Zidane & Andersen - The Top 10 Universal Delay Factors in Construction Projects
Zidane & Andersen - The Top 10 Universal Delay Factors in Construction Projects
Zidane & Andersen - The Top 10 Universal Delay Factors in Construction Projects
Top 10
The top 10 universal delay factors universal
in construction projects delay factors
Downloaded by NORWEGIAN UNIVERSITY OF SCIENCE & TECHNOLOGY, Doctor Bjørn Andersen At 01:18 27 April 2018 (PT)
Abstract
Purpose – Projects often face delays and unnecessary use of time due to various factors and reasons, and
hence suffer from unfavourable consequences. The purpose of this paper is to identify the universal delay
factors from an intensive literature review, complemented by delay factors in major Norwegian construction
projects based on empirical data.
Design/methodology/approach – The study in which this paper is based includes an intensive literature
review, and semi-quantitative open survey questionnaires. This paper addresses frequency and type of delay
factors in construction projects, in Norway based on the survey, and worldwide based on the previous studies.
Findings – From the study, the causes of delays facing the Norwegian construction industry are: poor
planning and scheduling; slow/poor decision-making process; internal administrative procedures and
bureaucracy within project organisations; resources shortage (human resources, machinery, equipment);
poor communication and coordination between parties; slow quality inspection process of the completed
work; design changes during construction/change orders; sponsor/owner/client lack of commitment and/or
clear demands (goals and objectives); late/slow/incomplete/improper design; office issues; and users’ issues.
And the top 10 universal delay factors are: design changes during construction/change orders; delays in
payment of contractor(s); poor planning and scheduling; poor site management and supervision; incomplete
or improper design; inadequate contractor experience/building methods and approaches; contractor’s
financial difficulties; sponsor/owner/client’s financial difficulties; resources shortage (human resources,
machinery, equipment); and poor labour productivity and shortage of skills.
Research limitations/implications – When it comes to the identification of delay factors in major
Norwegian projects, the research is based on a sample of 202 respondents from an open survey questionnaire.
It should be noted that analysing a large population of respondents that have been asked open questions can be
challenging due to the vague findings it might lead to. Also, when it comes to the identification of the universal
delay factors, there were different methods used by different authors, within different context. Similar future
studies in Norway based on qualitative and quantitative methods will give better verification for the findings.
Practical implications – This paper has documented the critical delay factors/causes in Norway.
The results of this study will help project managers, in Norway and elsewhere, to be aware and know about
the potential causes of delay in their construction projects, which will help to identify the possible risks in the
early phases of the project. Another practical implication is to make project managers and policy makers
conscious that delays are quite universal, making it necessary to identify them as a first step.
Social implications – The identification of delays factors and causes can permit projects to implement
mitigation actions to avoid delays, thus allowing delivering schools, hospitals and other necessary
infrastructure on schedule or ahead of schedule to society.
Originality/value – This paper highlights most (almost all) of the studies in the literature, including to the
study done in Norway, concerning the delay factors in construction projects and large construction projects in
general. This wide review of relevant literature will save time other academicians from having to conduct
similar studies. This study will assist both academic and professional experts providing more insight about
the delay causes in large-scale construction projects.
Keywords Norway, Construction projects, Delay causes, Delay factors, Top 10, Universal
Paper type Research paper
1. Introduction
The construction industry is one of the major industries which contributes significantly to International Journal of Managing
Projects in Business
the growth and economy of any country. Among the substantial problems in the © Emerald Publishing Limited
1753-8378
construction industry is time overruns. Construction delays play a key role in the success or DOI 10.1108/IJMPB-05-2017-0052
IJMPB failure of a project. There are many factors contributing to delays in construction projects.
Delays occur in most construction projects, and the magnitude of these delays varies
considerably from one project to another. It is essential to define the actual causes of delay in
order to minimise, mitigate, and avoid delay in any construction project. The delay factors
Downloaded by NORWEGIAN UNIVERSITY OF SCIENCE & TECHNOLOGY, Doctor Bjørn Andersen At 01:18 27 April 2018 (PT)
are crucial within a construction project, and it is vital that all organisations have certain
knowledge regarding this issue in order for the project to be completed effectively and
satisfactorily (Wong and Vimonsatit, 2012).
Delay in the construction industry is a “universal” phenomenon, and it has become a typical
part of the project’s construction lifetime (Sambasivan and Soon, 2007; Sweis et al., 2008).
Assaf and Al-Hejji (2006) defined it as “the time overrun either beyond completion date
specified in a contract, or beyond the date that the parties agreed upon for delivery
of a project”. Trauner et al. (2009, p. 25) defined delay in construction projects as: “to make
something happen later than expected; to cause something to be performed later than planned;
or to not act timely. It is what is being delayed that determines if a project or some other
deadline, such as a milestone, will be completed late”.
Most of the construction projects are frequently behind schedule due to various reasons.
Unfortunately, even nowadays, with all the advanced technologies and the good
understanding of project management and engineering techniques, the problem of delays
has not been solved (Sweis et al., 2008; Yang et al., 2013). A study done by Sweis (2013) shows
that 81.5 per cent of construction projects in Jordan experienced delay during the period
1990-1997. According to Assaf and Al-Hejji (2006), 76 per cent of the contractors indicated that
the average time overrun is between 10 and 30 per cent of the original planned duration, while
about 56 per cent of the consultants specified the same percentage. In addition, a study from
Faridi and El-Sayegh (2006) revealed that 50 per cent of the construction projects in the UAE
encounter delays and they were not completed on time. Similar research investigated the delay
factors and their effects in the literature from a total of 45 countries worldwide.
Over the last 40 years, significant attention has been paid to identify possible causes of delays
(Yang et al., 2013). To identify these causes, some authors (e.g. Doloi, Sawhney and Rentala, 2012;
Kazaz et al., 2012; Sambasivan and Soon, 2007; Assaf and Al-Hejji, 2006; Faridi and
El-Sayegh, 2006; Chan and Kumaraswamy, 1997; Chan and Kumaraswamy, 1995) have used
semi-quantitative methods like surveys and questionnaires, whilst others like Asnaashari et al.
(2009) have employed purely qualitative methods like interviews to identify causes.
This paper aims to highlight the theories around delay factors in construction projects in
general; among all considerations, we particularly included the delay factors in the
Norwegian construction projects based on an empirical study. Therefore, the research
questions covered in this paper are:
RQ1. What are the delay factors in major Norwegian projects based on an empirical study?
RQ2. What are the top 10 delay factors for each study done in 45 countries worldwide?
RQ3. What are the top 10 universal delay factors based on 46 countries and 103 studies?
This study represents a compilation of the multiple studies done in different countries
worldwide about the causes of, or factors in, construction delays. Few studies have been
done in Europe, and thus we hope this tiny work will also contribute to a better
understanding of time and flow problems in projects, since we contributed in this paper also
by an empirical study regarding delay factors in Norway.
2. Literature review
2.1 Delay in construction projects
According to Al-Khalil and Al-Ghafly (1999), delays can undesirably effect project
stakeholders. To the client, delays can be perceived as implying loss of revenue due to a lack
of rentable space or a lack of production facilities. On the other hand, to the contractor, Top 10
delays can mean higher overhead costs, plus higher material and labour costs, because the universal
project takes longer than was planned. The possibility of delivering projects on time can be delay factors
marked as an indicator of efficiency, but the construction activities involve many
Downloaded by NORWEGIAN UNIVERSITY OF SCIENCE & TECHNOLOGY, Doctor Bjørn Andersen At 01:18 27 April 2018 (PT)
unpredictable factors and variables which arise from various sources (Assaf and Al-Hejji,
2006). These variables may include environmental circumstances, availability of resources,
stakeholders’ performance, and contractual relations. Nevertheless, Trauner et al. (2009)
stated that a construction project is hardly ever finished within the planned time.
Projects running behind schedule may serve as an indicator of poor productivity and
bad project performance (Ramanathan et al., 2012). Any delay in a project may lead to
cost and time overruns, and these two are often related (Sambasivan and Soon, 2007).
Delays can also cause increased cost, plus loss of competitive advantage and market
share. Additional costs may be incurred through disputes and claims between involved
parties (Odeh and Battaineh, 2002). When projects are delayed, they are either extended or
accelerated, and therefore incur additional costs. It is common practice to keep a
percentage of the estimated project cost as a contingency allowance in the contract price
(Ramanathan et al., 2012). For the project owner, delays may lead to a loss of revenue
through the lack of production facilities, rentable space, or shortcomings with present
facilities. For the contractor, delays may result in cost overruns due to the longer period
of project work, penalties incurred, and higher material and labour costs (Assaf and
Al-Hejji, 2006; Khoshgoftar et al., 2010).
83 83
80
80 73 75
72
64 65 64
60
52 50
48 49 48 47 48
45 43 44 44 44 46
41 43 40 42
40 35 35 35 35 33
31 33
28 27 30 28
Figure 1.
25 22 25
21
20
10 The classification of
0 delay factors/causes
by countries and
Afghanistan
Australia
Bangladesh
Benin
Botswana
Burkina Faso
Cambodia
Egypt
Ethiopia
Ghana
Hong Kong
India
Indonesia
Iran
Iraq
Jordan
Kenya
Kuwait
Lebanon
Libya
Malawi
Malaysia
Nigeria
Oman
Pakistan
Palestine
Portugal
Qatar
Rwanda
Saudi Arabia
Singapore
South Africa
South Korea
Syria
Taiwan
Tanzania
Thailand
Turkey
UAE
Uganda
UK
USA
Vietnam
Zambia
Zimbabwe
their numbers
3. Methodology
This study builds on past studies when it comes to the identification of universal delay
factors, by investigating the most important delay factors identified by other researchers
worldwide. For the writing of this paper, we used two main sources of data:
(1) first, findings from semi-quantitative survey questionnaires; and
(2) the second source of data is an intensive systematic literature study.
Thus, we explain each method separately, starting by presenting the data from the survey as
they will be combined with the results from the other studies to identify universal delay factors.
Figure 2.
The survey
questionnaire
have more than ten years of construction industry experience; a further 25 per cent have five
to nine years of experience. Most of the respondents are project managers (54 per cent) and
team members (40 per cent). In total, 60 per cent of the respondents are from public
organisations, and 40 per cent from private companies.
The participants represent clients, owners, sponsors, contractors, subcontractors, and
suppliers. Years of working experience of the participants and their role in the projects play
an important part in answering the survey; by drawing on respondents in all layers of the
construction project, we will have a more complete picture of all the different perspectives of
delay factors.
With the exception of the background data, the questions were formulated as open-ended
questions, allowing the respondents to write their answers in free text. The analysis of the
data was performed through these steps:
(1) Coding the collected data, assigning high-level category labels to all free-text
responses. The categories applied were based on more or less agreed-upon
categories from the extant literature, but creating new categories where factors from
the survey did not fit such pre-existing categories.
(2) First-pass analysis: grouping of identical or near-identical responses and assigning
frequencies of response to each delay factor. The affinity of the factors to the
categories was assessed through parsing the free-text formulations of delay factors,
but ultimately this relied on the researchers’ insight into the topic and ability to
correctly interpret the factors.
(3) Second-pass analysis: grouping-related responses and identifying the dominant Top 10
delay factors. universal
(4) Third-pass analysis: looking for differences in response across project role, length of delay factors
experience, and sector.
Downloaded by NORWEGIAN UNIVERSITY OF SCIENCE & TECHNOLOGY, Doctor Bjørn Andersen At 01:18 27 April 2018 (PT)
Following the analysis of the data collected, the authors grouped commonly identified delay
factors into 11 groups; each group had sub-groups with the same interpretation (e.g. poor
planning and scheduling, which is the sum of the five sub-groups; last minute tasks; unclear
demands from project manager; poor project planning; lack of or no delegation; and
poor project management performance). A similar approach was used on the remedies that
were suggested by the respondents. Finally, the results emerging from our data were
compared with the existing literature to verify whether the identified delay factors are in
accordance with previous findings, or if they supplement them.
When it comes to the validity of the findings, validity refers to whether a research is
really measuring what it claims to be measuring (Saunders et al., 2012). The findings are
based on using a clustering analysis of qualitative survey data, where the study is based on
self-reported perception of delay factors by project parties (namely clients, owners,
sponsors, contractors, subcontractors, suppliers) which tends to vary, and may not always
be reliable. Furthermore, the study did not distinguish between ranking by individual
project parties. However, the findings are consistent with similar studies assessing the
causes of delay in construction projects.
It is important to state that the findings from this survey cannot be generalised, since it
represents reported respondent experiences involved in sample of projects based. It should
be noted that analysing a large population of respondents that have been asked open
questions can be challenging due to the vague findings it might lead to. As shown in
Figure 2, the open question is a single question, which asks about the delay causes in the
last projects that the respondent had been involved in. However, this kind of approach to
collecting data does not permit high validity compared, for example, to semi-structured or
unstructured interviews, where these are conducted carefully and allow the possibility to
clarify the questions and to be able to explore responses and themes from a variety of angels
(Saunders et al., 2012).
subcontractors”). Or we used similar factors when it may reflect the same meaning between
one study and another (e.g. “complex project seen from contactor perspective”, “inexperienced
contractor”, “poor building methods”, etc., will all be in the category “inadequate contractor
experience/building methods and approaches”). The result of this intensive literature study is
a list of the top 10 delay factors for 45 countries worldwide, where Norway is the 46th in the
list based on the findings presented in this paper. The number of sources and research studies
used is 104 research articles, the 105th article is this study (there are 103 results presented in
the findings section because we grouped Doloi, Sawhney and Iyer (2012) with
Doloi, Sawhney and Rentala (2012), and Ahmed, Azhar, Castillo and Kappagantula (2003)
with Ahmed, Azhar, Kappagntula and Gollapudil (2003), since they presented the same
results and were based on the same research). The number of delay factors which appeared by
repetition is 33 delay factors. To identify the “top ten universal delay factors”, we considered
the frequency of the 33 repeated delay factors in the 103 studies, then based on the original
ranking, we calculated the new universal ranking.
The calculation of the overall ranking index for the 33 delay factors is based on this equation:
10
1 X10 X Ni
ORI ¼ ðN i Þ
F i¼1 i¼1
i
where ORI is the overall ranking index; the number F is the number of rows (the total number of
studies, which is equal to 103); the number i is the actual ranking (from 1 to 10, since all the
rankings are about the top 10); Ni represents the frequency of each rank in one column (e.g. from
the results in Table III. column 1 for the delay factor “sponsor/owner/client’s financial
difficulties”, and for the value of the rank i ¼ 1, we will have N1 ¼ 10; column 8 for the delay
factor “design changes during construction/change of orders”, and for the value of the rank
i ¼ 7, we will have N7 ¼ 12, etc.). The overall ranking is based on the value of the ORI; the higher
the ORI, the better the ranking of the delay factor. We used ORI to distinguish it and avoiding
confusing it with the relative importance index (RII). RII is used to rank the delay factors based
on quantitative survey; many studies used it – e.g., Abd El-Razek et al. (2008).
The results obtained from this intensive literature review cannot be fully generalised,
since it complements previous studies on the same topic done executed different methods
with no normalised unified measure for all of those studies. The data used can be considered
as secondary data, and the problem with secondary data, especially when brought to use
from multiple sources (103 studies in the case of this paper), is the measures used, which do
not quite match each other. This may cause a problem when undertaking the analyses
believing that we have found a direct relation between all the results from previous studies.
Unfortunately, there is no solution to this situation, beyond checking the robustness of the
studies and try to use their classifications and normalise for all of them.
4. Findings
Our findings, as discussed in the methodology chapter, come first from a survey conducted
in Norway, and second, from an intensive literature review.
and
and
and Song
and
Table III.
Major delay factors
classified by countries,
(continued) then by authors
IJMPB
Downloaded by NORWEGIAN UNIVERSITY OF SCIENCE & TECHNOLOGY, Doctor Bjørn Andersen At 01:18 27 April 2018 (PT)
Table III.
The last row of Table III represents the results of this study based on the major Norwegian
construction industry. Since we had all the top 10 delay factors of 103 studies worldwide
and based on the equation in the methodology section of this paper, we calculated the
“Overall Ranking Index” and the final ranking of the 33 factors is in Table IV.
From Table IV, some of the delay factors, even those with high frequency compared to
the precedent delay factor, are ranked lower (e.g. 6 – “Delays in payment of contractors”,
with a frequency of 61, and 16 – “Poor planning and scheduling”, with a frequency of 64),
and the reason for this is that the calculation of the “Overall Ranking Index” takes into
consideration both the frequency and the original ranking of the delay factor.
done in Saudi Arabia. There were six critical delay factors in common within the list of the
first 10 in both studies. However, the delay factor “Poor planning and scheduling”, which is
number one in this study, was classified among the lowest in their list. Another similarity
was observed to the study of Rahsid et al. (2013) from Pakistan, which showed five similar
delay factors from the top 10 lists in each of the two studies. Again, the number one delay
factor of our study was not in their critical delay factors, however several were, including
the third and the fifth from our study.
Most of the delay factors/causes in Norway are similar to other studies’ results in other
countries. To avoid a lengthy discussion, our comparison is oriented towards the
most critical delay factors of other studies (typically the top 10 major delay factors) of
other similar studies. The similar delay factors are discussed in relation to our findings
as follows:
(1) “Poor planning and scheduling”, this is cited in the top 10 critical delay factors
in 64 studies and classified number one in six studies, which are: Adeyemi and
Masalila (2016) in Botswana; Sweis et al. (2008) in Jordan; Mezher and Tawil (1998) in
Lebanon; Tumi et al. (2009) in Libya; Alaghbari et al. (2007) in Malaysia; and
Aiyetan et al. (2011) in South Africa.
IJMPB (2) “Slow/poor decision-making process”, listed as one of the top 10 delay factors in
32 studies, where it is number one in three of them. The authors of the studies ranking
it number one are: Ezeldin and Abdel-Ghany (2013); Alwi and Hampson (2003);
and Gündüz and AbuHassan (2016).
Downloaded by NORWEGIAN UNIVERSITY OF SCIENCE & TECHNOLOGY, Doctor Bjørn Andersen At 01:18 27 April 2018 (PT)
association between delay factors and causes of changes. However, after slight comparison
between the topics of “Delay factors in construction projects” with “Change causes in
construction projects”, we may have a special reflection. Almost certainly, we will have a feeling
that “delays” and “changes” are generated from the same causes (e.g. the studies where we can
see the strong overlap between the two topics are Wu et al. (2005) and Sun and Meng (2009)).
However, this does not mean equivalence; changes are one of the delay factors, but delays are
not systematically causes of changes. Very few examples of the same causes of changes and
delays from this study compared to Wu et al. (2005) and Sun and Meng (2009) are: slow
decision-making process, unforeseen geological conditions, poor planning and scheduling, poor
site management and supervision, incomplete or improper design, etc.
If we have a close look at the delay factors with a frequency higher than 20, the list of the
23 top critical delay factors may be in any country and any project case; these are standard
and are not tailored to a specific country or a special context. However, regarding the
remaining ten factors, some of them fit only a special context and country (e.g. 29 – “Security
and/or unstable political situation”, and 28 – “Corruption/fraudulent practices”, etc.).
Another observation regards the delay factors with a frequency higher than 30.
These top 16 delay factors may be described as the universal internal delay factors; the
reason behind calling them internal is because the type of the stakeholders behind the origin
of these delay factors are internal to the project (i.e. mostly sponsor/client/owner,
consultants, designers, contractors).
We may say that if the list was extended to the top 20 or 30 delay factors for each study, the
final list would certainly exceed the 33 delay factors. However, the number of studies would be
reduced almost by half, since there were many authors who limited their list to ten delay factors
or slightly higher. As an example, in our survey we generated only 11 delay factors groups.
Based on the literature study, the delays have serious effects on project objectives. Some of
the effects are schedule and cost overrun of the project. It also creates other negative effects,
which even sometimes means abandoning of the project. It should be pointed out that the
next logical step is to identify possible mitigation actions to deal with the identified delay
factors/causes; this will be presented in another paper based on part 2 of the survey.
Most of the studies in Table III give indications how to reduce construction delays. The main
message of all the studies is that all the internal stakeholders of the project should know about
the delays they are causing (sponsor, client, owner, contractor, consultant, subcontractors, etc.).
Thus, having a database of delay causes within each organisation is more than a necessity, this
database should be updated progressively after evaluation of new delay factors/causes, and the
changes of the context, which lead to a change of the root causes of the delays.
that cover 46 countries worldwide. Based on the findings, we ranked the most often cited
delay factors (which total 33 delay factors) and came up with the top 10 universal delay
factors in the construction industry, which are: design changes during construction/change
orders; delays in payment of contractors; poor planning and scheduling; poor site
management and supervision; incomplete or improper design; inadequate contractor
experience/building methods and approaches; contractor’s financial difficulties; sponsor/
owner/client’s financial difficulties; resources shortage (human resources, machinery,
equipment); and poor labour productivity and shortage of skills.
The study in this paper including the intensive literature review related to all the listed
studies show that the factors/causes of delays differ between countries for various reasons
(e.g. project type, project context, political situation, government policy, environment,
working cultures, management style, methods of construction, geographical condition,
stakeholders, the economic situation, perspectives of researchers, etc.). It will be interesting
to check the causes’ roots for delay causes based on those few listed various reasons.
We believe that the results of this study can be of immense help to the practitioners
(sponsors/ owners/clients, contractors, subcontractors, and consultants) and especially to
academics. The practitioners can better understand the dynamics of managing projects and
make efforts to reduce the incidences of delays. The academic researchers can conduct
similar studies in other countries and identify causes delays. As mentioned earlier, some
causes may be unique to certain countries (e.g. security and political stability).
The results of this study will help project managers in Norway to be aware and know
about the potential causes of delay in their construction projects, which will help to identify
the possible risks in the early phases of the project. Another practical implication is to make
project managers and policy makers conscious that delays are universal. The identification
of delays factors and causes will permit seeing their effects and also mitigation actions if
these delays are harmful to the benefits of the society.
Besides the limitations stated in the methodology section, this study did not discuss the
103 different methodologies of the previous completed studies nor try to classify them based
on their robustness to answer the question related to the identification of the delay factors/
causes. Therefore, examination of varies methodologies used in the identification and
classification of delay factors/causes to find the most appropriate methods is a prospective
area for further study. Knowing that the methods used are mostly quantitative, it would be
relevant to apply qualitative methods in some studies.
Based on the results of the survey in Norway, it would be interesting to conduct a
qualitative study based on semi-structured or in-depth interviews with some of the
respondents. The choice of respondents should cover different stakeholders and preferable
from management, since they are those who can see the whole picture of what happened in
their projects. The aim of this would be to confirm the grouping of the delay factors, since
initially the grouping was done by the researchers after analysing the data.
References
Abbasnejad, B. and Izadi Moud, H. (2013), “Construction delays in Iranian civil engineering projects: an
approach to the financial security of construction business”, Life Science Journal, Vol. 10 No. 2,
pp. 2632-2637.
Abd El-Razek, M.E., Bassioni, H.A. and Mobarak, A.M. (2008), “Causes of delay in building
construction projects in Egypt”, Journal of Construction Engineering and Management, Vol. 134
No. 11, pp. 831-841.
Abdul-Rahman, H., Berawi, M., Berawi, A., Mohamed, O., Othman, M. and Yahya, I. (2006), “Delay Top 10
mitigation in the Malaysian construction industry”, Journal of Construction Engineering and universal
Management, Vol. 132 No. 2, pp. 125-133.
delay factors
Acharya, N.K., Im, H.M. and Lee, Y.D. (2006), “Investigating delay factors in construction industry:
Downloaded by NORWEGIAN UNIVERSITY OF SCIENCE & TECHNOLOGY, Doctor Bjørn Andersen At 01:18 27 April 2018 (PT)
Elawi, G.S.A., Algahtany, M., Kashiwagi, D. and Sullivan, K. (2015), “Major factors causing
construction delays in Mecca”, Journal for the Advancement of Performance Information &
Value, Vol. 7 No. 1, pp. 1-11.
Elhag, T.M.S. and Boussabaine, A.H. (1999), “Evaluation of construction costs and time attributes”,
Proceedings of the 15th ARCOM Conference, Vol. 2, September, pp. 473-480.
Emam, H., Farrell, P. and Abdelaal, M. (2015), “Causes of delay on infrastructure projects in Qatar”,
Proceedings of the 31st Annual ARCOM Conference, Association of Researchers in Construction
Management, Nottingham and Lincoln, pp. 773-782.
Enshassi, A., Al-Najjar, J. and Kumaraswamy, M. (2009), “Delays and cost overruns in the construction
projects in the Gaza Strip”, Journal of Financial Management of Property and Construction,
Vol. 14 No. 2, pp. 126-151.
Enshassi, A., Arain, F. and Al-Raee, S. (2010), “Causes of variation orders in construction projects in the
Gaza Strip”, Journal of Civil Engineering and Management, Vol. 16 No. 4, pp. 540-551.
Ezeldin, A.S. and Abdel-Ghany, M. (2013), “Causes of construction delays for engineering projects:
an Egyptian perspective”, Building Solutions for Architectural Engineering, Architectural
Engineering Conference, State College, PA, 3-5 April, pp. 54-63.
Fallahnejad, M.H. (2013), “Delay causes in Iran gas pipeline projects”, International Journal of Project
Management, Vol. 31 No. 1, pp. 136-146.
Faridi, A.S. and El-Sayegh, S.M. (2006), “Significant factors causing delay in the UAE construction
industry”, Construction Management and Economics, Vol. 24 No. 11, pp. 1167-1176.
Frimpong, Y. and Oluyowe, J. (2003), “Significant factors causing delay and cost overruns in construction
of groundwater projects in Ghana”, Journal of Construction Research, Vol. 4 No. 2, pp. 175-187.
Frimpong, Y., Oluwoye, J. and Crawford, L. (2003), “Causes of delay and cost overruns in construction
of groundwater projects in developing countries: Ghana as a case study”, International Journal
of Project Management, Vol. 21 No. 5, pp. 321-326.
Fugar, F.D. and Agyakwah-Baah, A.B. (2010), “Delays in building construction projects in Ghana”,
Construction Economics and Building, Vol. 10 Nos 1-2, pp. 103-116.
Gardezi, S.S.S., Manarvi, I.A. and Gardezi, S.J.S. (2014), “Time extension factors in construction
industry of Pakistan”, Procedia Engineering, Vol. 77 No. 1, pp. 196-204.
Gidado, K. and Niazai, G.A. (2012), “Causes of project delay in the construction industry in
Afghanistan”, Engineering, Project and Production Management (EPPM) Conference, University
of Brighton, Brighton, 10-11 September.
Gould, F. (2012), Managing the Construction Process: Estimating, Scheduling, and Project Control,
Pearson Education Inc., New York, NY.
Gündüz, M. and AbuHassan, M.H. (2016), “Causes of construction delays in Qatar construction
projects”, International Journal of Civil, Environmental, Structural, Construction and
Architectural Engineering, Vol. 10 No. 4, pp. 516-521.
Gündüz, M., Nielsen, Y. and Özdemir, M. (2013a), “Fuzzy assessment model to estimate the probability
of delay in Turkish construction projects”, Journal of Management in Engineering, Vol. 31 No. 4,
pp. 1-14.
Gündüz, M., Nielsen, Y. and Özdemir, M. (2013b), “Quantification of delay factors using the relative
importance index method for construction projects in Turkey”, Journal of Management in
Engineering, Vol. 29 No. 2, pp. 133-139.
Haseeb, M., Lu, X., Bibi, A., Dyian, M. and Rabbain, W. (2011), “Problems of projects and effects of
delays in the construction industry of Pakistan”, Australian Journal of Business and
Management Research, Vol. 1 No. 5, pp. 41-50.
IJMPB Haseeb, M., Lu, X., Hoosen, A.B. and Rabbani, W. (2011), “Causes and effects of delays in large
construction projects of Pakistan”, Kuwait Chapter of Arabian Journal of Business and
Management Review, Vol. 1 No. 4, pp. 18-42.
Hwang, B.G., Zhao, X. and Ng, S.Y. (2013), “Identifying the critical factors affecting schedule
Downloaded by NORWEGIAN UNIVERSITY OF SCIENCE & TECHNOLOGY, Doctor Bjørn Andersen At 01:18 27 April 2018 (PT)
performance of public housing projects”, Habitat International, Vol. 38 No. 2, pp. 214-221.
Kaliba, C., Muya, M. and Mumba, K. (2009), “Cost escalation and schedule delays in road construction
projects in Zambia”, International Journal of Project Management, Vol. 27 No. 5, pp. 522-531.
Kamanga, M.J. and Steyn, W.V. (2013), “Causes of delay in road construction projects in Malawi:
technical paper”, Journal of the South African Institution of Civil Engineering, Vol. 55 No. 3,
pp. 79-85.
Kaming, P.F., Olomolaiye, P.O., Holt, G.D. and Harris, F.C. (1997), “Factors influencing construction
time and cost overruns on high-rise projects in Indonesia”, Construction Management and
Economics, Vol. 15 No. 1, pp. 83-94.
Kazaz, A., Ulubeyli, S. and Tuncbilekli, N.A. (2012), “Causes of delays in construction projects in
Turkey”, Journal of Civil Engineering and Management, Vol. 18 No. 3, pp. 426-435.
Keane, P.J. and Caletka, A.F. (2015), Delay Analysis in Construction Contracts, John Wiley & Sons,
Chichester.
Khoshgoftar, M., Bakar, A.H.A. and Osman, O. (2010), “Causes of delays in Iranian construction
projects”, International Journal of Construction Management, Vol. 10 No. 2, pp. 53-69.
Kikwasi, G. (2013), “Causes and effects of delays and disruptions in construction projects in Tanzania”,
Australasian Journal of Construction Economics and Building-Conference Series, Vol. 1 No. 2,
pp. 52-59.
Kim, S., Tuan, K.N. and Luu, V.T. (2016), “Delay factor analysis for hospital projects in Vietnam”,
KSCE Journal of Civil Engineering, Vol. 20 No. 2, pp. 519-529.
Kim, Y., Kim, K. and Shin, D. (2005), “Delay analysis method using delay section”, Journal of
Construction Engineering and Management, Vol. 131 No. 11, pp. 1155-1164.
Koushki, P.A., Al-Rashid, K. and Kartam, N. (2005), “Delays and cost increases in the construction of
private residential projects in Kuwait”, Construction Management and Economics, Vol. 23 No. 3,
pp. 285-294.
Kvale, S., Brinkmann, S., Anderssen, T.M. and Rygge, J.F. (2009), Det Kvalitative Forskningsintervju,
Gyldendal akademisk, Oslo.
Le-Hoai, L., Dai Lee, Y. and Lee, J.Y. (2008), “Delay and cost overruns in Vietnam large construction
projects: a comparison with other selected countries”, KSCE Journal of Civil Engineering, Vol. 12
No. 6, pp. 367-377.
Lo, T.Y., Fung, I.W. and Tung, K.C. (2006), “Construction delays in Hong Kong civil engineering
projects”, Journal of Construction Engineering and Management, Vol. 132 No. 6, pp. 636-649.
Luu, V.T., Sang, N.M. and Viet, N.T. (2015), “A conceptual model of delay factors affecting government
construction projects”, ARPN Journal of Science and Technology, Vol. 5 No. 2, pp. 92-100.
Luu, T.V., Kim, S., Tuan, N.V. and Ogunlana, S.O. (2009), “Quantify schedule risk in construction
projects using Bayesian belief networks”, International Journal of Project Management, Vol. 27
No. 1, pp. 39-50.
Mahamid, I. (2013), “Frequency of time overrun causes in road construction in Palestine: contractors’
view”, Organization, Technology & Management in Construction: An International Journal,
Vol. 5 No. 1, pp. 720-729.
Mahamid, I., Bruland, A. and Dmaidi, N. (2012), “Causes of delay in road construction projects”,
Journal of Management in Engineering, Vol. 28 No. 3, pp. 300-310.
Mansfield, N.R., Ugwu, O.O. and Doran, T. (1994), “Causes of delay and cost overruns in Nigerian
construction projects”, International Journal of Project Management, Vol. 12 No. 4, pp. 254-260.
Marshall, C. and Rossman, G.B. (1995), Designing Qualitative Research, Sage, Thousand Oaks, CA.
Marzouk, M.M. and El-Rasas, T.I. (2014), “Analyzing delay causes in Egyptian construction projects”, Top 10
Journal of Advanced Research, Vol. 5 No. 1, pp. 49-55. universal
Mezher, M.M. and Tawil, W. (1998), “Causes of delays in the construction industry in Lebanon”, delay factors
Engineering Construction and Architectural Management, Vol. 5 No. 3, pp. 252-260.
Downloaded by NORWEGIAN UNIVERSITY OF SCIENCE & TECHNOLOGY, Doctor Bjørn Andersen At 01:18 27 April 2018 (PT)
Motaleb, O. and Kishk, M. (2013), “An investigation into the risk of construction project delays in the
UAE”, International Journal of Information Technology Project Management, Vol. 4 No. 3,
pp. 1149-1157.
Muhwezi, L., Acai, J. and Otim, G. (2014), “An assessment of the factors causing delays on building
construction projects in Uganda”, International Journal of Construction Engineering and
Management, Vol. 3 No. 1, pp. 13-23.
Muya, M., Kaliba, C., Sichombo, B. and Shakantu, W. (2013), “Cost escalation, schedule overruns and
quality shortfalls on construction projects: the case of Zambia”, International Journal of
Construction Management, Vol. 13 No. 1, pp. 53-68.
Mydin, M.O., Sani, N.M., Taib, M. and Alias, N.M. (2014), “Imperative causes of delays in construction
projects from developers’ outlook”, MATEC Web of Conferences, Vol. 10, 31 May-2 June 2013.
Nkado, R. (1995), “Construction time-influencing factors: the contractor’s perspective”, Construction
Management and Economics, Vol. 13 No. 1, pp. 81-89.
Nyoni, T. and Bonga, W.G. (2017), “Towards factors affecting delays in construction projects: a case
of Zimbabwe”, Dynamic Research Journals – Journal of Economics and Finance, Vol. 2 No. 1,
pp. 12-28.
Odeh, A.M. and Battaineh, H.T. (2002), “Causes of construction delay: traditional contracts”,
International Journal of Project Management, Vol. 20 No. 1, pp. 67-73.
Odeyinka, H.A. and Yusif, A. (1997), “The causes and effects of construction delays on completion cost
of housing project in Nigeria”, Journal of Financial Management of Property and Construction,
Vol. 2 No. 3, pp. 31-44.
Ogunlana, S.O., Promkuntong, K. and Jearkjirm, V. (1996), “Construction delays in a fast-growing
economy: comparing Thailand with other economies”, International Journal of Project
Management, Vol. 14 No. 1, pp. 37-45.
Okpala, D. and Aniekwu, A. (1988), “Causes of high costs of construction in Nigeria”, Journal of
Construction Engineering and Management, Vol. 114 No. 2, pp. 233-244.
Omoregie, A. and Radford, D. (2006), “Infrastructure delays and cost escalation: causes and effects in
Nigeria”, Proceedings of the 6th International Postgraduate Research Conference in the
Built and Human Environment, International Council for Research and Innovation in Building
and Construction, Delft University of Technology, Delft, 3-4 April 2014.
Oshungade, O.O. and Kruger, D. (2017), “A comparative study of causes and effects of project delays
and disruptions in construction projects in the South African construction industry”, Journal of
Construction Engineering and Project Management, Vol. 7 No. 1, pp. 13-25.
Petticrew, M. (2001), “Systematic reviews from astronomy to zoology: myths and misconceptions”,
British Medical Journal, Vol. 322 No. 7278, pp. 98-101.
Pourrostam, T. and Ismail, A. (2011), “Significant factors causing and effects of delay in
Iranian construction projects”, Australian Journal of Basic and Applied Sciences, Vol. 5 No. 7,
pp. 450-456.
Pourrostam, T. and Ismail, A. (2012), “Causes and effects of delay in Iranian construction projects”,
International Journal of Engineering and Technology, Vol. 4 No. 5, pp. 598-601.
Rahman, M.D., Lee, Y.D. and Ha, D.K. (2014), “Investigating main causes for schedule delay in
construction projects in Bangladesh”, Journal of Construction Engineering and Project
Management, Vol. 4 No. 3, pp. 33-46.
Rahsid, Y., Haq, S. and Aslam, M. (2013), “Causes of delay in construction projects of Punjab-Pakistan:
an empirical study”, Journal of Basic and Applied Scientific Research, Vol. 3 No. 10, pp. 87-96.
IJMPB Ramanathan, C., Narayanan, S.P. and Idrus, A.B. (2012), “Construction delays causing risks on time
and cost – a critical review”, Australasian Journal of Construction Economics and Building,
Vol. 12 No. 1, pp. 37-57.
Ren, Z., Atout, M. and Jones, J. (2008), “Root causes of construction project delays in Dubai”, in Dainty, A.
Downloaded by NORWEGIAN UNIVERSITY OF SCIENCE & TECHNOLOGY, Doctor Bjørn Andersen At 01:18 27 April 2018 (PT)
pp. 554-563.
Yang, J.B. and Wei, P. (2010), “Causes of delay in the planning and design phases for construction
projects”, Journal of Architectural Engineering, Vol. 16 No. 2, pp. 80-83.
Yang, J.B., Chu, M.Y. and Huang, K.M. (2013), “An empirical study of schedule delay causes based on
Taiwan’s litigation cases”, Project Management Journal, Vol. 44 No. 3, pp. 21-31.
Yang, J.B., Yang, C.C. and Kao, C.K. (2010), “Evaluating schedule delay causes for private participating
public construction works under the Build-Operate-Transfer model”, International Journal of
Project Management, Vol. 28 No. 6, pp. 569-579.
Zaneldin, E.K. (2006), “Construction claims in United Arab Emirates: types, causes, and frequency”,
International Journal of Project Management, Vol. 24 No. 5, pp. 453-459.
Zewdu, Z.T. (2016), “Construction projects delay and their antidotes: the case of Ethiopian construction
sector”, International Journal of Business and Economics Research, Vol. 5 No. 4, pp. 113-122.
Further reading
Assaf, S.A., Al-Khalil, M. and Al-Hazmi, M. (1995), “Causes of delay in large building construction
projects”, Journal of Management in Engineering, Vol. 11 No. 2, pp. 45-50.
Sepasgozar, S.M., Razkenari, M.A. and Barati, K. (2015), “The importance of new technology for delay
mitigation in construction projects”, American Journal of Civil Engineering and Architecture,
Vol. 3 No. 1, pp. 15-20.
Corresponding author
Youcef J.-T. Zidane can be contacted at: youcef.zidane@ntnu.no
For instructions on how to order reprints of this article, please visit our website:
www.emeraldgrouppublishing.com/licensing/reprints.htm
Or contact us for further details: permissions@emeraldinsight.com