FIN5FMA Tutorial 4 Solutions
FIN5FMA Tutorial 4 Solutions
Project A
$6,000 $8,000
NPV $10,000 $2,066 .12
1.10 (1.10) 2
Project B
1 1 /(1.10) 4
NPV $10,000 $4,000 $2,679 .46
0.10
As the projects cannot be repeated, Project B should be selected because it has the
higher NPV.
b. Assume that the projects can be repeated and that there are no anticipated
changes in the cash flows. Use the replacement chain analysis to determine the
NPV of the project selected.
Project A
The NPV for Project B over the 4-year period (from Part a.) is $2,679.46. As such,
based on the replacement chain analysis, Project A should be selected over Project B
because it provides a higher NPV over the 4-year common-life period.
c. Make the same assumptions as in Part B. Using the equivalent annual annuity
(EAA) method, what is the EAA of the project selected?
Project A
1 1 /(1.10) 2
Annuity factor ( PVIFA 10%, 2 ) 1.7355
0.10
Project B
1 1 /(1.10) 4
Annuity factor ( PVIFA 10%, 4 ) 3.1699
0.10
Based on the EAA method, Project A would be selected as it has the highest EAA
value. This decision signal is consistent with that from the replacement chain
approach in Part b.
b. What are the incremental net cash flows that will occur at the ends of Years 1
through 5?
This requires calculation of the depreciation allowances each year for the new
machine, and then using these to calculate the incremental cash flows from the
replacement of the new machine:
Depreciable Depreciation Depreciation Change in
Year MACRS % basis allowance allowance depreciatio
(new) (old) n
1 33% $150,000 $49,500 $9,000 $40,500
2 45% $150,000 $67,500 $9,000 $58,500
3 15% $150,000 $22,500 $9,000 $13,500
4 7% $150,000 $10,500 $9,000 $1,500
5 0% $150,000 $0 $9,000 -$9,000
Note
The $6,500 deduction in the Year 5 NCF represents the after-tax opportunity cost of
not being able to sell the old machine at the end of its useful life.
c. What is the NPV of this project? Should Erley replace the old machine?
Explain.
Thus, the company should replace the existing machine with the new machine as the
incremental replacement NPV is positive.
a. Assume that each of these projects is independent and that each is just as risky
as the firm’s existing assets. Which set of projects should be accepted, and what
is the firm’s optimal capital budget?
As the projects are independent and have the same level of risk as the overall firm, the
company should select all of the projects which have an IRR greater than the firm’s
WACC of 12.5%. Thus, the firm should select projects A, B, C, D and E and its
optimal capital budget is the sum of the costs of these projects ($5,250,000).
b. Now, assume that Projects C and D are mutually exclusive. Project D has an
NPV of $400,000, whereas Project C has an NPV of $350,000. Which set of
projects should be accepted, and what is the firm’s optimal capital budget.
If projects C and D are mutually exclusive, then the firm can only select one of them
rather than both. Based on the NPV criteria, the firm should select Project D as it
provided a higher NPV (and also has a higher IRR). As a result, the firm’s capital
budget is now $4,000,000 and includes projects A, B, D and E.
c. Ignore Part b and assume that each of the projects is independent but that
management decides to incorporate project risk differentials. Management
judges Projects B, C, D and E to have average risk; Project A to have high risk;
and Projects F and G to have low risk. The company adds 2% to the WACC of
those projects that are significantly more risky than average, and it subtracts 2%
from the WACC of those projects that are substantially less risky than average.
Which set of projects should be accepted, and what is the firm’s optimal capital
budget?
Low-risk projects
Projects F and G will both be accepted because their IRRs (12.3% and 12.2%) are
greater than the required return of 10.5%
Average-risk projects
Projects B, C, D and E will still be accepted because their IRRs are greater than
the firm’s average required return (WACC) of 12.5%
High-risk projects
Project A will be rejected because its IRR of 14.0% is less than the required return
on high-risk projects of 14.5%
Thus, the selected projects are projects B, C, D, E, F and G and the firm’s optimal
capital budget is $6,000,000.
0 1 2 3 NPV @ Yr. 0
50% Prob. | | |
6 6 6
-10 +20 $12.170
-9 -4 26
| | | -6.556
50% Prob. 1 1 1