ETAP Workshop Notes 3D Database: Theoretical Concepts

Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

ETAP Workshop Notes

3D Database
Theoretical concepts
ETAP relies on a three-dimensional database concept to implement all Presentations,
Configurations and Base/Revision Data. The use of this multi-dimensional database concept
allows you to independently select a particular Presentation, Configuration and Revision Data
within the same project database.

These selections can be used in conjunction with multiple loading categories and multiple study
cases to quickly and efficiently perform system design and analysis. This will avoid inadvertent
data discrepancies created when multiple copies of a single project file are used to maintain a
record of various system changes.

This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 1 of 8
ETAP Workshop Notes

3D Database
Purpose and Description
This section is to explain functionalities of 3D database in ETAP which includes Configuration,
Presentation and Base & Data Revision.

Creating Configurations
Procedure
1. Open LF-Example OTI file shown below.

2. Go to Configuration Manager, Click on New to create a new configuration and name it


as Single out.

Configuration
Manager

This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 2 of 8
ETAP Workshop Notes

3D Database

3. Click on Configuration Status drop down button, select Single out configuration and
proceed to make changes in the configuration as shown below.

This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 3 of 8
ETAP Workshop Notes

3D Database
4. Go to configuration manager, check for the device status as shown below.

5. Check Differences in Display Options to note the differences in the configurations as


shown below.

This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 4 of 8
ETAP Workshop Notes

3D Database
Creating Presentation
Procedure
1. Click on New Presentation to create OLV2 as shown below.

New
Presentation

2. To hide CB1, right click on it & uncheck visible option as shown below. Similarly hide
all circuit breakers except bus couplers.

This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 5 of 8
ETAP Workshop Notes

3D Database

3. Compare both the OLV1 & OLV2 as shown below.

This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 6 of 8
ETAP Workshop Notes

3D Database
Revision data
Procedure
1. Click on Data Manager to create new revision.

Data Manager

2. Click on Create and name new revision as Revision 1.

3. Select Revision1, change %Z of transformer T1 & T3 to 12% in the OLV.


4. Go to Base revision, click on Data Manager to compare Base and Revision1.
5. Click on Properties in the Display options to view the changed data.

This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 7 of 8
ETAP Workshop Notes

3D Database

6. Create new revision as Revision 2.


7. Select Revision2, change %Z of transformer T2 & T3 to 8%.
8. Go to Base revision, click on Data Manager to compare Base and Revisions.
9. Click on Properties in the Display options to view the changed data as shown below.

10. Click on Merge button & merge Revision 1 inside Revision 2. Check the results of
merge operation as shown below.

This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 8 of 8