Process Piping Systems: Scrubber Design and Installation Requirements
Process Piping Systems: Scrubber Design and Installation Requirements
Process Piping Systems: Scrubber Design and Installation Requirements
NOTE: Non-intercooled, dry gas stages of compression may not require liquid separation, but
provisions must be made to remove lubricating oil, if applicable.
2. Design and construct scrubbers in accordance with good engineering practice and industry standards for
two-phase separators and pressure vessels. ISO-13631 provides scrubber specifications. Provide full
diameter skirts with a thickness equal to or greater than the vessel wall thickness (minimum 1/2 inch (13
mm)).
3. Support scrubbers with full-depth structural members.
4. Position all scrubber attachments such as relief valves, sight glasses, instrumentation, drain lines, and
tubing close to the scrubber and support as required. Bullseye style sight glasses are recommended.
5. Ariel requires nozzle reinforcement pads or long weld neck flanges.
Pulsation Bottles
1. High acoustical pulsation can increase frame, cylinder, gas piping, and equipment vibrations. An
acoustical study will determine if the package requires pulsation bottles when not already required by
customer specifications. An acoustical study will determine if acoustical or mechanical resonances exist
that require correction. When analyzing acoustical pulsation responses, consider single-acting cylinder
and all cylinder load steps. Single-acting cylinders can present the worst case scenario for acoustical
analysis. High acoustically driven vibration can result from single-acting cylinder operation when not
considered. Contact Ariel for information beyond that of the Ariel Performance Program.
Relief Valves
1. Provide relief valves on the initial stage suction and the discharge of every stage of compression, set to
operate in compliance with ISO-13631. Install discharge relief valves upstream of each individual gas
cooler section.
NOTE: Consider all possible types of equipment failure or poor operation and protection of
piping systems when selecting relief valve locations and settings.
2. Ensure adequate relief valve settings as well as cylinder and component MAWP's for process settle-out
pressures during shutdown.
3. Pilot operated relief valves must include a back-flow protection feature when connected to a common
vent line.
CAUTION: The compressor cylinder may or may not be the system component with the
lowest pressure rating. Set relief valve based on the lowest rated connected equipment.
Gas Coolers
1. Determine if the package requires gas cooling if not already required by customer specifications.
Consider ambient conditions, anticipated operating conditions, geographical location, and customer
requirements.
2. The discharge gas temperature predicted by the Ariel Performance Program is the expected
temperature at the compressor cylinder discharge flange. Account for any heat loss between the
compressor cylinder and cooler inlet flanges and size the cooler accordingly.
3. Account for cooler fan power consumption when engine driven.
4. Cooler design and construction must comply with good engineering practice and industry standards for
heat exchangers.
5. Consider associated liquid condensates in the cooler design. This includes both heat load and gas flow
from top to bottom through the cooler sections.
6. Some applications require automated temperature control to avoid excessive condensates and dense
phase above critical point. Applications may include heavy gases, CO2, acid gas, etc.
The contents of this document are proprietary and confidential. They are the property of Ariel Corporation and may
not be disclosed, reproduced, or used for manufacture in part or in whole without written permission from Ariel
Corporation.