Define "Project Charter".: The Engineers Choice Construction Firm"
Define "Project Charter".: The Engineers Choice Construction Firm"
Define "Project Charter".: The Engineers Choice Construction Firm"
SUMMER 19-20
Answer: The project charter is a document where a project is defined. It provides the project
manager with the authority to apply organizational resources to project activities. In a project
charter scope, objectives and participants are described.
The Engineers Choice Construction firm has been awarded a contract for the construction of a 25-storied
multipurpose building. The construction must start by 28 th February 2021 and be completed within three
years. A penalty clause of tk 75,000 per month of delay beyond 27 th February of 2024 as written in the
contract. Jamaluddin, the managing director of the company, called a planning meeting. In the meeting
he expressed great satisfaction at obtaining the contract and revealed that the company could profit as
much as tk 4,00,00,000 on this project. This total project will cost $80,00,00,000 according to the
contact. He was confident that the project could be completed without any delay. Kamal Uddin Lotus,
the project manager, agreed that in a normal time delays might develop due to shortage of manpower
and equipment. However, he reminded the MD that for such a large project, the company would have
to use outsourced equipment. Past experience indicated a sixty-forty chance of a strike.
The building is a modern structure with five meeting rooms capacity of 2000 person per room and three
convention centers with capacity of 5000 per hall along with two indoor auditoriums for concert. The
project begins with acquiring the land, an activity that lasts two months. Once the land is acquired, the
work can start on the architectural design of the structure, famous architect Ms. Tania Karim will be
hired for this, this will take one month. The work in the construction site involves construction of each
floor taking one year, HVAC system, Electrification, surface drainage system along with sewerage line
and water supply system which lasts 1.5 months for each. Installing fire extinguishing system will take
2.5 months.
Once the construction is done it’s time to go for interior designing, roof top gardening and roof top
swimming construction. Interior designing will take 3 months, gardening and swimming pool another 6
months. Painting will take one month. The gas line installation will take another one month. The building
will have no gymnasium facilities and outdoor auditoriums. The Now it’s time for grand opening by the
president of Engineers Choice Construction firm Mr. Hadis Uddin.
Question:
Create a Project Charter on the above-mentioned project which will include general information,
stake holders name, project objectives, business justifications, project deliverables, project exclusion,
project milestones, project approach, assumptions and constrains, project success criteria.
12 Marks
1. PROJECT CHARTER
GENERAL INFORMATION:
Date: 25th February 2021
Project Title: The Engineers Choice Construction Firm
Project Sponsor: The Engineers Choice Construction firm it-self will do sponsorship.
Start Date: 28th February 2021 Finish Date: 28th February 2024
Budget This total project will cost $80,00,00,000 according to the contact.
Information:
Stakeholders:
Jamaluddin
Kamal Uddin lotus
Ms. Tania Karim
Mr. Hadis Uddin
Project Objectives:
Business justification:
The managing director Jamaluddin said the company could profit as much as tk 4,00,00,000 on
this project.
Project Deliverables:
The interior designing, roof top gardening and roof top swimming construction.
The gas line installation.
Painting.
Exclusion:
gymnasium facilities
outdoor auditoriums.
Training.
HR.
Project Milestone:
Approach:
Project charter
WBS
PMIS
Project schedule
Weekly and monthly meeting.
Assumption and Constraints:
Assumptions: no delay for work completion.
5. Sony has invented android, smart, LCD TV instead of CRT TV to keep track with modern technology.
This is a project under ______Technological advance______________ strategic need.
6. Smart phone, software to deal the registration and admission of University, invention of geyser,
washing m/c are the examples of project by different firms under _____Technological
advance_______________ strategic need.
7. Mr. Savya Sachi has designed the wedding lehenga for Anushka Sharma. This was a project under
___________customer request________________________________ strategic need.
9. The process of reviewing all change requests; approving changes and managing changes to
deliverables, organizational process assets, project documents, and the project management plan; and
communicating their disposition is called __________________________________________________.
11. One of the project knowledge rea is Time MGT. The project MGT tools and techniques include for this
are ________scope________________, ________cost____________ and
________quality______________. 1.5 marks
12. In weak, balanced and strong Matrix the project budget is managed by _______project
manager_________________, ______________________________ and
_____functional______________________ manager. 1.5 marks
15. Saifur’s has started coaching for Chinese and Russian language to earn more revenue. This is a
project under _______business need________________________________ strategic need.