Daily Report in Revised Formats 310120
Daily Report in Revised Formats 310120
Daily Report in Revised Formats 310120
3
Daily Progress Report of CNG & Earthwork
Date- 11/18/2018
Clearing and Grubbing Earthwork in MCW
Approved
Package Work Done Cumulative Borrow Area
No. Daily Work Done Daily Work Done % Remark
Scope (Km) (Km) % Progress Scope (Cum) Work done Qty (Cum)
Target(Km) Today1(Km) Target(Cum) Today (Cum) Progress
Cumulative (Cum)
1 2 3 4 5 6 7 8 9 10 11 12 13
(A) Main Carriageway
I 40.47 40.47 0.00% 9,661,991 39,385 0.00%
II 39.70 39.70 0.200 5.290 13.32% 11,111,631 39,324 1,550 311,350 2.80% 111,000
III 41.70 41.70 0.00% 11,600,000 35,373 0.00%
IV 42.70 42.70 0.00% 9,661,994 34,161 0.00%
V 54.00 54.00 0.00% 12,647,498 41,323 0.00%
VI 28.20 28.20 0.00% 6,884,521 24,298 0.00%
VII 46.08 46.08 0.00% 10,434,296 32,839 0.00%
VIII 47.97 47.97 0.00% 11,184,620 41,271 0.00%
TOTAL 340.824 340.824 0.200 5.290 1.55% 83,186,551 287,973 1,550 311,350 0.37% 111,000
(B) Service Road
I 0.00%
II 55.01 5,000 #N/A #N/A 0.00%
III 0.00%
IV 0.00%
V 0.00%
VI 0.00%
VII 0.00%
VIII 0.00%
TOTAL 5,000 #N/A #N/A 0.00% -
Purvanchal Expressway Project Format D-1.7
Daily Progress Report of Subgrade, GSB, WMM, DBM, BC
Date- 11/18/2018
Subgrade GSB WMM DBM BC
Package Scope* Cumulative Work % Cumulative % Cumulative Work done % Cumulative Work % Cumulative Work done %
No. (Km)
Layer Target till done on Cumulative Excess/
Work done Progress Shortfall
Work done Cumulative
Target till on Previous Work done
Excess/
Progress Shortfall Target till on Cumulative Progress Excess/
Work done Shortfall Target till done on Cumulative Excess/
Work done Progress Shortfall Target till on Cumulative Progress Excess/
Work done Shortfall
Remark
month end Previous (Km) (Against (+/-) month end day (Km) (Km) (Against (+/-) month end Previous (Km) (Against (+/-) month end Previous (Km) (Against (+/-) month end Previous (Km) (Against (+/-)
(Km) day (Km) Scope) (Km) Scope) (Km) day (Km) Scope) (Km) day (Km) Scope) (Km) day (Km) Scope)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
(A) Main Carriageway
Layer-1
I 80.94 8.000 0.000 0.000 0.000 0.000 -
Layer-2
Layer-1
III 83.40 44.800 22.796 12.212 11.398 0.000 -
Layer-2
Layer-1
IV 85.40 34.400 21.800 14.600 11.600 0.000 -
Layer-2
Layer-1
V 108.00 54.000 32.000 9.000 0.000 0.000 -
Layer-2
Layer-1
VI 56.40 18.000 6.000 3.000 0.000 0.000 -
Layer-2
Layer-1
VII 92.17 8.860 8.860 1.610 1.610 0.000 -
Layer-2
Layer-1
VIII 95.94 38.000 27.000 4.500 3.000 0.000 -
Layer-2
681.648 Layer-1 0.000 0.000 0.00% 0.000 0.000 0.00% 0.000 0.000 0.00%
TOTAL 236.060 -30.000 138.456 0.000 0.000 0.00% -20.000 50.922 -6.000 27.608 0.000 0.000 0.000
681.648 Layer-2 0.000 0.000 0.00% 0.000 0.000 0.00% 0.000 0.000 0.00%
II
III
IV
VI
VII
VIII
TOTAL
1- In Main Carriageway the scope of the work is taken as two times length of the package considering LHS & RHS are being constructed separately.
2- The targets will be modified after receiving revised work program from Contractor.
Format D-1.8
STATUS OF ROAD WORKS ON MCW OF PURVANCHAL EXPRESSWAY
PACKAGE NO- 2 Date- 11/18/2018
Package Length:79.400 (3 lane Km)
Daily Progress of GSB, WMM, DBM and Concrete
GSB WMM DBM Concrete
Cumulative
Progress as on 0.000 Km 0.000 Km 0.000 Km
03.08.19
Average Daily Target=
Target 4499 MT 267 m 0 MT 0m ____ MT _____ m 349 Cum
Average of
Month
Cumulative for
6,818 780 42,093 4,535 35,457 9,803 11,478
Month