Module 3 - Supply Chain Management Practice Problems
Module 3 - Supply Chain Management Practice Problems
Practice Problems
1. Consider an item that is ordered on a monthly basis. The daily demand for the item is
200 and the lead-time for supply is 7 working days. A month consists of 25 working
days.
a. What is the average cyclic inventory in the system?
b. What is the pipeline inventory in the system?
2. For the above problem let the cost of ordering is USD 100 per order and the cost of
carrying inventory is USD 10 per unit per year of inventory.
a. What will be the cost of the existing plan of ordering inventory?
b. What will be the economic order quantity (EOQ)?
c. What will be the new cost of the plan if the organization chose to order as per
EOQ?
4. Consider the above situation. Suppose the demand has gone up by 10%. What will be
the impact (in terms of the cost of the plan) if the company decides to order with the
revised EOQ?
5. Consider an item with the following demand attributes:
Mean weekly demand = 140; Standard deviation of weekly demand = 50; Review
Period = 2 weeks.
a. Compute the safety stock required for a periodic review system when the lead
time is 1 week and the desired service level is 95%.
b. What is the order-up to-level for this policy?
The supplier of the item takes on an average 2 weeks to deliver once the order is
placed. Design an appropriate inventory control policy for a periodic review system
for a review frequency of 4 weeks for a 99% service level
1 (a) Every time the inventory ordered is 5,000. Since the inventory in the system
varies from 5,000 to 0, the average cyclic inventory is 2500; 1 (b) 1400
2 (a) USD 26,200; (b) 1095.45 (or 1096); (c) USD 10,960
3 (a) 692.8 (or 693); (b) 57.74 (or 58) orders in a year; (c) total ordering cost = total
carrying cost = 34,640 (numbers may slightly vary if we compute with rounded
values) (d) Both values are same (numbers may slightly vary if we compute with
rounded values)
4 For the increase in demand (10%). if we revise EOQ and accordingly the cost of the
plan, the new cost is total ordering cost = total carrying cost = 36,332, representing
only about 4.88% increase in cost of the plan.