Faculty of Engineering Petroleum Engineering Department: Drilling Engineering I Third Stage
Faculty of Engineering Petroleum Engineering Department: Drilling Engineering I Third Stage
Faculty of Engineering Petroleum Engineering Department: Drilling Engineering I Third Stage
Drilling Engineering I
Third Stage
Lecture # 2
Introduction to Drilling
Pshtiwan Jaf 1
pshtiwan.jaf@koyauniversity.org
Oil & Gas Field Life
Abandonment
• At some point in the life of the field the
costs of production will exceed the
revenue from the field and the field will
be abandoned.
2
Oil & Gas Field Life
3
Drilling Personnel
Drilling Personnel
• Drilling a well requires many different skills and involves many companies.
• The oil company who manages the drilling and/or production operations is known as the operator.
• In joint ventures one company acts as operator on behalf of the other partners.
• The oil company will employ a drilling contractor to drill the well.
• The drilling contractor owns and maintains the drilling rig and employs and trains the personnel
required to operate the rig.
• During the course of drilling the well certain specialized skills or equipment may be required (e.g.
logging, surveying) which are provided by service companies.
• These service companies develop and maintain specialist tools and staff and hire them out to the
operator and contractor, generally on a day-rate basis. 4
Drilling Personnel
Drilling Personnel, cont.
• The contracting strategies for drilling a well or wells range from day-rate contracts
to turnkey contracts.
• In the case of the day-rate contract, the operator prepares a detailed well design
and program of work for the drilling operation and the drilling contractor simply
provides the drilling rig and personnel to drill the well.
• The contractor is paid a fixed sum of money for every day that he spends drilling
the well.
• All consumable items (e.g. drilling bits, cement), transport and support services
are provided by the operator.
5
Drilling Personnel
Drilling Personnel, cont.
• In the case of the turnkey contract, the drilling contractor designs the well,
contracts the transport and support services and purchases all of the
consumables, and charges the oil company a fixed sum of money for whole
operation.
• The role of the operator in the case of a turnkey contract is to specify the drilling
targets, the evaluation procedures and to establish the quality controls on the
final well.
• In all cases the drilling contractor is responsible for maintaining the rig and the
associated equipment.
6
Drilling Personnel
Drilling Personnel, cont.
• The operator will generally have a representative on the rig (sometimes called the
“company man”) to ensure drilling operations go ahead as planned, make decisions
affecting progress of the well, and organize supplies of equipment.
• He will be in daily contact with his drilling superintendent who will be based in the
head office of the operator.
• There may also be an oil company drilling engineer and/or a geologist on the rig.
• The drilling contractor will employ a toolpusher to be in overall charge of the rig.
• He is responsible for all rig floor activities and liaises with the company man to ensure
progress is satisfactory. 7
Drilling Personnel
Drilling Personnel, cont.
• The manual activities associated with drilling the well are conducted by the
drilling crew.
• Since drilling continues 24 hours a day, there are usually 2 drilling crews.
• Each crew works under the direction of the driller (a person who runs the drilling
rig).
• The crew will generally consist of a derrickman (a person who guides the drill
pipe in and out of the elevators), 3 roughnecks (a person who
connects/disconnects pipe using tongs), plus a mechanic, an electrician, a crane
operator and roustabouts (general laborers perform all other unskilled labor as
necessary). 8
Drilling Personnel
Personnel involved in drilling a well
9
Drilling Proposal
Drilling Proposal
• The proposal for drilling the well is prepared by the geologists and reservoir
engineers in the operating company and provides the information upon which
the well will be designed and the drilling program will be prepared.
10
Drilling Program
Drilling Program
• The drilling program is prepared by the Drilling Engineer and contains the
following:
11
Drilling Process
Drilling Process
1. Searching for oil & gas reservoir
• The search for oil and gas requires a knowledge of geography, geology and
geophysics.
13
Drilling Process
Drilling Process
2. Establish infrastructure for the drilling site
• It may be necessary to build a road to access the drilling site, or purchase boats if
drilling an offshore well.
• Water, electricity, food, and sanitation equipment will also need to be accounted
for.
• Preparations will vary depending on the type of environment the well is being
drilled in. An offshore well, for example, will require a different set of equipment
than will a conventional terrestrial (land-based) oil well. 14
Drilling Process
Drilling Process
2. Establish infrastructure for the drilling site, cont.
15
Drilling Process
Drilling Process
3. Dig in
• Before drilling the actual oil well, the interested
company will have to do a lot of digging. Begin by
clearing and leveling the designated area.
• The dimensions (depths and diameters) used in this example are typical but could
be different in other parts of the world.
• The following description is only an overview of the process of drilling a well (the
construction process). The design of the well, selection of equipment and
operations involved in each step will not discussed in this chapter.
18
Drilling Process
5. Drilling the Well
A. Installing the 30₺ Conductor
• The first stage in the operation is to drive a large
diameter pipe to a depth of approximately 100 ft
below ground level using a truck mounted pile-driver.
20
Drilling Process
5. Drilling the Well
B. Drilling and Casing the 26₺ Hole
• The first hole section is drilled with a drill bit, which has a smaller diameter than
the inner diameter (I.D.) of the conductor.
• Since the I.D. of the conductor is approximately 28”, a 26” diameter bit is
generally used for this hole section.
• This 26" hole will be drilled down through the unconsolidated formations, near
surface, to approximately 2000’.
21
Drilling Process
5. Drilling the Well
B. Drilling and Casing the 26₺ Hole, cont.
• If possible, the entire well, from surface to the reservoir would be drilled in one
hole section.
• The well is therefore drilled in sections, with casing being used to isolate the
problem formations once they have been penetrated.
• This means however that the wellbore diameter gets smaller and smaller as the
well goes deeper and deeper.
22
Drilling Process
5. Drilling the Well
B. Drilling and Casing the 26₺ Hole, cont.
• The well will then be designed such that the dimensions of the borehole that
penetrates the reservoir, and the casing that is set across the reservoir, will allow
the well to be produced in the most efficient manner possible.
• In the case of an exploration well the final borehole diameter must be large
enough to allow the reservoir to be fully evaluated.
• When the drill bit reaches approximately 2000’ the drillstring is pulled out of the
hole and another string of pipe (surface casing) is run into the hole.
23
Drilling Process
5. Drilling the Well
B. Drilling and Casing the 26₺ Hole, cont.
• This casing, which is generally 20" O.D., is delivered to
the rig in 40 ft lengths (joints).
• Once this depth has been reached the troublesome formations in the 17 1/2" hole are
isolated behind another string of casing (13 5/8" intermediate casing).
• This casing is run into the hole in the same way as the 20” casing and is supported by
the 20” wellhead housing whilst it is cemented in place.
• When the cement has set hard the BOP stack is removed and a wellhead spool is
mounted on top of the wellhead housing.
• This wellhead spool supports the weight of the next string of casing and the BOP stack
which is required for the next hole section. 27
Drilling Process
5. Drilling the Well
C. Drilling and Casing the 17 1/2₺ Hole, cont.
28
Drilling Process
5. Drilling the Well
D. Drilling and Casing the 12 1/4₺ Hole
• When the BOP has been re-installed and pressure tested, a 12 1/4"
hole is drilled through the oil bearing reservoir.
• Porosity and permeability measurements can be conducted on this core sample in the
laboratory.
• In some cases tools will be run in the hole which will allow the hydrocarbons in the sand
to flow to surface in a controlled manner.
• Since the produced fluid is allowed to flow through the drillstring this test is termed a
drill-stem test or DST.
• If all the indications from these tests are good then the oil company will decide to
complete the well. If the tests are negative or show only slight indications of oil, the
well will be abandoned. 30
Drilling Process
6. Completing the Well
• Completion is the process in which the well is enabled to
produce hydrocarbons.
32
Drilling Process
6. Completing the Well, cont.
• The annulus between the production casing and the production tubing is sealed
off by a device known as a packer.
• This device is run on the bottom of the tubing and is set in place by hydraulic
pressure or mechanical manipulation of the tubing string.
• When the packer is positioned just above the pay zone its rubber seals are
expanded to seal off the annulus between the tubing and the 9 5/8" casing.
33
Drilling Process
6. Completing the Well, cont.
• The BOP’s are then removed and a set of valves (Christmas Tree) is installed on
the top of the wellhead.
• The Xmas tress is used to control the flow of oil once it reaches the surface.
• After a flow path is made, acids and fracturing fluids are pumped into the well to
fracture, clean, or otherwise prepare and stimulate the reservoir rock to
optimally produce hydrocarbons into the wellbore.
34
Drilling Process
6. Completing the Well, cont.
Completion schematic
35
Drilling Process
36