Resource Loading Sheet
Resource Loading Sheet
Resource Loading Sheet
1 Excavation cm
2 Lean Concrete
3 Base slab & wall Steel fixing
4 base slab concrete
5 Wall Steel
6 wall concrete
7 top slab parapet steel
8 top slab perapet concrete
9 Backfil
10 Footing & wall steel
11 Footing & wall Concrete
12 Structural Excavation Works
13 Granular Backfill
14 Reinforcement Works
15 Riprap
16 Plum Concrete
17 Concrete Class B Works
18 Lean Concrete Works
19 Grouted RipRap Class A
20 Dismantling of Structure and Obstructions
21 Structural Excavation
22 Granular Backfilling works
23 Class A3 Concrete Works
24 Class A1 Concrete Works
25 Pile Load Testing
26 Pile Boring Works
27 Pile Reinforcement, Concrete Works, Pile Cap, Peirs & Transum
28 Girder Casting Complete with all respects including Prestressing
29 Girder Launching Works
30 Deck Corcrete Works
31 Formation of Embekment
32 Concrete Leveling Pad for Reinforced Earth Wall, Concrete Class A1
33 Reinforced Earth Walls (a, I-iv)
34 Construction of Reinforced Earth Concrete Wall
35 Coping & Counterbalance Slab
36 Reinforced Earth Walls Coping & Counterbalance Slab Reinforced Earth Walls
37 Geotechnical Investigation (Soil Investigation works)
38 Common Backfilling works
39 Concrete Works (Lean, A3)
40 Alumunium Alucobond Cladding Works
41 Stairs Rail Works complete in all respects
42 Chequered Plate & Bolt Works
43 Polyurethane paint & sand blasting Works
44 Fiber Glass Canopy Works
45 Land preparation with Pedestrian Pavers
46 Misc for Lighting & Drainage System
47 Excavation & Termite Proofing Works
48 PCC Works
49 Back Filling Works
50 RCC Works (Footings, Plinth Beams, Column, Walls, Slabs, Stairs, Perapit including donduits et
51 Water Proofing
52 Block Masonry Work
53 Plaster Work
54 Flooring (PCC, Stonolithic, Epoxy Paint)
55 Tile & Marble Works (Carpet, Floor, Porcelain, Wall, Faced, Granite, Skirting)
56 Paint Works (Emulsion, Epoxy, Enamel, Stoving)
57 Pre - Cast Concrete Brackets
58 False Ceiling (Suspended, Gypsum Board, Aluminium Perforated)
59 Railing Works (Wall & Floor Mounted, Stair Railing)
60 Doors & Windows Works
61 Kitchen Cabinet (Floor, Wall), Kitchen Hood
62 Plinth Protection & Final Installations
63 Water Supply System (PPR Pipes) & Plumbing Fixtures
64 Drainage System & External Sewer
65 Supply, Installation of Split & Decorative Type ACUs
66 Supply, installation refrigerant, PVC Pipes & Realated Works
67 Equipment and Accessories
68 Supply & Installation of Fire Fighting Pipes and Fittings
69 Supply & Installation of valves and accessories
70 Lighting System
71 Power Distribution System
72 Earthing Works & Low Current System
73 Supply, installation testing & commissioning of Electric "Passenger Elevator"
74 RCC Works (Footings, Plinth Beams, Column, Walls, Slabs, Stairs, Perapit)
75 Supply, Installation of PACUs & ACUs
76 Supply, installation refrigerant, uPVC Pipes & Realated Works
77 Supply & Installation of Fire Fighting Pipes & Fittings
78 Supply, Installation of Decorative Type ACUs
79 Supply & Installation of Fire Fighting Accessories
80 Rail & Doors & Windows Works
81 Drainage System
82 Supply, Installation of Split ACUs, FAHUs, Refrigerant & uPVC pipes
83 Vertical Equipment (Reach Stacker, Forklifter, Fire tender)
84 Relocation of utilities
85 Demolishing of existing buildings
86 Environmenntal Management Plan (EMP)
87 Security Plan
88 Civil Works
89 Electrical Works
90 Plumbing Works
91 Water Tank
92 Furnishing
93 Lab Equipment
94 Custom Relocation
95 Taxi Stand
96 Walkways
97 FC Yard
98 Dirt Track
99 Water Supply (PPR Pipes) & Plumbing Fixtures
100 Supply & Installation of Firefighting accessories
101 Water Supply System (PPR Pipes) & Fixtures
102 HVAC Works (Complete In All Respects)
103 Supply & Installation of Fire Fighting Accessories
104 HVAC complete Installation of Equipment and Accessories
105 HVAC Equipment and Accessories
106 Supply, Installation of Decorative Type ACUs, DFCU
107 Steel Structure Roof
108 Water Supply System (PPR Pipes)
109 Clearing & Grubbing Works
110 Compaction of Natural Ground
111 Formation & Embekment from Roadway, Borrow Excavation.
112 Subgrade Works
113 Sub Base Works
114 Water Bound Macadam / Base Course
115 Asphalt Complete Works
116 Breaking of existing road pavement structure
117 TuffTiles incl Sand cushion
118 Premoulded Joint Filler with Bitumastic Joint Seal
119 Providing & Laying Polythene Sheet
120 Providing & Laying Geotextile
121 PVC Pipe for Dowels
122 Metal Guard Rail Works Complete in all respects
123 Traffic Road Signs Works
124 Barrier Works
125 Lean Concrete work
126 KERB Stones installation
127 Aluminium Pavement Works
128 Pavement Marking in Reflective Paint
129 Granular Backfill Works
130 Concrete Works (Lean, A1, A3)
131 Pile works of Gantry Sign boards
132 Supply & Installation of Gantry Boards
133 Clearing & Grubbing
134 Granular Sub Base
135 Aggregate Base Course
136 Prime Coat
137 Asphalt Wearing Course (Awc)
138 Utilities (Water Supply Pipeline + Electric Poles + Optical Fiber etc)
139 Establishment, operation and maintenance of material testing Laboratory
140 Block Masonry Works
141 Diesel Generators / Fuel Transportation System
142 Dismantling Existing
143 External Metal Sheds
144 Public Health & Sanitary
145 Fire Suppression Services
146 Walkways & Sheds
147 Weigh Bridges
148 Fork Lifter, Reach Stacker & Fire Tender)
149 Pedestian Movement & Landscape Area
150 Master Plan P & H
151 Master Plan FSS
152 Master Plan Electrical
153 HVAC SUNDRIES
Resource List
Per Day Productivity Supervisor Forman Site Engineer Steel fixer Mason Helper Skilled labor Rigger
225 1 1 1 4
ete Class A1
"Passenger Elevator"
s, Stairs, Perapit)
uPVC pipes
testing Laboratory
Fabricator Plumber Pump Opr Plant Opr welder supervisor Foreman Excavator Dumper Tractor with Tr
1 1
Loader TM Crane