Chapter - 2 "Audit Strategy, Planning & Execution": Lecture - 18
Chapter - 2 "Audit Strategy, Planning & Execution": Lecture - 18
Chapter - 2 "Audit Strategy, Planning & Execution": Lecture - 18
(i) Meaning:
(a) Developing an overall plan for the expected scope & conduct of audit and
(b) Developing an audit programme showing NTE of Audit procedures
18.1
Audit Planning, Strategy and Execution Chapter 2
(2) Audit Strategy:
(i) Meaning:
Designing Audit Approaches to achieve necessary audit assurance at the lowest cost.
whole.
18.2
Chapter 2 Audit Planning, Strategy and Execution
- Audit strategy and audit plan are inter-related to each other because change
- The audit strategy is prepared before the audit plan. The audit plan contains
- The audit strategy provides the guidelines for developing the audit plan.
- Audit strategy establishes the scope, timing and direction of the audit and
- Detailed audit plan would include the nature, timing and extent of the audit
18.3
Audit Planning, Strategy and Execution Chapter 2
(3) Audit Programming:
(i) Meaning:
(a) Detailed plan of work prepared by auditor for carrying out an audit.
control.
procedures etc.
18.4
Chapter 2 Audit Planning, Strategy and Execution
(iv) Circumstances requiring changes in Audit Programme:
requirements of SA 315.
(a) List the risk that need to be reviewed for each segment of audit.
(b) Capture for each risk the controls that exist or those that are needed
controls.
Note: While making Risk & Control assessment auditor need to consider the
Materiality levels.
designed.
of accounting data.
18.5
Audit Planning, Strategy and Execution Chapter 2
(a) The auditor should review and assess the conclusions drawn from the
on the F.S.
required by SA 700.
18.6