Switchgears and Switchboard Assemblies
Switchgears and Switchboard Assemblies
5. Verify the fuse and/or circuit breaker sizes and types correspond to drawings and
coordination study as well as to the circuit breakers address for microprocessor-
communication packages.
7. Inspect bolted electrical connections for high resistance using one of the following methods.
8. Confirm correct operation and sequencing of electrical and mechanical interlock systems.
9. Lubrication requirements
14. Verify that filters are in place and/or vents are clear.
15. Perform visual and mechanical inspection of instrument transformers in accordance with
Section 7.10.
2. Verify that primary and secondary fuse or circuit breakers ratings match drawings.
3. Verify correct functioning of draw out disconnecting and grounding contacts and
Interlocks.
2. Electrical Test.
4. Perform insulation-resistance test on each bus section, phase to phase and phase to ground
for one minute in accordance with table 100.1.
5. Perform an overpotential test on each bus section, each phase to ground with phases not
under
8. Perform current injection tests on the entire current circuit in each section of switchgear.
1. Perform current tests by secondary injection with magnitudes such that a minimum
of 1.0 ampere flows in the secondary circuit. Verify correct magnitude of current at
each device in the circuit.
2. Perform current tests by primary injection with magnitudes such that a minimum of
1.0 ampere flows in the secondary circuit. Verify correct magnitude of current at
each device in the circuit.
9. Determine accuracy of all meters and calibrate watt-hour meters in accordance with Section
7.11. Verify multipliers.
10. Perform phasing check on double-ended or dual-source switchgear to insure correct bus
phasing from each source.
3. Verify correct secondary voltage by energizing primary winding with system voltage.
Measure secondary voltage with the secondary wiring disconnected.
4. Verify correct function of control transfer relays located in switchgear with multiple
control power source.
2. Perform secondary wiring integrity test. Verify correct potential at all devices.
3. Test Values
2. Bolt-torque levels should be in accordance with Table 100.12 unless otherwise specified
by manufacturer.
3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as
indicated in the manufacturer’s published data. If manufacturer’s data is not available,
investigate any values which deviate from similar bus by more that 50 percent of the
lowest value.
6. Insulation-resistance values for control wiring shall be a minimum of 2.0 mega ohms.
ATS-2003.24