Job Safety Analysis: Work at Height

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 2

Job Safety Analysis

TASK: Work at Height.

LOCATION: SAMIF DATE: 27/8/2020


SUPERVISOR: M. Imtiaz DESIGNATION: Safety Officer

Recommended Action / Control


Work Sequence (Job / Task Steps) Potential Hazards
Measures
 Material will be fastened properly
Transporting of scaffolding material  Material can fall. before transporting to site.
at site.  Personal injury.  Only experienced, skilled, and
 Unauthorized / trained person should be allowed
untrained/  All hand tools should be inspected
inexperienced prior to start of job
personnel on the  Scaffolding pipes with corrosion
job should not be used.

Unloading of scaffolding material  Uneven ground  Material will be unloaded by
 Faulty/ poor certified riggers.
condition  Certified boom truck operator will
scaffolding carry out the task
material

Storage of scaffold material  Wrong material  Material will be stored in a


handling/ falling designated area.
object  Material will be stored on scaffold
 Personnel injury. racks.
 Personnel fall.  Hard barricade and signage will be
 Object falls. provided
 Property loss

Erection & dismantling of  Improper  Ground surface should be levelled


scaffolding. scaffolding  Red tag must be placed/ hanged at
erection the start of scaffolding
 Tag system not  Ensure vertical pipes alignment and
check it with hand level
 Ensure all joints are properly
tightened
 Use bracing pipes and outriggers
pipes where necessary.
 Only certified scaffolders will
perform the job.
 Scaffolders will be trained on safe
working at height.
Job Safety Analysis

 Above 1.8m height safety harness


will be with double lanyard. 100%tie
off will be ensured.
 Scaffold platform will not be
overloaded.
 Handrail and toe boards will be
installed with scaffolding platform.
 All employees will work with proper
PPEs.
 Ladder should be constructed at
suitable.
 Metal planks should be properly
placed on pipes with hooks and use
binding wire for binding where
necessary
 No person should go in drop zone.
Scaffolding area.
 Area should barricade while erection
or dismantling the platform.

Overhead electrical power lines  Electric shock due  Ensure overhead clearance while
to power line operating the equipment

Housekeeping  Property loss  Housekeeping


 Slip/trip  Area barricading
 Fall from height  PPE.