Big Box Retail - Roof Louver Around Stair Baseline Programme

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

ALBA BIG BOX RETAIL - ROOF LOUVER AROUND STAIR

TOWER Date
ALUMINUM
BASELINE PROGRAMME 27-Aug-20
Activity ID WBS / Activity
KEY DATES Productivity Qnty Duration (d) Start Finish
BGB-ATA-1 Project Commencement 30-Aug-20
BGB-ATA-2 Project Duration 85 30-Aug-20 22-Nov-20
BGB-ATA-3 Project completion 22-Nov-20

ENGINEERING 22 31-Aug-20 22-Sep-20


SHOP DRAWINGS
BGB-ATA-4 Shop drawings- Preperation and submission 7 31-Aug-20 7-Sep-20
BGB-ATA-5 Shop drawings - Review and approval 14 8-Sep-20 22-Sep-20

STRUCTURAL CALCULATION
BGB-ATA-6 Structural calculation - Preperation and submission 3 31-Aug-20 3-Sep-20
BGB-ATA-7 Structural calculation - Review and approval 14 3-Sep-20 17-Sep-20

MATERIAL SUBMITTAL
BGB-ATA-8 Material submittal for powder coat finish - Preperation and submission 3 31-Aug-20 3-Sep-20
BGB-ATA-9 Material submittal for powder coat finish - Review and approval 14 4-Sep-20 18-Sep-20

BGB-ATA-10 Material submittal for louver system - Preperation and submission 3 3-Sep-20 6-Sep-20
BGB-ATA-11 Material submittal for louver - Review and approval 14 7-Sep-20 21-Sep-20

PROCCUREMENT 21 8-Sep-20 29-Sep-20


BGB-ATA-12 Proccurement of aluminum louver 21 8-Sep-20 29-Sep-20
BGB-ATA-13 Proccurement of aluminum profiles 21 8-Sep-20 29-Sep-20
BGB-ATA-14 Proccurement of steel members 10 18-Sep-20 28-Sep-20
BGB-ATA-15 Proccurement of powder coat 10 19-Sep-20 29-Sep-20
BGB-ATA-16 Proccurement of fastners 10 18-Sep-20 28-Sep-20

FABRICATION 38 30-Sep-20 7-Nov-20


ZONE - 02 m2/day m2
BGB-ATA-17 Fabrication of louver panels and frames above stair Z2- S1 20 37.64 2 30-Sep-20 3-Oct-20
BGB-ATA-18 Fabrication of louver panels and frames above Lift- L1/L2 20 36.74 2 3-Oct-20 5-Oct-20

ZONE - 03 m2/day m2
BGB-ATA-19 Fabrication of louver panels and frames above stair- Z3-S2 20 45.9 2 6-Oct-20 8-Oct-20
BGB-ATA-20 Fabrication of louver panels and frames above stair- Z3-S3 20 55.86 3 8-Oct-20 11-Oct-20

ZONE - 04 m2/day m2
BGB-ATA-21 Fabrication of louver panels and frames above stair-3 20 34.66 2 12-Oct-20 14-Oct-20

ZONE - 05 m2/day m2
BGB-ATA-22 Fabrication of louver panels and frames above stair- S1 20 32.62 2 15-Oct-20 17-Oct-20
BGB-ATA-23 Fabrication of louver panels and frames above stair- S2 20 16.2 1 17-Oct-20 18-Oct-20
BGB-ATA-24 Fabrication of louver panels and frames above stair- S3 20 31.32 2 18-Oct-20 20-Oct-20

# Not Confidential - Internal


BGB-ATA-25 Fabrication of louver panels and frames on papaet edge between zone 2&3 (Ht=3m) 20 72 4 20-Oct-20 24-Oct-20

ZONE - 06 m2/day m2
BGB-ATA-26 Fabrication of louver panels and frames above stair- S2 20 22.43 1 25-Oct-20 26-Oct-20
BGB-ATA-27 Fabrication of louver panels and frames above stair- S3 20 35.13 2 26-Oct-20 28-Oct-20
BGB-ATA-28 Fabrication of louver panels and frames above stair- S4 20 35.43 2 28-Oct-20 30-Oct-20
BGB-ATA-29 Fabrication of louver panels and frames above stair- S5 20 73.4 4 30-Oct-20 3-Nov-20
BGB-ATA-30 Fabrication of louver panels and frames on top of parapet at grid 27 20 44 2 3-Nov-20 5-Nov-20
BGB-ATA-31 Fabrication of louver panels and frames on top of wall 20 32.1 2 5-Nov-20 7-Nov-20

CONSTRUCTION 45 8-Oct-20 22-Nov-20


SITE CLEARANCE
BGB-ATA-32 Site clearance for Zone 2 7-Oct-20
BGB-ATA-33 Site clearance for Zone 3 8-Oct-20
BGB-ATA-34 Site clearance for Zone 4 10-Oct-20
BGB-ATA-35 Site clearance for Zone 5 11-Oct-20
BGB-ATA-36 Site clearance for Zone 6 12-Oct-20

INSTALLATION OF MAJLIS STRUCTURES 42 8-Oct-20 19-Nov-20


ZONE - 02 m2/day m2
BGB-ATA-37 Installation of louver panels and frames above stair Z2- S1 18 37.64 2 8-Oct-20 11-Oct-20
BGB-ATA-38 Installation of louver panels and frames above Lift- L1/L2 18 36.74 2 11-Oct-20 13-Oct-20

ZONE - 03 m2/day m2
BGB-ATA-39 Installation of louver panels and frames above stair- Z3-S2 18 45.9 3 14-Oct-20 17-Oct-20
BGB-ATA-40 Installation of louver panels and frames above stair- Z3-S3 18 55.86 4 17-Oct-20 21-Oct-20

ZONE - 04 m2/day m2
BGB-ATA-41 Installation of louver panels and frames above stair-3 18 34.66 2 22-Oct-20 24-Oct-20

ZONE - 05 m2/day m2
BGB-ATA-42 Installation of louver panels and frames above stair- S1 18 32.62 2 25-Oct-20 27-Oct-20
BGB-ATA-43 Installation of louver panels and frames above stair- S2 18 16.2 1 27-Oct-20 28-Oct-20
BGB-ATA-44 Installation of louver panels and frames above stair- S3 18 31.32 2 28-Oct-20 30-Oct-20
BGB-ATA-45 Installation of louver panels and frames on papaet edge between zone 2&3 (Ht=3m) 18 72 5 30-Oct-20 4-Nov-20

ZONE - 06 m2/day m2
BGB-ATA-46 Installation of louver panels and frames above stair- S2 18 22.43 1 5-Nov-20 6-Nov-20
BGB-ATA-47 Installation of louver panels and frames above stair- S3 18 35.13 2 6-Nov-20 8-Nov-20
BGB-ATA-48 Installation of louver panels and frames above stair- S4 18 35.43 2 8-Nov-20 10-Nov-20
BGB-ATA-49 Installation of louver panels and frames above stair- S5 18 73.4 5 10-Nov-20 15-Nov-20
BGB-ATA-50 Installation of louver panels and frames on top of parapet at grid 27 18 44 2 15-Nov-20 17-Nov-20
BGB-ATA-51 Installation of louver panels and frames on top of wall 18 32.1 2 17-Nov-20 19-Nov-20

PROJECT HANDING OVER


BGB-ATA-52 Snagging and desnagging 20-Nov-20
BGB-ATA-53 As built and OM manual - Preperation and submission 20 1-Nov-20 21-Nov-20
BGB-ATA-54 Final handing over 1 22-Nov-20 22-Nov-20