Project 2000
Project 2000
Project 2000
Project 2000
Student Edition
Complete
Computer Courseware
© 2002 by CustomGuide, Inc. 1502 Nicollet Avenue South, Suite 1; Minneapolis, MN 55403
This material is copyrighted and all rights are reserved by CustomGuide, Inc. No part of this publication may be reproduced,
transmitted, transcribed, stored in a retrieval system, or translated into any language or computer language, in any form or by
any means, electronic, mechanical, magnetic, optical, chemical, manual, or otherwise, without the prior written permission of
CustomGuide, Inc.
We make a sincere effort to ensure the accuracy of the material described herein; however, CustomGuide makes no warranty,
expressed or implied, with respect to the quality, correctness, reliability, accuracy, or freedom from error of this document or the
products it describes. Data used in examples and sample data files are intended to be fictional. Any resemblance to real
persons or companies is entirely coincidental.
The names of software products referred to in this manual are claimed as trademarks of their respective companies.
CustomGuide is a registered trademark of CustomGuide, Inc.
Table of Contents
Introduction .......................................................................................................................... 7
Chapter One: The Fundamentals...................................................................................... 11
Lesson 1-1: Plan the Project ................................................................................................12
Lesson 1-2: Understanding Project Management ................................................................14
Lesson 1-3: What’s New in the Microsoft Project 2000 Database?.....................................16
Lesson 1-4: Understanding the Project 2000 Screen ...........................................................18
Lesson 1-5: Creating a New File .........................................................................................20
Lesson 1-6: Using Project Templates ..................................................................................22
Lesson 1-7: Entering Project Information............................................................................24
Lesson 1-8: Set the Working Time Calendar .......................................................................26
Lesson 1-9: Create a New Calendar ....................................................................................28
Lesson 1-10: Correcting Spelling and Using Undo or Redo ...............................................30
Lesson 1-11: Adjust the Timescale ......................................................................................32
Lesson 1-12: Saving the Project File ...................................................................................34
Lesson 1-13: Saving a Baseline Plan...................................................................................36
Lesson 1-14: Saving an Interim Plan...................................................................................38
Lesson 1-15: Getting Help...................................................................................................40
Chapter One Review............................................................................................................42
Chapter Two: Enter and Schedule the Task List ........................................................ 47
Lesson 2-1: Enter a Task......................................................................................................48
Lesson 2-2: Enter Task Durations........................................................................................50
Lesson 2-3: Creating a Milestone ........................................................................................52
Lesson 2-4: Copying, Moving, Inserting, and Deleting a Task............................................54
Lesson 2-5: Creating Recurring Tasks .................................................................................56
Lesson 2-6: Organize the Task List......................................................................................58
Lesson 2-7: Using Task Information and Task Notes ..........................................................60
Lesson 2-8: Linking and Unlinking Tasks ...........................................................................62
Lesson 2-9: Splitting Tasks..................................................................................................64
Lesson 2-10: Overlap or Delay Tasks ..................................................................................66
Lesson 2-11: Define Task Type............................................................................................68
Lesson 2-12: Effort-driven and Material-driven Scheduling ...............................................70
Lesson 2-13: Setting Task Deadlines and Constraints .........................................................72
Lesson 2-14: Assigning a Task Calendar .............................................................................74
Lesson 2-15: Task Indicators ...............................................................................................75
Chapter Two Review ...........................................................................................................76
Chapter Three: Enter and Assign Resources and Costs .............................................81
Lesson 3-1: Creating a Resource Sheet ...............................................................................82
Lesson 3-2: Entering Resource Availability.........................................................................84
Lesson 3-3: Grouping Resources.........................................................................................86
4 Microsoft Project 2000
Chapters
Each manual is divided into several chapters. Aren’t sure if you’re ready for a chapter? Look
at the prerequisites that appear at the beginning of each chapter. They will tell you what you
should know before you start the chapter.
Lessons
Each chapter contains several lessons on related topics. Each lesson explains a new skill or
topic and contains a step-by-step exercise to give you hands-on-experience.
Chapter Reviews
A review is included at the end of each chapter to help you absorb and retain all that you have
learned. This review contains a brief recap of everything covered in the chapter’s lessons, a
quiz to assess how much you’ve learned (and which lessons you might want to look over
again), and a homework assignment where you can put your new skills into practice. If you’re
having problems with a homework exercise, you can always refer back to the lessons in the
chapter to get help.
8 Microsoft Project 2000
In this lesson, you will learn how to apply number formats. Applying number formatting changes
You can also format howIn values are displayed—it
this lesson, you will learn doesn’t
how tochange
apply the actual
number information
formats. in any
Applying way. Excel
number is often
formatting changes
Tips and traps appear in the values
You by
canusing
Formatting
the
also format
values by toolbar
using the
smart
howenough
sign
values to
to indicate
smart
areapply
enoughcurrency
some number
displayed—it
to apply (such
some as
formatting
doesn’t
$548.67),
number
automatically.
change the
Excel will
formatting
For example,
actual information
automatically
automatically.
in anyifway.
Forapply
you Excel
use a dollar
the currency
example,
is often
if you usenumber
a dollar
margin. or Formatting
by selectingtoolbar
Format
or by → Cells
selecting
format
sign for you. currency (such as $548.67), Excel will automatically apply the currency number
to indicate
format for you.
The Formatting toolbar has five buttons (Currency, Percent, Comma, Increase Decimal, and
from the menu
Format and
→ Cells The Formatting
Decrease Decimal)toolbar
you canhas usefive buttons apply
to quickly (Currency,
commonPercent, Comma,
number Increase
formats. If noneDecimal,
of these and
buttons
clicking
from the menu and
Number tab. hasDecrease
what you’reDecimal)
looking you can
for, useneed
you to quickly apply
to use the common
Format Cellsnumber formats.
dialog box If none of
by selecting these →
Format buttons
clicking the
Icons and pictures appear in the Number tab. hasfrom
Cells whatthe
from
Cellsbox
dialog
menulooking
you’re
theasmenu
isn’t
and clicking
and
fast as
for, youtheneed
clicking
using
Number
to usetab.
the Number
the toolbar,
theFormatting
Format Cells
but ittab. Formatting
gives
numbers
dialog with
you morenumbers
box by
precisionwith
theselecting
and the
Format →
Format Cells
Format options.
formatting Cells
margin, showing you what to dialog
We’ll usebox
bothisn’t as fastinasthis
methods using the toolbar, but it gives you more precision and formatting options.
lesson.
We’ll use both methods in this lesson.
click or look for. 1. Select the cell range D5:D17 and click the Comma Style button on
Comma Style 1.theSelect the celltoolbar.
Formatting range D5:D17 and click the Comma Style button on
Comma
button Style theadds
Excel Formatting toolbar.(the comma) and two decimal places to the selected cell
a hundreds separator
button range.
Excel adds a hundreds separator (the comma) and two decimal places to the selected cell
Clear step-by-step instructions range.
• When you see a keyboard instruction like “press <Ctrl> + <B>,” you should press and
hold the first key (<Ctrl> in this example) while you press the second key (<B> in this
example). Then, after you’ve pressed both keys, you can release them.
• There is usually more than one way to do something in Project. The exercise explains the
most common method of doing something, while the alternate methods appear in the
margin. Use whatever approach feels most comfortable for you.
• Important terms appear in italics the first time they’re presented.
• Whenever something is especially difficult or can easily go wrong, you’ll see a:
NOTE:
immediately after the step, warning you of pitfalls that you could encounter if you’re not
careful.
• Our exclusive Quick Reference box appears at the end of every lesson. You can use it to
review the skills you’ve learned in the lesson and as a handy reference—when you need
to know how to do something fast and don’t need to step through the sample exercises.
Formatting a Worksheet 25
Formatting a Worksheet 25
Welcome to your first lesson on Microsoft Project 2000! Project 2000 is a high-powered
project management tool that you can use to control and track any kind of project once it has
been planned. With Project 2000, you can see every detail of your project simultaneously so
you can follow its progress.
For years, people have been completing projects, like mailing Christmas cards or building a
ten-ton steel bridge, without the aid of software. So why use project management software?
The answer is simple; your project will be completed as painlessly and problem-free as
possible.
Project 2000 can be a bit intimidating at first, with its big, blank default screen (the Gantt
chart), and its many buttons and views. But don’t worry; this chapter will familiarize you with
the elements and functions of Project 2000. Also, if you’ve already used more basic Microsoft
applications, such as Word, you’ll already know how to perform many simple Project 2000
tasks. With that in mind, this chapter is your introduction to Microsoft Project 2000 and the
world of project management. And so, without further ado, turn the page and let’s get started!
12 Microsoft Project 2000
Figure 1-1
Perhaps the most difficult process in Project 2000 is the first step: planning. Planning requires
constant research and editing. In fact, you may find that the planning stage of a project
doesn’t really end until you’re finished with the project.
So how can you prepare yourself, and what can you do to make this process pain-free? The
illustration above shows a common progression of steps to take when planning a project,
depending on the type of project you are tackling, and appears in further detail in the table
below. These steps are merely guidelines for planning a project and will change depending on
the type of project in which you are involved.
Step Description
Plan project Define phases and create a task list: Enter the tasks required to complete the
activities project, define the project’s phases, and add any supporting information to the task.
Show the project’s organization: Structure the tasks into their respective phases
as well as a hierarchy of summary tasks and subtasks.
Organize the project into a master project and subproject files: Complete a
large project (master project) by completing smaller projects (subprojects).
Estimate task durations: Estimate how long a task will take to complete,
considering nonworking time. Fine-tune durations with the task calendar.
Set task dependencies and constraints: Identify and link tasks that affect the
progress of another task.
Create interrelationships with projects: Identify tasks in the master project that
are dependent upon tasks in subprojects.
Plan for and Estimate resource needs: Compile a list of all the resources you will need and
gather change duration as necessary. Also get input from others involved in the project.
resources
Enter resource information and set working times: Update information about
the resources, and set the hours they will work.
Share resources among projects: Sharing resources can help make managing a
project’s progress easier.
Assign resources to tasks: Assign resources to specific tasks, including the
amount of time they are expected to work on the task.
Plan project Estimate costs: Research previous projects to estimate how much each task will
costs cost.
Define and share cost information: Prepare a budget, establish a baseline plan,
and share the information with the parties involved.
Prepare to manage costs: Set a fiscal year for the project, plan how to track and
manage costs, and track the cash flow plan.
Plan for quality Plan for quality: Define quality standards and determine how quality affects the
and risks overall scope of the project.
Identify and plan for risks: Research reliable resources, identify risks, and create
a plan of action to handle risk events should they occur.
Plan security Set up methods for communicating project information: Decide and establish a
and procedure for how you want to share project information with everyone involved.
communication
Protect project information: Depending on the communication resource you use,
set passwords, specify security settings, etc.
Optimize a Optimize the project plan to meet the finish date, plan for resources, and complete
project plan the project within its budget constraints.
Distribute a Depending on how you share and communicate the project’s information, distribute
project plan the project’s plan online or in printed format.
Remember, you have to do the planning of a project. Microsoft Project 2000 can only help
you record and keep track of all the tasks, resources, and costs within it.
14 Microsoft Project 2000
We all basically know what a project is, but here is a clear definition: A project is a temporary
series of actions undertaken to create a unique product or service. A project can be anything
from building a fleet of helicopters, to planning a wedding, to writing a sushi cookbook. All
projects have three things in common: (1) they have a start and end date, (2) they are an effort
made by people and equipment, and (3) they create a product or service. You’ve probably
already completed or are working on many projects as we speak. That means you already
have experience with project management.
Project management is the process of planning, organizing, and managing tasks and resources
to accomplish an objective, usually within constraints of time, resources, or cost. Project
? management has been a recognized profession since the 1950s but has been practiced since
the Stone Ages. Without project management, we would still be wearing animal hides and
rubbing sticks together to make fire.
?
Adjusting one of the An easy way to visualize the elements of project management is by using the Project Triangle,
Project Triangle as shown in Figure 1-2. The Project Triangle shows project management in terms of time,
elements affects the cost, and scope. Time is the amount of time it will take you to complete a project. Cost is the
other two. amount of money and time you will spend on the project. Scope is the quality, functions, and
features of your product or service. To see what happens to project management when one
side of the Project Triangle changes, see Table 1-2: If/Then in the Project Triangle.
Figure 1-3
Figure 1-4
A database is a
Before we start talking about new features, it helps if you actually understand what Project
collection of
2000 is—a database. In its simplest form, a database is a collection of information that is
information that is organized into a list. According to Microsoft, the Project 2000 database plan has been
organized into a list. improved considerably from Project 98 to increase performance and make it easier to work
with data. Here is what a good database does:
• Stores Information
A database stores lists of information that are related to a particular subject or purpose. A
database stores personal information, such as a list of aunt Mildred’s sushi recipes; or
business information, such as a list of hundreds of thousands of resources. A database
also makes it easy to add, update, organize, and delete information.
• Finds Information
You can easily and instantly locate information stored in a database. For example, you
can find all the recipes in your cookbook with the word “rice” in them, or all your
contractors located in the 58251 Zip Code.
• Analyzes Information
You can perform calculations on information in a database. For example, you could
calculate what percent of your total equipment comes from the state of Texas. You can
also present information in a professional-looking printed report.
• Manages Information
Databases make it easy to work with and manage huge amounts of information. For
example, you can change the due date for hundreds of tasks from 5/1/02 to 5/20/02 with a
few keystrokes.
• Shares Information
Most database programs (including Microsoft Project 2000) allow more than one user to
view and work with the same information at once. Such databases are called multi-user
databases.
Now that you know what a database is, here are some of the major additions to Project 2000:
Don’t worry if you don’t understand these features; the above table is a lot of tech-speak!
What’s important is that you learn how to use the program. That said, let’s get going…
Quick Reference
A database does these
things:
• Stores Information
• Finds Information
• Analyzes Information
• Manages Information
• Shares Information
18 Microsoft Project 2000
Views
bar Status bar Task entry Bar chart Scroll bars
table
Figure 1-5
The default screen for
You might find the Project program screen a bit confusing and overwhelming the first time
Project is the Gantt
you see it. What are all of those buttons, icons, menus, and lines for? This lesson will help you
Chart View. become familiar with the Project program screen. There are no step-by-step instructions in
this lesson—all you have to do is look at Figure 1-5 to see what everything you’re looking at
means. Relax! This lesson is only meant to help you get acquainted with the Project screen—
you don’t have to memorize anything.
Don’t worry if you find some of these objects confusing at first—they will make more sense
after you’ve actually used them.
One more important note about the Project program screen: Just as there are several different
types of database objects in Project, there are also many different program screens, something
that makes Project quite different from most Microsoft programs. The default screen for
Project is called the Gantt Chart view, which includes a Gantt table on the left side of the
window and a Gantt bar chart on the right. You will view more of the different screens as we
continue this chapter’s tour of Project.
20 Microsoft Project 2000
Figure 1-6
Figure 1-7
Once you have your project all planned out, you can begin entering it in a new file. Project
New button automatically opens to a new file, but it’s not very convenient to have to re-open the program
Other Ways to Open a if you want to start a new file, so this lesson shows you all you need to know about opening a
New Blank Project File: new file. After opening the file there are a few things you should do before starting to enter
tasks, but they are not discussed in this lesson.
• Click the New button.
Or… For now, concentrate on creating a new Blank Project file.
• Press <Ctrl> + <N>. 1. Select File → New from the menu.
The New dialog box appears. By default it opens to the General tab, which contains the
template for a Blank Project file. This is the type of file you will use to start a new
project most of the time.
Quick Reference
To Create a New File:
• Select File → New from
the menu.
Or…
• Click the New button.
Or…
• Press <Ctrl> + <N>.
22 Microsoft Project 2000
Figure 1-8
Figure 1-9
If you have a good plan set up for the project, and want to save a lot of time setting up a the
tasks, durations, and other aspects of the project, use a template. A template is a type of file
that is already set up for a particular type of project. For example, a New Product template has
many of the tasks that are required to develop a new product, and estimates for how long each
task will take. Then, if you need to add or delete a task or change a task duration, you can
easily modify the information in the template to reflect your own plans for the project.
The process for creating a new project file from a template is basically the same as creating a
new Blank Project file.
Figure 1-10
Other Ways to View You have probably noticed that when a new file is opened in Project, a dialog box appears on
Project Information:
the screen. It’s a good idea to fill out as much information as you know in this dialog box
• Select Project → before entering any tasks. It doesn’t take long to fill out, but the information is very important
Project Information because Project uses it to schedule the project.
from the menu.
1. Select Project → Project Information from the menu.
The Project Information dialog box appears, as shown in Figure 1-10.
The most important piece of information to enter is the start or end date. First you have
to decide if you want to plan your project from the start date, or the end date.
• Start Date: If you plan it from the start date you specify, Project will assign the
tasks to begin As Soon As Possible (ASAP), so the project doesn’t have to be
drawn out longer than necessary.
• End Date: If you plan the project from the end date you specify, Project will
assign the tasks to begin As Late As Possible (ALAP) so the project will be
completed on the appointed date.
In either case, Project automatically calculates the other date (start or end), depending
on the task and duration information you enter in the project.
2. Make sure Project Start Date appears in the Schedule from drop-down
list.
This is the default setting of Project Information. Now you must enter the start date for
the project. If you had chosen Project End Date, you would enter the projected end date
of the project.
Figure 1-11
The legend
identifies what
the different
markings
indicate on the
calendar The new
working hours
for the selected
day
Figure 1-12
You have already chosen the kind of calendar you want to use in the Project Information
dialog box (Standard), but you can further change the working hours for the calendar.
Currently, the Standard calendar defaults are Monday through Friday, 8:00 A.M. to 5:00 P.M.,
with an hour off for lunch. There may come a time when you need to change the working time
for a day, week, month, or the entire project. This lesson will show you how to change the
working hours.
For this project, you will be planning a wedding. Since most wedding services and shops
don’t open until 10 A.M., change the project’s working hours to 10:00 A.M. to 7:00 P.M.
Press and hold the
<Shift> key to select 1. Select Tools → Change Working Time from the menu.
a series of column The Change Working Time dialog box appears, as shown in Figure 1-11. First, let’s
headings. change the weekday working hours.
2. Click the M column heading for Monday. Press the Shift key and click the
F column heading for Friday.
All the weekdays, Monday through Friday, are selected on the calendar as shown in
Figure 1-12.
3. In the From: text box, type 10:00 AM. In the To: text box, type 7:00 PM.
Delete the second set of numbers, 1:00 PM and 5:00 PM. Love
Since this is such a big wedding, you might have to work on Saturdays as well.
4. In the calendar, click on the last S column heading for Saturday.
Groomsmen’s Gift
The weekdays are unselected, and the Saturday column is selected. Notice that the
column headings for the weekdays are underlined, and that the date boxes are shaded.
According to the Legend on the left side of the dialog box, this indicates that the
shaded date’s working hours have been changed, and that all the days of the week for
the column heading have been changed.
You want to check in with the families about the work done for each week, so change
the working time for Saturday.
5. Select the Nondefault working time option, and clear the From: and To:
text boxes. Enter 1:00 PM in the From: text box, and 4:00 PM in the To:
text box.
Your Saturday working hours are changed for the duration of the project.
What if you want to change the working hours for just one day?
6. Select the third Friday and Saturday of the month by holding down the
<Shift> key while clicking.
You have to attend a family reunion this weekend, so take the weekend off.
7. Select the Nonworking time option.
The working times are cleared, indicating that it is a nonworking day. Quick Reference
8. Click OK. To Change Working Time
The Change Working Time dialog box is closed, and your working hours calendar is in Your Project Calendar:
ready to go! 1. Select Tools → Change
NOTE: It is important to understand that if you change the working times to less than Working Time from the
eight hours a day, the Gantt Chart bars will not match up with the tasks menu.
durations. For example, the default start and working time for a day is 8 AM 2. Click the column heading
to 5 PM, but you have set the calendar for one hour of work each day. of the day(s) you want to
Therefore, if you estimate that a task will take one day to complete, but are change.
only working one hour a day, Project will still assume that it will take eight Or…
hours, so it will take eight days to finish the task. To fix this, however, you Select the specific
can change the calendar’s default options. date(s).
3. Click the Nondefault
time option.
Or…
Click the Nonworking
time option.
4. Change the times to the
hours you want to work in
the From: and To: text
boxes.
5. Click OK.
28 Microsoft Project 2000
Figure 1-14
There are times when a task will have different working times than the rest of the project. For
these instances, designate a new calendar for the task.
Create a new Sewing calendar for a task in this lesson.
4. Click the Make a copy of option. Select Standard from the drop-down
list.
Your calendar will be based off the schedule for the Standard calendar.
5. Click OK.
The Change Working Time dialog box appears once again, but this time you are going
to change the working time for the Sewing calendar.
6. Click the Tuesday column in the calendar. Press the <Ctrl> key and click
the Thursday column in the calendar.
The two columns are selected. Change these days to nonworking time.
7. Click the Nonworking time option in the dialog box, and click OK.
The only working days are Monday, Wednesday and Friday.
Quick Reference
To Create a New Calendar:
1. Select Tools → Change
Working Time from the
menu.
2. Click the New button in
the dialog box.
3. Enter a name for the new
calendar and choose to
create a new calendar, or
copy an existing one.
4. Click OK.
5. Change the working
hours and days for the
new calendar and click
OK.
30 Microsoft Project 2000
Figure 1-15
Figure 1-16
Figure 1-17
No matter how excellent you are with English and computers, you will probably need to use
Spelling button the Spelling and Undo or Redo features at some point during your project. This lesson teaches
you how to use these features.
Other Ways to Use
Spelling:
• Select Tools →
1. If necessary, navigate to your practice folder and open Lesson 1.
Spelling from the If you don’t know where your practice files are, ask your instructor.
menu. 2. Click the Spelling button on the Standard toolbar.
• Press <F7>. The Spelling dialog box appears highlighting the first misspelled word.
Quick Reference
To Use Spelling:
• Click the Spelling
button on the Standard
toolbar.
To Choose Specific
Spelling Options:
1. Select Tools → Options
from the menu.
2. Click the Spelling tab.
To Use Undo or Redo:
• Click the Undo or
Redo button on the
Standard toolbar.
Or…
• Select Edit → Undo or
Redo from the menu.
Or…
• Press <Ctrl> + <Z>.
32 Microsoft Project 2000
Minor scale:
Days
Figure 1-19
Figure 1-20
You can format your project’s timescale to customize how you view information over a period
of time. The timescale is the time grid area in the Gantt Chart and in other views where task
bars and nonworking time are displayed. Figure 1-18 shows the timescale header. The
timescale header consists of the major scale (upper portion) and minor scale (lower portion).
Change your timescale so that you can see the wedding project over a longer amount of time,
and give your nonworking time areas a new color.
Quick Reference
To Open the Timescale
Dialog Box:
• Select Format →
Timescale from the
menu.
Or…
• Double-click inside the
timescale header.
Or…
• Right-click the
timescale header and
select Timescale from
the shortcut menu.
To Adjust the Timescale’s
Time Period:
• Format it in the
Timescale dialog box.
Or…
• Select View → Zoom
from the menu and select
the time scale you want to
view.
34 Microsoft Project 2000
Figure 1-21
Figure 1-22
Saving a file in Project 2000 is very similar to saving a file in most Microsoft programs. This
lesson will show you how saving a project file is different.
A baseline is a snapshot of what the project looks like right now, and is used to track
project progress. You are not yet ready to create a baseline, however. Typically project
baselines are not saved until all the project’s information is entered in the file, and is as
fine-tuned as possible.
3. Select Save My Wedding without a baseline from the Office Assistant. Other Ways to Save a
Project File:
The file is saved without a baseline.
• Click the Save button
You might want to check the “Don’t tell me about this again” option in the Office
on the Standard toolbar.
Assistant box. Otherwise, the Planning Wizard will pop up every time you save the
project, until you save a baseline. Or…
• Press <Ctrl> + <S>.
Quick Reference
To Save a Project File:
1. Select File → Save As
from the menu.
Or…
Click the Save button on
the Standard toolbar.
Or…
Press <Ctrl> + <S>.
2. Type the file name in the
File name text box.
3. Click Save.
4. Choose to save with or
without a baseline if
necessary.
36 Microsoft Project 2000
Figure 1-23
Click Entire project Click Selected tasks to save the
to save all the information for selected tasks in
information in the a baseline or interim plan.
project.
example, you want to keep track of a task’s cost. The baseline estimate is $50, but the actual
cost is $60, a variance of $10. Now that you know this information, you can adjust other parts
of your project to meet cost constraints.
Note, however, that you can only view the variances of those items for which you've entered
baseline estimates. For example, if you didn't enter resource costs before you saved a
baseline, you will not be able to view resource-cost variances.
One more thing; always save a baseline wisely. There may be times when a project is so small
that you don’t need to compare progress, or you won’t have enough time to check project
variance. Also, if you haven’t entered enough information in the file to create a project
baseline, simply choose to save without a baseline until more information is ready to go.
Other Ways to Save a
1. Select Tools → Tracking → Save Baseline from the menu. Baseline:
The Save Baseline dialog box appears. You can either choose to save your baseline as • If you have made
an entire project, or just add selected tasks you may have entered to a baseline you significant changes to
saved earlier. We haven’t saved a baseline yet, so save the entire project. your project and you
haven’t started working
NOTE: You can only have one project baseline at a time, so save wisely. Make sure the
majority of your tasks and resources have been entered into your project. You on your tasks, select
can save up to ten Interim plans as you work to compare levels of progress— Project → Save from
more on those in another lesson. the menu. The Save
Baseline dialog box
2. Click the Save Baseline and Entire Project options as shown in Figure
should pop up. If it
1-23 and click OK.
doesn’t, go to step 2.
That’s it—you have saved a baseline for your project. Now, as work is completed and
tasks are updated, you can compare your work with the baseline to see how far along
you are, and to see how close your planning estimates were.
That’s all there is to saving a baseline plan. The trick is to actually use the baseline
information to track how your project is progressing, which you will learn more about as the
project develops.
Quick Reference
To Save a Baseline Plan:
1. Select Tools →
Tracking → Save
Baseline from the menu.
2. Click the Save Baseline
and Entire Project
options, and click OK.
To Clear a Baseline Plan:
1. Select Tools →
Tracking → Clear
Baseline from the menu.
2. Click the Save Baseline
and Entire Project
options, and click OK.
38 Microsoft Project 2000
Figure 1-24
While a baseline plan records how the complete project looks before any progress is recorded,
an interim plan is a snapshot of your project as it progresses. You can then compare interim
plan data to baseline plan data to assess task progress.
Interim plans are not nearly as detailed as baseline plans. A baseline saves 20 pieces of
information, compared to an interim plan that saves only two pieces of information; the start
and finish date of a task. You can save up to ten interim plans at a time.
Although you generally only save an interim plan after beginning task work, save an interim
plan right now just for practice.
Quick Reference
To Save an Interim Plan:
1. Select Tools →
Tracking → Save
Baseline from the menu.
2. Click the Save interim
plan bullet.
3. In the Copy textbox, click
the name of the current
interim plan.
4. In the Into textbox, click a
name for the next interim
plan or specify a new
name.
5. Click the Entire project
bullet and click OK.
Or…
Click Selected Tasks to
save a portion of the
schedule.
40 Microsoft Project 2000
Figure 1-27
If you’ve worked with other Microsoft programs, you’ve probably encountered the Microsoft
Office Assistant (that cute little know-it-all paperclip or another animated character). The
Office Assistant is a Help tool. Fortunately, there are many Help tools you can access in
Project 2000 if you have a question or problem. You can receive help from the Office
Assistant, Help Contents and Index, Help tutorials, or the “What’s This?” button.
The Reports dialog box appears. Notice the “What’s This?” button in the upper right To Open the Help Tutorial:
corner of the dialog box, next to the Close button. • Select Help → Getting
11. Click the What’s This? button. Started → Tutorial from
the menu.
Your pointer suddenly changes to a “What’s This?” pointer and has a question mark
attached to it. Use your “What’s This?” pointer to click on a report type in the Reports To Use the “What’s This?”
dialog box, and a description of that report type will appear. When you click on Button:
something with the “What’s This?” pointer, you will be shown an explanation or • In a dialog box, click
description. the “What’s This?”
12. Close the Reports dialog box by clicking the Close button. button to change your
pointer, and click on the
Congratulations! You have successfully navigated through the vast area of Microsoft Project
area of the dialog box
Help tools. Give yourself a pat on the back.
that’s confusing.
42 Microsoft Project 2000
Lesson Summary
Plan the Project
• Before entering information in a project file, you must have a clear idea of the scope and purpose
of the project.
Getting Help
• To Show the Microsoft Office Assistant: Select Help → Microsoft Project Help from the menu,
or press <F1>, or click the Help button.
• To Open Help Contents and Index: Select Help → Contents and Index from the menu.
• To Open the Help Tutorial: Select Help → Getting Started → Tutorial from the menu.
• To Use the “What’s This” Button: In a dialog box, click the “What’s This?” button and then click
the area in the dialog box you have a question about.
Quiz
1. What is NOT a component of the project triangle?
A. Effort
B. Time
C. Scope
D. Cost
3. You can change the project calendar to reflect the days and hours for
everyone on your project. (True or False?)
5. How can you access the Microsoft Assistant if you need help? (Select all
that apply.)
A. Press <F1>.
B. Select Help → Contents and Index from the menu.
C. Press the Help button.
D. Chant “Microsoft Assistant, Microsoft Assistant, Microsoft Assistant” three times.
7. You can change views in Project 2000 by: (Select all that apply.)
A. Selecting a new view from the View bar.
B. Hiding your toolbars.
C. Going to the View menu and select a new view.
D. Pressing <Alt> + <V> and press the underlined letter in a new view.
Homework
1. Start Microsoft Project 2000.
2. Navigate to your practice files and open the Homework 1 database.
3. Spellcheck this database using the spelling button.
4. Select Tools → Options from the menu and click the General tab. Enter “Don
Quixote” in the User Name text box, and click OK.
5. Switch to Resource Sheet view and then back to Gantt Chart view.
6. Select the first task, “Open a Lemonade Stand,” and change it to “Open a Slim-Fast
Stand.” Then use the Undo feature to undo what you just wrote.
Quiz Answers
1. A. Effort is not a component of the project triangle.
2. C. Gantt Chart view is the default view in Project 2000.
3. True. Do this by adjusting the timescale
4. D. This procedure will only insert a new task in the task list.
46 Microsoft Project 2000
5. A and C. Pressing <F1> and clicking the Help button will make the Microsoft Assistant
appear.
6. False. Saving the baseline plan is very important because it allows you to track your
project’s progress.
7. A, C, and D. You cannot change views by hiding your toolbars.
8. True. Most databases can share information, very few can not.
Diving into a blank database can be very intimidating at first. But don’t worry; all you have to
do is enter information into your project database, and Microsoft Project 2000 calculates and
creates a working schedule based on information you provide.
You can begin planning your project after you have defined your project goals and considered
the major phases of your project. For example, say you’re planning a wedding. Your major
goals are to decide on a date, book wedding services (caterer/DJ/photographer), choose your
wedding party and attire, plan a honeymoon, invite guests, and get married. The major phases
of your wedding planning might be divided into the months before the wedding, the week
before the wedding, the rehearsal dinner, and the wedding day. In this chapter, we are going to
organize a list of tasks to be completed, along with each task’s duration. Then, we’re going to
add people, equipment, and materials, and their costs to our plan. The lessons in this chapter
guide you through creating your project plan.
48 Microsoft Project 2000
Crack your knuckles and get ready—it’s time to enter tasks into your project! Tasks are really
the basis of every project because Project 2000 builds the project schedule on the information
you enter in tasks. Finally, you can develop a structure for the perfect fairytale wedding.
You should already have an idea of what you need to do to accomplish your project’s goals.
Start with large chunks of work and then break them down into smaller tasks. A task
represents an amount of work with a clear outcome, and it should be small enough for you to
track its progress regularly.
1. Navigate to your practice folder, and open Lesson 2A. Save the file as
Task List.
If you don’t know where your practice files are, ask your instructor.
The default Gantt Chart view is an easy view in which to enter tasks, although there is
an even easier view to use.
2. Scroll down the Views Panel and click the More Views button.
The More Views dialog box appears.
3. Select Task Sheet from the list and click Apply.
The screen appears in Task Sheet view. This view is basically the spreadsheet part of
Gantt Chart view.
4. Place your insertion point in the Task Name field.
When entering a task, try to pick a name that clearly identifies the task.
5. Type Engagement, and press <Enter>.
The task is numbered and named. Microsoft Project automatically enters information
for the remainder of the task information. Notice in the Duration column that there is
an estimated duration of one day for the task, followed by a question mark.
Quick Reference
To Enter a Task:
• Type the task’s name in
the Task Name field, and
press <Enter>.
50 Microsoft Project 2000
Figure 2-2
Quick Reference
To Enter a Duration:
• Enter a duration in the
Duration field.
52 Microsoft Project 2000
Figure 2-4
Enter a duration of 0 A Milestone Marker appears
(zero) days to turn a as a single spot on the chart
task into a milestone. instead of a task bar.
A milestone is a task that marks a significant event in your project. Though milestones don’t
require any work, they are valuable additions to any project. Whether it is the beginning or
end of a task, milestones are goals that keep you on the right track in your project’s
progression.
Quick Reference
To Create a Milestone:
1. Enter a duration of 0
(zero) days for a task.
Or…
1. Click the Task
Information button and
select the Advanced tab.
2. Check the Mark task as
Milestone checkbox, and
click OK.
54 Microsoft Project 2000
Figure 2-6
Other Ways to Copy a The gray moving line
Task: appears to show where the
task is being moved.
• Right-click the selected
task and select Copy
Task from the shortcut
menu.
Or…
• Select the task and
press <Ctrl> + <C>.
Figure 2-7
Other Ways to Delete a Chances are you will have to copy, insert, delete, and move tasks at some point in your
Task:
planning. If you’ve ever typed text in a program before and had to edit it, the steps in this
• Select the task and lesson will be a breeze.
push the Delete key.
Or… 1. Navigate to your practice files and open Lesson 2B, and save the file as
• Right-click the task and Task List.
select Delete from the If you don’t know where your practice files are, ask your instructor.
shortcut menu. First, copy a task in the list.
2. Click on the task #3 ID, the column to left of the task name.
Notice that all the fields in the row are selected.
3. Select Edit → Copy Task from the menu.
The “Send engagement announcements” task has been copied and placed on the
clipboard. Now enter it above the “Engagement” task.
4. Select the Engagement party task name. Select Edit → Paste from the Other Ways to Insert a
menu. New Task:
The “Send engagement announcements” task has been entered above the “Engagement • Right-click the number
party” task. You now have two “Send engagement announcements” tasks. to the left of a task, and
Now move the new “Send engagement announcements” task to the bottom of the list. choose New Task.
5. Click on the task #2 ID, the column to left of the task name so the entire Or…
row is selected. • Push the Insert key.
You are ready to move the task.
6. Click the selected task, and drag and drop the task to the end of the list.
A gray line should appear across the task list when you begin to move the task, as
shown in Figure 2-6. You don’t really need two “Send engagement announcements”
tasks, so go ahead and delete the last one.
Quick Reference
7. Click on the task #5 ID, and select Edit → Delete Task from the menu. To Copy a Task:
The task is deleted from the task list. • Select Edit → Copy
What if you need to insert a task? This is also easily done in Project. Task from the menu.
8. Click on the task #1 ID, and select Insert → New Task from the menu. • Right-click the selected
task and select Copy
A new blank task is entered in the project. Task from the shortcut
9. In the new blank task field, type Announcements and press <Enter>. menu.
Your new task entry is finished. • Select the task and press
Compare your changes to Figure 2-7. <Ctrl> + <C>.
To Move a Task:
1. Select the task and then
click it once more so the
pointer turns from a
to a .
2. Drag the task to a new
location.
To Delete a Task:
• Select Edit → Delete
Task from the menu.
• Select the task and
push the Delete key.
• Right-click the task and
select Delete from the
shortcut menu.
To Insert a Task:
• Click the task you want
your new task to appear
above, go to the Insert
menu, and choose New
Task.
• Right-click the number
to the left of a task, and
choose New Task.
• Press the Insert key.
56 Microsoft Project 2000
Figure 2-8
A recurring
task has
subtasks
underneath it
for all
recurrences.
Figure 2-9
Recurring tasks are tasks that repeat regularly, such as weekly visits to the Swedish masseuse
because you are SO stressed out from planning weddings! A recurring task can take place
daily, weekly, monthly, or yearly. You can specify the duration of each occurrence, when it
will occur, and for how long or how many times it should occur.
1. Go to the end of the task list. Select Insert → Recurring Task from the
menu.
The Recurring Task Information dialog box appears, as shown in Figure 2-8. You
would like to schedule three recurring appointments for mambo classes so the couple
will finally learn how to dance for the wedding.
First, name the task.
2. Type Mambo Mania class in the Task Name box.
Now enter the duration of the recurring tasks.
Quick Reference
To Create a Recurring
Task:
1. Select Insert →
Recurring Task from the
menu.
2. Enter information into
the Recurring Task
dialog box, and click OK.
58 Microsoft Project 2000
Figure 2-10
The length of a
summary task
depends on the
length of its
subtasks.
Figure 2-11
Other Ways to Insert a The more tasks you have in a project, the more confusing things can become. Therefore, you
New Task:
should organize your tasks into phases, or groups of related tasks. In Project, phases are
Right-click the number to grouped by summary tasks. Tasks underneath the summary tasks are called subtasks. Project
the left of a task, and calculates the duration of your summary tasks based on the details in your subtasks. If you
choose New Task. change information in your subtasks, the duration of your summary task will change.
1. Navigate to your practice files and open Lesson 2C. Save the file as The level of a task’s
Task List. indentation tells you
If you don’t know where your practice files are, ask your instructor. whether it is a
summary task or a
Insert the summary task names into the list.
subtask.
2. Select Announcements, and select Insert → New Task from the menu.
A new row appears.
3. Type Diplomatic Wedding - 800 guests in the Task Name field.
Enter another new task.
4. Select Reception sites and caterer, and select Insert → New Task
from the menu. Type Hire services in the new field.
Now you need to make the new tasks into summary tasks.
5. Press the <Shift> key and select tasks 2 and 16.
These tasks will be subtasks of the summary task, “Diplomatic Wedding - 800 guests”.
6. Click the Indent button on the Formatting toolbar.
Task 1, “Diplomatic Wedding - 800 guests,” becomes a summary task, and tasks 2
through 16 become subtasks. Indent button
You can also create summary tasks within summary tasks.
7. Under the task Announcements, select tasks 3 through 7.
These are all subtasks of the “Announcements” summary task.
8. Click the Indent button on the Formatting toolbar.
Task 2 becomes a summary task, and tasks 3 through 7 become subtasks.
There is one more summary task to deal with.
9. Under the Hire Services task, select tasks 9 through 16 and click the
Indent button on the Formatting toolbar.
Your Task Sheet should look similar to Figure 2-10.
Go back to Gantt Chart view to see what the chart looks like.
10. Click the Gantt Chart button in the Views panel.
Notice that the summary task bars appear as in black, and extend as far as the longest Quick Reference
subtask. To Create a Summary
Structuring your tasks into phases is easy, isn’t it? If you want to hide the subtasks under a Task:
summary task, click the “hide subtasks” button next to the summary task or on the Formatting 1. Either insert a new task to
toolbar. If you want to show the subtasks again, click the “show subtasks” button next to the be used as a summary
summary task or on the Formatting toolbar. task, or use one you
already entered.
2. Under your summary
task, select the tasks you
want to use as subtasks.
3. On the Formatting toolbar,
click the Indent button.
To View a Level of a
Phase:
• Click the Show button
on the Formatting
toolbar.
60 Microsoft Project 2000
Figure 2-12
Task Information
button
Figure 2-13
Other Ways to Change So far you have been working with tasks on a surface level. This lesson is going to dig deeper
Task Information: as you explore the Task Information dialog box and enter Task Notes.
• Right-click the task
and select Task 1. Select the Send save the date announcements task #6 and click the
Information. Task Information button.
Or… The Task Information dialog box appears, as shown in Figure 2-12.
• Select the task and Change the duration for this task.
select Project → Task 2. In the Duration text box, delete 0d and type 3 days. Click OK.
Information from the Terrific! You have just changed a task’s information. Notice that the change has also
menu. been made to the task in Gantt Chart view.
NOTE: You can also edit multiple tasks, although most project managers choose not
to. To edit multiple tasks, select the group of tasks you want to edit and click
the Task Information button. Make edits in the Multiple Task Information
Task Notes dialog box.
button
You can also enter notes for a task.
3. Go to the end of the task list and type Find wedding gown to enter a
new task.
When you add a note
Now enter a note for the type of wedding gown you want to find.
to a task, the notes
4. Click on the task you just typed, and click the Task Notes button on the indicator appears in
Standard toolbar. the Indicators field.
The Task Information dialog box appears with the Notes tab in front, as shown in
Figure 2-13. Enter text and an illustration.
5. In the large text box, type MUST have puffy sleeves, and then click
the Insert Object button in the dialog box.
Insert Object
The Insert Object dialog box appears. button
6. Click the Create from File bullet, click the Browse button and navigate
to your practice folder, select dream dress.bmp, and click OK, OK.
You just inserted a picture into the Notes tab. Go ahead and view it.
7. Take a look at your dress picture in the Notes tab and click OK.
You are back to the Gantt Chart view.
Refer to the table below for more information on what the Task Information dialog box Other Ways to Enter a
can do. Task Note:
• Right-click the task
and select Task Notes.
Table 2-1: Task Information dialog box Or…
Tab Description • Click on the Notes
General Use this tab to enter, review, or change basic information about the selected tab in the Task
task. For example, change task durations, track task progress, and enter a start Information dialog box.
or finish date.
Predecessors Use this tab to enter, review, or change predecessor information about the
selected task. Enter a predecessor for the current task and select the
predecessor type, and enter lag time or lead time.
Resources Use this tab to enter, review, or change resource assignments and assignment
units for the selected task.
Advanced Use this tab to enter, review, or change supplemental task information. For Quick Reference
example, enter a deadline for the task, change a task constraint, specify the To Use Task Information:
task calendar, or mark the task as effort-driven, or as a milestone.
• Select the task, click
Notes Use this tab to enter or review notes for a selected task. For example, add new the Task Information
notes about a task, revise or add to existing notes, format the font and button, and make edits in
alignment of notes, or insert objects into a note. the dialog box.
To Enter a Note for a Task:
• Select a task and click
the Task Notes button
from the Standard toolbar.
Or…
• Right-click the task and
select Task Notes.
Or…
• Click on the Notes tab in
the Task Information
dialog box.
62 Microsoft Project 2000
Figure 2-15
The Task Dependency
dialog box
Figure 2-16
Linking arrows
Linking arrows appear, indicating
that the two tasks
are linked.
Figure 2-14
Figure 2-15
Linking tasks allows you to put things in order. For instance, you can’t sew turquoise sequins
onto your wedding dress until you have a wedding dress to sew on. Likewise, you can’t send a
deposit to the caterer until you hire a caterer.
To select nonadjacent
The task whose start or finish date depends on another task is called the successor. The task
tasks, hold down the that the successor is dependent on is the predecessor. For example, “Book a caterer” would be
<CTRL> key and click a predecessor, while “Send caterer a deposit” is the successor. When tasks are linked, changes
the task name. To to the predecessor’s dates affect the successor’s dates.
select adjacent tasks, In this lesson, make a link so that the “Draft contract and notice to proceed with wedding
hold down <Shift> key plans” task is a predecessor, and “Hire services” is a successor.
and click the first and
last task you want to 1. Click the Draft contract and notice to proceed with wedding plans
link. task #7.
You must select tasks in the order that you want them linked.
2. Press the <Shift> key and click the Hire services task #8.
The two tasks are ready to be linked.
Figure 2-17
The status window tells The dividing tool
you the date the split
task is going to begin.
You can split a task if you have to interrupt it and complete it on a later date. A task can be
Split Task button split as many times as necessary.
1. Navigate to your practice files and open Lesson 2D and save the file as
Task List.
If you don’t know where your practice files are, ask your instructor.
Uh-oh. The search for the perfect puffy-sleeved wedding gown is going to have to go
on hold for two weeks when the bride goes on a campaign tour with her father across
Wyoming. Split the task to account for the time.
2. Select the Find wedding gown task #30
Now split that task.
Quick Reference
To Remove a Split:
• Drag the split portions
until they touch.
To Split a Task:
1. Select the task and click
the Split button.
2. Use the dividing tool to
choose a splitting spot in
the task’s Gantt bar, and
then click it.
66 Microsoft Project 2000
Figure 2-19
Figure 2-20
Figure 2-21
After you link tasks, you can also overlap or delay them. Overlapping linked tasks means that
you want the successor (second) task to begin before the predecessor (first) task ends.
Therefore, you give the successor task lead time. Delaying a task means that there will be
some time between the predecessor task ending, and the successor task beginning. Therefore,
you give the successor task lag time.
Sound confusing? Look at it in terms of our wedding:
You want to start planning the wedding colors before you decide on bridesmaid dresses so
you can coordinate the available options. You’d better overlap those two linked tasks.
1. Click the Sew bridesmaid dresses task #38, because it’s the one you
want to add lead time to. Click the Task Information button.
The Task Information dialog box appears.
Task Information 2. Click the Predecessors tab.
button The task that “Sew bridesmaid dresses” is linked to appears in the Task Name column.
Now enter the lead time information.
3. In the Lag column, type –3 days. You can also enter lead
This means the “Sew bridesmaid dresses” task will start three days before the “Choose or lag time in
wedding colors” task has ended. percentages.
NOTE: When you are entering lead time for a task, always put a minus sign (-) in
front of the amount of lead time. Otherwise, Project 2000 will think you are
entering lag time.
4. Click OK.
Notice on the Gantt Chart that the “Sew bridesmaid dresses” task now has lead time on
the “Choose wedding colors” task.
Next you need to order your wedding invitations early, so they have plenty of time to Other Ways to Add Lead
be made and mailed. However, you want to wait until closer to the wedding to send or Lag Time to a Task:
them out. Thus, you should probably add lag time to the “Send out invitations” task. • Double-click the link line
5. Click the Send out invitations task #47, because it’s the one you want to on the Gantt Chart and
add lag time to. Then click the Task Information button. then type in the amount
of lead or lag time in the
The Task Information dialog box appears.
Lag box of the Task
6. Click the Predecessors tab. Dependency dialog
The task that “Send out invitations” is linked to appears in the Task Name column. box. (Remember to put
Now enter the lag time information. a minus sign before
7. In the Lag column, type 4 weeks. lead time.)
This means the “Send out invitations” task will start four weeks after the “Order
invitations” task has ended.
8. Click OK.
Notice on the Gantt Chart that the “Send out invitations” task now has lag time behind
the “Order invitations” task.
9. Close the file.
Excellent. You have changed task relationships. Quick Reference
To Enter Lead or Lag
Time:
1. Click on a successor task,
and click the Task
Information button.
2. Click the Predecessors
tab and enter a lead or
lag time in the Lag box.
Or…
• Double-click the link line
on the Gantt Chart and
then type in the amount of
lead or lag time in the Lag
box of the Task
Dependency dialog box.
*Remember to put a minus
sign before lead time.
68 Microsoft Project 2000
Error! Reference
Defining task types helps Project know how you want your project to be scheduled. For any
task, you can choose which piece of the equation Microsoft Project calculates by setting the
task type.
When you define the task type, you are giving a value to a part of this equation: duration =
work/assignment units. Project uses this formula to determine the duration of each task.
Change the task type for some of the project’s tasks in this lesson.
Quick Reference
To Define Task Type:
1. Select the task.
2. Click the Task
Information button on
the Standard toolbar.
3. Click the Task type list
arrow to select the type
you want to assign to the
task.
70 Microsoft Project 2000
Figure 2-23
You can assign as many material resources as you want to a task, but you have to be mindful
of scheduling multiple work resources. Project’s Effort driven scheduling feature plays a
major role in assigning multiple work resources to a task. If you assign only one work
resource to work full-time on a task, the amount of task work and the duration will be the
same. However, the amount of task work will be different from the duration if you assign
more than one work resource to work on a task, or if a work resource is only working part-
time. Confused? Take a look at this Effort driven scheduling formula:
Duration x Units = Work
You can see how many
Now consider this scenario: The duration for a task is one week. We have set up our project
hours are in your
calendar so that a week equals 40 hours of work, so the one-week task duration is 40 hours.
calendar’s work week Let’s say you want to assign two work resources—Sue and Sallie—to complete this task.
by selecting Tools → Assuming they will each be giving 100% of their time to your task, the total units will be
Options from the 200% (Sallie @ 100% + Sue @ 100%). Here is the formula:
menu, and click the
Calendar tab. 40 hours task duration x 200% resource units = 80 hours of work
Thus, with two work resources, 80 hours of work will be completed in a one-week duration.
Because this is double the work completion that you had originally planned for, Project’s
Effort driven scheduling feature shortens the task duration from one week to half of a week. If
you don’t mind your task duration being shorter, then you’re good to go; assign multiple work
resources to tasks wherever you want. But if you don’t want the duration for a task shortened,
then you have to shut Effort driven scheduling off when you enter more than one work
resource for a task.
Assign Resources
button
1. If necessary, navigate to your practice folder and open Lesson 2E, and
save the file as Tuxes.
If you don’t know where your practice folder is, ask your instructor.
Grandma Jeanette is helping pick out tuxes, but the best man should help out so Remember: Effort
nobody ends up with something baby blue and ruffled. You have to assign a second driven scheduling
resource to the task “Find groomsmen’s tuxes,” but you don’t want to change the doesn’t apply to
duration of the task. You’d better turn off Effort driven scheduling before you assign a material resources.
second resource to this task.
2. Select task 41 Find groomsmen’s tuxes click the Task Information
button and select the Advanced tab.
Do you see the Effort driven check box? It’s in the lower-right quarter of the Task You can turn off
Information dialog box. Effort driven
3. Click the Effort driven check box so that there is no checkmark inside it, scheduling for every
new task that you
then click OK.
create. Select Tools →
This task’s Effort driven scheduling is now turned off. When you assign another Options from the
resource to this task, the duration of the task will not change. Assign the “Harry (best menu, click the
man)” resource to the “Find groomsmen’s tuxes” task.
Schedule tab, and
4. Select the Find groomsmen’s tuxes task, click the Assign Resources uncheck the New tasks
button, select the Harry (best man) resource from the Assign are effort driven check
Resources dialog box, and click Assign, Close. box.
Notice on your Gantt Chart that a second resource has been added to the “Find
groomsmen’s tuxes” task, but the duration of the task has not changed.
The concept behind Effort driven scheduling and multiple resources can be a bit confusing;
good thing it’s easy to turn off and on!
Quick Reference
To Turn Off Effort Driven
Scheduling for a Single
Task:
• Select a task, click the
Task Information button,
select the Advanced tab,
and uncheck the Effort
driven check box.
To Turn Off Effort Driven
Scheduling for All New
Tasks:
• Select Tools →
Options from the menu,
click the Schedule tab,
and uncheck the New
tasks are effort driven
check box.
72 Microsoft Project 2000
Task Information
button
Figure 2-24
Deadlines are very helpful in project management. Not only are they a project goal to shoot
for, but they also help Project indicate whether a task has been completed on schedule. It’s
important to understand that setting a deadline doesn’t affect how tasks are scheduled, but you
can adjust a task schedule to meet a deadline, if you want.
Task constraints are also helpful in scheduling tasks. They help specify when a task should
You can drag the begin or end. There are different types of constraints as well: flexible, moderate, and
deadline arrow on the inflexible. Each type of constraint is used differently.
Gantt Chart to change
the deadline date. 1. Select Develop budget estimate task 17 and click the Task
Information button on the Standard toolbar.
The Task Information dialog box appears.
2. Click the Advanced tab.
Now you can enter the deadline date for this task.
3. In the Deadline box, select May 31, 2000, and click OK.
A small green deadline arrow appears on the Gantt Chart for the task “Develop budget
estimate”.
Now add a constraint to a task.
4. Select Plan honeymoon task 55, click the Task Information button on
the Standard toolbar, and click the Advanced tab.
The Advanced tab of the Task Information dialog box appears.
Let’s add a constraint to make sure the honeymoon planning is done the day before the
wedding.
5. Click the Constraint type list arrow and select Finish No Later Than
from the drop-down list.
Now enter the date that the task must finish no later than.
Figure 2-25
At some point, you will probably want to use a different calendar for a task than the base
calendars available in Project. This lesson will show you how to assign a different calendar to
a task.
This project has already been inserted into this project or another master project.
Lesson Summary
Enter a Task
• Type the task’s name in the Task Name field, and press <Enter>.
Create a Milestone
• Enter a duration of 0 (zero) days for a task. Or, click the Task Information button and select the
Advanced tab, check the Mark task as Milestone checkbox, and click OK.
• To Move a Task: Select the task and then click it once more so the pointer turns from a to a
, and drag the task to a new location.
• To Delete a Task: Select Edit → Delete Task from the menu, or select the task and push the
Delete key, or right-click the task and select Delete from the shortcut menu.
• To Insert a Task: Click the task you want your new task to appear on top of, go to the Insert
menu, and choose New Task, or right-click the number to the left of a task, and choose New Task,
or push the Insert key.
• To Enter a Note for a Task: Select a task and click the Task Notes button from the Standard
toolbar, or right-click the task and select Task Notes, or click on the Notes tab in the Task
Information dialog box.
Splitting Tasks
• To Split a Task: Select the task and click the Split button, then use the dividing tool to choose a
splitting spot in the task’s Gantt bar, and click it.
• To Remove a Split: Drag the split portions until they touch.
Adding Deadlines
• To Enter a Task Deadline: Click the task you want to add a deadline to and click the Task
Information button, click the Advanced tab and enter a deadline into the Deadline box.
• To Change the Deadline Date: Drag the deadline arrow on the Gantt Chart to a different date.
Quiz
1. Which of these is NOT a task type?
A. Fixed Duration
B. Fixed Units
C. Fixed Work
D. Fixed Budget.
2. When you click a linked task it jumps to the task to which it is linked. (True
or False?)
7. What is a milestone?
A. The last task you need to complete for your project to be finished
B. A task that signifies a major event in your project
C. A task that is behind schedule
D. Road markers that Fred, Barney, Betty, and Wilma used
Homework
1. Start Microsoft Project 2000.
2. Navigate to your practice files and open the Homework 2 database.
3. Go to task #23, “Go International,” and make it a summary task. The three tasks
below it will be its subtasks.
4. Enter a new task above task #12. Name the new task “Make tablecloth from
bedsheets.”
5. Enter a duration of 3 days for your new task.
6. Delete task #15, “Dress up in a lemon costume.”
7. Select Tools → Change Working Time and make Monday, January 28, 2002 a
nonworking day.
8. Insert a recurring task above task #23. Name the task “Mail “Lemon Leader”
newsletter,” have it occur monthly on every 1st Friday, have it start on February 4,
2002, ending after 5 occurrences.
9. Edit task #20, “Hire a CEO,” so that it says “Hire a rich CEO.”
10. Make task #6, “Make a pretty sign,” into a milestone.
11. Unlink tasks #3 and #4.
12. Give task #5, “Build stand,” a deadline of February 14.
13. Split task #15, “Hang signs around town.”
14. Close Homework 2 without saving changes.
80 Microsoft Project 2000
Quiz Answers
1. D. Fixed budget is not a task type.
2. False. In Project 2000, linked tasks are tasks which depend on each other for scheduling
reasons.
3. C. Put a question mark after a task’s duration if you are estimating the duration.
4. B. To delete a task, right-click the task and select Delete from the menu.
5. A. The Summary task organizes subtasks into a phase.
6. False. A recurring task repeats regularly, not irregularly.
7. B. A Milestone is a task that signifies a major event towards the completion of your
project.
8. B. Splitting a task allows you to interrupt the task and finish it on a later date.
Tasks cannot be completed without resources. Resources are the people, material, and
equipment needed to complete a project. When you assign a resource to a task, Project 2000
looks at the resource’s cost and availability. Cost refers to how much money a resource will
require. Availability establishes when a resource can work on a task, and for how long. Project
does a terrific job of managing the resources assigned to tasks.
Assigning resources to tasks helps to keep things organized in the project. For example, you
don’t want to accidentally schedule a task to be done when a resource isn’t available, or forget
to find someone to complete a certain task. Setting up resources is well worth the time if you
have deadlines or money constraints for your project. If you don't enter resource information,
Project calculates your schedule using only task duration and dependencies.
82 Microsoft Project 2000
Figure 3-1
The resource sheet is a list of resources for your project. You can assign a resource to a task
without entering the resource in the resource sheet, but that’s not recommended. Instead, enter
all of your resources in the resource sheet before you assign them to tasks so you have
organized resource records.
Resource sheets consist of two types of resources—work resources and material resources.
Work resources are the people and equipment that complete project tasks. Material resources
are the goods needed by the work resources to complete tasks. For example, say that orange
chiffon bridesmaid dresses are going to be hand-made for the wedding. The work resource
would be a seamstress or tailor, and the material resources would be fabric, thread, orange
sequins, etc.
Enter some resources in the resource sheet for the wedding project.
Resource Sheet 1. Navigate to your practice folder and open Lesson 3A. Save the file as
button Resource List.
If you don’t know where your practice files are, ask your instructor.
2. On the View Bar, click the Resource Sheet button.
The blank Resource Sheet appears. Go ahead and start filling it up.
Other Ways to Open the 3. Type Mrs. Fru Fru in the first line of the Resource Name column and
Resource Sheet: press <Enter>.
• Select View → Mrs. Fru Fru is the wedding planner, so she will have some big contributions to the
Resource Sheet project.
from the menu.
Add a few more resources to the list.
4. Type the following resources in the list:
Johnson/Anderson families
Fatman Buns n’ Rolls
Orange sequins
In case you need to insert a resource in the middle of a list, insert a new resource like If you choose not to
you would a new task in the task list. Notice that Project automatically assigns an add resources into the
initial to each resource when it is entered. This information is used in baseline and resource sheet before
interim plans, used to track the progress of the project. you assign them to
The next step is to designate the resource type. There are two types to choose from: tasks, select Tools →
work and material. Options from the menu
and click the General
5. Go to the orange sequins Type cell. Click the list arrow in the cell.
Tab. Check the
The default resource type is Work. The list arrow doesn’t appear until the cell is “Automatically add
selected. All the other resources you’ve entered are work resources. Orange sequins are new resources” option,
a material resource, however. and Project will then
6. Select Material from the drop-down list and press <Enter>. add resources into the
Notice that the following fields change according to the resource type. resource sheet as they
7. Place the cursor in the Material Label field, and type 1 oz. bags. are assigned to tasks.
A “Material Label” is the unit you use to measure a material resource. You’ll keep
track of your usage of sequins by how many 1 oz. bags you buy.
Next, let’s explore the Max. Units field.
8. Go to the Fatman Buns n’ Rolls Max. Units field, and make sure that
100% is selected.
The Max. Units field represents the maximum capacity of a resource to finish a task.
Giving the bakery a 100% max means that the bakery will give 100% of its time to
completing a task. If you wanted the bakery to complete two tasks at one time, you
would assign it a 50% max. (50% x 2 tasks = 100%).
Last, enter a more recognizable abbreviation for this resource.
9. Go to the Initials field, and type FBR and press <Enter>.
That’s all there is to entering basic resource information.
Don’t worry about entering costs with your resources yet; we’ll cover that later.
Quick Reference
To Create a Resource
Sheet:
• On the View bar, click the
Resource Sheet button
and then enter resources
and fill in the respective
fields.
To Open the Resource
Sheet:
• Click the Resource
Sheet button.
Or…
• Select View →
Resource Sheet.
84 Microsoft Project 2000
Figure 3-2
Most resources in a project will not be needed for the duration of the entire project. Therefore,
you can enter resource availability; the dates when the resource will be needed. In other
words, it’s like entering the start and finish dates for the resource.
6. Select the second cell in the Available From field and enter 12/11/00.
Leave N/A in the Available To field.
By leaving the Available To cell as “N/A”, Project assumes the resource will be
finished at the Project’s end date.
The bakery will work on baking the cake during these dates, but at a different percent
of units available. There aren’t any other projects going on that week, so they can work
full force on the wedding cake.
7. Enter 100% in the Units cell and press <Enter>. Click OK.
The bakery will work on the wedding cake with their full resources from 12/11/00 to
the project end date.
Note that there's a distinction between differing resource availability and work
contours. The Resource Availability table adjusts maximum unit availability
throughout a project, while work contours adjust varying levels of work throughout a
specific assignment.
While the Resource Availability table changes a resource’s maximum units over the life
of the project, it does not change resource rates over time. To set differing resource
rates, set the resource cost table. You can do this on the Costs tab of the Resource
Information dialog box.
8. Close the project file.
Quick Reference
To Enter Resource
Availability:
1. Select the resource.
2. Click the Resource
Information button on
the Standard toolbar.
3. Enter the Available To and
Available From dates in
the Resource Availability
table.
4. Enter the Maximum Units
available in the Units field.
86 Microsoft Project 2000
Figure 3-3
The resource is
grouped with the other
resources in the group.
Figure 3-4
Although you can’t assign a group of resources to a single task, it is helpful to organize
resources into logical groups for organizational purposes. Just enter a group name for the
resource, and you can easily sort resources by using resource groups.
1. Navigate to your practice folder and open Lesson 3B. Save the file as
Resource List.
If you don’t know where your practice files are, ask your instructor.
2. Click on the Resource Sheet button in the View bar to open the
resource sheet.
Grouping allows you to view how resources are related, similar to outlining the task
list. In fact, it may be a good idea to group resources by the summary tasks in which
they are used.
Assign the first resource to a group. Notice that other resources have already been
given groups.
3. Click in the Group field for the first resource, Harry (bestman).
Resource Sheet
Harry is going to pick up the tuxes for everyone on the wedding day. button
4. Type Ceremony attire in the Group field and press Enter. Other Ways to Open the
Resource Sheet:
Giving a resource a group is easy, isn’t it?
• Select View →
Now see how the resource sheet changes when you group the resources. Resource Sheet.
5. Select Project → Group by: → Resource Group from the menu.
There—your resources are now sorted into groups on your resource sheet, as shown in
Figure 3-4.
If you want to ungroup your resources and go back to viewing them in the order they were
entered, go to Project → Group by: → No Group.
Quick Reference
To Group Resources:
1. Make sure you are in
Resource Sheet view.
2. Enter group names in the
resources’ group fields.
3. Select Project → Group
by: → Resource Group
from the menu to group
the resources.
88 Microsoft Project 2000
Figure 3-5
You should have already defined a project calendar for your project. Thus, your working time
and nonworking time are set. But did you know you can change the calendar for just one
Resource Sheet resource? Changing a single resource’s calendar comes in handy when you have a resource
button that works different hours than your other resources, or when a resource takes a vacation.
One of your resources, Grandma Jeanette, is going to Las Vegas for a week in May. You’d
better change her resource calendar so you don’t accidentally schedule her to help you pick
out tuxes during the time that she’s away. Change Grandma Jeanette’s resource calendar.
1. Click the Resource Sheet button on the view bar to open the resource
sheet.
Select a resource.
2. Click on the Grandma Jeanette resource in the family help group.
Now open this resource’s calendar.
3. Select Project → Resource Information from the menu.
The Resource Information dialog box appears.
4. Select the Working Time tab, and scroll through the calendar window
until you come to May 2000.
You are ready to change the calendar.
5. Press the <Shift> key and select May 15th through the 19th, as shown in
Figure 3-5.
Make the days you just selected into nonworking time.
6. Click the Nonworking time bullet to the right of the calendar. Other Ways to Open the
Resource Information
NOTE: If you had clicked the “Use default” bullet, the selected days would return to Dialog Box:
the Project Standard calendar default, which is Monday through Friday, 8:00
A.M. to 12:00 P.M., and 1:00 P.M. to 5:00 P.M. If you had clicked the • Click on a resource and
“Nondefault working time” bullet, you could have changed your resource’s press <Shift> +
working hours in the “From” and “To” boxes. <F2>.
7. Click OK.
If you try to assign a resource to a task during the resource’s nonworking time, the task An alternative to
will be moved or extended to the next available working time for the resource. changing the working
time schedule would be
Whew! Now Grandma Jeanette can be a high roller for a week before you need her assistance to create a new
with tuxes. calendar and assign it
to the resource.
Quick Reference
To Change a Resource
Schedule:
1. Select the task and click
the Resource
Information button on
the Standard toolbar.
2. Click the Advanced tab.
3. Click the Calendar list
arrow and select a
calendar from the drop-
down list.
90 Microsoft Project 2000
Figure 3-7
If you want a task done, you must assign a resource to do it. After you assign resources to
tasks, you can change the assignments at any time. In this lesson, we’re going to deal with
Assign Resources work resources.
button
You really want to complete all of your wedding project tasks, so you’d better start assigning
resources to the tasks.
3. Select the Cal’s Calligraphy resource from the Assign Resources dialog
box. Click the Assign button.
A checkmark and 100% appear next to the “Cal’s Calligraphy” resource as shown in
Figure 3-6.
NOTE: “100%” automatically appears next to a resource when you assign it to a task.
This means that 100% of a resource’s time will be devoted to the task on the
days the task covers. In other words, the resource will be working full-time.
You can lower the percentage if you want that resource to work on more than
one task in a given day, or if you just want them to work part-time.
4. Click the Close button. Did you know you can
replace one resource
The resource has been assigned to the “Address invitations” task. To view the resource
with another? Just
assignment, scroll to the right until you see the end of the task bar for the “Create guest
list” task. The name of the resource should be listed after the task bar, as shown in select the task whose
Figure 3-7. resource you want to
replace and press the
NOTE: If you accidentally assign a resource to too many tasks, the overallocated Assign Resources
resource will be shown in red in resource views. You will learn more about button. Then, in the
balancing overallocated resources in another lesson. Assign Resources
Don’t assign multiple work resources to a task just yet; multiple work resource assignments dialog box, select the
are slightly different than single work resource assignments. For more information about assigned resource,
assigning multiple work resources to a task, see the chapter on Effort driven scheduling and click the Replace
multiple work resources. button, select a new
resource(s), and click
OK.
Quick Reference
To Assign Work
Resources:
• Select a task and click the
Assign Resources
button, then select your
work resources and click
Assign.
To Replace One Resource
with Another:
• Select the task whose
resource you want to
replace, click the Assign
Resources button, select
the assigned resource,
click Replace, select a
new resource, and click
Assign.
92 Microsoft Project 2000
Figure 3-9
It’s good to assign material resources to tasks so you can see how much material you are
using, and at what cost. For example, the wedding will be on a fish farm in South Dakota, so
you’re keeping with the wedding theme by having fish nets all over the place in the reception
hall and gummi worms with fish hooks through them as favors at the reception. Project will
keep track of how many bags of gummi worms you use, what the total costs of the fish nets
are, etc.
In this lesson, assign the material resources needed to sew the bridesmaid dresses.
1. Select task 38, Sew bridesmaid dresses, and click the Assign
Assign Resources Resources button.
button
The Assign Resources dialog box appears.
2. In the list of resources, select Orange chiffon fabric and click the
Assign button.
You have assigned the “Orange chiffon fabric” resource to the task, but you must also
enter how many yards of the orange chiffon fabric you need.
3. In the Units field next to “Orange chiffon fabric,” type 25 yards, and
press Enter.
Now assign the “orange sequins” material resource to the same task.
4. In the list of resources, select orange sequins and click the Assign
button.
Enter the number of 1oz. bags of sequins you need.
5. In the Units field next to “orange sequins,” type 5 and press Enter.
You have just assigned two material resources to the “Sew bridesmaids dresses” task.
There should be checkmarks next to the material resources you assigned, as shown in
Figure 3-8.
6. Click the Close button.
The Assign Resources dialog box closes and the names of the material resources you
just assigned appear at the end of the “Sew bridesmaid dresses” task bar, as shown in
Figure 3-9.
7. Close the file without saving your changes.
Quick Reference
To Assign Material
Resources:
1. Select a task.
2. Click the Assign
Resources button.
3. Select the material
resources for your task.
4. Enter how many units of
each resource you need.
5. Click the Assign button.
6. Click Close.
94 Microsoft Project 2000
Figure 3-10
If you want a project done right, you have to budget wisely. However, the majority of us are
not accountants or bookkeepers. Thankfully, Project 2000 lets you enter resource costs and
then calculates amount totals for you. There are three different types of costs in a project: rate-
based, per use and fixed. You will learn how to use rate-based and per use costs in this lesson.
1. Navigate to your practice files and open Lesson 3C. Save the file as
Resource List.
Resource Sheet
button If you don’t know where your practice files are, ask your instructor.
2. Click the Resource Sheet button.
Enter a rate-based cost for a work resource.
3. Go to resource 6, All-80’s DJ Team and click in the Std. Rate field.
This is where you enter the pay rate for the awesome “All-80’s DJ Team” resource. See
Table 3-1: Cost Entry Fields for a description of Std. Rate and the other fields in which
you can enter costs. The resource works at the rate of $150/hour, so enter the rate in the
field.
4. Type 150/hr and press Enter.
The cost “$150.00/hr” appears in the Std. Rate field. That was easy, wasn’t it?
Now enter a per use cost.
5. Go to resource 10 Mambo Mania Dance Studio and click in the
Cost/Use field.
This service costs $30 for each class.
Figure 3-11
A Fixed Cost is the cost of a task, no
matter what the duration or amount of
work involved is.
Fixed costs are different from rate-based or per use costs. Fixed costs don’t change if the
duration or amount of work needed to complete a task change. Assign a fixed cost to a
resource in this lesson.
Resource Sheet
button
Figure 3-11
Are you beginning to lose track of your numerous wedding expenses? Are you over or under Other Ways to View
your project budget? Or do you just want to see an overview of your task and resource costs? Costs:
If you answered yes to any of these questions, take advantage of Project’s awesome cost view • Select View menu→
abilities. Task Usage →
Format menu →
1. Click the Resource Sheet button in the View bar. Details → Cost.
Specify that you want to look at costs.
NOTE: If you wanted to see your task costs, you would go to the View bar, click More Quick Reference
views, and select Task Sheet.
2. Select View → Table → Cost from the menu.
To View Costs of Tasks or
Resources:
The costs are listed for you, as shown in Figure 3-12.
• Make sure you are in
3. Close the file without saving your changes. Resource Sheet view,
and then select View →
Table → Cost from the
menu.
Or…
• Select View → Task
Usage → Format menu
→ Details → Cost.
98 Microsoft Project 2000
Lesson Summary
Creating a Resource Sheet
• To Create a Resource Sheet: On the View bar, click the Resource Sheet button and then enter
resources and fill in the respective fields.
• To Open a Resource Sheet: Click the Resource Sheet button, or select View → Resource
Sheet from the menu.
Grouping Resources
• To Group Resources: Make sure you are in Resource Sheet view, enter group names in the
resources’ group fields, and select Project → Group by: → Resource Group from the menu to
group the resources.
Entering Costs
• To Enter Resource Costs: Make sure you are in Resource Sheet view and enter amounts in the
Std. Rate field, the Ovt. Rate field, or the Cost/Use field. Then, choose when you’d like to start
accruing the resource cost in the Accrue At field.
Viewing Costs
• To View Costs of Tasks or Resources: Make sure you are in Resource Sheet view, then select
View → Table → Cost from the menu. Or, select View menu → Task Usage → Format menu
→ Details → Cost from the menu.
Quiz
1. What are the two types of resources?
A. Work and Cost.
B. Work and Written.
C. Work and Material.
D. Oil and Coal.
2. You can’t change the working calendar for just one single resource. (True
or False?)
6. You can’t assign more than one resource to a task. (True or False?)
Homework
1. Start Microsoft Project 2000.
2. Navigate to your practice files and open the Homework 3 database.
3. Go to Resource Sheet view, and add a work resource named “Mom” who works for
$0.50 an hour. Enter “employees” in the Group field for this resource.
Quiz Answers
1. C. The two types of resources are work and material.
2. False. You can change a single resource’s working calendar.
3. A. Mrs. Rate is not a cost entry field.
4. D. A fixed cost does not change, even if the amount of work, materials or duration change
to finish the task.
5. B. Overallocated resources appear in red.
6. False. You can assign more than one resource to a task.
7. C. Quanto is not a type of project cost. The types of project costs are Current, Baseline,
Actual, and Remaining.
Chapter Four:
Viewing the Project
Database
Chapter Objectives: ; Prerequisites
• Use Common Views, More Views, and Split Views • Have a project in which
you have entered tasks,
• Use Tables and Filters resources, and costs
• Know the basic
• View Sorted and Grouped Information
elements of the Project
• View the Project’s Critical Path 2000 screen
Chapter Task: View your project from many angles and learn to
organize the information you view.
One of Project 2000’s best attributes is that it lets you view project information from dozens
of different angles. This chapter is pretty cut-and-dry; it shows you some common ways to
view various aspects of the project’s information, such as resource overallocation, the critical
path, and task or resource details. This chapter also shows you different ways to organize
information with filters, groups, and fields.
104 Microsoft Project 2000
Views
bar
Figure 4-1
So, you’ve been using the Project screen for a while now, but still haven’t used all the views
available. If you’ve been following along, you’ve learned that certain views are better than
other for performing specific tasks. For example, Resource Sheet view is better for inserting
resources than Network Diagram view.
The default view for Project is the Gantt Chart view, which is also the view you will probably
use most often. There are many other views in Project, and they can be broken down into two
basic types of views: task views, and resource views. Task views display information about
tasks in a project. Resource views display information about resources in a project. These
different views allow you to work with your project’s data more easily, depending on what
you want to do. This lesson will show you how to switch views, and help you understand
what different views are best used for.
Figure 4-2
Most of the time you will be able to see the information you need in one of the common
views. When you need to be more specific about the information you view, however, try using
More Views one of the views available in the More Views dialog box.
button
1. Scroll to the bottom of the View bar and click the More Views button.
The More Views dialog box appears with more views to choose from, as shown in
Figure 4-2.
2. Scroll down the list, select Tracking Gantt from the list, and click Apply.
The project is shown in Task Entry view, which is half Gantt view, half task details and
information. Return to the default Gantt Chart view.
3. Click the Gantt Chart button in the View bar.
Refer to the table below to see a description of each view.
Figure 4-3
Figure 4-6
You may find that a single view does not display all the information you want to see. In these
instances you will want to use a split view. A split view displays two views of the project in
the same window. For example, you could display Gantt Chart view in the top half of the
window and Task Usage view in the bottom half of the window.
This lesson will show you how to use a split view.
Notice that the bottom view isn’t a view you’ve seen before. This is Form View, which
is the default view when a window is split. It displays more information on the selected
task or resource in the top view. Right-click the Form View to see different information
about the selected resource or task. Refer to
2. Click in the bottom pane of the window.
To display a different view in the pane, you must first select it.
3. Click the Tracking Gantt button in the Views panel.
The Tracking Gantt view is displayed for the task selected in the top view.
4. Scroll down the task list in the Gantt Chart top panel and select task 10
Reception sites and catering.
The Tracking Gantt view in the bottom pane displays the task and the amount of work
performed on the task.
As you begin tracking and making changes to your project, you will find splitting
views to be more useful.
5. Select Window → Remove Split from the menu.
Figure 4-6
Figure 4-5
Tables are great because they allow you to view only the fields that you want to view. A table
is a group of data, organized into rows and columns. Just as there are two main types of
Gantt Chart views, there are two main types of tables: Task tables can be applied to task views, and
button resource tables can be applied to resource views.
1. Make sure you are in Gantt Chart view. Select View → Table → Work
from the menu.
Notice that the second column, “Duration”, changes to “Work”. Scroll to the right in
the sheet and view the other fields available in the Work table. Tables are fairly easy to
figure out. Each table is named by the information it focuses on. For example, this
table focuses on how much work is done in the project. The different fields in each
table are easier to see in a spreadsheet view. Go back to the original table.
2. Select View → Table → Entry from the menu.
You are back to your original table in Gantt Chart view.
The table below lists all the tables from the common views in the Views bar.
Sorting resources isn’t much different from sorting tasks. The only difference is that there are
different sorting types you can use. Refer to the following table, Table 4-7: Resource Sort
Types, for information on the resource sorting options.
Quick Reference
To View Sorted
Information:
• Select Project → Sort,
and then choose a sorting
option.
To Cancel a Sort:
• Select Project → Sort
→ by ID to return to the
default sort.
114 Microsoft Project 2000
Figure 4-8
Figure 4-9
We’ve touched upon filtering tasks and resources in previous lessons, but this lesson will
concentrate solely on grouping. Grouping is handy for organizing so you can focus on a
variety of project angles.
Like filters in the previous two lessons, tasks and resources can be grouped. This lesson
reviews grouping by tasks, and the following lesson reviews grouping by resources.
1. If necessary, navigate to your practice files and open Lesson 4. Save the
file as Project Views.
If you don’t know where your practice files are, ask your instructor.
You can group the project by task or resource, but for this lesson group by task.
2. If necessary, click the Gantt Chart button in the Views panel.
The project displays the tasks in the project.
Figure 4-10
Figure 4-11
Once again, this lesson will concentrate on grouping, but with resources this time. Grouping is
handy for organizing information into significant groups so you can focus on a variety of
project angles.
1. If necessary, navigate to your practice files and open Lesson 4. Save the
file as Project Views.
If you don’t know where your practice files are, ask your instructor.
For this lesson, group by resource.
2. Click the Resource Sheet button in the Views panel.
The project displays all the resource in the project.
3. Select Project → Group by from the menu.
Who knew there were so many ways to group the project’s resources? Only one way to
group tasks will be used in this lesson, but you can refer Table 4-9: Resource Group
Types to see a description of all the different ways to group resources.
Figure 4-14
Applying a filter to a view can let you focus on specific information. When you use a filter, it
will show or emphasize tasks that only meet the filter criteria. There are two different ways
you can filter a project: by its resources, and by its tasks. In this lesson, we will explore how
to filter using tasks.
1. Make sure the project is in Gantt Chart view, so that the project’s tasks
are displayed.
Gantt view is the default view and it displays all of the project’s tasks.
2. Select Project → Filtered for: from the menu.
A list of all the different types of filters you can choose from appears, as shown in
Figure 4-12. Refer to Table 4-10: Task Filters for a description of all the options
available.
There are two basic types of filters you can use:
• Interactive filter: Displays a dialog box for entering filter criteria each time you
apply the filter. Interactive filters are followed by an ellipses in the menu.
• Highlighting filter: Displays all tasks or resources and highlights the tasks or
resources that match the filter criteria.
Try using an interactive filter to define a date range filter.
Figure 4-17
Filters are useful views that allow you to focus on specific information in a project. When you
use a filter, it will show or emphasize tasks that only meet the filter criteria. In this lesson, you
will explore the second way to use filters; resource filters.
• Interactive filter: Displays a dialog box for entering filter criteria each time you
apply the filter. Interactive filters are followed by an ellipses in the menu.
• Highlighting filter: Displays all tasks or resources and highlights the tasks or
resources that match the filter criteria.
Use another interactive filter in this lesson.
4. Select Resource Range from the Filter menu.
The Resource Range dialog box appears. Specify the range you want to view in the
dialog box.
5. Type 2 in the first text box, and type 10 in the second text box of the
dialog box, as shown in Figure 4-16.
Every resource that is between these ID numbers will appear in the filter.
6. Click OK.
The 2-10 IDs appear, as shown in Figure 4-17.
Now turn the filter off using a highlight filter.
7. Select Project → Filter for: → All Resources from the menu.
You are back to the default view with no filters.
Figure 4-19
If you finished the previous lesson, you already know how to use the interactive and highlight
filters. Now try using the AutoFilter option, which is both an interactive and a highlighting
filter.
4. Click outside the Resource Name list to close it. Click the Type list
arrow.
Only four entries appear: Work, Materials, All and Custom. Notice that the Type
heading appears in blue, indicating that is has been used as filter criteria.
5. Select Material from the drop-down list.
Only the material resources appear in the project window.
AutoFilters are useful because they are easy to use, especially if you are searching for
specific information, but aren’t sure what the criteria is. For example, you can filter the
material list you just created so it is even more specific.
6. Click the Group list arrow. Select Reception from the drop-down list.
Now the project is filtered so that the only resources shown are materials that will be
used at the reception. Pretty cool, eh?
Now return off the filter.
7. Select Project → Filtered for: → AutoFilter from the menu.
The filters you specified are turned off, and all the resources are shown once again.
Quick Reference
To Use the AutoFilter:
1. Select Project →
Filtered For: →
AutoFilter from the
menu.
2. Click the drop-down list
button of the category by
which you want to filter
the project.
3. Select the criteria by
which you want to filter
the project from the list.
124 Microsoft Project 2000
Noncritical
tasks (blue)
Critical tasks
(red)
Figure 4-20
In a project schedule, some tasks affect the overall project length more than others do. These
tasks, called critical tasks, must be completed on time so that the project sticks to its schedule.
If a task has no slack time, it is a critical task. If a task has some slack time, it is not a critical
task.
The critical path is the series of critical and noncritical tasks that will push a project’s
schedule further back if the tasks are not completed. If you want to shorten the duration of a
project, you have to shorten the critical path. Over the life of a project, the critical path will
change from time to time. Take a look at the storybook wedding project’s critical path.
5. Select View → Zoom from the menu. Click Entire Project, and click OK,
as shown in Figure 4-20.
Now you can see critical tasks over the entire range of your project.
Return to the Gantt Chart view.
6. Click the Gantt Chart button in the Views panel.
That’s it! Now make sure that you and your resources complete those critical tasks by viewing
your project’s status.
Quick Reference
To View the Critical Path:
• Select View → More
Views, select Detail
Gantt, and click Apply.
To View Only Critical
Tasks:
• Select Project →
Filtered for: → Critical
from the menu.
126 Microsoft Project 2000
Figure 4-21
Click the Previous Click the Next button
button to view the to view the next
next entry’s entry’s information.
information.
Other Ways to View the Because Project is so powerful, it’s easy to lose track of who is assigned to what task and the
Task Form:
amount of time the task will take. It can sometimes be hard to find information for a task and
• Select a task and select its resources when you need it quickly.
Window → Split from
the menu. Select a task from the wedding project and view its details.
Lesson Summary
Using Common Views
• Select a new view from the View bar, or go to the View menu and select a new view, or press
<Alt> + <V> and then the underlined letter in a new view.
Using Tables
• Select View → Table from the menu, and select the table you want to view.
Using AutoFilters
• To Use the AutoFilter: Select Project → Filtered For: → AutoFilter from the menu. Click the
drop-down list button of the category by which you want to filter the project and select the criteria
by which you want to filter the project from the list.
Printing a View
• To Print a View: Open the view you want to print and select File → Print from the menu. Choose
your print options. When you are ready to print, click OK.
Quiz
1. Tasks that affect the overall project length more than other tasks do are
called what?
A. Subtasks
B. Major Tasks
C. Critical tasks
D. All tasks affect the project equally
2. You can view the entire length of your project on one screen. (True or
False?)
Homework
1. Start Microsoft Project 2000.
2. Navigate to your practice files and open the Homework 4 database.
3. View this project’s critical path, and then go back to the default view.
4. Use zoom to view your entire project.
5. Make the project window split so that the Gantt Chart is in the upper half of the
window and the Task Form is in the bottom half of the window.
Quiz Answers
1. C. Critical tasks affect the project more than other tasks do.
2. True. Yes, the length of your project can be condensed into one screen.
3. B. There is no such thing as sifting information in Project 2000.
4. False. You can change fields in a view by going to View → Table, and choosing a table
option.
5. D. Calendar view is the easiest view to print out by the month.
Chapter Five: Update
and View Project
Progress
Chapter Objectives: ; Prerequisites
• Update Tasks, Resources, and Costs • Have a project in which
you have entered tasks,
• Check Duration, Work and Cost Variance resources, and costs
• Understand project
• View Project Statistics
management
• Check Earned Value
• Identify and Fix Project Trouble Spots
When you’re done customizing and entering tasks, resources, and costs into your project, you
can you sit back and ignore your project for a few weeks, right?
Wrong! Even though Project 2000 calculates your task durations, budget, etc. for you, you
still need to track the progress of your project. You’ll need to update your tasks, make sure
resources aren’t working to slow or too fast, and monitor a variety of other things. Also,
tracking allows you to look up specific information, like how much you spent on resources on
a particular day, etc. If you keep your project information up to date, you can always see the
most recent status of your project, which allows you to catch problems before they get out of
hand. This chapter shows you many ways to track your project.
Let’s start entering progress and tracking your project information!
136 Microsoft Project 2000
1. Navigate to your practice files and open Lesson 5A. Save the file as
Wedding Progress.
If you don’t know where your practice files are, ask your instructor.
Type the percentage of the task that is complete to indicate the actual progress of the
task. Then, Project calculates the task's actual and remaining duration using this
number. If you enter a percentage for summary tasks, the progress is distributed to its
subtasks.
An actual duration is 2. Select task 55 Plan Honeymoon, and select Tools → Tracking →
the amount of duration Update Tasks from the menu.
work already done,
The Update Tasks dialog box for this task appears. Enter a completion percentage for
while a remaining
the task 55.
duration is the amount
of duration work left. 3. Type 30% in the % Complete text box.
It’s very important to monitor tasks that finish early or late, because they can make
significant changes to your schedule. Tasks that finish early allow resources to be
reassigned to work on other tasks. Tasks that finish late throw off the schedules for the
tasks after them. If you can, enter actual start and finish dates for your tasks on a
regular basis to keep your schedule up to date.
4. In the Start text box, type 5/8/00, because you started this task five days
later than you had scheduled. Click OK.
The Update Tasks dialog box closes and you return to the Gantt Chart. Notice two
things: the “Plan Honeymoon” task has been marked 30% by a black bar in its task bar,
and the task bar has been moved to show a starting date of 5/8/00.
If you have a task that you know will take more or less time to finish than you had
originally planned, you should enter either an actual or a remaining duration for that Quick Reference
task. Keeping up on your tasks’ durations allows your project’s schedule to run much To Open the Update Task
smoother and allot time for delays or problems. dialog box:
5. Select View → Toolbars → Tracking from the menu. 1. Select the task you want
The Tracking toolbar is a good tool to use when updating the progress in the project. to update.
6. Select task 49, Ask attendants to be in wedding, and click the Update 2. Select Tools →
Tasks button on the Tracking toolbar. Tracking → Update
The Update Tasks dialog box appears. Enter a remaining duration for this task. Tasks from the menu.
7. In the Remaining dur text box, type 3 weeks. Click OK. Or…
The duration for task 49 changes from 2 weeks to 3 weeks. 1. Select View → Toolbars
Next, change the actual duration for the “Find a Wedding Dress” task. → Tracking from the
8. Select task 30 Find wedding gown, and click the Update Tasks button. menu.
The Update Tasks dialog box appears. You have just finished two weeks of work, so 2. Select the task you want
update this task! to update, and click the
9. In the Actual dur text box, type 2 weeks. Click OK. Update Tasks button on
the Tracking toolbar.
Task 30 is now 50% complete, because two weeks of work out of the one-month
duration has been completed. To Update Task
Now, what if you want to update a task’s work for just one day? You’re in luck; Percentages:
changing a task’s work time period in a timephased field lets you update task work for 1. Update the task
a particular day or week. completion percentage in
10. Click the Task Usage button in the Views panel. the Update Tasks dialog
box.
You are in Task Usage view, and want to look at actual work for a task.
11. Select Format → Details → Actual Work from the menu. To Update Tasks with
Dates:
Now enter new actual work for the “Fit bridesmaid dresses” task.
1. In the Start textbox, type
12. Scroll down to task 42, Fit bridesmaid dresses, and click the Go To a new starting date.
Selected Task button on the Standard toolbar.
The insertion point jumps to the dates for the selected task. Now enter the new actual To Update Tasks with
work already performed for the task. Durations:
13. In the Actual work field, under Tuesday, 7/18/00, type 5 hours and press
1. Enter a Remaining dur
or an Actual dur for the
Enter.
task.
The actual work for task 42, “Fit bridesmaid dresses” has been updated.
To Update Tasks with
NOTE: When you enter actual work, the remaining work (if there is any) is divided Time Periods:
equally among the assigned resources, depending on their schedules.
1. Open Task Usage view.
2. Select Format → Details
→ Actual Work from the
menu.
3. In the Actual work field
for a task, type a time
period value.
138 Microsoft Project 2000
By updating the actual work that a resource has completed, you can track the progress of your
schedule through your resources. When you update a resource’s actual work, Project 2000
calculates remaining work by subtracting the actual work from the total work the resource is
scheduled to complete. This lesson will show you how to update actual work for individual
resources.
1. Click the Task Usage button in the View panel. Then select View →
Table → Work from the menu.
You are in the Work table in Task Usage view. Update actual work for Cal’s
Calligraphy.
2. Under task 46, Address invitations select the Cal’s Calligraphy
resource.
Now look at Cal’s Calligraphy Actual Work field, which says 30h. Cal worked another
five hours, so record the resource’s work.
3. Click the Actual field for Cal’s Calligraphy. Type 35 in the field and press
<Enter>.
You’re done; you have added five hours to Cal’s Calligraphy’s actual work.
Another way to track actual work is by time periods in timephased fields. Timephased
fields allow you to keep your resources up to date because you can enter information
for a particular day—or time period—in your schedule.
4. Click the Resource Usage button in the Views panel.
You are now in Resource Usage view. Choose to view a different table.
5. Select View → Table → Work from the menu.
Now view work details.
6. Select Format → Details from the menu and make sure Actual Work is You can change work
selected. for larger time periods
You are ready to update a timephased field, a field that is broken down to a specific (like weeks) by
time period such as a day or week. changing the range of
7. Select resource 25 Grandma Jeanette from the resource list and click time on the timescale.
the Go To Selected Task button on the Standard toolbar.
Look at the Act. W fields for resource 25. Grandma Jeannette has worked extra hard on
Thursday, so update her actual work.
8. In the Thursday 6/15/00 resource 25 Act. W field for Make wedding
favors, type 9 hrs.
Notice that the other work fields for resource 25 change to reflect the new actual work
hours.
Quick Reference
To Update Resources with
Actual Work:
1. Open Task Usage view.
2. Select View → Table →
Work from the menu.
3. Find the resource you
want to update
underneath its assigned
task, and enter the new
actual work value into its
Actual field.
To Update Resources with
Time Periods:
1. Open Resource Usage
view.
2. Select View → Table →
Work from the menu.
3. Select Format → Details
from the menu and make
sure Actual Work is
selected.
4. Find the Act. W field for
the time period where you
want to change work time.
5. Enter the new work value
in the Act. W field.
140 Microsoft Project 2000
Figure 5-4
In this view,
the timescale
has been
adjusted to
show weeks.
Even though Project automatically updates costs as tasks progress, there are times when you
might want to update your costs manually. For instance, your project might fall behind
schedule and throw your cost updating off, or you might need to enter a cost change very
quickly. Also, tracking actual costs by time period in timephased fields in Project keeps your
project up to date because you can update information for a single day, or for many days,
depending on how the timeline is formatted. This lesson will show you how to update costs
using both methods.
1. Click the Task Usage button in the Views panel. Select Tools →
Options from the menu and click the Calculation tab.
First, turn off the automatic updating option.
2. Uncheck the Actual costs are always calculated by Microsoft
Project checkbox, and click OK.
Now go to Task Usage view, and change the table.
You can enter cost
values for days, weeks,
or months.
Figure 5-6
Variance is the difference between baseline information and actual information in a field.
Project lists variance as positive or negative. Negative variance indicates that tasks are ahead
of schedule, and positive variance indicates that tasks are behind schedule. Negative or
positive variance in resource assignments can be good or bad. For instance, although it’s nice
when resources finish a task ahead of time, it may indicate that your resources have not been
allocated properly.
1. Navigate to your practice files and open Lesson 5B and save the file as
Quick Reference Wedding Progress.
If you don’t know where your practice files are, ask your instructor.
To Check Duration
Variance: 2. Click the More Views button in the Views panel, select Task Sheet from
the dialog box, and click Apply.
1. Select View → Table →
Variance from the menu. Now you can see more task fields on one screen.
2. Scan the Start and 3. Select View → Table → Variance from the menu.
Baseline Start fields for You are now in a Task Variance table view.
differing values, which Compare Start and Baseline Start fields.
indicate variance.
4. Look at the Start and Baseline Start fields for task #9, Research
3. Then, look at the Start Services.
Var. and Finish Var.
The Start and Baseline Start fields have different dates in them, indicating that there is
fields to see amounts of
variance.
variance calculated for
the start and finish of your 5. Look at the Start Var. and Finish Var. fields for task #18.
schedule. There is a negative variance of -0.75 in the Start Var. field, which means the task
started ahead of schedule. However, there is a positive variance of two days in the
Finish Var. field, which means the task is two days behind. Oops!
Figure 5-7
You can check how much total work a resource is accomplishing by looking at the variance
between a resource’s baseline work and actual work. This is especially helpful if you schedule
tasks based on the availability of resources. If you're managing resource assignments in your
project, you need to make sure resources complete task work in the time scheduled. Since
you've saved a baseline for your project, you can check the resource task work variance
information.
The variance
between the total
cost and the
baseline cost
Figure 5-8
By checking cost variance, you can see if there are any tasks that cost more than you
budgeted. You can catch cost overruns before they become serious and either adjust your
schedule or budget accordingly. Project calculates the cost of each resource’s work, the total
cost for each task and resource, and the total project cost, so checking variance lets you view a
lot of information.
1. Click the More Views button in the Views panel, select Task Sheet from
the dialog box and click Apply.
Now you can see more task fields on one screen.
2. Select View → Table → Cost tab.
Good—now compare the values in the Total Cost and Baseline fields. Is there any
variance (difference) between the fields?
Quick Reference 3. Look at the Total Cost and Baseline fields for task 9, Research
To Check Cost Variance: Services.
1. Open Task Sheet view. There is a variance of $600 between these fields. You will learn to deal with variance in
a later lesson. You’re done for now.
2. Select View → Table →
Cost from the menu. NOTE: One more thing—if you want to see cost variance information for the
3. Check the Variance field project rolled up into one task, display the project summary task. Go to
to view variance in the Tools → Options → View tab. Under options, check the Project summary
cost. task check box, and click OK.
Figure 5-9
3. Click the Close button and close the project file without saving changes. To View Entire Project
Costs:
Table 5-1: Project Statistics 1. Select Project →
Project Information from
Cost Description the menu.
Current The cost as it is right now. 2. Click the Statistics
Actual The cost that has been added up to date. For example, if a resource’s pay rate button.
is $10 an hour and it works five hours, the actual cost would be $50.
Baseline The project cost at the last time a baseline was saved for the project.
Remaining The estimated cost that has yet to be added up.
146 Microsoft Project 2000
Figure 5-11
Earned value indicates how much of your budget should have been spent based on your
baseline budget and the amount of work done so far. The Earned Value table allows you to
compare your expected progress with the actual progress you have accomplished. It compares
your tasks’ baseline schedules with actual schedules in terms of cost. The Earned Value table
also helps you predict whether tasks will finish under or over budget based on cost calculation
while tasks are in progress. For example, if a task is 25% complete and the actual cost of the
task calculated to date is $100, you can see if $100 is more than, less than, or equal to 25% of
the baseline cost that you budgeted for.
Quick Reference
To Check Earned Value:
1. Select View → Table →
More Tables from the
menu.
2. Select Earned Value
from the list and click.
Apply.
3. Check the fields for
various values, especially
BCWP (Budgeted Cost of
Work Performance/
Earned Value), SV
(Earned Value Schedule
Variance), and CV
(Earned Value Cost
Variance).
148 Microsoft Project 2000
Figure 5-13
You have put a lot of work into planning this wedding. Wouldn’t it be horrid if your resources
didn’t finish their tasks (like sending out invitations)? Use Tracking Gantt view to check your
project’s task bars; it shows the current schedule on top of the baseline schedule for each task.
The Tracking Gantt will help you find trouble spots in your schedule.
3. Scroll over in your Tracking Gantt until you get to about February 17 on
your timescale.
Look at task 33, “Create a Guest List.” Its top and bottom halves don’t match up, and it
is throwing off the rest of the tasks behind it. Change the constraint that is assigned to
this task so that it won’t be a trouble spot anymore.
4. Select task 33 Create a Guest List, click the Task Information button,
choose the Advanced tab, change the Constraint type to Start No Later
Than, and click OK. Task Information
button
The “Create a Guest List” task is no longer a trouble spot! Good thing the Tracking
Gantt pointed it out to you! Also, notice that many of the other tasks are no longer
critical tasks; that means you can be a bit more flexible with getting them done. You’re
all done with this lesson.
5. Close the file without saving changes.
Quick Reference
To Fix Project Trouble
Spots:
1. Open the Tracking Gantt
view.
2. Select View → Table →
Variance from the menu.
3. Change the constraint
type to resolve the trouble
spot.
150 Microsoft Project 2000
Lesson Summary
Updating Tasks
• To Open the Update Task Dialog Box: Select the task you want to update and select Tools →
Tracking → Update Tasks from the menu. Or, select View → Toolbars → Tracking from the
menu, select the task you want to update, and click the Update Tasks button on the Tracking
toolbar.
• To Update Task Percentages: Update the task completion percentage in the Update Tasks
dialog box.
• To Update Tasks with Dates: In the Start textbox, type a new starting date.
• To Update Tasks with Durations: Enter a Remaining dur or an Actual dur for the task.
• To Update Tasks with Time Periods: Open Task Usage view and select Format → Details →
Actual Work from the menu. In the Actual work field for a task, type a time period value.
• Remember that if you enter an actual finish date for a task, make sure the task is 100% complete.
• An actual duration is how much duration work you already have done, while a remaining duration is
how much duration work you have left.
Updating Resources
• Actual work is the amount of work you have already done.
• To Update Resources with Actual Work: Open Task Usage view, then select View → Table →
Work from the menu. Find the resource you want to update underneath its assigned task, and
enter the new actual work value into its Actual field.
• To Update Resources with Time Periods: Open Resource Usage view and select View →
Table → Work from the menu. Then, go to Format → Details, and make sure Actual Work is
selected. Find the Act. W field for the time period where you want to change work time and enter
the new work value in the Act. W field.
Updating Costs
• To Turn off Automatic Cost Updating: Before you update costs manually, you need to turn off
automatic updating. Select Tools → Options from the menu and click the Calculation tab, and
uncheck the Actual cost are always calculated by Microsoft Project checkbox, and click OK.
• To Update Costs Manually: Open Task Usage view and select View → Table → Tracking from
the menu. Scroll to the right in the spreadsheet and enter updated costs in the Act. Cost fields for
tasks.
• To Update Costs with Time Periods: Open Task Usage view and select View → Table → Cost
from the menu. Then, select Format → Details and make sure the Cost and Act. Cost options
are selected. Select View → Zoom from the menu and select the timescale option you want, then
under your chosen date(s), enter a new cost in the Cost field for a specific task.
Quiz
1. Under which menu will you find “Update Tasks”?
A. Edit
B. Tools
C. McDonalds
D. Format
4. Actual work is the amount of work that still needs to be completed. (True or
False?)
6. What do you do if you want to see all of the available table fields for a
view?
A. Give your screen a good kung-fu kick.
B. Open a table toolbar.
C. Switch to Table Usage view.
D. Drag the sidebar to the right of your screen.
8. Before you update a cost manually or by time period, you must first turn on
Project 2000’s automatic cost updating option. (True or False?)
9. _______ indicates how much of your budget should have been spent based
on your baseline budget and the amount of work done so far.
A. The summary task
B. Resource cost variance
C. Earned value
D. Wall Street
10. If you enter an actual finish date for a task, make sure the task _______.
A. has not yet been started
B. is really easy
C. is 100% complete
D. has multiple assigned resources
Homework
1. Start Microsoft Project 2000.
2. Navigate to your practice files and open the Homework 5 database.
3. Update task 5, “Build stand,” with 30% completion.
4. Give tasks #8, “Buy lemons,” and #9, “Buy sugar,” a new actual start date of January
30, 2002. Allow the scheduling conflict, since this will not actually change the start
date of any other tasks.
5. Give task #12, “Make tablecloth from bedsheet,” a remaining duration of 3 days.
6. Open the Variance table in Gantt Chart view and make it bigger, then find the
summary task with negative variance.
7. Now change the table from Variance to Work and find which task has work variance.
8. Go to Task Usage view, and then open the Work table. Make the Table bigger. Now,
enter a new actual work value of 3 hours for “Snoogie” under task #12, “Make
tablecloth from bedsheet.”
9. Go to Resource Usage view, and then select Format → Details from the menu and
make sure Work and Act. Work are selected. Scroll over to Tuesday, February 5th.
Give the Bill Gates resource an actual work update of 12h for the “Build stand” task
on Feb. 5th.
10. Shut off the “Actual costs are always calculated by Microsoft Project” option in the
Calculation tab of the Options dialog box. Open Task Usage view. Make the table a
Tracking table. For task #5, “Build stand,” give the Bill Gates resource an Actual
Cost of $5.00.
11. Go to Gantt Chart view, and then open the Earned Value table. (Hint- Look under
“More Tables.”) What is the total estimated actual cost of your project thus far?
(Hint- Look at the estimated actual cost field for your project’s summary task.)
Quiz Answers
1. B. You will find “Update Tasks” under Tools → Tracking.
2. A. When you update a task, a black bar appears in the task’s bar, signifying the percent of
completion.
3. A. A warning indicator appears next to a task if there is a scheduling conflict.
4. False. Actual work is the amount of work that has already been completed.
5. D. Project 2000 displays variance as positive or negative.
6. D. Drag the sidebar to the right of your screen to see all available fields in a view.
7. B. In the Earned Value table, BAC stands for Budget At Completion.
8. False. Before you update a cost manually or by time period, you must first turn off Project
2000’s automatic cost updating option.
9. C. Earned value indicates how much of your budget should have been spent based on
your baseline budget and the amount of work done so far.
154 Microsoft Project 2000
10. C. If you enter an actual finish date for a task, make sure the task is 100% complete.
You may notice a few problems as you track the progress of your project; no project is
perfect. For example, your project might not be calculated to finish until after your scheduled
finish date. In this case, you may need to schedule some overtime work for your resources. Or
you may have some resources that are overallocated. In this case, you may need to assign
work to other resources.
Most of the lessons in this chapter deal with adjusting resource work in order to balance a
project’s tracked progress because resources are the easiest project element to amend.
Oftentimes, problems that seem too large to handle can be easily fixed with a bit of careful
resource work or cost balancing. You may have touched on some of the content in these
lessons already, but use this chapter as a guide to balance your progress when problems arise
in your project plan.
156 Microsoft Project 2000
Figure 6-1
To change resource
allocation monitoring,
select Tools →
Resource Leveling from Figure 6-2
the menu.
A project can be quickly thrown off-balance if you have resource overallocation. A resource
overallocation arises when the number of units or hours assigned to a resource are greater than
the maximum number of hours available during that time period. For example, if you assigned
Ms. Fru Fru, the Wedding Planner, to three tasks at the same time at 100%, she would be an
overallocated resource. It’s better to recognize overallocated resources early in the project
rather than after deadlines have been missed. You can view overallocated resources in
Resource Sheet view, Resource Usage view, Resource Allocation view, and Resource Graph
view.
1. Navigate to your practice files and open Lesson 6A, and save the file as
Balancing.
If you don’t know where your practice files are, ask your instructor.
Quick Reference
To View Resource
Overallocation:
1. View the project in a
resource view.
2. Find resources
highlighted in red.
*You can view overallocation
in most resource views.
Overallocated resources are
always highlighted in red.
158 Microsoft Project 2000
Figure 6-3
Your resources can become overallocated when they are assigned to more work than they can
finish in their scheduled working hours. Overallocated resources make your project
unbalanced. Leveling is allowing Project to split and delay tasks in order to get rid of resource
overallocation. Note that allowing Project to level your project may change the start and finish
dates for overallocated tasks’ successors. Generally, Project will only level noncritical tasks
(tasks with slack) to avoid affecting other tasks’ schedules.
This lesson shows you how to identify the details of overallocated resources and fix the
overallocation problem with leveling, thus balancing your project.
Mrs. FruFru the wedding planner is overallocated. Lighten her load.
3. Click the Mrs. Fru Fru ID number to select the entire resource.
For now, we’re just going to balance this resource. Save the other overallocated
resource for another lesson.
4. Select Tools → Resource Leveling from the menu.
The Resource Leveling dialog box appears. Choose your leveling options. You can
choose to level certain detailed parts of your project, or your entire project.
5. Click the Automatic bullet and the Level entire project bullet.
These options indicate that the selected task will be leveled automatically, for the
duration of the entire project.
6. Click the Level Now button.
The Resource Leveling dialog box closes and the Level Now dialog box appears. We
just want to level the entire project’s overallocated resources that we selected in step 4.
7. Click the Selected Resources option and click OK.
Mrs. Fru Fru is no longer highlighted in red. That’s how you know it is no longer
overallocated.
Quick Reference
To Automatically Level
Your Resources:
1. On the view bar, click the
Resource Usage button.
2. Select Project →
Filtered For →
Overallocated
Resources from the
menu.
3. Select Tools →
Resource Leveling from
the menu.
4. Click the Automatic
bullet and the Level
Entire Project bullet,
then click the Level Now
button.
5. Click the Selected
Resources option or the
Entire Pool option and
click OK.
160 Microsoft Project 2000
Figure 6-4
The Leveling
Delay field
When you have overallocated resources, you can choose to have Project level them (delay and
split their assigned tasks), or you can choose to manually delay tasks assigned to
overallocated resources.
Delaying a task means that you are postponing it until your assigned resource has time to
work on it. You should note that delaying a task also delays the start dates of the task’s
successors and can affect the finish date of your project. To avoid this, delay noncritical tasks
(tasks with slack) first, and only delay them up to the amount of slack that is available for
each task. This lesson teaches you how to delay a task manually so your project will be
balanced.
You have scheduled one of your resources, Grandma Jeanette, to do too many tasks at once.
Therefore, she is overallocated. Be nice to the old lady and delay some of her tasks.
4. In the top half of the window, scroll down until you see the resource 16
Grandma Jeanette.
“Grandma Jeanette” and her working hours are highlighted in red. That means the
resource is overallocated.
5. Select the overallocated resource, Grandma Jeanette.
The bottom screen displays tasks that Grandma Jeanette is assigned to. It looks like
Grandma Jeanette has two tasks scheduled at the same time. They are “Find a wedding
dress” and “Find tuxes.” The “Find a wedding dress” task can’t be delayed because it
doesn’t have slack. However, the “Find tuxes” task has slack, so it can be delayed.
6. In the Leveling Delay field for the Find tuxes task, type 7 days and
press Enter.
Great! Notice that because you manually added delay time to this resource’s task, the
resource is no longer overallocated.
NOTE: Never enter more lag (delay) time than you have slack time, or else your
schedule will be thrown off.
7. Close the project file without saving changes.
Quick Reference
To Manually Delay
Resource Work:
1. Select View → More
Views, select Resource
Allocation, and click
Apply.
2. Drag the sidebar to the
right in Resource
Allocation view so that
the Leveling Delay field
shows in the bottom
screen table.
3. In the top screen, select
an overallocated resource
(or any sort of resource
you want to delay).
4. In the Leveling Delay
field for one of the
resource’s tasks, type a
delay period.
5. Press Enter.
162 Microsoft Project 2000
Figure 6-6
Sometimes, it is impossible to resolve overallocation for a resource that is just packed with
tasks to complete. When this happens, it is better to reassign the task to a different resource
with more time than trying to squeeze delays and overtime into an overallocated resource.
Balancing task work keeps your project on track.
Your resource Grandma Jeanette is feeling run down and has too many tasks to complete in
time for the wedding. To help Grandma Jeanette out, reassign one of her tasks to another
resource.
1. Navigate to your practice files, open Lesson 6B and save the file as
Assign Resources Balancing.
button
If you don’t know where your practice files are, ask your instructor.
Other Ways:
• Select Tools →
2. Click the Resource Usage button in the View bar.
Resources → You are now in Resource Usage view. Make overallocation detail rows available for all
Assign Resources of your resources.
from the menu. 3. Select Format → Details → Overallocation from the menu.
An Overallocation row now shows for each task. Find the Grandma Jeanette resource.
4. Scroll down to resource 16, Grandma Jeanette.
We can tell that Grandma Jeanette is overallocated, because she and her work hours are
highlighted in red. Look at her tasks. Reassign the “Find a wedding dress” task,
because it seems to be the longest task. But first, we need to go back to the Gantt
Chart.
5. Click the Gantt Chart button in the View bar.
Reassign the “Find a wedding dress” task.
6. Go to task 7, Find a wedding dress, and click its ID field to select the
whole task.
Now we need to reach into the pool of resources.
7. Click the Assign Resources button on the Standard toolbar.
The Assign Resources dialog box opens. Reassign the resources for “Find a wedding
dress” task so Grandma Jeanette is no longer overallocated.
8. In the dialog box, scroll to the Grandma Jeanette resource, select it,
and click Remove. (If you get an Actual Values message, click Yes.)
Great—now reassign a resource to the “Find a wedding dress” task.
NOTE: When you reassign a resource to a task, you may lose your updated Quick Reference
information for that task. For example, if the task is 30% done before you
reassign a new resource to it, you will have to enter 30% again after To Reassign Work to
reassignment. Another Resource:
9. In the dialog box, scroll to the Crazy Ernie (the recluse neighbor) 1. Click the Resource
resource, select it, and click Assign. Usage button in the View
bar.
Crazy Ernie, the recluse neighbor, is now assigned to the “Find a wedding dress” task,
and Grandma Jeanette is no longer overallocated. (If you want to check these details, 2. Select Format → Details
go back to Resource Usage view.) Sure, Crazy Ernie is a bit weird—he owns a warthog → Overallocation from
and wears a cooking sieve for a hat—but he would probably feel honored to help pick the menu.
out a wedding dress. 3. Look at your
10. Click the Close button to close the Assign Resources dialog box. overallocated resources.
Choose an overallocated
Now Grandma Jeanette has less to do. Have fun with Crazy Ernie!
resource, and then
choose a task that is
assigned to the
overallocated resource.
4. Click the Gantt Chart
button in the Views bar.
5. Click the overallocated
resource’s task ID field so
the whole task is
selected.
6. Click the Assign
Resources button on the
Standard toolbar.
7. Scroll to the overallocated
resource assigned to the
task.
8. Click the Remove button.
9. Choose a different, free
resource to assign to the
task and click the Assign
button.
164 Microsoft Project 2000
Figure 6-7
If you have a resource that is overallocated but the task assigned to it has to be done by a
certain date, you can assign overtime to the resource. (If, of course, the resource agrees to
working overtime.) This would allow the resource to finish the task on time, without being
marked as overallocated. When your resources finish their tasks on time without being
overallocated, your project is balanced and has fewer glitches.
You are going to need about fifty more wedding favors for your South Dakota fish farm
wedding than you had originally planned. How are you going to get fifty more gummi worm-
on-fishhook table favors made in the time you have scheduled? Erin, the Maid of Honor, will
probably be okay with working some overtime in order to get the favors done.
5. In the bottom Task Entry screen, select the Erin (maid of honor)
resource and enter 2 hours in this resource’s Ovt. Rate field. Press
Enter.
You are done! Erin should be able to finish those fifty gummi worm favors in two
hours of overtime work. Your guests are going to lover those clever, fishing-themed
treats!
6. Close the file without saving changes.
Quick Reference
To Schedule Resource
Overtime:
1. Select Views → More
Views from the menu,
select Task Entry view,
and click Apply.
2. Right-click in the gray
area of the bottom Task
Entry screen and choose
Resource Work from the
drop-down list.
3. Select a task in the top
screen of your split
window.
4. In the bottom screen, go
to one of the task’s
resources and enter an
overtime value in the Ovt.
Rate field.
5. Press the <Enter> key.
166 Microsoft Project 2000
Lesson Summary
Identifying Resource Overallocation
• To View Resource Overallocation: View the project in a resource view. Find resources
highlighted in red.
• You can view overallocation in most resource views. Overallocated resources are always
highlighted in red.
Quiz
1. Overallocated resources appear in which color:
A. Black
B. Red
C. Blue
D. Chartreuse
2. Automatic leveling allows Project to ____ and ____ tasks in order to get rid
of resource overallocation.
A. track and balance
B. cut and paste
C. split and delay
D. reschedule and reassign
3. Generally, Project 2000 will only level ______ tasks (tasks with slack) to
avoid affecting other tasks’ schedules.
A. unimportant
B. noncritical
C. superfluous
D. underassigned
168 Microsoft Project 2000
4. When manually delaying a task, never enter more lag (delay) time than you
have slack time. (True or False?)
7. When you reassign a resource to a task, you will not lose your updated
information for that task. (True or False?)
Homework
1. Start Microsoft Project 2000.
2. Navigate to your practice files and open the Homework 6 database.
3. Identify the overallocated resource.
4. Fix the overallocated resource using automatic leveling. (If you get a dialog box that
says the overallocated task can’t be leveled, push the Stop button and continue.)
5. Manually delay task #23, “Build a chain of stands,” five days.
6. For task #5, “Build stand,” give the Bill Gates resource an overtime rate of five
hours. (Note that the duration of task #5 will change.)
7. Reassign task #11, “Borrow spoon from grandma,” from your “Mom” resource to
“The Worm (little sister)” resource.
Quiz Answers
1. B. Overallocated resources appear in red.
2. C. Automatic leveling allows Project 2000 to split and delay tasks in order to get rid of
resource overallocation.
3. B. Generally, Project 2000 will only level noncritical tasks (tasks with slack) to avoid
affecting other tasks’ schedules.
4. True. If you enter more lag (delay) time than you have slack time, your schedule will be
unbalanced.
5. A. Enter a resource’s overtime into the Ovt. Rate field.
6. C. When it is impossible to resolve an overallocated resource, you can reassign the
overallocated resource’s work.
7. False. When you reassign a resource to a task, you will lose your updated information for
that task. You will need to re-enter updated information, such as how much of the task
has been completed.
8. D. You will probably need to balance your tracked progress, because no project is perfect.
Chapter Seven:
Working with Reports
Chapter Objectives: ; Prerequisites
• Choose a Report • Have a project in
which you have entered
• Use Report Details tasks, resources, and
costs
• Define Report Contents
• Understand project
• Sort a Report management
The other people working on your project can better understand the project by seeing printed
information. Thus, it is a good idea to print reports containing your project information for
other people to see. You can format, customize, define, and sort specific information in reports
so they are tailored to certain people. Also, it’s handy to print reports so you can review your
project information without getting eyestrain from your computer screen. This chapter teaches
you how to organize and print a report.
172 Microsoft Project 2000
Figure 7-1
Figure 7-2
You’ve decided you want to print project information in the form of a report, but how do you
know which report to want to use? Project 2000 comes with 22 predefined reports you can
print. This lesson teaches you how to choose what type of a report to print, based on what
information you want to see.
1. Navigate to your practice files and open Lesson 7A and save the file as
Reports.
If you don’t know where your practice files are, ask your instructor.
First, preview the list of Project’s 22 standard reports.
2. Select View → Reports from the menu.
The Reports dialog box appears, as shown in Figure 7-1. The Reports dialog box
presents you with five different report category buttons, plus a button for creating your
own custom report. The five report categories are Overview reports, Current Activities
Reports, Costs reports, Assignments reports, and Workload reports. See the information
below to decide which report category you want to open based on which reports it
contains.
Figure 7-3
Figure 7-4
You can’t customize details in all of Project’s standard reports; in some reports, the only thing
you can customize is text. Also, the details that you can customize vary between reports.
Some customizable details of different reports include: showing gridlines, showing cost totals,
and repeating the first table column on every report page.
You would like to print a report about the tasks in your project that are “slipping,” or, the tasks
that have been rescheduled from their original baseline date. But you don’t want just any
ordinary Slipping Tasks report; you want a Slipping Tasks report with these added details:
gridlines, borders, totals, and assignment work.
2. Click the Current Activities report category button and click the Select
button.
The Current Activities Reports dialog box appears. Notice the Slipping Tasks report.
3. Click the Slipping Tasks report button and click the Edit button so you
can customize the report’s details.
The Task Report dialog box appears. You want to customize with details, so…
4. Click on the Details tab.
This is where you can choose what details you want to customize your report with.
5. Check the Work, Border around details, Gridlines between details,
and Show totals check boxes.
You’ve chosen your details, so you are ready to preview your report and take a look at
the details you’ve added.
6. Click OK.
Now you are back to the Current Activities Reports dialog box.
7. Make sure the Slipping Tasks report is selected and click the Select
button to preview your printed report.
Your Slipping Tasks report appears in Print Preview. Notice that it contains the
details—gridlines, borders, work assignments, and totals—you added earlier.
8. Click Close, Close to close the Report preview and the Reports dialog
box.
Quick Reference
To Use Report Details:
1. Select View → Reports
from the menu.
2. Select a report category
button and then click
Select.
3. Select a report and click
Edit.
4. If the report is
customizable, the Task
Reports dialog box will
appear. (Not all reports
are customizable.)
5. Click on the Details tab.
6. Check the details that you
want to appear in your
report.
7. Click OK.
8. Click the Select button to
preview your printed
report.
176 Microsoft Project 2000
Figure 7-5
Figure 7-6
Different reports can be defined in very different ways. Some ways in which you can define
report contents are: choosing your row heading, adjusting a date range, and choosing a new
table to display.
3. Select the Task Usage report button and click the Edit button so you
can customize the report’s details.
The Crosstab Report dialog box appears. You want to define report contents, so…
4. Click on the Definition tab.
This is where you can choose what details you want to customize your report with.
Let’s choose to highlight tasks that have not been completed in your report. Let’s also
define them with actual work.
5. Click the Filter list arrow and select Incomplete Tasks from the drop-
down list. Check the Highlight check box.
Incomplete tasks will be shown in the report.
6. Select Actual Work from the Work drop-down box.
That’s the only defining we’ll do for now.
7. Click OK.
You are returned to the Workload Reports dialog box. Now you can preview the Task
Usage report to see how you’ve defined it.
8. Make sure the Task Usage report button is selected, then click the
Select button.
Your Task Usage report appears in Print Preview. Notice that all of the incomplete
tasks have been highlighted, and actual work appears in the chart cells.
9. Close the report preview and all dialog boxes.
Quick Reference
To Define Report
Contents:
1. Select View → Reports
from the menu.
2. Select a report category
button and then click
Select.
3. Select a report and click
Edit.
4. If the report is definable,
the Task Reports dialog
box will appear. (Not all
reports are definable.)
5. Click on the Definition
tab.
6. Define your report with
the options in the
Definition tab.
7. Click OK.
8. Click the Select button to
preview your printed
report.
178 Microsoft Project 2000
Figure 7-7
Figure 7-8
Sorting a report allows you to put your report information in a certain order. You can’t sort
information in all of Project’s standard reports, but many reports have a variety of ways they
can be sorted. Some of the different ways you can sort reports are by task ID, duration, and
resource initials.
Figure 7-9
You may want to add a page element—such as a header, footer, margin, or border—to your
report. Page elements allow you to put your name, the project finish date, a design, and more
on each page of your report. This lesson won’t lead you through the exact steps of adding all
the possible page elements to your report, because that would take forever. Instead, this lesson
will give you a quick description and procedure for each page element.
Let’s add page elements to an Earned Value report.
2. Select the Costs category button and click the Select button.
The Costs Reports dialog box appears. Notice the Earned Value report.
3. Select the Earned Value report button and click Select.
The Earned Value Report appears in Print Preview. Now, choose to add page elements
to your report.
4. At the top of Print Preview, click the Page Setup button.
The Page Setup dialog box appears. Notice that it has various tabs for creating page
elements. Practice adding page elements with the Page Setup dialog box.
5. Click Cancel to close the dialog box, and close the report preview.
Margins Using this tab, you can adjust any margin setting using the up and down arrow
buttons, and you can choose whether or not you want a border on your pages.
Tab Instructions
Header This tab allows you to add text or a picture at the top of your printed pages. You
can align text in a header to the left, center, or right of the top by clicking on the
corresponding tab. In the General drop-down list, you can choose what sort of
text you would like in the header and then click Add to have it automatically
entered into the header. In the Project field drop-down list, you can choose what
project information you would like in the header and then click Add to have it
automatically entered into the header. Lastly, you can add things like the date or
a picture using the buttons in the Header tab.
Footer This tab allows you to add text or a picture at the bottom of your printed pages.
You can align text in a footer to the left, center, or right of the bottom by clicking
on the corresponding tab. In the General drop-down list, you can choose what
sort of text you would like in the footer and then click Add to have it
automatically entered into the footer. In the Project field drop-down list, you can
choose what project information you would like in the footer and then click Add
to have it automatically entered into the footer. Lastly, you can add things like
the date or a picture using the buttons in the Footer tab.
Legend This tab is only accessible when you add page elements to printed views.
View This tab is only accessible when you add page elements to printed views
Quick Reference
To Add Page Elements to
a Report:
1. Select View → Reports
from the menu.
2. Select a report category
button and then click
Select.
3. Select a report and click
Select.
4. In Print Preview, click the
Page Setup button.
5. In the Page Setup dialog
box, use the various tabs
to add page elements to
your report.
182 Microsoft Project 2000
Figure 7-10
Figure 7-11
You can save your project as a Web page so that you can share your project information over
the Internet or even a company’s intranet. That way, the people involved with your project can
view your project information from anywhere in the world!
3. Select the Compare to Baseline map and click the Edit button to
preview the map’s fields.
The Define Import/Export Map dialog box appears. In the Options tab, you can choose
what basic data to include in your map. In the Mapping tabs, you can check out the
fields in your map. Leave the Options and Mapping tabs as they are.
4. Click OK to close the Define Import/Export Map dialog box.
You are back to the Export Mapping dialog box. Finish saving your project information
as a Web page.
5. Click the Save button.
Your project information is saved as a Web page.
6. Close the file without saving changes.
The next step to publishing the project on the Web involves having a Web site and a
server.
Quick Reference
To Save a Project as a
Web Page:
1. Select File → Save As
Web Page from the
menu.
2. Click the Save button.
3. Select a type of map from
the Export Mapping
dialog box. (At this point,
you can click Edit to view
the map’s fields. Click OK
to close the Define
Import/Export Map
dialog box when you’re
done.)
4. Click Save to finish
saving.
184 Microsoft Project 2000
Lesson Summary
Choosing a Report
• To Choose a Report Type: Select View → Reports from the menu, select a report category
button and click Select, then click a report button and click Select.
• The five report categories are: Overview, Current Activities, Costs, Assignments, and Workload.
Sorting a Report
• To Sort a Report: Select View → Reports from the menu, select a report category button, click
Select, then select a report and click Edit. If the report is sortable, the Task Reports dialog box
will appear. Click on the Sort tab, sort your options, and click OK. Click the Select button to
preview your printed report.
Quiz
1. Which of these is NOT a report category?
A. Work Activities
B. Costs
C. Assignments
D. Overview
2. The Custom button in the Reports dialog box doesn’t contain predefined
reports. (True or False?)
3. In some Project 2000 predefined reports, ______ is the only thing you can
modify.
A. text
B. content
C. workload
D. Print Preview
7. Which of these Page Setup tabs is not accessible when you add page
elements to a report?
A. Legend
B. Footers
C. Margins
D. Page
Homework
1. Navigate to your practice files and open the Homework 7 project file.
186 Microsoft Project 2000
2. Select View → Reports from the menu to open the Reports dialog box and identify
the five report category buttons. What does the sixth button do?
3. Format the text for the Cash Flow report so that all of the text is purple. The Cash
Flow report is located in the Costs report category.
4. Define the Resource Usage report so that the time period is in days instead of weeks.
The Resource Usage report is in the Workload report category.
5. Sort the Who Does What report so that it is sorted by ID, then by Baseline Finish,
both in descending order. The Who Does What report is in the Assignment report
category.
6. Add the baseline finish date to the footer in the Tasks in Progress report. The Tasks
in Progress report is in the Current Activities report category.
7. View the Cash Flow report in Print Preview. Use the Zoom, One Page, Multiple
Pages, and Navigational Arrow buttons.
8. Print the Cash Flow report and close the homework file.
Quiz Answers
1. A. Work Activities is not a report category; the five report categories are: Overview,
Current Activities, Costs, Assignments, and Workload.
2. True. The Custom button in the Reports dialog box does not contain predefined reports
because it is used to create new, custom reports.
3. A. In some Project 2000 predefined reports, text is the only thing you can modify.
4. B. To open the Reports dialog box, go to View → Reports.
5. B. You can choose to sort report information in ascending or descending order.
6. C. Project 2000 offers you 22 predefined reports to work with.
7. A. The Legend and View tabs are not accessible when you add page elements to a report.
8. False. You can’t make changes to a report in Print Preview.
Single projects are the basis for project management, but sometimes it is necessary to work
with multiple projects so one can see across-project data. A manager may need to see total
individual workloads and schedules for resources for multiple project assignments. Also,
looking at current multiple project resource needs can help project managers plan for future
long-term resource planning.
Fortunately, Project 2000 provides the capability to observe and manage multiple open project
files. This chapter will show you how to do something as simple as viewing multiple open
files, and it will show you advanced management techniques like consolidating project files
and creating a shared resource pool.
188 Microsoft Project 2000
Figure 8-2
When you insert a subproject into a master project, you create a consolidated project file. The
ability to insert one project file into another project file allows you to piece together
information to create an overall project plan.
To consolidate projects, you must either insert a subproject into a master project or create a
new consolidated project window. In this lesson, we will insert a subproject into a master
project. However, many Project users have problems with task information in their
subprojects when they consolidate through insertion. Therefore, you might want to go on to
the next lesson and learn to create a consolidated project by making a new consolidated
project window.
Quick Reference
To Consolidate Projects:
1. Open a project you would
like to insert other
projects into.
2. Select a task above which
you would like to insert a
subproject.
3. Select Insert → Project
from the menu.
4. Select a project insert.
5. Click the arrow on the
Insert button and choose
whether or not to insert
the subproject(s) as read-
only.
190 Microsoft Project 2000
When projects
are
consolidated,
they renumber
the task list.
Figure 8-4
When you merge projects together, you create a consolidated project file. The ability to
A consolidated project consolidate files allows you to piece together information to create an overall project plan, or
can be made of up to combine various projects into a master project plan.
1,000 combined files.
There are two ways to consolidate projects: create a new consolidated project window, or
insert one project into another. In this lesson, we will create a new consolidated project
window, the more trustworthy method of the two.
3. Select Lesson 8A and Subproject, select Gantt Chart from the View Press the Shift or
drop-down list, and click OK. Control key to select
Your new consolidated project window appears. Scroll down the window to see where multiple files.
the two projects were consolidated.
NOTE: Each project that is consolidated in your new window is marked by a
consolidated project icon in the indicator column.
4. Close the new consolidated window without saving changes.
Go on to the next lesson to link projects.
Quick Reference
To Consolidate Projects in
a New Window:
1. Open the projects that
you would like to
consolidate.
2. Select Window → New
Window from the menu.
3. Select the project names
you want to consolidate,
select a view, and click
OK.
192 Microsoft Project 2000
Figure 8-5
Figure 8-6
If you want to connect projects but do not want to completely consolidate them, you connect
them with task links. When you create cross-project links, keep in mind that the scheduling
dates for predecessor tasks will impact the scheduling dates for successor tasks.
Connect two wedding planning projects with links.
1. Make sure both projects are in Gantt Chart view. Select Window →
Arrange All from the menu.
The projects align horizontally in your Project window.
Link a task from the Subproject file to a predecessor task in Lesson 8A.
Figure 8-8
A resource pool is a collection of resources that allows you to share resources among multiple
projects. A resource pool allows you to schedule resources' work across projects, identify
conflicts between assignments in different projects, and see how a resource's time is used in
multiple projects. Each project that uses resources from the resource pool is called a sharing
file. The best way to create a resource pool is to create a new project file for the resource
information to make it easy to manage resource information and task assignments between
sharing files and the resource pool.
1. Navigate to your practice files and open the Resource Pool and
Subproject files.
If you don’t know where your practice files are, ask your instructor.
We will be sharing the resources of the Resource Pool with the Subproject file.
2. Select Window → Arrange All from the menu.
Your lessons are arranged top-to-bottom in the window.
Figure 8-9
Figure 8-10
As you probably learned in the earlier stages of managing a Project file, it is important to
monitor the critical path for a project. Likewise, it is important to keep an eye on multiple
critical paths in a consolidated project so you will be able to tell if adjustments you make to
the project plans will affect the critical paths. This lesson will teach you how to view multiple
critical paths and then view the overall critical path across projects.
Figure 8-11
Figure 8-12
Viewing information for a subproject that you inserted into a master project is simple.
The Lesson 8A file is a master project that has two subprojects, “Bridal Basics,” and “Groom
Duties” inserted into it. View information about this subproject by first selecting the
subproject’s summary task.
4. Click the Project Info button in the Inserted Project Information dialog
box.
The Project Information dialog box appears.
5. Click the Statistics button in the Project Information dialog box.
You have successfully viewed your inserted subproject information.
6. Close the subproject dialog boxes and close the project file.
Quick Reference
To View Inserted
Information:
1. Open a project file that
has had a subproject
inserted into it.
2. Select the summary task
for the inserted project.
3. Click the Task
Information button.
4. Click the Advanced tab.
5. To see additional
information, click the
Project Info button and
then the Statistics
button.
200 Microsoft Project 2000
Figure 8-13
Figure 8-14
A workspace is the area where your multiple projects reside when you are working with them.
If you save a workspace, Project will record which files you are working on and will open
those same files when you open the workspace file again. That way you don’t have to spend
time opening files one by one when you want to work with them.
First, you need to open your wedding-related files.
1. Navigate to your practice files and open Lessons 8A, 8B, and
Subproject.
If you don’t know where your practice files are, ask your instructor.
Save your workspace with your multiple files in it.
Quick Reference
To Save a Workspace:
1. Open the project files that
you want to appear in
your workspace.
2. Select File → Save
Workspace, and
remember where you
saved your workspace
3. Close all open files.
4. Navigate to the place
where you saved your
workspace and then open
your workspace.
5. All of the open project
files that were saved in
your workspace should
open.
202 Microsoft Project 2000
Figure 8-16
Adding a column to a consolidated project file is a handy thing to do if you want to view
subproject information. For instance, you can add a “Subproject” column to a resource table
in a consolidated file that will show the subproject where each source originated.
Quick Reference
To Add Columns to a
Consolidated Project:
1. Open a consolidated
project file.
2. Select a column heading
in the Task Entry table
that you want to insert a
new column in front of.
3. Select Insert → Column
from the menu.
4. Select a field name, type
in a title, and click OK.
204 Microsoft Project 2000
Figure 8-17
Figure 8-18
You can save a baseline for an entire consolidated project or for selected tasks. Saving a
baseline is helpful because it allows you to track changes and updates in tasks and
assignments; you can compare current project information to baseline information.
First, save a baseline for selected subproject tasks. Find the “Groom Duties” subproject.
4. Select the Save baseline option, select the Selected tasks option and
click OK.
You have saved a baseline for the selected tasks in the “Groom Duties” subproject.
Now save an overall baseline for the entire consolidated project. But first, view the
Gantt Variance table to get an idea of which project tasks already have baseline dates.
5. Select View → Table: → Variance from the menu.
Notice that the “master” project tasks have baseline dates, but the subproject tasks
don’t have baseline dates. (Unless, of course, you’ve saved a baseline for them, as you
have for the “Groom Duties” subproject.) Reapply the default task entry table.
6. Select View → Table: → Entry from the menu.
Save an overall baseline for the entire consolidated project.
7. Select Tools → Tracking → Save Baseline from the menu.
The Save Baseline dialog box appears. Choose to save a baseline for the entire project.
8. Make sure the Save baseline and Entire project options are selected
and click OK.
You have saved an overall baseline for a consolidated file.
Quick Reference
To Save a Baseline for
Selected Tasks in a
Consolidated Project:
1. Select the tasks that you
want to save a baseline
for.
2. Select Tools →
Tracking → Save
Baseline from the menu.
3. Select the Save baseline
option, then click the
Selected tasks option
and click OK.
To Save an Overall
Baseline for a
Consolidated Project:
1. Select View → Table →
Entry from the menu.
2. Select Tools →
Tracking → Save
Baseline from the menu.
3. Select the Save baseline
option, click the Entire
project option and click
OK.
206 Microsoft Project 2000
Lesson Summary
Consolidating Projects
• Open a project you would like to insert other projects into. Select a task above which you would like
to insert a subproject. Select Insert → Project from the menu and select a project insert. Click the
arrow on the Insert button and choose whether or not to insert the subproject(s) as read-only.
Saving a Workspace
• Open the project files that you want to appear in your workspace, then select File → Save
Workspace from the menu and remember where you saved your workspace. Close all open files,
then navigate to the place where you saved your workspace and open your workspace. All of the
open project files that were saved in your workspace should open.
Quiz
1. To organize open project files on your screen, select Window → _____.
A. Order All
B. View All
C. Organize All
D. Arrange All
2. Light-gray tasks that are linked across projects are called _____ tasks.
A. ghost
B. phantom
C. ghoul
D. spooky
3. Where do your open project files reside when you are working on them?
A. a laborspace
B. a workspace
C. outerspace
D. a projectspace
208 Microsoft Project 2000
6. After you insert projects into a consolidated file, you can still access each
of the projects separately. (True or False?)
7. In which tab of the Options dialog box can you change multiple critical path
options?
A. Tab key
B. General tab
C. Calculation tab
D. Edit tab
Homework
1. Start Microsoft Project 2000.
2. Navigate to your practice files and open the Homework 8A database and the
Homework 8B database.
3. Arrange the two projects you have open on your screen. (Hint: Go to the Window
menu.)
4. Link task #13, “Sell lemon bars at stand,” in Homework 8B to a predecessor task,
task #15, “Dye the dog lemon yellow,” in Homework 8A.
5. Create a resource pool between Homework 8A and Homework 8B. (Remember to
make sure you don’t have any resource duplicates with different names, and to check
the start and finish dates of each Homework project.)
6. Save a workspace named “Lemonade.”
7. Create a new consolidated project window for Homework 8A and Homework 8B to
save them as one project.
8. Add a new column to the Task Entry table in the new “Lemonade” consolidated
project’s Gantt Chart. Have the column show a “Project” field and title the column
“From.”
9. View all of the multiple critical paths in your new “Lemonade” consolidated project.
10. Save an overall project baseline for your new “Lemonade” consolidated project.
Quiz Answers
1. D. To organize open project files on your screen, select Window → Arrange All.
2. A. Light-gray tasks that are linked across projects are called ghost tasks.
3. B. Your open project files reside in a workspace when you are working on them.
4. False. A resource pool project file only has resources in it.
5. B. A project that is inserted into a master project is called a subproject.
6. True. After you insert projects into a consolidated file, you can still access each of the
projects separately.
7. C. You will probably need to balance your tracked progress, because no project is perfect.
8. C. To resize a project table, grab the divider bar and drag it left or right.
Chapter Nine:
Customizing the
Project
Chapter Objectives: ; Prerequisites
• Change Bar Styles • Have a project in which
you have entered
• Create Custom Groups, Tables, Forms, Reports, and Views tasks, costs, and
resources
• Use the Organizer
• Know the basic
• Add Hyperlinks to Tasks and Resources elements of the
Project 2000 screen
Chapter Task: Customize your project
You might think that you need to be a computer expert to customize Project 2000 elements,
but you’re wrong. The user-friendly lessons in this chapter help you create and customize
menus, filters and forms with ease. It’s good to know how to customize elements, even if you
think you’ll be using Project’s default elements most of the time. A person involved with your
project may want to see very specific information, or might want to enter information into a
precise project area. Being able to customize elements allows you to get extremely detailed
with organizing or finding information in your project. Through customizing your project
elements, you can tailor your project to fit your specific needs.
212 Microsoft Project 2000
Apply styles to
a chart element
in this area.
Figure 9-1
Figure 9-2
You are becoming tired of looking at your blue/black/red Gantt Chart every day; your Gantt
Chart needs some serious style changes. Thankfully, the makers of Project took mercy on your
To format your whole
style-sensitive feelings and created the Bar Styles dialog box. Give your Gantt Chart bars
Gantt Chart, press the
some personality.
Gantt Chart Wizard
button.
1. Navigate to your practice files and open Lesson 9A. Save the file as
Custom Project.
If you don’t know where your practice files are, ask your instructor.
Open the Bar Styles dialog box and put your good taste to use.
2. Select Format → Bar Styles from the menu.
The Bar Styles dialog box appears.
Quick Reference
To Open the Bar Styles
dialog box:
• Select Format → Bar
Styles from the menu.
To Change Bar Styles:
• Open the Bar Styles
dialog box and customize
your bars.
214 Microsoft Project 2000
Figure 9-4
Figure 9-5
Project 2000 has groups you can use to group your information, but you still may want to
create your own groups. You should already know how to group information before you begin
this lesson.
While you’ve been working on the wedding project, you’ve had a bit of trouble with a couple
of your tasks. For instance, Seamstress Bob wouldn’t sew your dresses until he had horsehair
thread shipped in from Turkey. And ordering the cake has been a major pain because the baker
can’t find fishing pole-shaped tiers, which you must have. Make a group for tasks that are
hard to work with.
Quick Reference
To Create a Custom
Group:
1. Select Project → Group
by → More Groups from
the menu.
2. Click the New button in
the More Groups dialog
box.
3. Type the group name in
the Name field.
4. Select a field to group by
in the Group By drop-
down list.
5. Choose Ascending or
Descending order.
6. Click OK.
216 Microsoft Project 2000
Figure 9-8
We do not advocate
You may want to create your own filters if standard filters don’t provide what you need. For
modifying original
example, you may want to filter a screen only for tasks with costs over $500 in the month of
filters. Instead, copy a February, but Project 2000 doesn’t offer that filter. Thus, you will need to create your own
filter first and then filter. In this lesson, you are going to learn how to create your own custom filters.
modify it to customize
it for your use. 1. Select Project → Filtered for: → More filters from the menu.
The More Filters dialog box appears.
2. Click the New button in the More Filters dialog box.
The Filter Definition dialog box appears. Name the new filter.
3. Type Hard to Work With in the Name field.
Now set the criteria for the Hard to Work With filter.
4. Click the Field Name list arrow and select Text 1 from the drop-down
list.
The filter will look at the criteria in this field.
5. Click the Test list arrow and select contains from the drop-down list.
The filter will test the information in the Text 1 field for each task to see if it contains
the value specified.
6. Click the Value(s) list arrow and type Yes.
The filter will filter out any tasks that contain “Yes” in the Text 1 field.
Ready to try it?
7. Click OK to close the Filter Definition dialog box.
The More Filters dialog box appears.
8. Select the Hard to Work With filter and click Apply.
The project is filtered to show only tasks that contain the value “Yes” in the Text 1
field, as shown in Figure 9-8.
9. Select Project → Filtered for: → All Tasks from the menu.
All the tasks are displayed once again.
You can also create filters with multiple tests and values. Refer to the table below to
create more complex filters.
10. Close the file without saving changes.
Figure 9-11
When you are in a view, you can choose how to view task and resource information by using
various tables. You should already know how to change tables in a view—that is a basic move
in Project 2000. But you probably don’t know how to create a custom table yet, which is what
this lesson will teach you to do.
Create a custom table that shows task ID, costs and durations together.
1. Navigate to your practice files and open Lesson 9B. Save the file as
Custom Project.
If you don’t know where your practice files are, ask your instructor.
For people who don’t know how to use Project 2000, forms are the easiest place to enter
project information. They especially come in handy when you need information entered
quickly.
Create a custom form so Project is easier to use.
5. Double-click the text field to view the Item Information dialog box. Type
Task Name in the Item Information dialog box and click OK.
Now add a text field to the form.
6. Select Item → Fields from the menu. Click the Field list arrow and
select Name from the drop-down list. Click OK.
The Name textbox appears underneath the Task Name field. Move the Name textbox
so it sits to the right of the Task Name field.
7. Click and drag the Name textbox so it sits to the right of the Task Name
field, as shown in Figure 9-13. The Item menu
Enter a field for cost. contains your form
options.
8. Select Item → Field from the menu. Click the Field list arrow and select
Cost from the drop-down list. Click OK.
A Cost field textbox appears in the form.
Enter a group box on the form named “Notes”.
9. Select Item → Group Box from the menu.
A Group box appears on your form. Name and format it.
10. Double-click the Group box. Type Notes in the Item Information dialog
box and click OK.
Now resize and place the group box.
11. Click and drag the Group box below the Cost field. Then grab the right
side of the Notes box and drag it so it covers the length of the form, as
shown in Figure 9-14.
Now enter a field in the Notes box.
12. Select Item → Field from the menu. Click the Field list arrow and select
Notes from the drop-down list. Click OK.
Quick Reference
A new Notes field appears on your form. Move and resize it.
To Create a Custom Form:
13. Drag the new Notes field to inside of the Notes box, and resize it, as
shown in Figure 9-15. 1. Select Tools →
Customize → Forms
Finally, you’re done adding items to your form. from the menu.
14. Select File → Save from the menu. Then select File → Exit from the 2. Click the New button in
menu to close the Custom Form Editor. the Forms dialog box.
You are back to the Customize Form dialog box. 3. Give your new form a
Your new custom form, “Updating” is in the Customize Form dialog box list. Try out name, a keystroke
your new form on a task. (optional), and press OK.
15. Click Cancel to close the dialog box. Select task 22 Book DJ for Dance. 4. Select the Item menu
This is the task you want to update. Go ahead and retrieve the Updates form you just and insert the text, group
created. boxes, buttons, or fields
you would like on your
16. Select Tools → Customize → Forms from the menu.
form.
The Forms dialog box appears.
5. Format the items you
17. Select Updates from the list in the Forms dialog box and click Apply. added to the form.
The form you created appears on the screen with the information for the specified 6. Select File → Save from
fields for the task. Now, update the cost of this task. the menu.
18. Type $500 in the Cost field and click OK. 7. Select File → Exit from
The task is updated, and your custom form is a great success. the menu.
222 Microsoft Project 2000
Figure 9-20
Although Project 2000 offers you 22 predefined standard reports to work with, you may find
that none of them fit your needs. Thus you can edit—define, sort, or choose details for—an
existing report, or you can create your own custom report. Create a new custom report in this
lesson.
Quick Reference
To Create a Custom
Report:
1. Select View → Reports
from the menu.
2. Select a report category
button and then click
Select.
3. Click the New button.
4. Select a type of report to
create and click OK.
5. Choose your custom
report formatting options
and click OK.
6. Select your new report
name from the list and
click Preview to preview
it.
224 Microsoft Project 2000
Figure 9-21
Figure 9-22
Though Project has many different views, you can still create a custom view for your wedding
planning project. For example, you might want to create a view that is automatically filtered
and grouped for certain information without having to go to menus to filter and group. You
can create a view from scratch, modify a copy of an existing view, or directly modify a view.
Do not directly modify a view; instead, make a copy of a view before you make
modifications.
Quick Reference
To Create a Custom View:
1. Select Views → More
Views from the menu.
2. Click the New button.
3. Make sure the Single
View bullet is selected
and click OK.
4. Enter a name, screen,
table, group, and filter.
5. Select your new view and
click Apply.
226 Microsoft Project 2000
Figure 9-23
Figure 9-24
In order to complete this lesson, you should have already created some custom groups, tables,
forms, and filters. This is because this lesson is about sharing your custom tables, forms, and
filters with other projects. Without the organizer, the custom elements you created would only
be available in the project in which you created them.
You already have the wedding project your table will be copied from open, Lesson 9C. Now
open the lemonade stand project that the table will be copied to using the Organizer.
Figure 9-25
Task and Resource hyperlinks allow users to access existing files or Web pages, link to other
tasks and resources, open other documents, or send e-mail. In other words, hyperlinks help
you to increase your Project functionality.
7. Click the Gantt Chart button from the Views panel, then select View →
Table → Hyperlink from the menu.
You can now see the Hyperlink table. Add a file hyperlink.
8. Select task 25, Order cake and click the Insert Hyperlink button on the
Standard toolbar.
The Insert Hyperlink dialog box appears.
Enter a name for the hyperlink in the “Text to display” textbox, and then browse for the
file you want to link to.
9. Type Dream Cake in the Text to display textbox. Click the File button to
browse for the cake file.
The Link to File dialog box appears. Find the cake file in your practice files.
10. Navigate to your practice files and select the Cake file. Click OK.
Cake.doc now appears in the “Type the file or Web page name” textbox.
11. Click OK to close the Insert Hyperlink dialog box and add the link.
The hyperlink has been added.
That’s the basic procedure for adding hyperlinks to tasks or resources in a project.
12. Close the Lesson 9C file.
Quick Reference
Before You Add a
Hyperlink:
• Choose your
appropriate view (Gantt
Chart, Resource Sheet,
etc.) and select View →
Table → Hyperlink from
the menu.
To Add a Hyperlink to a
Task or Resource:
1. Select the task or
resource and select
Insert → Hyperlink from
the menu.
2. Enter text in the Text to
Display textbox.
3. Select the type of
hyperlink you want to
insert, and enter the
address or file name of
the hyperlink’s
destination.
4. Click OK.
230 Microsoft Project 2000
Lesson Summary
Changing Bar Styles
• To Open the Bar Styles dialog box: Select Format → Bar Styles from the menu.
• To Change Bar Styles: Open the Bar Styles dialog box and customize your bars.
Quiz
1. You can change the look of your Gantt bars in the __________.
A. Group Definition dialog box
B. Barber shop
C. Formatting menu
D. Bar Styles dialog box
3. The Organizer allows you to share custom tables, forms, and filters with
other projects. (True or False?)
Homework
1. Start Microsoft Project 2000.
2. Navigate to your practice files and open the Homework 9 database.
3. Select Format → Bar Styles from the menu to open the Bar Styles dialog box, then
make your task bars green with a solid (no dots or stripes) pattern.
4. Use the Organizer to copy a custom form called “LemonLaws” from the Homework
9 project file to the Wedding Preparation project file. Make sure that the Homework
9 project file is still open, then open the Wedding Preparation project file. Go to
Format → Organizer → Forms tab.
In the left “Forms Available In” textbox, select Homework 5 from the drop-down
list. Then copy the “LemonLaws” form from Homework 5 to Wedding Preparation.
Go back to the Gantt Chart.
5. Select View → More Views from the menu and create a new single view with these
properties:
Name: Detailed Incomplete Tasks
Screen: Gantt Chart
Table: Schedule
Group: No Group
Filter: Incomplete Tasks
Choose to show your new view, and then apply it to your screen. Go back to your
default Gantt Chart.
6. Add a Web address hyperlink to any task in the Gantt Chart.
Quiz Answers
1. D. Format your task bars in the Bar Styles dialog box.
2. B. There is no such thing as a “floater” in Project 2000.
3. True. The Organizer allows you to share elements between projects.
4. C. Erasing a Project 2000 default view does not allow you to customize.
5. B. Menus are always saved in the Global.mpt file.
6. D. Macros are a series of commands and functions.
7. A. You can add four types of hyperlinks to task or resources: Web address, E-mail, File,
and Current document.
234 Index
Index
A E
Assign Earned Value........................................142
material resource............................... 92 editing
new calendar ..................................... 74 redo ....................................................30
reassign work .................................. 158 spelling...............................................30
work .................................................. 90 undo ...................................................30
C F
Calendar Filter ....................................................116
assign ................................................ 74 Autofilter .........................................120
create new ......................................... 28 resources ..........................................118
Consolidate ......................................... 184 tasks .................................................117
master project.................................. 184
G
new window.................................... 186
subproject........................................ 184 Group
Cost resources ..........................................114
accrue................................................ 95 tasks .................................................112
earned value .................................... 142
entry .................................................. 94 H
fixed .................................................. 96 help
per use............................................... 94 contents and index .............................40
rate-based .......................................... 94 Office Assistant..................................40
update.............................................. 136 tutorials ..............................................40
view................................................... 97 What's This ........................................40
critical path hyperlinks ............................................224
multiple projects ............................. 192
view................................................. 122 L
Custom Lag time.................................................66
bar style........................................... 208 Lead time ...............................................66
filters ............................................... 212 Leveling
forms ............................................... 216 automatically....................................154
groups ............................................. 210 manually ..........................................156
reports ............................................. 218 Linking
tables ............................................... 214 projects.............................................188
views ............................................... 220
M
D
Milestone .....................................See Task
database................................................. 16
N
Nonworking time ...................................26
O Resource pool
sharing ............................................. 190
Office Assistant......................................40
organizer ..............................................222 S
Overallocation .....................................152
Saving
balancing..................................154, 156
baseline plan ......................................36
leveling ............................154, 156, 158
baseline plan .................................... 200
reassign work...................................158
file......................................................34
Overtime ..............................................160
interim plan........................................38
P web page.......................................... 178
Scheduling
Planning Wizard ....................................34
Effort-driven ......................................70
Predecessor ..................................See Task
Material driven ..................................70
Print .....................................................125
overtime........................................... 160
Project
Sort ...................................................... 110
insert ................................................184
resources.......................................... 111
planning .............................................12
tasks................................................. 110
screen.................................................18
spellchecker ...........................................31
Project file
Successor ..................................... See Task
create new..........................................20
template .............................................22 T
Project Information
Tables .................................................. 108
defined ...............................................25
Task
dialog box ..........................................21
constraints..........................................72
entering ..............................................24
copy ...................................................54
multiple project statistics .................194
critical.............................................. 122
statistics ...........................................141
deadlines............................................72
project management...............................14
defined...............................................48
Project Statistics ..................................141
delete .................................................54
Project Triangle
details .............................................. 124
description .........................................14
duration..............................................50
R elapsed duration.................................51
entry...................................................48
Recurring task..............................See Task
indicators ...........................................75
Reports.................................................167
insert ..................................................54
contents............................................172
linking................................................62
details...............................................170
milestone ...........................................52
page elements ..................................176
move ..................................................54
page setup ........................................176
overlap...............................................66
sort ...................................................174
phases ................................................58
types.................................................168
predecessor ........................................62
Resource
recurring task.....................................56
assign material ...................................92
splitting..............................................64
assign work........................................90
subtasks .............................................58
availability .........................................84
successor............................................62
balancing overallocation..........154, 156
summary tasks ...................................58
defined ...............................................81
task information.................................60
details...............................................124
task notes ...........................................60
entry...................................................82
unlinking............................................62
grouping.............................................86
update .............................................. 132
overallocation ..................................152
Task information dialog box
schedule .............................................88
defined...............................................61
type ....................................................83
Timescale...............................................32
update ..............................................134
236 Index