Pre - Feasibility Report: Tanganamal Sand Quarry
Pre - Feasibility Report: Tanganamal Sand Quarry
Pre - Feasibility Report: Tanganamal Sand Quarry
VILLAGE TANGANAMAL
TEHSIL SHAHPUR
DISTRICT BETUL
STATE MADHYA PRADESH
MINERAL SAND
KHASRA NO. 209
PROJECT PRAPONENT
M/S. HOTEL UMA RESIDENCY
ADDRESS- CHANKYAPURI SATNA (M.P.) 1
Page
This pre – feasibility report, report has been prepared as per guidelines of
MOEF and sample application available on website of the department of
environment and forest. The contents of the report are geological, legal,
operating, economic, social environmental and other relevant factors
associate with the activities and are considered in sufficient details in
representative forms. We have tried to provide necessary information that it
could be reasonably serve as basic for the final decision by competent
authority to issue environmental clearance to the proposed project.
EXECUTIVE SUMMARY
The Proposed Sand quarry site is covering an area of 4.00 hectare at Village-
Tanganamal, Tehsil-Shahpur, District Betul, M.P. lease area is well connected
with village road SH19B-31 km and the lease area is 45 km from district HQ
Betul nearest railway station Shahpur is about 25 km by road from the site.
The proposed excavation area is less that 25 hectare hence belonging to B2
category. the mining, plan has been approved by the regional head , geology
and mining , betul , m.p. vide letter no. KHANIJ-2/N.K.10/2020/709 dated
02.06.2020 the details of other area of excavation/quarry lease falling within
a radius of 500m are mentioned in EMP.
PARTICULARS DETAILS
Name of project TANGANAMAL SAND QUARRY
Village TANGANAMAL
Tehsil SHAHPUR
District BETUL
QUARRY lease area 4.00 hectare
Khasra No. 209
Geographical coordinates
Latitude 22°10'58.54"N
Longitude 77°39'12.82"E
2
Page
River / Nalla No major river / nalla is located within the
500 m of lease area.
Forest (Np , Sanctuary, Bio Div .) Mining area does not fall within 10 km from
boundary of national park , sanctuary , Bio
diversity area.
Mineral Sand
Land use Govt. land
Lease Validity 3 Years
Production capacity 72000 cubic meter / year
Estimated project cost Rs. – 25 lakh.
Emp cost 20,60,000/-
Man power 50 Skilled / Unskilled
Machinery Jack Hammer drill , Dumper , truck etc.
Water requirement and supply Drinking water 2.0 kld plantation and
environment management 2.0 kld. Thus total
5 kld water will be required and will be
arrange from nearby village on personal
basis.
Nearest habitation / town Tehsil Shahpur– 25 km
Nearest dispensary PHC – Tanganamal– 1 km , District
Hospital –Betul 45 km
Nearest Airport Bhopal approx 130 km
Nearest Railway station Shahpur Railway station about2 5 km
3
Page
2. GENERAL
v
The proposed sand Quarry area is 4.00 hectare. Sand mining average capacity
shall be 72000 cubic meters annually, mode of excavation will be opencast
semi mechanized. Lease area / Status of land of lease area are Govt. Revenue
land .Mining project does not require any land acquisition nor raw material.
proposed project.
(III) Need for the project and its importance to the country and / or
region :
Mineral Sand is most commonly used as building and road
construction. The basic objective of the project is fulfillment of the
demand of mineral in the region and effective utilization. sand will be
supply to nearby area to fulfill the local requirement. After fulfillment
of local requirement it will sold in adjoining areas.
(IV) Demand – supply :
Mineral Sand is used as building and road material. Lot of
development work like road and building are going on in the region
.It has sufficient demand to sustain the supply of proposed mineral
production.
(V) Import VS. Indigenous production :
This is indigenous production. This will not be neither exported nor
imported.
(VI) Export possibility :
Not expected.
(VII) Employment Generation (Direct and Indirect ) due to the
project :
Total 50 Numbers of person, Including skilled and unskilled, are
likely to be engaged in this project most of these persons will
deployed from nearby villages.
3. PROJECT DESCRIPTION
5
Page
(I) Type of project including interlinked and interdependent projects:
The proposed project is sand quarry in which Sand have been involved. There
is no any interlinked and interdependent project.
Location:
Location and the geo co-ordinates of the lease area already mention in salient
features of the project.
Raw material is not required for the sand excavation project, only mining
tools are required. the crushed material of varies in size (20mm, 40mm,
60mm ) will be carried out by the truck / tractor trolley .
6
Page
(V) Resource optimization / recycling and resource envisaged in the
project , if any , should be briefly outlined :
The total water requirement for the project is estimated 6.0 KLD for mining
spraying and domestic used and will be sourced from nearby village. No
electricity is required even so if required in future the same will be
arranged by taking connection from MPSEB.
7
Page
4. SITE ANALYSIS
(I) Connectivity
Connectivity details are already given in the salient features of the project.
8
Page
5. PLANING BRIEF
Sand mining along with mechanical crushing in the region is a rural business
which is categories as small scale unit. It is classified as semi skilled and under
any staff oriented mining industries. The area is not covered under any town
planning or development authority. Hence no need of any such planning by
the proponent also.
Due to proposed mining activity there will not be influx of people from outside
as only local people will be engaged.
Mining will be done as per detail given in mining plan. Green belt shall be
developed along periphery of the lease area. Details of land use pattern have
already been given in previous chapter.
It is not expected for the project under consideration, since the project will
not exert any unbearable load on any of this available infrastructure (School,
Hospital etc.)