Project Delivery Partner PDP PDF
Project Delivery Partner PDP PDF
Project Delivery Partner PDP PDF
Before we begin, we should first know more about Project Delivery Partner (PDP). A
Project Delivery Partner (PDP) represents an entity that possesses significant amount of project
and construction expertise that will assume the project delivery risk from “the project Owner”
after the project has been competitively tendered.
PDP is normally used in a mega huge project such as government projects where 2 or more
legal binded (Legal Agreement) parties join venture to accomplish the project. PDP is there to be
the primary backbone for the particular project. Without them, probably the project can only
remain as a dream. For example in Malaysia, the current PDP project is the KVMRT (a Gov-
Private Project) by MMC-GAMUDA.
With the PDP strategy, the Project Owner enjoys the best of both worlds where the mega
project is divided into multiple packages for competitive bidding to ensure maximum spread,
while reducing risk of cost overrun and late completion – borne by the PDP.
The main concept of PDP is that the PDP assumes complete risk ownership and
accountability for project deliver, from conceptualization till date of completion, including
specifications to cost, time and quality by integrating all contractors (civil, infrastructure and
systems) involved.
The Project Owner, on the other hand, will be able to maintain full control and cognizance
of the delivery process, including the award of tenders, land acquisitions and progress
supervision.
Like any other project, there are duties, roles and even challenges of PDP that we will
discuss. As said in the task, we will propose the most suitable procurement route for the new Hi
Tech township fast-track development project. We will also include relationships and challenges
faced and risk management strategies in implementing fast track procurement project.
Duties and Roles of PDP
There is an extent of duties and roles of PDP which have to be done liability
in the project. Due to the legally binding relationship, they have the liability to
ensure their duties are complete. The PDP will take on the multiple integrated or
concurrent roles. The below are the gist of duties of PDP:
-Ensure successful completion within the pre-determined target cost and date
(deliver on time & on budget).
-Reduce risk in design, construction and integration (effective & efficient).
-Encapsulate (summarize) the engineering design, procurement, system
work and technical specification to ensure optimum performance of all other
work package contractors in terms of Quality, Safety and Time.
-Responsible for packaging works calling tenders on(tendering), evaluating
bids, selection contracts and distribute awards on behalf.
-Enable project to be rolled out efficiently in phases.
-Attending to the delivery obligations.
-Ensure performance of all other contractors.
-Alignment options and review, preparations and submissions for the
scheme, public display, land acquisition, construction and supervision, as
well as testing and commissioning for safe keeping.
Challenges Faced by PDP
The Project Delivery Partner (PDP) forms the primary/main backbone of the mega
project and will interface with all contractors which can run by the hundreds,
depending on the scale of the project, while ensuring targets for the project’s cost,
workmanship quality and completion schedule are achieved.
The PDP will take on the multiple integrated or concurrent roles including
alignment options and review, preparations and submissions for the scheme, public
display, land acquisition, engineering design, tendering, construction and
supervision, as well as testing and commissioning for safe keeping. The below are
the challenges and hardships faced by PDP:
By using Design and Build method, the time taken in the whole period will
be shorten. This is because this method is using an integrated or concurrent
method. Which means the design stage and the building stage is combined where a
single contractor is appointed who is responsible/liable for both the design and
construction of the building. Both the stages will be start at almost the same time.
The contractor will take liability on both the design and build and be liable on both
as it provides a single point responsibility so that in the event of a building failure
the contractor is solely liable. Therefore, the cons of this method is although the
project will complete quicker, the contractor will uphold a higher liability and risk.
The contractor will use their own in-house designers to design the building or
designers appointed by the contractor to design the project.
Start Completion
Design Stage
Construction Stage
CII formed the Best Modern Practices for Design in Fast Track Research Team to study
this method of project execution. The main objective was to identify best practices that impact
the performance of the design phase in order to support timely procurement and construction of
an overall fast-track project. Secondary objectives included identification of correlation between
use of CII Best Practices and performance of the design phase, and identification of challenges
faced in managing the design of fast track projects.
The correlation between the performance of the design phase and the use of various
Construction Industry Institute (CII) Best Practices (BPs) was evaluated. Statistically significant
correlation was found between design schedule performance and the following four CII Best
Practices:
1. Pre-Project Planning
2. Alignment
3. Constructability
4. Change Management
The correlation between these BPs and design schedule performance meant that the more
rigorously these practices were implemented in the projects, the better the schedule performance
of the design phase. When asked to identify the top best practices for success of design phase in
fast-track projects, an overwhelming majority of industry practitioners identified the above
practices.
Correspondingly, the research also found that the most commonly faced challenges in
managing design in fast track projects included:
5. Coordination and teamwork within the design team and between organizations
The final cost of the project is uncertain when construction begins because design is not
complete. With the traditional Design-Bid-Build process a complete set of construction
documents and specifications describes what the builder agrees to build and serves as the heart of
the contract. On Fast-Track projects, the design, construction documents and specifications are
incomplete, so setting the final cost presents problems. To deal with this difficultly, owners
typically use a cost-reimbursable contract with the builder (a construction manager or a general
contractor). The contract may include a cost estimate with no guarantee or there may be a
Guaranteed Maximum Price (GMP). However, even with a GMP, there can be argument over the
scope of work covered by the GMP since the design was incomplete when the contract was
executed.
There is also a risk that work built in an early phase of the project may not suit later design
decisions. For instance, if the building shape changes after the foundations are built, there is
increased cost and delay to modify the completed foundations. Or an item of equipment that is
selected late in the process may require drains or water and power connections that were not
anticipated early in the project.
If time is not crucial, owners may take a prudent approach to finish design and get a fixed lump-
sum price before starting construction (the Design-Bid-Build process). However, if there is a
reason to speed project delivery, Fast-Track can be used with any project delivery strategy, such
as CM at Risk and Agency CM (see Construction Management),Design–
build, Bridging and Integrated Project Delivery. Even the traditional Design-Bid-Build process
can use Fast-Track concepts by bidding separate general construction contracts for phases of the
work.
However, many owners choose experienced project teams and consider the rewards to be well
worth the risks. One source states that Fast-Track is used on 40 percent of building projects.
Efficient risk management entails that risk should lie with the party able to best manage it. In pro
curement what is relevant is not only the capacity to identify and bear the risks but also the relati
ve attitudes to risk on the part of the government and the contractor. The nature of the risks and h
ow best to deal with them would depend on the relative complexity of the project, the relativ
e importance of quality aspects vis‐à‐
vis costs for the procurer, the innovation intensity ), the heterogeneity of the projects, and other
aspects on the supply side. So how to manage risk and what are the strategies? The strategies can
be state with:
1) Coordination and incentive challenges
-Coordinating and communication between the parties, client and suppliers.