Text NATM - 21 - 09
Text NATM - 21 - 09
Text NATM - 21 - 09
Design stages
ROCK
Aggregate, consisting of mineral components, developed from
natural processes, characterised by the types and amount of the
minerals and grain structure
INTACT ROCK
Mineral aggregate, whose properties predominantly are deter-
mined by the physical/chemical bond
ROCK MASS
Accumulation of various rock units which form a structural frame-
work including discontinuities
SOIL
Accumulation of inorganic, solid particles with occasional organic
admixtures. The properties are predominantly governed by the
granulomeric composition, the compaction, and the water content
DISCONTINUITY
General term for any mechanical discontinuity in a rock mass having
zero or low tensile strength. Collective term for most types of joints,
bedding planes, schistosity planes, weakness zones and faults
BOUNDARY CONDITIONS
Conditions influencing construction processes and methods which
are not of a geotechnical nature
FRAMEWORK PLAN
Summary of the Geotechnical Design, including relevant parame-
ters used in the design, and application criteria for the assignment
of excavation and support methods
REQUIREMENTS
Definition of required parameters to safeguard serviceability, safety,
and the environment
The typical support elements in NATM are shotcrete and rock dow-
els. Steel ribs or lattice girders provide limited early support before
the shotcrete hardens and ensure correct profile geometry. If
ground conditions require support at or ahead of the excavation
face, face dowels, shotcrete, spiles or pipe canopies are installed as
required.
The basis for the design of tunnels in rock depends on both the
ground conditions and the usage of the tunnel (water, road, railway
tunnel, etc.). Tunnels excavated in sound rock are generally horse-
shoe shaped, whereas tunnels excavated in poor rock generally re-
quire an invert arch to ensure stability.
Drill, charge, blast Mucking Steel rib, wire mesh, Rock bolting
shotcrete application
To increase the shear strength of the rock mass, the key support
element is the use of rock dowels. The shotcrete lining thickness is
typically 0.2 m to 0.3 m. In case of large displacements longitudinal
slots in the shotcrete lining and yielding support elements are
placed to allow deformation without damage to the lining. Once
the rock pressure is significantly reduced and stabilisation of the
opening is confirmed by monitoring, the slots in the lining are
closed with shotcrete.
For top heading, bench and invert the thickness of the shotcrete lin-
ing, the lattice girder spacing and the distance from the tunnel face
to the invert closure is defined in the design. Instrumentation is
used to monitor the surface settlements as well as the performance
of the primary lining and to validate the design.
In this example the side wall drifts are staggered and served as both
a pilot tunnel and a foundation for the crown support. The side wall
drifts are advanced individually employing an excavation sequence
with a short top heading followed by early invert closure as shown
Fig. 11: Typical excavation and support for side wall drift method
in Fig. 11. The size of a side wall drift has to meet space require-
ments for the intended excavation plant. Also the shape of tempo-
rary side walls has to be designed in a way that does not deviate too
much from an oval shape with sharp bends in the crown and invert.
Fig. 13: Typical excavation sequence for side wall drift method
Preliminary design
Tender design
Final design
Alignment
Topographical conditions
Legal aspects
Safety requirements
M & E requirements
Cost estimate
Construction programme
The design engineer is also responsible for tasks involving public re-
lations and project management.
Site investigation
Cost estimate
- Instruction to bidders
- Project description
- Information on geotechnical conditions, monitoring and
evaluation of monitoring results, etc.
- Drawings
- Technical specifications for materials and workmanship
- Construction programme, time, duration and staging of the
project
- Conditions of contract
- Itemised bill of quantities, measurement and payment
- Framework design
Tender assessment
The final design stage includes the following tasks in the design of-
fice:
Framework design
As-built documentation
5.2 Methods
The following methods are primarily employed to investigate the
ground conditions:
Field mapping
Trial pits
Geophysical measurements
Field tests
Laboratory tests
Grain sizes
Plasticity, compaction
Density
For rock the description does distinguish between intact rock and
rock mass. The intact rock description includes the following ele-
ments:
Mineral content
Petrographic identification
Intact rock
Degree of weathering
Karst formation
Hydrothermal alteration
Fault zones
- Tectonic origin
- Orientation
- Width
- Composition
- Constituents: fault gouge, cataclasite, remnants of host rock
Groundwater levels
Permeability
Hydraulic conductivity
Transmissivity
Water chemistry
Primary stresses
Swelling potential
Conductivity, transmissivity
Abrasivity
Seismic activity
Radioactivity
Groundwater contamination
PHASE 2: CONSTRUCTION
During construction, all ground parameters relevant to the geo-
technical design have to be collected, recorded, and evaluated to
determine the Ground Type. Considering these influencing factors,
the actual System Behaviour in the excavation area is assessed ac-
cording to the stipulations of the design. Excavation and support
measures have to be chosen based on the criteria laid out in the
framework plan and the safety management plan. The geotechnical
design and the framework plan have to be continuously updated
based on the findings on site. The improved quality of the geotech-
nical model allows an optimisation of the construction while ob-
serving all safety and environmental requirements. The relevant
data and assumptions made for all decisions during design and
construction have to be recorded. Relevant information in connec-
tion with the ground properties, Ground and System Behaviour has
to be documented, evaluated and analysed in both phases.
The basic procedure for geotechnical design begins with the de-
termination of the Ground Types and ends with the definition of the
excavation classes. The outline of the design procedure is illustrated
in the flow chart shown in Fig. 14.
STEP 2
DETERMINATION OF GROUND BEHAVIOUR (GB)
The second step involves evaluating the potential Ground Behav-
iours considering each Ground Type and local influencing factors,
including the relative orientation of relevant discontinuities to the
excavation, ground water conditions, stress situation, etc. The
Ground Behaviour is defined for each section having similar ground
properties and influencing factors. The Ground Behaviour has to be
evaluated for the full cross-sectional area without considering any
modifications including the excavation method and sequence as
well as support or other auxiliary measures. The evaluated project
specific Ground Behaviours shall be assigned to basic Ground Be-
1 Stable Stable ground with the potential for localised gravity induced
falling or sliding of small blocks
2 Potential of discontinuity con- Discontinuity controlled, gravity induced falling and sliding of
trolled block fall blocks in large volumes, occasional local shear failure on
discontinuities
4 Voluminous stress induced Stress induced failure involving large ground volumes and
failure large deformation
5 Rock burst Sudden and violent failure of the rock mass, caused by
highly stressed brittle rocks and the rapid release of accu-
mulated strain energy
6 Buckling Buckling of rocks with a narrowly spaced discontinuity set,
frequently associated with shear failure
11 Ground with frequently Combination of several behaviours with strong local varia-
changing deformation char- tions of stresses and deformations over longer sections due
acteristics to heterogeneous ground (i.e. in heterogeneous fault zones;
block-in-matrix rock, tectonic melanges)
STEP 3
SELECTION OF CONSTRUCTION CONCEPT
A feasible construction concept is chosen based on the ground
characteristics and the determined Ground Behaviour for each char-
STEP 4
ASSESSMENT OF SYSTEM BEHAVIOUR (SB) IN THE EXCAVATION
AREA
Under consideration of the construction concept, including se-
quence of construction, stability of the face and perimeter, and the
spatial stress distribution, the System Behaviour in the excavation
area is assessed (see Fig. 15)
STEP 5
DETAILED DETERMINATION OF THE EXCAVATION AND SUPPORT
METHOD AND EVALUATION OF SYSTEM BEHAVIOUR IN THE SUP-
PORTED AREA
The excavation and support methods are fixed in quality and quan-
tity, considering probable further excavation steps, and the System
Behaviour determined. The evaluated System Behaviour is then
compared to the requirements.
STEP 7
DETERMINATION OF EXCAVATION CLASSES
In the final step of the design process, the excavation classes are de-
fined based on the evaluation of the excavation and support meas-
ures. The excavation classes form a basis for compensation clauses
in the tender documents. In Austria the evaluation of excavation
classes is based on the regulations in ONORM B 2203-1.
Fig. 16: Example of face mapping with extrapolation showing the surrounding ground
STEP 2
ASSESSMENT OF SYSTEM BEHAVIOUR IN THE EXCAVATION AREA
Based on the predicted ground conditions the System Behaviour in
the section ahead has to be assessed under consideration of the in-
fluencing factors, in comparison to the framework plan. Particular
attention has to be paid on potential failure modes.
STEP 3
DETERMINATION OF EXCAVATION AND SUPPORT MEASURES AND
PREDICTION OF SYSTEM BEHAVIOUR IN SUPPORTED SECTION
To determine the appropriate excavation and support measures the
criteria laid out in the framework plan have to be followed. Conse-
quently, it has to be verified whether the actual ground conditions
(Ground Type, System Behaviour) comply with the prediction. The
additional data obtained during construction form the basis for the
determination of the applied excavation and support methods. The
goal is to ensure safety and economy during construction of the
tunnel. The System Behaviour has to be predicted for the next exca-
vation section, considering the ground conditions and the chosen
construction measures. Record of this process must be kept.
STEP 4
VERIFICATION OF SYSTEM BEHAVIOUR
In monitoring the System Behaviour, compliance with the require-
ments and criteria defined in the geotechnical safety management
plan can be verified. When differences between the observed and
predicted behaviour occur, the parameters and criteria used during
excavation for the determination of the Ground Type and the exca-
vation and support have to be reviewed (see Fig. 17). When the dis-
The targets are mounted on special bolts with an adapter (see Fig.
19). Targets are installed close to the face and zero readings done
immediately after installation. Readings are typically taken daily; the
frequency is reduced with distance to the face and decreasing rates
of displacements.
Fig. 18: Example of monitoring section (optical 3D displacement measurements, extensometers, pie-
zometers, measuring dowels, strain gauges and pressure cells)
8.2.4 Piezometer
Piezometers are used to measure the ground water pressure.
Contour plot of the level of loading in the lining (see Fig. 25)
Fig. 23: Deflection curve diagram for crown position showing the estimation of “pre-displacements”
and construction of trend line
Deflection curves are usually combined with a trend line. Trend lines
are created by connecting values from the deflection curves at a
constant distance behind the face (see Fig. 23).
The displacement vector trend L/S (in this case for the crown point)
deviates from a “normal” orientation against the direction of exca-
vation when approaching the zone of soft ground. The “normal”
vector orientation strongly depends on the ground structure and
stress conditions and has to be determined separately for each
condition.
After entering the soft zone, the vector tends to return to the “nor-
mal” orientation. When approaching the stiff ground, an inverse
tendency can be observed. The displacement vector deviates in di-
rection of excavation and reaches a maximum at the transition. Af-
ter entering the stiff zone, the vector returns to normal.
The level of loading is defined as the ratio between the stress and
the ultimate strength of shotcrete. It is usually shown as contour
plot.
(Note: Red colour indicates very high load level; Blue colour indi-
cates a low load level)
Fig. 26: Example of the distribution of the level of loading in the shotcrete lining at a certain time;
Tunnel driven with side wall galleries and core excavation
8.4 Interpretation
8.4.1 Development of displacements with time
For constant advance rate and uniform boundary conditions, con-
tinuously decreasing displacement rates over time indicate a stabili-
sation process. Subsequent excavation steps, like bench or invert
excavation lead to a temporary increase in displacement rates. In-
creases and decreases in the advance rate result in a change in the
displacement rates, making the interpretation difficult in cases
where advance rates are variable.
Fig. 31: Deflection curves showing the increased displacements in the fault zone, encountered at
around chainage 1160
Comparability of bids
For all other activities such as site installation, final lining and finish-
ing work fixed time periods are foreseen in the contract.
(qSUPPORT f RATING )
f SUPPORT
a RATING
The support quantities are related to a tunnel length of one meter.
The rating factor (fRATING) reflects the relative time required for the in-
stallation of the considered type of support and is given in Table 3
of ONORM B 2203-1.
GROUND
Unforeseen subsurface conditions (e.g. unforeseen faults, weak-
nesses zones, subsurface obstacles);
CONSTRUCTION
Failure of construction equipment
PROJECT IMPLEMENTATION
Change of guidelines
Environmental regulations
Safety standards
CONSEQUENCE
Cost and time implications of risk-relevant hazards are derived from
cost estimates and the performance assumptions (e.g. advance
rates).
Deterministic method
Probabilistic method
The effects of risks are combined and the associated costs are de-
termined by mathematical models.
Apart from organisation and execution of the work, the site man-
ager of the contractor must ensure quality requirements are met
and completed on schedule.
11.1.5 Geologist
The client appoints geologists which independently record geo-
logical conditions at the face and eventually advise on additional
probing ahead. It is their task to produce short term predictions for
the next round length.
CHAPTER 1, 2, 3 & 4:
[1] ITA Austria (2008): The Austrian Art of Tunnelling in Con-
struction, Consulting and Research, Ernst & Sohn
[14] Guenot, A.; Panet, M.; Sulem, J. (1985): A new aspect in tun-
nel closure interpretation, In E. Ashworth (ed.), Research
and engineering applications in rock masses, Proc. 26th U.S.
Symp. Rock Mech., South Dakota School of Mines & Tech-
nology, Rapid City, 26-28 June 1985, Vol. 1, 455-460, Rotter-
dam: Balkema
[17] Jeon, J.S.; Martin, C.D.; Chan, D.H.; Kim, J.S. (2005): Predicting
ground conditions ahead of the tunnel face by vector ori-
entation analysis, Tunnelling and Underground Space Tech-
nology 20, 344-355, Elsevier
[26] Schubert, P.; Kopčič, J.; Štimulak, A.; Ajdič, I.; Janko, L. (2005):
Analysis of Characteristic Deformation Patterns at the Tro-
jane Tunnel in Slovenia, Felsbau 23, No. 5, 25-30, Essen: VGE