Test Report

Download as docx, pdf, or txt
Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1/ 7

Test Record

SAMPLE PRESSURE RECORD


Company
System

Description of instrument (make/model) Serial number of instrument


Test section no.miles MP to MP Station no. to Station no. Location of chart recorder MP Station no. Start: Time
Date
End: Time Date Contractor rep. Title Date Pipeline company rep. Title Date Project engineer Date

Notes:
MP = mile post.
This pressure information should be included on the permanent record of pressure versus time. Placing this information on a stick-on label and sticking
the label to the permanent record might be considered.

Figure A-1—Sample Pressure Record

SAMPLE TEMPERATURE RECORD Company


System

Description of instrument (make/model) Serial number of instrument


Test section no.miles MP to MP Station no. to Station no. Location of chart recorder MP Station no. Start: Time
Date
End: Time Date Contractor rep. Title Date Pipeline company rep. Title Date Project engineer Date

Notes:
MP = mile post.
This temperature information should be included on the permanent record of temperature versus time. Placing this information on a stick-on label and
sticking the label to the permanent record, or using a rubber stamp, might be considered.

Figure A-2—Sample Temperature Record


SAMPLE PRESSURE TEST Test section
RECORD AND CERTIFICATION Date

Company System
Description from to
New construction ❍
Requalification ❍ Replacement or relocation ❍ Pipeline ❍ Station ❍
Test medium: water ❍ Other Inhibitor Design data
code: ❍ B31.4 ❍ B31.8 (Appendix N) ❍ Other

Pipe design data

Specification Weld joint Design Wall Design


and grade factor factor OD thickness SMYS pressure Comments

Pressure test:
Test pressure should be as follows:
Minimum at high point % SMY Maximum at low point % SMY

Elevations: Low point High point DWT


Qualifications:
Date of test: Duration of test
Testing and recording witnessed by Date
Company Title Company representative
Title

Testing pressure:
Maximum at low point for % SMYS
Minimum at high point for % SMYS
Qualified to operate at for % SMYS
Report checked by Date
Approved by Time
Testing company

Attached documents:
Pressure record ❍ Pressure and temperature log ❍ Temperature record ❍
Test instrument calibration data ❍ Sketch or diagram ❍ Qualification calculations ❍
Profile ❍ Failure records ❍

Comments:

Notes:
OD = outside diameter, SMYS = specified minimum yield strength, SMY = specified minimum yield, DWT = deadweight tester.
For test sections containing more than one type of pipe, the maximum test pressure at low point and minimum test pressure at high point and
resulting SMYS need to be calculated for each type of pipe.

Figure A-3—Sample Pressure Test Record and Certification


SAMPLE QUALIFICATION
CALCULATIONS Company
System

Pipeline Data (at controlling location) OD WT Specification


Internal pressure at SMYS psi
Test medium: Fresh water? (Yes, at 0.433 psi/ft) (No) Other at psi/ft
Design test pressure: Maximum psi Minimum psi
Test section number
From station (MP ) to station (MP )
Time and dates: From hours to hours
(Time) (Date) (Time) (Date)
Deadweight tester data
Location: Station (MP ) Elevation ft Tester pressure: Beginning psi
ending psi minimum psi Acceptable? (Yes) (No)
Use tester pressure of psi at station Elevation
(P) (E)

Minimum Pressure in Test Sectiona Maximum Pressure in Test Sectiona

Highest elevation in test section ft Lowest elevation in test section ft


(H) (L)
Location: Station (MP ) Location: Station (MP )
Difference in elevation from tester: Difference in elevation from tester:
– = ft – = ft
(H) (E) (H) – (E) (E) (L) (E) – (L)
Pressure at highest elevation: Pressure at highest elevation:
= Tester pressure – (Difference in elevation x psi/ft) = Tester pressure – (Difference in elevation x psi/ft)
= – ( x ) = – ( x )
(P) (H) – (E) (P) (E) – (L)
= = Minimum test pressure = = Maximum test pressure
= % SMYS = % SMYS

--`,,`,,`,,,,`,````,,`,```,,``,-`-`,,`,,`,`,,`---
Maximum allowable operating pressure in this test section = 72% SMYS = psi or
80% minimum test pressure = psi or
or controlling component (circle whichever is lowest).
Calculated by Approved by
Remarks

Date

Notes: OD = outside diameter, wt = wall thickness, SMYS = specified minimum yield strength, MP= mile post, p = pressure, E = elevation, H = highest, L =
lowest. aFor test sections containing more than one type of pipe, the 72-percent SMYS minimum test pressure and resulting percentage of SMYS need to be
calculated for each type of pipe and used in determining the maximum allowable operating pressure.

Figure A-4—Sample Qualification Calculations


SAMPLE PRESSURE AND Company
TEMPERATURE LOG System

Test section no. From station no. MP


to station no. MP
Pressure/temperature sensor station no.
Start of test period: Time Date
End of test period: Time Date

Pressure Pipe Ambient Pressure Pipe Ambient


No. Time (psig) temp. temp. No. Time (psig) temp. temp.

1. 25.

2. 26.

3. 27.

4. 28.

5. 29.

6. 30.

7. 31.

8. 32.

9. 33.

10. 34.

11. 35.

12. 36.

13. 37.

14. 38.

15. 39.

16. 40.

17. 41.

18. 42.

19. 43.

20. 44.

21. 45.

22. 46.

23. 47.

24. 48.

Figure A-5—Sample Pressure and Temperature Log


--`,,`,,`,,,,`,````,,`,```,,``,-`-
`,,`,,`,`,,`---

PRESSURE TEST Company


RECORD OF FAILURE System
Line section
From station no. to station no.

Leak Leak Leak Deadweight Deadweight Deadweight Failure


Date Time Station No. Elevation (psi) Elevation (psi) Station Description
PR
ES
SU
RE
TE
STI
NG
OF
LI
QU
ID
PE
TR
OL
EU
M
PI
PE
LIN
ES

13

Copyright American Petroleum Institute


Reproduced by IHS under license with API Licensee=Perez Companc/5955403001
No reproduction or networking permitted without license from IHS Not for Resale, 09/27/2004 13:22:34 MDT

You might also like