Project Title: Proposed Waiting Shed Location: Brgy. Lumbia, Cagayab de Oro City Owner: Lgu-Brgy. Lumbia, Cdoc

1) The project involves constructing a waiting shed in Brgy. Lumbia, Cagayan de Oro City. 2) It will take 24 days to complete and involves tasks such as excavation, concrete works, masonry works, installation of formworks, rebar works, and roofing works. 3) A network diagram and manpower schedule is provided to show the sequence and duration of each task as well as the labor requirements over the 24 day period.

Uploaded by

Mac KY
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (3 votes)
957 views

Project Title: Proposed Waiting Shed Location: Brgy. Lumbia, Cagayab de Oro City Owner: Lgu-Brgy. Lumbia, Cdoc

1) The project involves constructing a waiting shed in Brgy. Lumbia, Cagayan de Oro City. 2) It will take 24 days to complete and involves tasks such as excavation, concrete works, masonry works, installation of formworks, rebar works, and roofing works. 3) A network diagram and manpower schedule is provided to show the sequence and duration of each task as well as the labor requirements over the 24 day period.

Uploaded by

Mac KY
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Project Title: PROPOSED WAITING SHED

Location: BRGY. LUMBIA, CAGAYAB DE ORO CITY


Owner: LGU-BRGY. LUMBIA, CDOC

No. of Days to Finish


No. List of Task tems Predecessor ES EF
Task (days)
A Excavation 2 -- 0 2
B Fabrication of Rebar Works for Footing and Columns 2 A 2 4
C Installation of Rebar Works for Footing 1 B 4 5
D Concreting of Footing 1 C 5 6
E Fabrication of Rebar Works for Beams 2 B 4 6
F Installation of Rebar Works for Columns and Lower beams 1 D, E 6 7
G Installation of Formworks for Columns and Lower Beam 1 F 7 8
H Concreting of Columns and Lower beams 4 G 8 12
I Installation of Rebar Works for Upper Beams 1 F 8 9
J Removal of Formworks for Columns and Lower Beams 1 H 12 13
K Backfilling Works 1 J 12 14
L Masonry Works 1 K 14 15
M Concrete Works for Benches 1 M 15 16
O Installation of Formworks for Upper Beams 1 J,I 13 14
P Concreting of Upper Beams 2 O 14 16
Q Removal of Formworks for Upper Beams 2 P 18 20
R Fabrication of Trusses 2 M 16 18
S Installation of Trusses 1 R, Q 18 20
T Intstallation of Purlins 1 S 20 21
U Installation of Roofing and Accessories 2 T 21 22
V Instation of PVC Pipe Downspout 1 U 22 23
W Installation of Electrical Works 1 V 23 24
NETWORK DIAGRAM (PERT-CPM)

5 6 8 12
12 13 14 15
16 18
Critical Path
D H J K L M R Non-Critical Path

14

16
C 4 5 G 7 8

13
0 2 2 4

15
6 7
A B
START

F
2 2 20 21 21 22 23 24

T U V W

FINISH
4 6 8 9 22 23
14 16 16 18
E I O P Q S 18 20

13 14

Manpower Schedule
Days 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Laborer 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1
Skilled 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1
Total 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 2 2 2