, which is the distance from the top side of the beam bottom fillet to
the PNA, is shown in Figure 2-42 and is defined by the following equation.
MPFsteel − MPFconc − 2b f -top t f -top Fydf -top 2kwidth kdepth Fydw 2htw Fydw
=y5 − −
2k width Fydw 2k width Fydw 2k width Fydw
Note that it is unlikely that the PNA will be this low. It requires a very large
beam bottom flange and/or cover plate.
MPFsteel − MPFconc − 2b f -top t f -top Fydf -top 4k width kdepth Fydw 2htw Fydw
=y6 − −
2b f -bot Fydf -bot 2b f -bot Fydf -bot 2b f -bot Fydf -bot
Note that it is unlikely that the PNA will be this low. It requires a very large
beam bottom flange and/or cover plate.
Figure 2-43 Rolled Steel Section with PNA Within the Beam Bottom Flange, Positive Bending
Figure 2-45 Rolled Steel Section With PNA Within the Cover Plate, Positive Bending
The term y7, which is the distance from the top of the cover plate to the PNA, is
shown in Figures 2-45 and 2-46 and is defined by the following equation.
MPFsteel − MPFconc − 2b f -top t f -top Fydf -top 4kwidth kdepth Fydw 2htw Fydw 2b f -top t f -top Fydf -top
=y7 − − −
2bcp Fydcp 2bcp Fydcp 2bcp Fydcp 2bcp Fydcp
Figure 2-46 User Defined Steel Section with PNA Within the Cover Plate,
Positive Bending
Note that it is unlikely that the PNA will be this low. It requires an extremely
large cover plate. In the event the PNA was in the cover plate, the distance yp
would become negative.
If the PNA is in the concrete slab above the steel section, the procedure
described in the previous subsection of this section entitled PNA in the
Concrete Slab Above the Steel Beam is followed.
If the PNA is within the steel section, the program assumes that the PNA
occurs in the top flange of the beam. The distance y2 is calculated as described
previously for the PNA within the beam top flange. The calculated distance y2
is then checked to see if it actually is within the beam top flange. If it is, the
location of the PNA has been identified.
If the calculated distance y2 is not within the beam top flange, the program
continues by assuming that the PNA occurs in the beam top fillet. (Note that if
the beam is a user defined beam, there is no top fillet and the program skips
directly to assuming that the PNA is in the beam web.) The distance y3 is
calculated as described previously for PNA within the beam top fillet. The
calculated distance y3 is then checked to see if it actually is within the beam top
fillet. If it is, the location of the PNA has been identified.
If the calculated distance y3 is not within the beam top fillet, the program
continues by assuming that the PNA occurs in the beam web. The distance y4 is
calculated as described previously for the PNA within the beam top fillet. The
calculated distance y4 is then checked to see if it actually is within the beam
web. If it is, the location of the PNA has been identified.
In any practical case, the PNA is not expected to be below the beam web.
However, in the event the PNA has not yet been located, the program continues
down the beam section through the bottom fillet, the bottom flange, and finally
the cover plate until the location of the PNA has been identified.
where:
In the preceding equation, the values used for Tpiece, Cpiece and xPNA-piece can
assume the tension and compression values of ten constituent pieces of the
composite section, and their respective centroidal distances from the PNA. The
constituents parts are concrete above the metal deck on the left and right,
concrete within the metal deck as ribs at the left and right, the beam top flange,
the beam top fillet (of rolled shapes only), the beam web, the beam bottom
fillet (of rolled shapes only), the beam bottom flange, and the cover plate. Note
that the program ignores reinforcing bars in concrete. The corresponding
compression forces are CC1, CC2, CFT, CKT, CWeb, CKB, CFB, and Ccp. The
corresponding tensile forces are TC1, TC2, TFT, TKT, TWeb, TKB, TFB, and Tcp.
(Please refer to Figures 2-33 to 2-46 for graphical representations of these
forces.) Note that based on the assumption that concrete cannot take tension,
TC1anTC2 are always zero. For any piece from the steel shape, if C for a piece
exists, T for that piece is zero unless the PNA falls within that piece.
Depending on the location of the PNA, the compression and tension forces and
their corresponding xPNA for all constituent pieces of the composite section are
given as follows:
Concrete above the metal deck on the left side of the beam: The concrete
can carry a compression force only; tension is not allowed in the concrete.
The following equations are used for the compression force in the concrete
above the metal deck.
The following equations are used for the distance from the center of the force
in the concrete above the metal deck to the PNA.
zp
xPNA = , if the PNA is above the metal deck,
2
tc
xPNA= z p − , if the PNA is below the solid slab.
2
For partial composite connection, the PNA is always in the depth of the steel
shape. In that case, the CC1 is determined based on the depth of the effective
slab thickness as described in the subsection entitled Location of Plastic
Neutral Axis of the section Composite Moment Capacities of a Partially
Composite Beam with a Plastic Stress Distribution. If the bottom of the
effective concrete in the concrete slab is above the metal deck, CC1 is based
on the effective depth a1, else it is based on total thickness.
CC1 0.85 f cd beff a1 , if the effective line is above the metal deck, a1 < tc
CC1 = 0.85 f cd beff tc , if the effective line is below the solid slab.
For partial composite connection, the following equations are used for the
distance from the center of the force in the concrete slab above the metal
deck to the PNA.
a
xPNA =z p − 1 , if effective line is above the metal deck, a1 < tc ,
2
t
xPNA= z p − c , if effective line is below the solid slab.
2
Note that the terms zp, tc, and hr in the preceding equations must be for the
left side of the beam.
Concrete above the metal deck on the right side of the beam: The
concrete can carry a compression force only; tension is not allowed in the
concrete. The following equations are used for the compression force in the
concrete above the metal deck. Note that these equations are applied to each
side of the beam separately.
The following equations are used for the distance from the center of the force
in the concrete above the metal deck to the PNA.
zp
xPNA = , if the PNA is above the metal deck,
2
tc
xPNA= z p − , if the PNA is below the solid slab.
2
For partial composite connection, the PNA is always in the depth of the steel
shape. In that case, CC1 is determined based on the depth of the effective slab
thickness as described in the subsection entitled Location of Plastic Neutral
Axis of the section Composite Moment Capacities of a Partially Composite
Beam with a Plastic Stress Distribution. If the bottom of the effective
concrete in the concrete slab is above the metal deck, CC1 is based on the
effective depth a1; else it is based on total thickness.
CC1 0.85 f cd beff a1 , if the effective line is above the metal deck, a1 < tc ,
CC1 = 0.85 f cd beff tc , if the effective line is below the solid slab.
For partial composite connection, the following equations are used for the
distance from the center of the force in the concrete slab above the metal
deck to the PNA.
a
xPNA =z p − 1 , if effective line is above the metal deck, a1 < tc ,
2
t
xPNA= z p − c , if effective line is below the solid slab.
2
Note that the terms zp, tc, and hr in the preceding equations must be for the
right side of the beam.
Concrete within height of metal deck on the left side of the beam: The
concrete can carry a compression force only; tension is not allowed in the
concrete. The following two equations are used for the compression force in
the concrete within the metal deck. Also note that these equations apply only
if the span of the metal deck ribs is oriented parallel to the beam span. If the
metal deck ribs are oriented perpendicular to the beam span, there is no
compression force allowed on the concrete within the metal deck ribs.
wr ( z p − tc )
CC 2 = 0.85 f cd beff , if the PNA is within the metal deck ribs,
Sr
wr hr
CC 2 = 0.85 f cd beff , if the PNA is below the metal deck ribs.
Sr
The following equations are used for the distance from the center of the force
in the concrete within the metal deck ribs to the PNA.
z p − tc
xPNA = , if the PNA is within the metal deck ribs,
2
hr
xPNA = z p − tc − , if the PNA is below the metal deck rib.
2
For partial composite connection, the PNA is always in the depth of the steel
shape. In that case, CC2 is determined based on the depth of the effective slab
thickness as described in the subsection entitled Location of Plastic Neutral
Axis of the section Composite Beam with a Plastic Stress Distribution. If the
bottom of the effective concrete in the concrete slab is within the metal deck,
CC2 is based on the effective depth a2; else it is based on the total rib depth.
wr a2
CC 2 = 0.85 f cd beff , if the effective line is within the metal deck rib,
S2
wr hr
CC 2 = 0.85 f cd beff , if the effective line is below the metal deck rib.
S2
For partial composite connection, the following equations are used for the
distance from the center of the force in the concrete deck rib above the
effective line.
tc a2
xPNA = z p − − , if the effective line is within the metal deck ribs,
2 2
t h
xPNA = z p − c − r , if the effective line is below the metal deck rib.
2 2
Note that the terms zp, tc, and hr in the preceding equations must be for the
left side of the beam.
Concrete within height of metal deck on the right side of the beam: The
concrete can carry a compression force only; tension is not allowed in the
concrete. The following two equations are used for the compression force in
the concrete within the metal deck. Also note that these equations apply only
if the span of the metal deck ribs is oriented parallel to the beam span. If the
metal deck ribs are oriented perpendicular to the beam span, there is no
compression force allowed on the concrete within the metal deck ribs.
wr ( z p − tc )
CC 2 = 0.85 f cd beff , if the PNA is within the metal deck ribs,
Sr
wr hr
CC 2 = 0.85 f cd beff , if the PNA is below the metal deck ribs.
Sr
The following equations are used for the distance from the center of the force
in the concrete within the metal deck ribs to the PNA.
z p − tc
xPNA = , if PNA is within the metal deck ribs,
2
hr
xPNA = z p − tc − , if PNA is below the metal deck rib.
2
For partial composite connection, the PNA is always in the depth of the steel
shape. In that case, CC2 is determined based on the depth of the effective slab
thickness as described in the subsection entitled Location of Plastic Neutral
Axis of the section Composite Beam with a Plastic Stress Distribution. If the
bottom of the effective concrete in the concrete slab is within the metal deck,
CC2 is based on the effective depth a2; else it is based on the total rib depth.
wr a2
CC 2 = 0.85 f cd beff , if the effective line is within the metal deck rib,
S2
wr hr
CC 2 = 0.85 f cd beff , if the effective line is below the metal deck rib.
S2
For partial composite connection, the following equations are used for the
distance from the center of the force in the concrete deck rib above the
effective line.
tc a2
xPNA = z p − − , if the effective line is within the metal deck rib,
2 2
t h
xPNA = z p − c − r , if the effective line is below the metal deck rib.
2 2
Note that the terms zp, tc, and hr in the preceding equations must be for the
right side of the beam.
Beam top flange: The force in the beam top flange can be tension,
compression, or compression in the upper portion of the flange and tension in
the lower portion. The following equations are used for the tension and
compression forces in the beam top flange.
TFT = b f -top t f -top Fydt -top , if the PNA is above the top of the top flange,
=TFT b f -top ( t f -top − y2 ) Fydf -top , if the PNA is within the top flange,
TFT = 0, if the PNA is below the bottom of the top flange,
CFT = 0, if the PNA is above the top of the top flange,
CFT = b f -top y2 Fydf -top , if the PNA is within the top flange,
CFT = b f -top t f -top Fydf -top , if the PNA is below the bottom of the top flange.
The distance of tension force, TFT, in the top flange to the PNA is given by
the following equations.
t f -top
xPNA = y p − d + , if the PNA is above the top of the top flange,
2
t f -top − y2
xPNA = , if the PNA is within the top flange,
2
xPNA = 0, if the PNA is below the bottom of the top flange.
The distance of compression force, CFT, in the top flange to the PNA is given
by the following equations.
xPNA = 0, if the PNA is above the top of the top flange,
y2
xPNA = , if the PNA is within the top flange,
2
t f -top
xPNA = z p − t c −hr − , if the PNA is below the bottom of the top flange.
2
Note the terms zp, tc, and hr in the preceding equations must all be for the left
side of the beam or all for the right side of the beam. It does not matter which
side of the beam is used, but all of the terms must be consistent.
Beam top fillet: The force in the beam top fillet can be tension, compression,
or compression in the upper portion of the fillet and tension in the lower
portion. The following equations are used for the tension and compression
forces in the beam top fillet. Note that these equations do not apply to user
defined sections.
TKT = k width kdepth Fydw , if the PNA is above the top of the top fillet,
=TKT k width ( kdepth − y3 ) Fydw , if the PNA is within the top fillet,
TFT = 0, if the PNA is below the bottom of the top fillet,
C KT = 0, if the PNA is above the top of the top fillet,
CKT = k width y3 Fydw , if the PNA is within the top fillet,
CKT = k width kdepth Fydw , if the PNA is below the bottom of the top fillet.
The distance of the tension force in the top fillet, TKT, to the PNA is given by
the following equations.
kdepth
xPNA = y p − d + t f -top + , if the PNA is above the top of the top fillet,
2
kdepth − y3
xPNA = , if the PNA is within the top fillet,
2
xPNA = 0, if the PNA is below the bottom of the top fillet.
The distance of the compression force in the top fillet, CKT, to the PNA is
given by the following equations.
Note the terms zp, tc, and hr in the preceding equation must all be for the left
side of the beam or all for the right side of the beam. It does not matter which
side of the beam is used, but all of the terms must be consistent.
Beam web: The force in the beam web can be tension, compression, or
compression in the upper portion of the web and tension in the lower portion.
The following equations are used for the tension and compression forces in
the beam web.
The distance of the tension force in the web, TWeb, to the PNA is given by the
following equations.
h
xPNA = y p − d + t f -top + kdepth + , if the PNA is above the top of the web,
2
h − y4
xPNA = , if the PNA is within the web,
2
xPNA = 0, if the PNA is below the bottom of the web.
The distance of the compression force in the web, CWeb, to the PNA is given
by the following equations.
Note the terms zp, tc, and hr in the preceding equation must all be for the left
side of the beam or all for the right side of the beam. It does not matter which
side of the beam is used, but all of the terms must be consistent.
Beam bottom fillet: The force in the beam bottom fillet can be tension,
compression, or compression in the upper portion of the fillet and tension in
the lower portion. The following equations are used for the tension and
compression forces in the beam bottom fillet. Note that these equations do
not apply to user defined sections.
TKB = k width kdepth Fydw , if the PNA is above the top of the bottom fillet,
=TKB k width ( kdepth − y5 ) Fydw , if the PNA is within the bottom fillet,
TKB = 0, if the PNA is below the bottom fillet,
CKB = 0, if the PNA is above the top of the bottom fillet,
CKB = k width y5 Fydw , if the PNA is within the bottom fillet,
CKB = k width kdepth Fydw , if the PNA is below the bottom fillet.
The distance of the tension force, TKB, to the PNA is given by the following
equations.
3kdepth
xPNA = y p − d + t f -top + + h, if the PNA is above the top of the bottom fillet,
2
kdepth − y5
xPNA = , if the PNA is within the bottom fillet,
2
xPNA = 0, if the PNA is below the bottom fillet.
The distance of the compression force, CKB, to the PNA is given by the
following equations.
Note the terms zp, tc, and hr in the preceding equation must all be for the left
side of the beam or all for the right side of the beam. It does not matter which
side of the beam is used, but all of the terms must be consistent.
Beam bottom flange: The force in the beam bottom flange can be tension,
compression, or compression in the upper portion of the flange and tension in
the lower portion. The following equations are used for the tension and
compression forces in the beam bottom flange.
TFB = b f -bot t f -bot Fydf -bot , if the PNA is above the top of the bottom flange,
=TFB b f -bot ( t f -bot − y6 ) Fydf -bot , if the PNA is within the bottom flange,
TFB = 0, if the PNA is below the bottom flange,
CFB = 0, if the PNA is above the top of the bottom flange,
CFB = b f -bot y6 Fydf -bot , if the PNA is within the bottom flange,
CFB = b f -bot t f -bot Fydf -bot , if the PNA is below the bottom flange.
The distance of the tension force in the bottom fillet, TFB, to the PNA is given
by the following equations.
t f -bot
xPNA = y p − d + t f -top + 2kdepth + h + , if the PNA is above the top of the bottom flange,
2
t f -bot − y6
xPNA = , if the PNA is within the bottom flange,
2
xPNA = 0, if the PNA is below the bottom of the bottom flange.
The distance of the compression force in the bottom fillet, CFB, to the PNA is
given by the following equations.
Note the terms zp, tc, and hr in the preceding equation must all be for the left
side of the beam or all for the right side of the beam. It does not matter which
side of the beam is used, but all of the terms must be consistent.
Cover plate: The force in the cover plate can be tension, or compression in
the upper portion of the cover plate and tension in the lower portion.The
following equations are used for the tension and compression forces in the
cover plate.
TCP = bcp tcp Fydcp , if the PNA is above the top of the cover plate,
The distance of the tension force in the cover plate, TCP, to the PNA is given
by the following equations
tcp
xPNA = y p − d + t f -top + 2kdepth + h + t f -bot + if the PNA is above the top of the cover plate,
2
tcp − y7
xPNA = if the PNA is within the cover plate.
2
The distance of the compression force in the cover plate, CCP, to the PNA is
given by the following equations
The program determines the location of the PNA by comparing the maximum
possible compressive force that can be developed in the concrete, MPFconc,
with the maximum possible tensile force that can be developed in the steel
section (including the cover plate, if applicable), MPFsteel.
If the deck ribs are oriented parallel to the beam span, MPFconc is calculated as
follows.
wr hr wr hr
MPFconc = 0.85 f cd beff tc + + 0.85 f cd beff tc + ≤ pMPFsteel
Sr left S r right
Note that the maximum concrete force has contributions from the left and right
sides of the beam that are treated separately and may be different.
MPF
= steel (A F s yd + bcp tcp Fydcp )
MPFsteel
= (b t
f -top f -top Fydf -top + tw h + b f -bot t f -bot Fydf -bot + bcp tcp Fydcp )
Note that for a partial composite case, the expressions for MPFsteel remain the
same. The expressions of MPFconc have an upper limit based on steel’s axial
capacity. Here p is the partial composite connection (PCC), which theoretically
ranges from 0 to 1.
When computing the location of the PNA, it important to remember that the
concrete is assumed to take no tension. Also, the concrete in the metal deck
ribs is considered effective in compression only if the metal deck ribs are
oriented parallel to the beam span.
The maximum concrete and steel forces are compared to determine whether the
PNA is within the concrete slab or the steel section. Since MPFsteel≥MPFconc,
the PNA is within the steel section.
Since the PNA is within the steel section, there are several general locations for
it. After the general locations have been identified, it is a straightforward
process to determine the location of the PNA. The general locations are as
follows:
Within the beam top fillet (applies to rolled shapes from the program's
section database only).
Within the beam bottom fillet (applies to rolled shapes from the program's
section database only).
Note it is very unlikely that the PNA would be below the beam web but there is
nothing in the program to prevent it. This condition would require a very large
beam bottom flange and/or cover plate. Each of the PNA locations in the steel
section is described following the description of the PNA in the concrete slab.
Then, the program assumes that the PNA occurs in the top flange of the beam.
The distance y2 is calculated as described previously for PNA within the beam
top flange. The calculated distance y2 is then checked to see if it actually is
within the beam top flange. If it is, the location of the PNA has been identified.
If the calculated distance y2 is not within the beam top flange, the program
continues by assuming that the PNA occurs in the beam top fillet. (Note that if
the beam is a user-defined beam, there is no top fillet and the program skips
directly to assuming that the PNA is in the beam web.) The distance y3 is
calculated as described previously for PNA within the beam top fillet. The
calculated distance y3 is then checked to see if it actually is within the beam top
fillet. If it is, the location of the PNA has been identified.
If the calculated distance y3 is not within the beam top fillet, the program
continues by assuming that the PNA occurs in the beam web. The distance y4 is
calculated as described previously for the PNA within the beam top fillet. The
calculated distance y4 is then checked to see if it actually is within the beam
web. If it is, the location of the PNA has been identified.
In any practical case, the PNA is not expected to be below the beam web.
However, in the event the PNA has not yet been located, the program continues
down the beam section through the bottom fillet, the bottom flange and finally
the cover plate until the location of the PNA has been identified.
Next the program sums the compressive forces of these eight items, starting
with the item at the highest elevation and proceeding downward. As each item
is added into the sum, the sum of the compressive forces is compared with the
p(MPFsteel) as determined in the previous subsection.
As soon as the sum of forces exceeds p(MPFsteel), the program recognizes that
the last location considered is below the bottom of the effective concrete, and
the second to last location considered is above the bottom of the effective
concrete. Using this information, the program can solve directly for the
location of the bottom of the effective concrete.
Figure 2-47 shows the internal concrete forces for a rolled steel section (a user
defined steel section is similar) for the condition where the bottom of the
effective concrete is in the concrete slab above the metal deck. In this case, a1
represents the distance from the top of the concrete slab to the bottom of the
effective concrete. Note that the distance a1 can be different on the left and
right sides of the beam.
Figure 2-48 shows the internal concrete forces for a rolled steel section (a user
defined steel section is similar) for the condition where the bottom of the
effective concrete is within the height, hr, of the metal deck ribs. In this case, a2
represents the distance from the top of the metal deck ribs to the bottom of the
effective concrete. Note that the distance a2 can be different on the left and
right sides of the beam.
If the bottom of effective concrete is in the concrete above the metal deck, a2 is
set equal to 0. If the bottom of effective concrete is within the height of the
metal deck, a1 is set equal to tc.
Figure 2-48: Rolled Steel Section With Bottom of Effective Concrete Within the Height, hr, of
the Metal Deck Ribs, Positive Bending With Partial Composite Connection
All of the preceding terms have been described in the subsection Plastic
Moment Capacity for Positive Bending in the previous section entitled
Composite Plastic Moment Capacity for Positive Bending. The exception is
that the forces in the concrete slabs and concrete ribs in the metal decks, both at
the left and right sides of the beam, are expressed in terms of a1 and a2 instead
of zp and hr only. Also the corresponding xPNAs have been expressed in terms of
a1 and a2. All of these exceptions have been described previously there.
When calculating the moment capacity, concrete or reinforcing steel below the
bottom of the effective concrete is not considered in the calculation.
Note that the PNA for a partially composite beam always lies within the steel
beam section, not the concrete slab. Thus it is not necessary to check for the
PNA location within the concrete slab.
The positive moment capacity for a composite beam with an elastic stress
distribution is determined by considering five locations in the composite
section. These locations are as follows:
A moment capacity is calculated based on the allowable stress and the section
modulus at each of these five locations that are applicable to the beam
considered. The smallest moment capacity calculated is the positive moment
capacity for the beam. Figure 2-49 illustrates the allowable stress assumed for
each of those locations.
Compression E
φbcc α1 f c′ s
Ec
tc φbcc Fyr
hr
φbcs Fyf -top
yeff
The following equations are used to calculate the positive moment capacity
regarding stresses at the five key locations in the beam section. Note that in
these equations, if there is full composite connection, the term y is substituted
for the term yeff.
Es I eff
M n = 0.85 f cd -left
Ec -left
d + hr -left + tc -left − yeff
Es I eff
M n = 0.85 f cd -right
E
c -right d + hr -right + tc -right − yeff
I eff
M n = Fydf -top
d − yeff
I eff
M n = Fydf -bot
yeff
I eff
M n = Fydcp
yeff + tcp
The terms Ieff, Seff, and yeff that are used in the preceding equations are
determined based on the procedure described in the section entitled Effective
Section Properties for Partial Composite Connection in this chapter.
This chapter provides a detailed description of the algorithms used by the programs
in the design/check of structures in accordance with “EN 1994-1-1:2004 —
Design of composite steel and concrete structures” (Eurocode 4-2004).
3.1 Notation
Abare Area of the steel beam (plus cover plate) alone, mm2.
Ac Area of concrete within the slab effective width that is above the
elastic neutral axis (ENA) for full composite action, mm2. For
beams with metal deck ribs running perpendicular to the beam
span, only the concrete above the metal deck and above the ENA
is included. For beams with metal deck ribs running parallel to
the beam span, the concrete above the metal deck and the
concrete in the deck ribs are included if it is above the ENA. This
value may be different on the left and right sides of the beam.
Notation 1
Composite Beam Design Eurocode 4-2004
Av Shear area of the web equal to the overall depth d times the
web thickness tw, mm2.
CFT Compressive force in the top flange of the steel beam, N. This
force occurs only when the plastic neutral axis is below the top
of the beam.
3-2 Notation
Chapter 3 - Design Process
CWeb Compressive force in the steel beam web, N. This force occurs
only when the plastic neutral axis is within the beam web.
Notation 3-3
Composite Beam Design Eurocode 4-2004
3-4 Notation
Chapter 3 - Design Process
Notation 3-5
Composite Beam Design Eurocode 4-2004
Neff The effective number of beams resisting the heel drop impact,
unitless.
3-6 Notation
Chapter 3 - Design Process
St-eff The section modulus for the partial composite section referred
to the top of the equivalent transformed section, mm3.
Sxc Section modulus about the x axis of the outside fiber of the
compression flange, mm3.
Notation 3-7
Composite Beam Design Eurocode 4-2004
Sxt Section modulus about the x axis of the outside fiber of the
tension flange, mm3.
SRmax Maximum number of shear stud connectors that can fit in one
row across the top flange of a composite beam, unitless.
V Shear force, N.
Zx, Zy Plastic section modulus about the x and y axes of the beam
respectively, mm3.
ar For a user defined section, the ratio of the web area to the
flange area, but not more than 10, unitless.
3-8 Notation
Chapter 3 - Design Process
a2 Distance from the top of the metal deck to the bottom of the
effective concrete for partial composite connection when the
bottom of the effective concrete is within the height of the
metal deck, mm.
a3 Distance from the top of the metal deck to the elastic neutral
axis when the elastic neutral axis is located in the slab above
the metal deck, mm.
a6 Distance from the top of the metal deck to the elastic neutral
axis when the elastic neutral axis is located within the height
of the metal deck, mm.
b Width, mm.
bf-bot Width of the bottom flange of a user defined steel beam, mm.
d Depth of a steel beam from the outside face of the top flange
to the outside face of the bottom flange, mm.
Notation 3-9
Composite Beam Design Eurocode 4-2004
hc For rolled shapes, twice the distance from the beam centroid to
the inside face of the compression flange less the fillet or
corner radius. In a user defined section, twice the distance
from the centroid of the steel beam alone, not including the
cover plate even if it exists, to the inside face of the
compression flange, mm.
kdepth Distance from the inner face of a rolled beam flange to the
web toe of a fillet, mm.
l22, l33 Laterally unbraced length of a member for buckling about the
local 2 and 3 axes of the beam respectively, mm.
3 - 10 Notation
Chapter 3 - Design Process
m For a user defined section, ratio of the web yield stress to the
flange yield stress, unitless.
rd Distance from the top of the beam flange to the bottom of the
metal deck, mm.
r22, r33 Radius of gyration about the local 2 and 3 axes of the beam
respectively, mm.
t Thickness, mm.
tf-top Thickness of the top flange of a user defined steel beam, mm.
Notation 3 - 11
Composite Beam Design Eurocode 4-2004
y Distance from the bottom of the bottom flange of the steel beam
section to the elastic neutral axis of the fully composite beam,
mm.
ybare The distance from the bottom of the bottom flange of the steel
beam to the neutral axis of the noncomposite steel beam plus
the cover plate if applicable, mm.
ye The distance from the elastic neutral axis of the bare steel
beam alone (plus cover plate, if applicable) to the elastic
neutral axis of the fully composite beam, mm.
yeff The distance from the bottom of the bottom flange of the steel
beam to the neutral axis of the partially composite beam, mm.
y2 Distance from the top of the top flange of the steel beam
section to the plastic neutral axis when the plastic neutral axis
is within the beam top flange, mm.
3 - 12 Notation
Chapter 3 - Design Process
y4 For a rolled steel beam, the distance from the bottom of the
top fillet to the plastic neutral axis when the plastic neutral
axis is within the beam web, mm. For a user defined steel
beam, the distance from the bottom of the top flange to the
plastic neutral axis when the plastic neutral axis is within the
beam web, mm.
z Distance from the elastic neutral axis of the steel beam (plus
cover plate, if it exists) alone to the top of the concrete slab,
mm. Note that this distance may be different on the left and
right sides of the beam.
ΣA Sum of the areas of all of the elements of the steel beam section,
mm2.
ΣA tr
Sum of the areas of all of the elements of the composite steel
beam section, mm2.
Sum of the product Atr times y1 for all of the elements of the
Σ(A y ) tr 1
composite steel beam section, mm3.
Sum of the product A times y12 for all of the elements of the
Σ(Ay 1
2
)
steel beam section, mm4.
Sum of the product Atr times y12 for all of the elements of the
Σ(A y tr 1
2
)
composite steel beam section, mm4.
ΣI O
Sum of the moments of inertia of each element of the composite
steel beam section taken about the center of gravity of the
element, mm4.
Notation 3 - 13
Composite Beam Design Eurocode 4-2004
ΣQ n
Sum of the nominal strength of the shear connectors (shear stud
or channel) between the considered point and the point of zero
moment, N.
ΣQ n-pcc
Required nominal strength of the shear connectors (shear stud
or channel) between the considered point and the point of zero
moment for partial composite connection percentage, PCC, N.
ΣQ n-100
Required nominal strength of the shear connectors (shear stud
or channel) between the considered point and the point of zero
moment for full (100%) composite action, N.
ε Coefficient dependent on fy
λ Non-dimensional slenderness
3 - 14 Notation
Chapter 3 - Design Process
λw Slenderness parameter
Design Methodology 3 - 15
Composite Beam Design Eurocode 4-2004
3 - 16 Design Methodology
Chapter 3 - Design Process
Design Methodology 3 - 17
Composite Beam Design Eurocode 4-2004
In Eurocode 4-2004 design, the transformed section properties are used for
calculating deflection, and they are used when the moment resistance is
determined based on an elastic stress distribution; that is, when the web is
noncompact.
3 - 18 Design Methodology
Chapter 3 - Design Process
and is specified to be considered. Flexural checks are also made for the
construction loads.
Box 17 - Camber
The program determines the camber for the beam, if it is specified to have
camber. Refer to Beam Deflection and Camber in Chapter 2for more information.
Design Methodology 3 - 19
Composite Beam Design Eurocode 4-2004
If the beam is assigned a regular, non-auto select property, the design for that
beam property will be provided or the beam will be indicated to be inadequate.
There are some additional aspects included in the composite beam design
module that are not directly addressed in the flowchart shown in Figure 3-1.
Those include designing beams in groups and designing beams with partial
length cover plates.
For more information on the design by group feature, refer to the section
entitled How the Program Optimizes Design Groups in Chapter 2. The
extension of the methodology described for designing by groups is relatively
simple and is assumed to be apparent to the reader.
3 - 20 Design Methodology
Chapter 3 - Design Process
When a beam has a partial length cover plate, the program checks not only the
design at the point of the maximum moment (Box 8 of Figure 3-1), but also the
design at the point of the largest moment where the cover plate does not exist.
The automatically created design load combination, using the Eurocode 0:2002
specification, for checking the strength of an unshored beam subjected to
construction loads. Eurocode 0:2002 allows load combinations to be defined
based on EC0 equation 6.10 or the less favorable EC0 equations 6.10a and
6.10b [NDP].
∑γ
j ≥1
G, j Gk , j + γ p P + γ Q ,1Qk ,1 + ∑γ i >1
Q ,i ψ 0,i Qk ,i (EC0 Eq. 6.10)
∑γ
j ≥1
G, j Gk , j + γ p P + γ Q ,1ψQ ,1Qk ,1 + ∑γ
i >1
Q ,i ψ 0,i Qk ,i (EC0 Eq. 6.10a)
∑ξ γ
j ≥1
j G, j Gk , j + γ p P + γ Q ,1Qk ,1 + ∑γ
i >1
Q ,i ψ 0,i Qk ,i (EC0 Eq. 6.10b)
∑G
j ≥1
k, j + P + AEd + ∑ψ
i >1
2,i Qk ,i (EC0 Eq. 6.12b)
The following load combinations are considered if the option is set to generate
the combinations based on EC0 equation 6.10.
The variable values and factors used in the load combinations are defined as:
where,
ΣWDL = The sum of all wet dead load (WDL) load cases defined
for the model. Note that if a load case is simply defined as
dead load, it is assumed to be a WDL load case.
ΣLL = The sum of all live load (LL) load cases defined for the
model.
ΣRLL = The sum of all reducible live load (RLL) load cases
defined for the model.
same as that for live load when considering construction loads (e.g., placing of
concrete, etc.). See R. Vogel (1991).
Σ
1.35( WDL + ΣSDL) (EC0 Eq. 6.10, 6.10a)
Σ
1.35 ( WDL + ΣSDL) + 1.5 (ΣLL + ΣRLL) (EC0 Eq. 6.10, 6.10a)
where,
ΣSDL = The sum of all superimposed dead load (SDL) load cases
defined for the model.
and the remainder of the terms are as defined previously in this section.
where all of the terms are as described previously. Note that all of the load
factors for this serviceability check are 1.0.
If the beam is unshored, the WDL portion of the deflection is based on the
moment of inertia of the steel beam alone and the remainder of the deflection is
based on the effective moment of inertia of the composite section. If the beam
is shored, the entire deflection is based on the effective moment of inertia of
the composite section.
the width-to-thickness ratios of the beam compression flange, beam web, and,
if it exists and is in compression, the cover plate. When a singly symmetric
beam is designed for noncomposite behavior, it is also checked for lateral
torsional buckling requirements.
The program classifies beam sections as either Class 1, Class 2, Class3, Class 4
or slender. It checks the section class requirements at each design location
along the beam for each design load combination separately. A beam section
may be classified differently for different design load combinations. For
example, a beam may be classified as Class 2 for design load combination A
and as Class 3 for design load combination B. Two reasons that a beam may be
classified differently for different design load cases are as follows.
The section classification requirements for beam webs depend on the axial load
in the beam. Different design load combinations may produce different axial
loads in the beam. This is an issue only when beam axial loads are specified to
be considered in the composite beam analysis and design.
At each design location, for each design load combination, the program first
checks a beam section for the section classification requirements for the
compression flange, web, cover plate (if applicable) and lateral torsional
buckling (if applicable) described herein. If the beam section meets all of those
requirements, it is classified as Class 1 or Class 2 for that design load
combination. If the beam section does not meet all of the Class 1 section
requirements, it is checked for the Class 2, or Class 3 or Class 4 requirements
for the flanges, web, cover plate (if applicable) and lateral torsional buckling (if
applicable) described herein. If the beam section meets all of those
requirements, it is classified as Class 4 for that design load combination. If the
beam section does not meet all of the Class 4 section requirements, it is
classified as slender for that design load combination, and the program does
not consider it for composite beam design.
Class 1 – section can form a plastic hinge with the rotation capacity
required from plastic analysis, without reduction of the resistance.
Class 2 – section can develop its plastic moment capacity, but has limited
rotation capacity.
Too Slender – section does not satisfy any of the criteria for Class 1, 2, 3,
or 4. This happens when tf < 3 mm or tw< 3 mm. Too Slender sections are
beyond the scope of the code. They are not checked/designed.
The following three tables identify the limiting width-to-thickness ratios for
classifying the various parts of the cross-section, subject to bending only,
compression only, or combined bending and compression.
N
ψ = − 1 + 2 Ed , −3.0 < ψ ≤ 1.0 (EC3 5.5.2, Table 5.2)
Af y
for I-sections, Channels:
1 h 1 N Ed
=
α − − ( t f − r ) , −1 ≤ α ≤ 1 (EC3 5.5.2, Table 5.2)
c 2 2 tw f y
Section Classification 3 - 25
Composite Beam Design Eurocode 4-2004
In Case A of the figure, the width of the cover plate is less than or equal to the
width of the beam bottom flange. In that case, the width-to-thickness ratio is
taken as b1/tcp, and it is checked as a flange cover plate.
In Case B of Figure 3-2, the width of the cover plate is greater than the width
of the beam bottom flange. Two conditions are checked in that case. The first
condition is the same as that shown in Case A, where the width-to-thickness
ratio is taken as b1/tcp and is checked as a flange cover plate. The second
3 - 26 Section Classification
Chapter 3 - Design Process
If the moment is positive, the cover plate will be in tension. In such a case, the
cover plate will be classified as Class 1 (Plastic) regardless of the width
thickness ratio. See Table 3-1 for details.
Beam
Beam
Cover plate
tcp
tcp
b1 b2 b1 b2
Cover plate
Case A Case B
When reviewing for lateral torsional buckling requirements, the value of Lb/ryc
is checked. Lb is the laterally unbraced length of beam; that is, the length
between points that are braced against lateral displacement of the compression
flange. The term ryc is the radius of gyration of the compression flange about
the y axis.
Section Classification 3 - 27
Composite Beam Design Eurocode 4-2004
The program calculates the moment resistance, Mc,Rd, only if the beam is Class
1 to Class 4 section. It does not calculate Mc,Rd if the section is slender. The
design moment, Mpl,Rd, for a noncomposite rolled steel beam section without a
W f
cover plate is calculated as M pl , Rd = pl y .
γM 0
The exact methodology used to compute the design moment resistance in the
other cases depends on whether the beam, including the cover plate if it exists,
is doubly or singly symmetric, and whether the beam web is classified as
Section Class 1, 2, 3 or Section Class 4 .
Is section doubly No
Is the beam web No Is the beam web No Beam section is
symmetric or a
compact? noncompact? classified as
channel?
slender and is not
Yes a Yes b Yes c designed. Go to
next trial section.
e f g
The figure has boxes labeled a through g; start in the box labeled a. Note that
the criteria used by the program to determine if a section is compact or
noncompact for the Eurocode 4-2004 specification is described in this chapter
in the section entitled Section Classification Requirements.
After the moment of inertia has been calculated, the section moduli and radius
of gyration are calculated using standard formulas. This process is repeated to
get properties about both axes. The torsional constant is determined by
summing the torsional constants for the various components of the section. For
example, it may be determined by summing the J's of a rolled section and the
cover plate, if applicable, or in a user defined section, by summing the J's for
the top flange, web, bottom flange and cover plate, if applicable.
The factored moment resistance in the major and minor directions is based on
the geometric shape of the section, the section classification for compactness,
and the unbraced length of the member. The bending strengths are evaluated
according to Eurocode 3-2005 as follows (EC3 Section 6.2):
The program uses the minimum of the flexure strength, Mc,Rd, computed from
the Cross-Sectional Strength, Overall Member Strength and Torsional and
Torsional-Lateral Buckling Strength.
Cross-Sectional Strength and Overall Member Strength: The Mc,Rd33 and Mc,Rd22
are calculated assuming that the member is laterally fully supported (l22 = 0
and l33 = 0) irrespective of its actual lateral bracing length.
If the capacities (Mc,Rd22and Mc,Rd33) are overwritten by the user, they are
assumed not to apply to this case and are ignored.
For Cross-Sectional Strength and Overall Member Strength cases, the moment
capacities are considered to be as follows:
Class 1 or 2 sections
W pl f y
M c , Rd M
= = pl , Rd (EC3 6.2.5(2))
γM 0
Class 3 sections
Wel ,min f y
M
= c , Rd M
= el , Rd (EC3 6.2.5(2))
γM 0
Class 4 sections:
Weff ,min f y
M c , Rd = (EC3 6.2.5(2))
γM 0
The plastic and elastic section modulus values, Wpl and Wel,min are part of the
frame section definition.
Weff,min is the effective section modulus, corresponding to the fiber with the
maximum elastic stress, of the cross-section when subjected only to moment
about the relevant axis. Weff,min is based on the effective widths of the
compression parts (EC3 6.2.9.3(2), 6.2.2.5(1)). It is determined based on EN
1993-1-5 code (EN 1993-1-5 4.4(2), Table 4.1, Table 4.2).
The effect of high shear on the design moment resistance, Mc,Rd, is considered
if:
To account for the effect of high shear in I-sections, and Channels sections,
subjected to major axis moment, the reduced design plastic resistance moment
is taken as:
nρAw2
W
pl , y − fy
4tw
=M y ,V , Rd ≤ M y ,c , Rd (EC3 6.2.8(5))
γM 0
2
2V
=ρ Ed − 1 (EC3 6.2.8(3))
V pl , Rd
Aw = hw t w (EC3 6.2.8(5))
Similarly, for I and Channel, if the minor direction shear is more than 0.5 times
the plastic shear resistance in the minor direction, the corresponding plastic
resistance moment is also reduced as follows:
nρA2f
W pl , z − fy
4t f
=M z ,V , Rd ≤ M Z ,c , Rd (EC3 6.2.8(5))
γM 0
where,
2
2Vy , Ed
=ρ − 1 (EC3 6.2.8(3))
Vy , pl , Rd
Af = b f t f (EC3 6.2.8(5))
M Ed
≤ 1.0 (EC3 6.3.2.1(1))
M b, Rd
fy
M b , Rd = χ LT Wy (EC3 6.3.2.1(3))
λ MI
− Class 1 or 2 sections
− Class 3 sections
− Class 4 sections
Wpl, Wel, and Weff have been described in the previous section.
1
=χ LT ≤ 1.0 (EC3 6.3.2.2(1))
Φ LT + Φ 2LT − λ 2LT
where the factor, Φ, and the non-dimensional slenderness, λ LT are taken as:
Φ
= LT 0.5 1 + α LT ( λ LT − 0.2 ) + λ LT 2 (EC3 6.3.2.2(1))
Wy f y
λ LT = (EC3 6.3.2.2(1))
M cr
The elastic critical moment, Mcr, is based on gross cross-section properties and
taken as:
0.5
π2 EI I L2 GI
=M cr C1 2 z w + cr2 T (EC3-1993 F1.1)
Lcr I z π EI z
where Iz, Iw, and IT are the minor axis inertia, warping constant, and torsion
constant, respectively; Lcr is the effective unbraced length for the lateral-
torsional buckling mode, and C1 is defined as:
where ψ is the ratio of the smaller to the larger end moments. The value of C1 is
also taken as 1.0 if the unbraced length is overwritten. The value of C1 can be
overwritten on a member-by-member basis.
Here, Lcr is the effective unbraced length for the lateral-torsional buckling
mode.
when KLTB is the effective length factor for the lateral-torsional buckling mode,
and LLTB is the unbraced length for the lateral-torsional buckling mode.
The imperfection factor, αLT is defined in Table 6-1 based on the respective
buckling curve, defined in Table 6-2 (EC3 6.3.2.2(2)).
M Ed
≤ 1.0 (EC3 6.2.5(1))
M c, Rd
where,
MEd = The maximum required flexural strength, that is, the maximum
applied factored moment, N-mm.
The program check does not include minor axis bending moment and axial
force for composite section. However, if the beam is found to be non-
composite, a more rigorous approach is used to check the section.
Bending Checks 3 - 35
Composite Beam Design Eurocode 4-2004
0.29αd 2 f ck Ecm
PRd = (EC4, Eqn. 6.19)
γv
where,
h
=α 0.2 sc + 1 for 3 ≤ hsc d ≤ 4 (EC4, Eqn. 6.20)
d
3 - 36 Steel Anchors
Chapter 3 - Design Process
The design shear resistance of shear studs in ribbed slabs where ribs are
parallel to the beam is taken as kl PRd .
wr H s
=kl 0.6 − 1.0 ≤ 1.0 (EC4, Eqn. 6.22)
hr hr
where, H s ≤ hr + 75mm
The design shear resistance of shear studs in ribbed slabs where ribs are
perpendicular to the beam is taken as kt PRd where PRd is calculated for the
solid slab using EQ4, Eqn. 6.18 using f u ≤ 450 N/mm2.
0.7 wr H s
=kt − 1.0 ≤ kt ,max (EC4, Eqn. 6.23)
nr hr hr
where, nr is the number of shear studs in one rib at a beam intersection, not to
exceed 2 in computations.
The terms f ck and Ecm can be different on the two sides of the beam. The
program calculates Prd for each side of the beam separately using the preceding
equation and uses the smaller value in the calculations.
Steel Anchors 3 - 37
Composite Beam Design Eurocode 4-2004
The total maximum horizontal shear that can develop due to crushing of
concrete, ∑ Q cn −100 , is given by
The total maximum horizontal shear that can be developed due to tensile
yielding of the steel section, ∑ Q ns −100 , is given by
∑ Q= s
n −100 As Fyd + bcp tcp Fydcp (Rolled Shape)
∑=
Q s
n −100 b f -top t f -top Fydf -top + htw Fydw + b f -bot t f -bot Fydf -bot + bcp tcp Fydcp (Welded)
Ac = Area of concrete slab within the effective width. It may include the
rib area if the rib is parallel to the beam, mm2.
N1 =
∑Q n −100
.
Qn
3 - 38 Steel Anchors
Chapter 3 - Design Process
ΣQn − PCC
N1 =
Qn
p=
∑Q n − PCC
∑Q n −100
3.10.3.2 Between the Point Load and the Point of Zero Moment
The program uses the following equation to check that the number of shear
connectors provided between a point load and a point of zero moment is
sufficient. This equation is not specified by CSA but is used by CSI as the
LRFD equivalent of Equation I4-5 in the AISC-ASD89 specification.
M Ed − M c , Rd steel alone
N 2 = N1
M c , Rd comp − M c , Rd steel alone
Steel Anchors 3 - 39
Composite Beam Design Eurocode 4-2004
V= V=
(
Av f y 3 ) (EC3 6.2.6(2))
c , Rd pl , Rd
γM 0
Note that in preceding equations, Av, the area of the web, is calculated as
shown in the following equation, where Ctop and Cbot are the depths of copes, if
any, at the top and bottom of the beam section. The copes are specified in the
overwrites.
hw ε
> 72 (EC3 6.2.6(6))
tw η
235
ε= with Fy in N/mm2 (EC3-1-5 5.1(2), EC3 Table 5.2)
Fy
It is assumed that transverse stiffeners exist only at supports and therefore the
slenderness parameter, λ w is taken as:
h
λw = w (EC3-1-5 5.3(3))
86.4t ε
The transverse stiffeners at the supports are assumed to create only a non-rigid
end post, leading to the shear contribution factor being taken as:
Vbf,Rd = 0
VEd
≤ 1.0 (EC4 6.2.2.4)
VRd
where,
VEd = The required shear strength, that is, the applied factored shear, N.
No check is made for shear on the net section considering the bolt holes.
Beam shear is checked at the ends of the beam only. In unusual cases, where
some of the load cases act downward and some act upward, the maximum
shear may occur elsewhere. For example, consider a beam that has a uniform
load acting downward over its entire length and a single concentrated load
acting upward at the center. Assume that the magnitude of the upward
concentrated load is equal to the magnitude of the uniform load times its
length. In that case, the end reactions are zero, and the maximum shear
occurs at the center of the beam. The program will check the shear at the
ends of the beam in this case but not at the center.
3 - 42 Deflection Check
Chapter 3 - Design Process
Floor Vibration 3 - 43
Appendix A
Preferences
The composite beam design preferences are basic assignments that apply to all
composite beams.Default values are provided for all composite beam design
preference items. Thus, it is not necessary to specify or change any of the pre-
ferences. However, at least review the default values for the preference items to
make sure they are acceptable.
A1 Factors Tab
Table A1 lists the preference items available for phi factors in Eurocode 4-2004
design.
A-1
Composite Beam Design Eurocode 4-2004
A2 Beam Tab
Table A2 lists the composite beam preference items available on the Beam tab
in the Preferences form.
Table A2: Composite Beam Preferences on the Beam Tab
Possible Default
Item Values Value Description
Shored? Yes/No No Toggle for shored or unshored construction.
Length in the middle of the beam over
MiddleRange which the program checks the effective
≥ 0% 70%
(%) width on each side of the beam, expressed
as a percentage of the total beam length.
Factor applied to live load for special
Pattern Live
≥0 0.75 pattern live load check for cantilever back
Load Factor
spans and continuous spans.
Stress Ratio The acceptable stress ratio limit. This item
>0 1.0
Limit applies to design optimization only.
Toggle for placement of a steel headed stud
anchor in a single segment. To place studs
Single
in a single segment with uniform spacing
Segment for Yes/No No
throughout the beam, select Yes. This
Studs?
factor has no effect on checking beams with
user defined studs.
Stud Increase Increase the steel headed stud anchor factor
>1 1
Factor over the calculated number.
Additional Additional steel headed anchor to be added
Integer ≥ 0 0
Minimum Studs to the calculated number.
A3 Deflection Tab
Table A3 lists the composite beam preference items available on the Deflection
tab in the Preferences form.
Table A3: Composite Beam Preferences on the Deflection Tab
Possible Default
Item Values Value Description
Pre-composite dead load deflection limita-
tion denominator. Inputting a value of 120
PreComp DL
≥0 0 means that the deflection limit is L/120.
Limit, L/
Inputting zero is special, since it means no
check has to be made for this item.
A-2
Appendix A - Preferences
A-3
Composite Beam Design Eurocode 4-2004
See the section entitle Beam Deflection and Camber in Chapter 2 for a descrip-
tion of beam deflection and camber.
A4 Vibration Tab
Table A4 lists the composite beam preference items available on the Vibration
tab in the Preferences form.
Table A4: Composite Beam Preferences on the Vibration Tab
Possible Default
Item Values Value Description
Percentage of live load plus reduced live
load considered (in addition to full dead
Percent Live
≥0 25% load) when computing weight supported by
Load (%)
the beam for use in calculating the first
natural frequency of the beam.
Toggle to consider the frequency as one of
Consider
Yes/No No the criteria to be used for determining if a
Frequency?
beam section is acceptable.
Minimum Damping ratio of the system (DG11 Table
>0 8 Hz
Frequency 4.1, DG11 Section 5.2).
Toggle to consider Murray's minimum
Consider
damping requirement as one of the
Murray Yes/No No
criteria to be used for determining if a beam
Damping?
section is acceptable.
Percentage of critical damping that is
Inherent inherent in the floor system. This item is
> 0% 4%
Damping (%) used when Consider Murray Damping item
is set to Yes.
A-4
Appendix A - Preferences
A5 Price Tab
Table A5 lists the composite beam preference items available on the Price tab
in the Preferences form.
Table A5: Composite Beam Preferences on the Price Tab
Possible Default
Item Values Value Description
Toggle to consider price rather than steel
Optimize for
Yes/No No weight when selecting the optimum beam
Price?
section from an auto select section list.
Installed price for a single shear stud con-
Stud Price ($) ≥0 $0
nector.
Camber Price Camber price per unit weight of steel beam
≥0 $0
($) (including cover plate, if it exists).
See "How the Program Optimizes Design Groups" in Chapter 2 for additional
information on the "Optimize for Price?" item.
Be sure to use the same currency units in the preferences (for example, U.S.
dollars) for the steel price in the material properties, the steel headed stud
anchor price, and the camber price.
A-5
Appendix B
Overwrites
The composite beam design overwrites are basic assignments that apply only to
those composite beams to which they are assigned. Default values are provided
for all composite beam overwrite items. Thus, it is not required that any of the
overwrites be changed. However, at least review the default values for the
overwrite items to make sure they are acceptable. When changes are made to
overwrite items, the program applies the changes only to the elements to which
they are specifically assigned; that is, to the elements that are selected when the
overwrites are changed.
B1 Beam
Table B-1 lists the composite beam overwrite items available.
Table B-1: Composite Beam Overwrites
Possible Default
Item Values Value Description
Shored? Yes/No No Toggle for shored or unshored construction.
(unshored)
Beam Fy ≥0 Specified in Yield stress of the beam, Fy. Specifying 0
Material in the overwrites means that Fy is as speci-
Properties fied in the material properties
B-1
Composite Beam Design Eurocode 4-2004
The Shored item affects both the deflection calculations and the flexural stress
calculations for the beam. See the section entitled Beam Deflection and Camb-
er in Chapter 2 for a description of beam deflection. If the beam is shored, no
checks are performed for the construction loading design load combination.
Typically, when a beam is designed using the Composite Beam Design post-
processor that beam is designed as a composite beam if it has a deck section
(not slab section) assigned along the full length of the specified Middle Range
on at least one side of the beam.
See Effective Width of the Concrete Slab in Chapter 2 for a description of the
beam effective width.
The beam yield stress and the cover plate yield stress both default to the yield
stress specified for the material property associated with the beam section.
B-2
Appendix B - Overwrites
In this program, the cover plate can have a yield stress that is different from
that of the beam, if desired. See Cover Plates in the section entitled Composite
Beam Properties in Chapter 2 for a description of cover plates.
When the C1 factor is program calculated, the program uses the following equa-
tion to calculate it unless the user has specified the Bracing Condition as
Length Specified.
where ψ is the ratio of the smaller to the larger end moments. The value of C1 is
also taken as 1.0 if the unbraced length is overwritten. The value of C1 can be
overwritten on a member-by-member basis.
When the C1 factor is program calculated and the Bracing Condition is set in
the overwrites to Length Specified, the program uses 1.0 for C1.
B-3
Composite Beam Design Eurocode 4-2004
The No. Point Braces and No. Uniform Braces items allow specification ofthe
actual bracing for the beam. These items are described in User-Specified Uni-
form and Point Bracing in Beam Unbraced Length and Design Check in Chap-
ter 2.
When the Bracing Condition is specified as Length Specified, two items may
be specified in addition to those shown in Table B2a. The two additional items
are shown in Table B2c.
Table B2c: Additional Composite Beam Overwrite Items When the Bracing Condition Is
Specified as Length Specified
Possible Default
Item Values Value Description
Absolute Yes/No No Toggle switch for whether the maximum
Length? unbraced length is given as an absolute
length or a relative length.
Unbraced L22 ≥ 0 and ≤ beam Length of Maximum unbraced length for buckling
length beam about the beam local 2 axis.
B-4
Appendix B - Overwrites
When the maximum unbraced length is specified as an absolute length, the ac-
tual maximum unbraced length is specified. When the maximum unbraced
length is specified as a relative length, the value specified is equal to the max-
imum unbraced length divided by the length of the beam. The relative length
specified is always between 0 and 1, inclusive.
See Beam Unbraced Length and Design Check Locations in Chapter 2 for ad-
ditional information about the unbraced length of the beam.
B3 Deck
Table B-3 lists the composite beam overwrite items available for the Deck.
Table B-3: Composite Beam Overwrites for the Deck
Possible Default
Item Values Value Description
B-5
Composite Beam Design Eurocode 4-2004
When the Deck ID is program calculated, the user must refer to the output data
to determine what the program assumed for this item. It is not shown in the
overwrites.
If the deck direction is program calculated, do not overlook the important note
about deck orientation in Multiple Deck Types or Directions Along the Beam
Length in the section EffectiveWidth of the Concrete Slab in Chapter 2.
B4 Shear Stud
Table B-4 lists the composite beam overwrite items available for the Shear
Studs.
Table B-4: Composite Beam Overwrites for the Steel Headed Stud Anchors
Possible Default
Item Values Value Description
Toggle to indicate if a user defined steel
User Pattern? Yes/No No
headed stud anchor pattern is defined.
0, indicating Uniform spacing of steel headed stud
there are no anchors along the beam. There is one shear
Uniform
≥0 uniformly stud per row along the beam.
Spacing
spaced
connectors
B-6
Appendix B - Overwrites
Table B-4: Composite Beam Overwrites for the Steel Headed Stud Anchors
Possible Default
Item Values Value Description
Number of sections in which additional
0, indicating uniformly spaced steel headed stud anchors
there are no are specified. Clicking in this box opens the
No. Additional
≥0 additional Additional Sections form, which can be
Sections
connectors used to specify the section length and the
specified number of uniformly spaced steel headed
anchors in the section.
Toggle for placement of a steel headed stud
anchor in a single segment. To place studs
Single in a single segment with uniform spacing
Yes/No No
Segment? throughout the beam, select Yes. This
factor has no effect on checking beams with
user defined studs.
Stud Increase Increase the steel headed stud anchor factor
>1 1
Factor over the calculated number.
Minimum Extra Additional steel headed anchor to be added
Integer ≥ 0 0
Studs to the calculated number.
6ds Minimum longitudinal spacing of steel
Min Long
>0 (i.e., six stud headed stud anchors along the length of the
Spacing
diameters) beam.
Maximum longitudinal spacing of steel
Max Long
>0 36 inches headed stud anchors along the length of the
Spacing
beam.
4ds Minimum transverse spacing of steel
Min Tran
>0 (i.e., four stud headed stud anchors across the beam
Spacing
diameters) flange.
Maximum number of steel headed stud
Max Studs
>0 3 anchors in a single row across the beam
per Row
flange.
Program Capacity of a single shear stud. Specifying
Program
Qr calculated or 0 in the overwrites means that this value is
calculated
>0 program calculated.
The program default value for the minimum longitudinal spacing of steel head-
ed stud anchors along the length of the beam is six shear stud diameters. Note
that this item is input as an absolute length, not as a multiplier on the stud
diameter.
B-7
Composite Beam Design Eurocode 4-2004
The program default value for the maximum longitudinal spacing of steel
headed stud anchors along the length of the beam is 1000 mm. This item is
taken as an absolute length by the program, not as a multiplier on the total slab
thickness as required by the code . The code specifiesthat the maximum longi-
tudinal spacing of steel headed stud anchors along the length of the beam shall
not exceed eight times the total slab thickness (rib height, hr, plus the concrete
slab above the metal deck, tc) or 1000 mm. If the total slab thickness is less
than 1000 mm/6 = 167mm, the program default value may be unconservative
and should be revised.
The program default value for the minimum transverse spacing of steel headed
stud anchors across the beam flange is four shear stud diameters. Note that this
item is input as an absolute length, not as a multiplier on the stud diameter. See
the section entitled Distribution of Steel Headed Stud Anchors on a Composite
Beam in Chapter 2 for an additional description of how steel headed stud anc-
hors are distributed on composite beams.
The “Max Studs per Row” item indicates the maximum number of steel headed
stud anchors that is allowed in a row across the beam flange. For wider beams,
the Min Tran Spacing item might indicate that more steel anchors could be ac-
commodated across the beam flange but the Max Studs per Row item will limit
the number of studs in any row. See the section entitled Distribution of Steel
Headed Stud Anchors on a Composite Beam in Chapter 2 for an additional de-
scription of how steel anchors are distributed on beams.
See Steel Headed Stud Connector in the section entitled Steel Anchors in Chap-
ter 2 for a description of how the program calculates the allowable shear load
for a single steel anchor. Note that when a Qr value is specified in the over-
writes, the program assumes that the specified value of Qr has already been
modified by any applicable reduction factors for the metal deck. Finally, note
that specifying 0 (zero) in the overwrites for this item means that the allowable
shear stud load is calculated by the program, not that it is zero.
Steel anchors are described in more detail in the sections entitled Distribution
of Steel Headed Stud Anchors on a Composite Beam,Number of Shear Studs
that Fit in a Composite Beam Segment, and User Defined Shear Connector
Patterns in Chapter 2.
B-8
Appendix B - Overwrites
B5 Deflection
Table B-5 lists the composite beam overwrite items available for Deflection.
Table B5: Composite Beam Overwrites for Deflection
Possible Default
Item Values Value Description
Toggle to consider live load and total load
Deflection Check Ratio,
Ratio deflection limitations as absolute or as
Type Absolute, Both
divisor of beam length (relative).
Pre-composite dead load deflection limita-
tion denominator. Inputting a value of 120
PreComp DL
≥0 0 means that the deflection limit is L/120.
Limit, L/
Inputting zero is special, since it means no
check has to be made for this item.
Post-composite superimposed dead plus
live load deflection limitation denominator.
Super DL+LL Inputting a value of 120 means that the
≥0 240
Limit, L/ deflection limit is L/120. Inputting zero is
special, since it means no check has to be
made for this item.
Live load deflection limitation denomina-
tor. Inputting a value of 360 means that the
Live Load
≥0 360 deflection limit is L/360. Inputting zero is
Limit, L/
special, since it means no check has to be
made for this item.
Net load deflection (total deflection minus
camber) limitation denominator. Inputting a
Total Camber value of 240 means that the deflection limit
≥0 240 is L/240. Inputting zero is special, since it
Limit, L/ means no check has to be made for this
item. Camber is subtracted from the total
load deflection before checking.
Pre-composite dead load deflection limita-
tion denominator. Inputting a value of 120
PreComp DL
≥0 0 means that the deflection limit is L/120.
Limit, abs
Inputting zero is special, since it means no
check has to be made for this item.
B-9
Composite Beam Design Eurocode 4-2004
See the section entitled Beam Deflection and Camber in Chapter 2 for a de-
scription of beam deflection and camber.
B6 Vibration
Table B6 lists the composite beam overwrite items available for Vibration.
B - 10
Appendix B - Overwrites
See the section entitled Floor Vibration in Chapter 2 for a description of beam
vibration.
B7 Miscellaneous
Table B-7 lists the composite beam miscellaneous overwrite items.
Table B-7: Composite Beam Overwrites for Miscellaneous Items
Possible Default
Item Values Value Description
Toggle to select if the beam depth is to be
Consider Beam considered in an auto select section list. If
Yes/No No
Depth? yes, maximum and minimum depths must
be input.
Maximum actual (not nominal) beam depth
Maximum
>0 44 inches to be considered in an auto select section
Depth
list.
Minimum actual (not nominal) beam depth
Minimum Depth ≥0 0
to be considered in auto select section list.
Maximum Maximum percent composite connection
>0 100
PCC(%) considered for the beam.
Minimum PCC Minimum percent composite connection
>0 25
(%) considered for the beam.
Reducible live load is multiplied by this
LL Reduction factor to obtain the reduced live load. If
0<, >1.0 1.0
Factor zero is selected, the program calculated
valued is used.
Reaction Multiplier applied to the earthquake portion
0<, >1.0 1.0
Factor of the load in a design load combination.
B - 11
Composite Beam Design Eurocode 4-2004
B - 12
Bibliography
Allen, D. E. and Murray, T. M., 1993, "Design Criterion for Vibrations due to
Walking," Engineering Journal, 4th Qtr, AISC, pp. 117-129.
Allen, D. E., and J.H. Rainer. 1976. Vibration Criteria for Long Span Floors.
Canadian Journal of Civil Engineering. Vol. 3, No.2. June.
Allen, D.E., J.H. Rainer, and G. Pernica. 1979. Vibration Criteria for Long Span
Concrete Floors. Vibrations of Concrete Structures. Publication SP-60.
American Concrete Institute. Detroit, MI.
Allen, D.L. 1974. Vibrational Behavior of Long Span Floor Slabs. Canadian
Journal of Civil Engineering. Vol. 1, No. 1. September.
Boresi, A. P., 1985. Advanced Mechanics of Materials, John Wiley & Sons, Inc.
ISBN 0-471-88392-1.
Bibliography - i
Composite Beam Design Eurocode 2-2004
CSI, 2012. CSI Lateral Load Manual, Computers and Structures, Inc., 1995
University Avenue, Berkeley, California, 94704.
Murray, T. M., Allen, D. E. and Unger, E. E., 1997, "Floor Vibrations due to
Human Activity," AISC Steel Design Guide Series 11.
Murray, T.M. and W.E. Hendrick. 1977. Floor Vibrations and Cantilevered
Construction. Engineering Journal. American Steel Institute of Steel Con-
struction, Inc. Vol. 14, No. 3.
Naeim, F. 1991. Design Practice to Prevent Floor Vibration. Steel Tips, Tech-
nical Information & Product Service. Structural Steel Educational Council.
September.
Vogel, R. 1991. “LRFD-Composite Beam Design with Metal Deck,” Steel Tips,
Technical Information & Product Service, Steel Committee of California,
March.
ii Bibliography