Structural Design of Buried Flexible Pipes For Trenchless Installations
Structural Design of Buried Flexible Pipes For Trenchless Installations
Structural Design of Buried Flexible Pipes For Trenchless Installations
TRENCHLESS INSTALLATIONS
1 INTRODUCTION
Trenchless methods of pipe installation continue to advance in terms of both capability and
reliability. Recently developed techniques allow installation of a much wider range of pipe
materials including flexible pipes with relatively low stiffness not necessarily manufactured
specifically for trenchless installations. Unfortunately design methods have generally not kept
pace with installation methods. AS/NZS 2566.1 (1) is used for the structural design of buried
flexible pipes in Australia and New Zealand but this standard specifically excludes trenchless
installations and states that it “does not give design guidelines for … bored, jacked or mole-
ploughed installations”. In an earlier publication presented at the Australasian Society for
Trenchless Technology (ASTT) No-Dig Downunder 2017 Conference (2) an overview of structural
design for both rigid and flexible pipes was provided for a range of different trenchless installation
techniques as detailed in both local and overseas publications. In this paper a summary of these
design methodologies will be provided with further information on how design can be carried out
for trenchless installation methods for plastic and other flexible pipes based on the existing
methodologies contained in AS/NZS 2566.1 with an emphasis on new pipe installations. Figure 1
shows an extract from a typical pipeline design drawing. In this example the designer has selected
PE100 SDR17 pipe to be “installed using trenchless technology”. The question that was and should
be asked is: “Is the SDR17 pipe suitable for this installation for the permanent design loads?” This
paper will provide the answer to this question.
-1-
2 TRENCHLESS INSTALLATION METHODS
Trenchless pipe installation methods are many and varied in terms of how pipe is installed. From
the perspective of the structural design of the pipe for permanent design loads, how the pipe is
installed is less important than what the installed pipe looks like in relation to the existing material
in which it was installed. We use the term material here quite deliberately because the material
could be either a soil or rock. Figure 2 shows some idealised examples of what such installations
might look like for different trenchless installation methods.
The examples shown in Figure 2 include both new pipe installations, (a) to (c) above, and typical
pipeline renovation installations, (d) to (f) above. The focus of this paper is new pipe installations
only. What is common to each of the new pipe installations is that the pipe is installed in a bore
with a diameter larger than the outside diameter of the pipe. These diagrams also show a pipe
concentric with the excavated bore and, in (b), the gap between the outside of the pipe and the
bore is filled with grout. These are all schematic representations and actual installations will not
necessarily look so symmetrical. For example, unless other measures are taken, it is unlikely pipes
will be central within the bore. Some of these issues are discussed later in the paper.
-2-
in this early work can be applied to trenchless installation methods.
For trenchless installations it is important to differentiate between loads applied during the
installation and those that will act on the pipe for the balance of its asset life. In this paper these
loads are differentiated as either:
i. Permanent design loads – these are loads that may be applied to a pipe after installation
and for the balance of its service life after it has been installed. Such loads are usually only
known by the pipeline designer and the initial pipe selection should be made by them after
a consideration of these loads; or
ii. Installation design loads – these are loads that are applied to the pipe during installation.
Such loads are usually only known by the pipe installation contractor and the pipe to be
installed should be either checked or selected based on a consideration of these loads.
The focus of this paper is on the permanent design loads although it should be understood that
the installation design loads may control the final pipe selection.
Of these loads only the first one is related to the method of installation. All others will act on the
pipe in the same way whether the pipe was installed in a trench or was installed using a trenchless
installation method and as such should be calculated as per current published methods such as
those in AS/NZS 2566.1.
AS/NZS 2566.1 states that the design load due to dead load of trench or embankment fill is
calculated from Equation 4.3 which is replicated as Equation 1 below:
𝑤𝑔 = 𝛾𝐻 [1]
Where 𝛾 is the assessed unit weight of trench or embankment fill and H is the cover or vertical
distance from the top of the pipe and the finished surface.
-3-
AS/NZS 2566.1 also states that this formula applies “where H ≤ 10D. For H > 10D results may be
conservative (refer Commentary).”
The Commentary, AS/NZS 2566.1 Supp. 1 (4), provides an alternative formula for estimating the
earth load (Equation 2 below), based on Terzaghi’s silo theory, including the silo reduction factor
(𝜅).
𝑤𝑔 = 𝜅𝛾𝐻 [2]
where:
𝐻
−2 ′ 𝐾𝑜 𝑡𝑎𝑛𝛿
1−𝑒 𝐵
𝜅= 𝐻
2 ′ 𝐾𝑜 𝑡𝑎𝑛𝛿
𝐵
Whilst AS/NZS 2566.1 specifically excludes providing advice on “bored” installations, Figure C 4.1
of the Commentary provides a suggested approach for “bores” which is replicated as Figure 3
below.
Whilst the use of the silo reduction factor is commonly adopted in different design standards,
there is variation in the actual design parameters used. Some of these variations are:
(a) The width of the slip plane. Some publications suggest that this should be the width of the
bore rather than the pipe diameter. Adopting the terminology of AS/NZS 2566.1, D is the
pipe diameter at the neutral axis which is probably not intended.
(b) The lateral earth pressure coefficient. DWA-A 161 (5) provides values for the silo
reduction factor based on a value of lateral earth pressure coefficient of 0.5.
(c) The friction angle on the slip plane. A number of publications including ASTM F 1962 (6)
and DWA-A 161 suggest that this angle should be equal to half the soil friction angle due
-4-
to there being insufficient actual movement in the soil above the pipe to engage the full
soil friction.
(d) The AS/NZS 2566.1 Supp. 1 equation ignores soil cohesion although some publications
suggest it should be. For design of concrete pipes, AS/NZS 3725 (7) includes this soil
parameter.
Akbarzadeh and Bayat (8) provide a good summary of some of the these issues as applied to
Horizontal Directional Drilling (HDD) although the principles disucssed are common to all
trenchless techniques. AS/NZS 2566.1 Supp. 1 provides a reference to the concrete pipe design
standard AS/NZS 3725 and states that this standard provides values of the product of Ko and tanδ
between 0.11 for soft clay and 0.16 for crushed aggregates.
DWA-A 161 provides values of soil friction angles for gravels and sands (Group 1 soils) of 32.5
degrees and for clays (Group 4) 15 degrees. Adopting δ = 0.5ø and K = 0.5, this results in the
product of K and tanδ of 0.07 for clays and 0.15 for sands and gravels. If one accepts the principle
adopted in DWA-A 161 of δ = 0.5ø, it could be concluded that adoption values of the product of Ko
and tanδ in AS/NZS 2566.1 Supp. 1 could result in too high a value of the silo reduction factor for
clays but it could also be argued that ignoring soil cohesion in clay is also conservative.
The criteria of adopting a cover height of 2 pipe diameters is common in a number of tunnelling
applications. It should be noted however that the height of the water table in rock could be in
excess of this value.
Figure 4 (a) is a conventional (trenched) installation. Figure 4(b) is a trenchless installation with the
pipe concentric in the bore with the gap (annulus) between the pipe and the bore filled with grout.
In this latter installation the grout is the key element.
-5-
(a) Conventional Installation (b) Trenchless Installation (Grouted)
There are a number of issues with the grout in the trenchless installation which need to be
considered. These are:
i. If the strength and thickness of the grout are too high, then the system will tend to behave
like a plastic lined rigid pipe. This may be ok, but it is then important to understand the
design methodology.
ii. Does the grout add to the overall load carrying capacity of the installation or in other
words can it be considered equivalent to the embedment for a conventional installation?
iii. Is the grout sufficient to assume that the native soil will provide side support to the pipe?
DWA-A 161 contains very different design equations and methodology to AS/NZS 2566.1. It does
however address the issue of grouting and side support and states:
“With flexible pipes – in an operating state and on the condition of having complete bedding –
the supporting effect of the lateral bedding reaction pressure can be accounted for when
horizontal deformations are caused as a result of vertical loading. Complete bedding exists when
the annular space is grouted permanently, and fully once jacking is complete. The method of
installation and the soil must guarantee these conditions.”
Unfortunately, DWA-A 161 does not provide any guidance on what constitutes grout or how it
should be specified. In the following section we provide some references to material requirements
for grout from different sources.
AS/NZS 2566.2 (10) Appendix K provides information on CLSM’s and states that they will provide a
material of suitable stiffness and stability as an alternative to mechanically compacted granular fill
used in the embedment or trench fill zones. Table K1 provides typical mix proportions for a material
-6-
that should achieve a compressive strength in the range 0.6 to 3.0 MPa at 28 days which is replicated
as Table 1 below.
Table 1 - Typical CLSM Mix Proportions (AS/NZS 2566.2 Appendix K)
Material % by mass
GP cement 2–6
Fly ash 0 – 20
Granular material 60 – 80
The origin of this suggested mix proportion is not known, but it is understood that a material with
such a high proportion of granular material (sand) is not likely to have the required workability for
grouting of trenchless installations and that a mix with just cement, fly ash, water and various
additives is more appropriate.
Vicroads Technical Note 07 (11) refers to the use of flowable fill available in three strength grades
with the lowest having a compressive strength in the range 0.5 to 2.0 MPa at 28 days. They refer to
materials with compressive strengths of between 0.3 and 0.7 MPa providing an equivalent bearing
capacity to well compacted fill materials.
In research on the use of grouts for use with slip lined pipe renovations, Smith, Hoult and Moore
(12) reported on results of testing for both a low and high strength grouts. The low strength grout
had an average compressive strength of 1.3 MPa and consisted of a cement/water/foam mixture
with about 60% foam in the mix by volume. They also reported that this grout had an elastic modulus
of 2,350 MPa and a Poisson’s ratio of 0.469. They concluded that this value of Poisson’s ratio is very
similar to many soils which combined with the low compressive strength “lends credence to the
assumption that it can be considered to be equivalent to having soil between the two pipes”. (In this
research grout was placed between a corrugated metal host pipe and a polyethylene slip-lined pipe).
The research also indicated that the low strength grout did not display any significant shrinkage but
the high strength (about 30 MPa compressive strength) grout did.
In summary, for flexible pipe design the grout needs to be considered as a soil and for this to occur
the compressive strength should not exceed about 1.0 MPa. For grouts in a thin annulus, say less
than 15 mm, this requirement is considered unnecessary. In this case the thin grout layer will crack
allowing the pipe to deflect but the grout is still likely to provide the necessary support such that
the side support from the native soil will be provided. It is also important that the grout has low
shrinkage.
There are a range of different trenchless installation methods which could be classified as
microtunnelling which allow the excavation of an unsupported bore which is then slip-lined with a
-7-
pipe which is either pushed or even pulled into position. Such methods allow installation of a range
of different plastic pipe materials including PVC, PE, PP and GRP. Of these only the GRP might be a
classified as an actual jacking pipe. Figure 5 shows some examples of such installations. Both these
examples are installed in rock but such installations may also be possible in stiff clays and some
other soils.
Figure 5(a) shows the installation of a DN225 uPVC pipe in a larger bore. Timber spacers have been
used to centralise the pipe in the bore. For this example, with installation in rock, the structural
design of the pipe may not be critical but in soil it may be. In this case grouting would be effective
along the full length of the bore and with spacers included the pipe would be centralised in the bore
and as such it would be reasonable to consider the grout as an embedment as for a conventional
installation. Grout however needs to act like a soil and based on the information contained in
Section 4.1, the grout should have a compressive strength between 0.5 and 1.0 MPa at 28 days and
have low shrinkage.
Figure 5(b) shows a GRP jacking pipe being slip lined into an excavated bore but with a much smaller
annulus. Grouting along the full length of this pipeline is likely to be still effective but with no spacers
and the small annulus the grout would be ignored in the design and the combined soil modulus
would be equal to that of the native soil.
If grouting is not done or is not effective, then the design provisions in Section 5 below may be
appropriate.
Whilst grouting may be a requirement, it may not be effective in filling the complete annulus along
the full length of the pipeline. The most common example of this would be installation of non-
person entry sized pipes in cohesionless soils or other soils for which the bore is unlikely to remain
stable for the complete duration of both the pipe installation and subsequent grouting. In this
situation there is likely to be voids in between the pipe and the native soil or if native soil collapses
onto the pipe there may be soil in the annulus of unknown consistency. As such, the contribution
to the strength of the installed pipe provided by the soil around the pipe should be ignored.
The main design equations in AS/NZS 2566.1 which contain the combined soil modulus are the
equations for both deflection and buckling. Buckling is perhaps the simplest to consider. The
capacity of the pipe installation is provided by the two equations for allowable buckling pressure
which are equations 5.4(4) and 5.4(5) in AS/NZS 2566.1 which are replicated as Equations 3 and 4
below.
1 24
𝑞𝑎𝑙𝑙 1 = 𝑆𝐷𝐿 10−3 [3]
𝐹𝑠 (1−𝜗2 )
The allowable buckling pressure for fill heights (H) of 0.5 m or greater is the greater of the value
determined by these two equations. For H < 0.5 m only Equation 3 applies. The first equation
(Timoshenko’s buckling equation), depends only on the long-term stiffness (𝑆𝐷𝐿 ) and Poisson’s
ratio (𝜗) of the pipe material. The second equation, known as Moore’s equation, is dependent on
both the long-term pipe stiffness and the combined soil modulus (𝐸 ′ ). If the native soil is not
effective in providing side support, then the combined soil modulus is zero and the allowable
buckling pressure is determined by Equation 3 only; resistance to buckling is provided by the
properties of the pipe only.
The deflection equation contained in AS/NZS 2566.1 is a modified version of the modified Iowa
equation and is Equation 5.2(2) in AS/NZS 2566.1 and is replaced as Equation 5 below.
-9-
∆𝑦 𝐾 𝑥 10−3 (𝑤𝑔 + 𝑤𝑔𝑠 + 𝑤𝑞 )
= [5]
𝐷 8 𝑥 10−6 𝑆𝐷𝐿 +0.061 𝐸 ′
As an alternative to AS/NZS 2566.1, ASTM F1962 (6) contains a formula for calculating deflection for
pipes installed using HDD which is this standard is Equation X2.5 which is replicated as Equation 6
below.
∆ 0.0125𝑃𝐸
= [6]
𝐷 (𝐸 ⁄12(𝐷𝑅−1)3
Where:
𝑃𝐸 = Earth pressure (kPa)
𝐸 = modulus of elasticity (kPa). A value of 260,000 kPa for PE100 was included.
𝐷𝑅 = pipe dimension ratio.
ASTM F1962 states that “as slurry surrounding the pipe [installed using HDD] provides essentially no
side support, there is little pressure at the springline to restrain vertical deflection. The primary
resistance to deflection is provided by the pipe’s stiffness.” The result for Equation 6 for the same
pipe is also plotted in Figure 6.
As can be seen in Figure 6, the result from the AS/NZS 2566.1 and ASTM F1962 equation is the same
for the same loading conditions. Whilst equations 5 and 6 look quite different they are essentially
the same formula if 𝐸 ′ is excluded.
Pipe Deflection
20.0%
18.0%
Δy/D AS/NZS 2566.1 Δ/D ASTM F1962
16.0%
Pipe Deflection (%)
14.0%
12.0%
10.0%
8.0%
6.0%
4.0%
2.0%
0.0%
0 2 4 6 8 10
Figure 6 - Deflection of DN450 PE100 SDR17 Pipe for Different E' Values
The only other calculation for the ungrouted trenchless installation that needs some explanation is
the calculation of ring bending strain. The formula for ring-bending strain in AS/NZS 2566.1 is
-10-
Equation 5.3.1(2). This includes the value of the shape factor (Df). As explained in AS/NZS 2566.1
Supp. 1, the shape factor adjusts strain values to account for the deflected pipe ring shape. Where
the pipe is a pure ellipse the shape factor is three. As the ratio of SDL/E′ decreases, the shape factor
increases accordingly. For the ungrouted trenchless installation the pipe shape will be an ellipse and
a shape factor of 3 is appropriate.
Calculations were performed for the DN450 PE100 pipe for a number of different design scenarios
using the Trenchless version of the software FlxPipe® (www.trenchless.flxpipe.com) and a
summary is presented in Table 2 below.
A silo reduction factor of 1.0 was adopted for all design scenarios – i.e. no soil load reduction due
to frictional effects. In this example the ratio H/D < 10 and as such a literal interpretation of Clause
4.3 of AS/NZS 2566.1 as explained in Section 3.1 above has been applied.
As explained in Section 4.2 above, grouting of small diameter non-person entry pipes can be
difficult. The first design scenario considered as detailed in Results 1 is the ungrouted installation
with the specified pipe (SDR17). As can be seen in the results the pipe deflection and buckling do
not meet the specified requirements of AS/NZS 2566.1 with the deflection exceeding the
maximum allowable value and the buckling factor of safety is less than the minimum
recommended value of 2.5.
-11-
The second design scenario considered as detailed in Results 2 is the ungrouted installation with a
higher stiffness (lower SDR) pipe (SDR11). As can be seen in the results this provides a significant
increase in pipe stiffness and acceptable deflection, strain and buckling results are all complying
with the minimum specified or recommended values in AS/NZS 2566.1.
The third design scenario considered as detailed in Results 3 is the grouted installation with the
specified pipe (SDR17) and a native soil modulus of 3 MPa. Again, acceptable results were
obtained. Whether or not grouting is actually possible with pipe of this diameter would depend
very much on the actual soil conditions and the actual techniques offered. If in doubt, a better
design option may be to use the higher stiffness pipe. The SDR17 also may not have sufficient axial
capacity to be pulled into place. The design of this aspect of the installation is beyond the scope of
this paper but ASTM F1962 would be a useful reference along with a paper by Bower and
Steedman (13) for information regarding applying ASTM F1962 design methods with PE100 pipe.
The suitability of using HDD for such an installation is worth further comment. HDD techniques are
particularly well suited to placing pipeline and conduits under obstacles such as roads, rivers,
major services etc. The technique is also well suited to pressure pipelines where control of the
vertical alignment is generally not critical. For gravity sewers and stormwater pipelines, as in this
example, it is important that pipes are installed on a consistent vertical alignment matching the
grade shown on the design drawings and this may be difficult to achieve using HDD in some
ground conditions. The other potential issue with HDD is the size of the annulus. For a pipe of this
diameter the recommended bore diameter is 1.5 x Pipe OD (14) or in this example 675 mm. This
results in a theoretical annulus of 112 mm. Although not shown in Figure 1, this example involved
installation of a pipeline longitudinally under suburban roads in a major city. This size of annulus
could lead to unacceptable settlements at the road surface if this annulus is not grouted. Grouting
of HDD installations, whilst possible, is not often done as there is a risk of heave and other
unintended consequences if it is not done well. As demonstrated in this paper, grouting does offer
a number of advantages for design and pipe selection but is also important to reduce settlement
risks.
7 CONCLUSIONS
There is a continuing trend to install plastic pipes using trenchless methods which have a pipe
stiffness originally intended for conventional (trenched) installations. It is important that design
methods keep pace with this installation capacity so that authorities can have confidence that the
installed pipe is suitable for all design loads which it may be subjected to during its service life.
This paper has demonstrated how the principles of AS/NZS 2566.1 can be applied with only limited
modification for design of flexible pipes installed using trenchless technology. A number of the
suggestions included in this paper could quite easily be incorporated into a future revision of
AS/NZS 2566.1. Grout and grouting are seen as a key design issue. Both need to be better
addressed and understood for all trenchless methods and in particular HDD. Relevant
specifications for both grout and grouting do need to be developed so that designers can be
confident that design intents are reflected in actual construction methods.
-12-
8 REFERENCES
1. Standards Australia and Standards New Zealand. AS/NZS 2566.1 Buried flexible pipelines Part 1:
Structural design. 5 January 1998. Sydney & Wellington : Standards Australia and Standards New
Zealand, 1998.
2. Bower, J.C. Pipeline Structural Design for Trenchless Applications. Gold Coast : ASTT, No-Dig
Downunder 2017.
3. Marston, A. and Anderson, A. O. The Theory of Loads on Pipes in Ditches and Tests of Cement
and Clay Drain Tile and Sewer Pipe. Ames : Bul. 31, 1913.
4. Standards Australia and Standards New Zealand. AS/NZS 2566.1 Supplement 1:1998 Buried
flexible pipelines Part 1: Structural design - Commentary. Sydney and Auckland : Standards
Australia and Standards New Zealand, 1998.
5. DWA German Association for Water, Wastewater and Waste. DWA-A 161E Static Calculation
of Jacking Pipes. Hennef : DWA German Association for Water, Wastewater and Waste, October
2017.
6. ASTM. ASTM F1962-11 Standard Guide for Use of Maxi-Horizontal Directional Drilling for
Placement of Polyethylene Pipe or Conduit under Obstacles, Including River Crossings. 1 May 2011.
West Conshohocken : ASTM International, 2011.
7. Standards Australia / Standards New Zealand. AS/NZS 3725:2007 Design for installation of
buried concrete pipes. Sydney and Wellington : Standards Australia and Standards New Zealand,
2007.
8. Akbarzadeh, H and Bayat, A. Investigating ASTM F 1962 arching factor for Polyethylene
installed by Horizontal Directional Drilling. Tunnelling and Underground Space Technology . 39
(2014) 50-57, 2012.
9. U.S. Department of the Interior Bureau of Reclamation. Method for Prediction of Flexible Pipe
Deflection M-25 Second Edition. s.l. : Bureau of Reclamation, 2015.
10. Standards Australia and Standards New Zealand. AS/NZS 2566.2 Buried flexible pipelines Part
2: Installation. 12 August 2002. Sydney and Wellington : Standards Australia and Standards New
Zealand, 2002.
11. Vicroads. Technical Note 07 Flowable Fill. https://www.vicroads.vic.gov.au/. [Online] 2008.
[Cited: 10 October 2019.]
12. Smith, T, Hoult, N.A., and Moore, I.D. Role of Grout Strength and Liners on the Performance of
Slip-Lined Pipes. ASCE Journal Pipeline Systems Engineering and Practice. 2015, Vol. 6, No. 4.
13. Bower, J.C. and Steedman, D. Design of HDD Installations Using Amercian Design Standards
and Locally Manufactured Polyetyhylene Pipe. Gold Coast : No-Dig Down Under 2015, 2015.
14. NASTT. Horizontal Directional Drilling Good Practices Guidelines. Cleveland : North American
Society for Trenchless Technology, 2017.
-13-