Manual B4601
Manual B4601
Manual B4601
0-2520-9302-01
Department Academy
Operating Manual Version 01
Language English
13-8874 ① P1 1 2013.11.20. 孙青
Operating Manual 0-2520-9302-01
Contents
1. Preface
3. Turbine installation
3.1 Preparation before installation
3.2 Installation
2-0300-01-01 Foundation prepare work
2-0310-01-01 Second foundation
2-7600-01-01 Thermal insulating layer
①1 处 13-8874 孙青 2013.11.20
Operating Manual 0-2520-9302-01
4.2 Starting up
-15 ℃
Inlet temperature:440+10
Extraction pressure: 0.3 MPa(a)
Vibration:
Allowable max. vibration value (outer shell) is 0.04mm during normal running
Steam turbine body:
Rotor weight: 5.25t
Hanging weight of upper cover: 7.9t
The weight of body section: 22.9t
Contour size of turbine body (length×width×Height): 4000×3500×3500
Hanger height: 5.5m(starting from working plane)
Regulating system:
Speed unequal rate: ~4%
Synchrony range: -6~+6%
Safety system
Action speed of emergency governor gear: 3270~3330r/min
Axial Displacement clearance of safe action:
Alarm: ±0.4mm
Stop: ±0.6mm
Assistant oil-pump catenation:
Startup oil pressure: 0.65Mpa(g)
Accident oil-pump catenation:
Startup lubr-oil pressure: 0.8Mpa(g)
Bearings tile temperature:
Alarm: 90℃
Stop:100℃
Fueller:
Non-oil weight:7.5t
Oil tank volume:5.3m3
Oil-box non-oil weight: 1.9t
Control Valve
The control valve functions for regulating the steam flow based on the command from
the control unit to make the controlled parameters (output or speed , inlet steam pressure,
back pressure and etc.) of the turbine meet the operation requirement. Fig.1 shows the
structure of the control valve.
The control valve consists of three main sections, the governing valve-- valve spindle,
valve beam, valve cone and valve seat, the operating mechanism-- support and lever, the
oil relay (refer to 1-1900-01-xx).
Based on the structure of the turbine casing and the requirement of the running
condition, one turbine may be equipped with 5 or 4 governing valves showed in Fig.2.
Fig.2 shows assembling of the governing valve schematically. The valve cone bolt (16)
is screwed in the valve cone (6) to the desired tightening moment and locked with taper
pin (17) (for the tightening moment, see the enclosed table below). The end of the pin
hole is flanged and riveted. The opening order and travel of each valve are determined
by the length S of the bush (7). h in the fig.2 means the valve idle travel. For the first
valve, h=2. The valve seat (8) is mounted in the bottom of the admission chest.
The admission chest showed in Fig.1 is adopted in most of the turbines. In this case, the
valve cones and the valve beam are mounted into the admission chest from its side after
they are assembled together. The valve beam is suspended in the seam chamber via two
valve spindles (9). The lower end of the valve spindle is shaped into the rabbet of
inverted-T. The rabbet is penetrated the hole in the valve beam and turned by 90 degrees,
so that the valve beam is seized. The valve cone is freely suspended in the valve beam
with the aid of the valve cone bolt. As long as the turbine remains at standstill, the valve
cone is seated upon its valve seat. When opening the valve, the valve beam is lifted by
the valve spindles and after the bush contacted to the valve cone bolt the valve cone will
thus be opened. The cover (3) is mounted at the place where the spindle penetrates
the admission chest. The guide bushes (10 and 12) are fitted at the upper and lower ends
of the cover, between them the seal ring made of flexible graphite is filled. In order to
eliminate the steam leaking around the valve spindle, tighten the press nut on the cover
to increase the tightening force on the seal ring, if necessary.
In some of the turbines the valve spindle packing showed in Fig.3 is used. The leakage
1. Sleeve
2. Bush
3. Bush
4. Seal ring made of flexible
graphite
5. Press nut element
Fig. 3
In the turbines with lower inlet steam parameter, the admission chest is slightly different
to that showed in Fig.1. In this case, the top of the admission chest is opened so as to
facilitate the mounting of the valve beam. The elliptical-shaped opening is covered with
the flat cover of the steam chamber. The valve spindle guide and sealing element are
mounted in the cover.
The support (13) is mounted on the casing top and positioned with the cylindrical pin.
The revolution axis of the support is severed as a pivot point for the lever (1). The one
end of the lever is connected with the valve spindle via the link (2), the other end is
hinged with the joint bearing at the top end of the oil relay connecting rod. When the oil
relay travels the valve beam will be lifted or lowered with the synchronization action of
two valve spindles.
The spring (14) is used against the steam force on the valve spindle and for supplying
sufficient closing force for the valve at the same time.
The bracket (11) used for supporting the oil relay (15) is mounted on the front end face
of the top casing. The oil relay is jointed to the bracket with the joint bearing and pin.
Therefore, the oil relay will swing in a narrow range around the pin during operation.
In order to eliminate the external force and moment that act on the oil relay and disturb
its normal operation, 2 or 3 groups of disk springs are fitted between the oil relay and
the bracket as required. Two groups of disk springs are adjusted according with the
The scale plate mounted on the side of the oil cylinder indicates the travel of the control
valve.
⎠ Caution: The piston rod of the oil relay can only be connected to the lever
when the following requirements are met for avoiding the valve
spindle pressed and bended. The piston of the oil relay should be
at position 0 (upper dead point) and the valve beam does not
contact to the valve cone with a minimum distance of 2 mm (see
Fig.2). The 0 position is indicated on the scale plate.
The first valve adopts the tapered valve cone for increasing the stability the turbine test
running and non-loaded operation of the turbo-generator (for individual turbine,
the second valve adopts the tapered cone too). The others are ball valve. In order to
improve the stress of the casing and the blades of the control stage, the second valve is
pre-opened and has a larger overlap with the first valve.
For the valve opening order , valve travel and flow of the control valve, refer to the
attached document “Characteristic line of control valve” 0-2505-T.Nr-00.
The spare part of the seal element for the valve spindle is supplied with the turbine set
(see “Spare parts list” for details). It can be changed if required.
“Mounting tool for valve beam” 2-8821-9005-xx supplied with the turbine set (only
supplied for the control valve larger than N40 or H32) is used to mount the valve beam
assembly into or dismount it from the admission chest from the casing side opening. For
the turbine with one emergency stop valve, the valve beam is mounted into or
dismounted from the opening located one side of the flange cover. For the turbine with
two emergency stop valves, when dismount the valve beam dismount one emergency
stop valve and valve seat, then take the valve beam assembly out with the mount
Adjusting system
Oil-relay
3. 活塞 piston
4. 壳体 body
6. 小孔 little hole
11. 弹簧 spring
Figure 1 oil-relay(Ⅰ)
Function
The oil-relay transfer the secondary oil signal input from govemor to the piston path,
controlling the opening of adjusting steam valve with lever, so ad to the steam flow rate into turbine
matches the needed flow rate and power.
Structure
Oil-relay consists mainly from pilot slide valve(8), body(4), piston(3) and feedback system,
oil-relay piston and valve installed commonly in the housing. On the piston rod(2) are installed the
feedback plate(1), the rotating disk(9) situated on pilot slide valve. Between rotating disk and spring
support installed thrust ball bearing(10). The acting force of spring depend on the position of
adjusting screw and bend angle lever.
Working principle
The variation of secondary oil pressure causes the up and down movement of pilot slide valve,
when the oil pressure rise, the slide valve move upwards, the pressure oil from pressure oil
opening(7) flows into piston upper section of oil-relay, and the piston lower section interlinked the
oil drainage opening, so as to move the piston downwards, and through lever system of adjusting
steam valve increase the opening of adjusting valve. At the same time, feedback plate(15) and bend
angle lever transmit the movement of piston to the adjusting screw(12), the adjusting screw
generates the reverse movement against pilot valve to enhance the feedback spring(11) force, ad the
result, the pilot slide valve return back on the middle position.
With adjusting bolt on the piston rod adjust obliquity of feedback plate to improve the ratio
between secondary oil pressure and piston rod path. The figure shows both are linear relation.
The role of feedback system is to be stabilized the action process, it forms feedback link with
bend angle lever, feedback plate and piston rod and pilot slide valve. The needle bearing(14) of one
nd of bend angle lever withstand against to feedback guide plate, the other end is connected th
adjusting bolt, which on acted the spring.
When the oil-relay acted, the returning oil feeds back to the oil absorbing opening of main oil
pump, the drainage oil of the oil-relay flows direct to the tank.
Figure 3 oil-relay(Ⅱ)
Emergency Governor
The emergency governor is a mechanical protection equipment of the turbine. It will
close the emergency stop valve and control valve via the emergency trip gear when the
turbine speed rose to the set tripping speed.
Usually, the emergency governor is fitted in the turbine rotor at the section located in
the front bearing housing, as showed in figure above. The guide ring (8) is fitted in
suitably machined bore in the rotor and pressed by the compression spring (9), which
presses the shoulder of the eccentric bolt (5) with other end. The supporting surface of
the eccentric bolt is against the positioning surface of the guide ring (4) that is pressed
on the positioning surface in the bore by the threaded cap (2) tightly. In the central hole
of the eccentric bolt the counterweight pin (6) is placed. The limit stud (1) is fixed in
the threaded cap to restrict the movement of the counterweight pin. The threaded cap
and the limit stud are locked with the headless screws (10). The counterweight screw (7)
is screwed in the hole of the eccentric bolt. In the guide rings the guide bushes (3 and 7)
made of Teflon are fitted, which are used for positioning and guiding the eccentric bolt.
An eccentricity exists between the centroid of the eccentric bolt with
the counterweight pin, so when the rotor rotating, the eccentric bolt will produce a
centrifugal force. Since the spring force is always larger than the centrifugal force of
the eccentric bolt within the operating speed range, the eccentric bolt remains at its
mounted position and does not move. Whenever the turbine speed is about to exceed
the set trip speed, the centrifugal force of the eccentric bolt overcomes the spring force,
diving the eccentric bolt in outward direction. The centrifugal force will increase steeply
with the increase of the eccentricity. Thereby the eccentric bolt moves out of the rotor
The reset speed (the speed at which the eccentric bolt return to its mounted position) of
the emergency governor for 3-series turbine is higher than the rated speed, so
the emergency trip gear can be reset when turbine speed dropped to the rated
speed, restarting the turbine.
The setpoint of the trip speed for the emergency governor is given in the technical data
section 0-0300-T.Nr.-xx of the Operating Instructions.
The action speed of the emergency governor when testing in the workshop of
the manufacturer is recorded in the “Report of Dynamic Balance and overspeed test for
Rotor” and the “No-load Test Report” of the Product Certificate.
When examining and repairing the emergency governor, use the attached tool
“Tow-hole Nut Driver” No.2-8811-0002-xx to mount or dismount the threaded cap. To
mount or dismount the counterweight screw, turn out the screw plug, turn in
the attached tool “Adjusting Bolt” No.2-7760-0001-xx to fit its taper end tightly against
the tapered hole in the eccentric bolt. In this way, the rotation of the eccentric bolt can
be prevented when the screw turned.
Solenoid Valve
Function
Two position Three way solenoid valve is mounted on the pressure oil pipe,
which is into the emergency system. It is able to cut off the pressure oil that is into
the emergency safety device, also result in the reaction of the emergency safety
device to make the trip oil discharge and make the trip valve shut down rapidly at
last.
The solenoid valve is controlled by the central control room or some protect
device (according to the actual need the solenoid valve is interlocked with the
protective physical value, which is converted into the electrical signal by the real
protect device).
Because the solenoid valve is the purchasing part, the detailed introduction is
1. 手柄 handle
3. 套筒 sleeve
6. 套筒 sleeve
7. 滑阀 pilot valve
8. 弹簧 spring
9. 活塞 piston
11. 壳体 body
图1 危急遮断油门
axial displacement of rotor is too big), the acting of emergency stop valve drainage
the emergency oil in emergency valve, at this time , the emergency valve rapidly
shut down, cut off the steam source into turbine. The emergency stop valve can only
Structure
Emergency stop valve installed on bearing support, slide valve can slide up and
down in the sleeve(3,6) correspondent to the end face the position limit and oil
pipeline sealing role. When the emergency stop valve don’t work, the spring(3) push
the slide valve the contacted position against to sleeve(3) end face.
The lower end of slide valve connected with carrier block(10) by the piston(9),
The lower end of slide valve connected with carrier block(10) by the piston(9),
The upper end of slide valve connected with handle(1) by positioning block.
Mode of action
When turbine on operation(figure 1), the slide valve of emergency stop valve
lies on inlet opening (4) of pressure oil, throughout throttle hole plate form the
emergency stop oil into emergency stop valve. Because the acting force of emergency
oil on the slide valve is bigger than the spring force, so that the slide valve
shoulder will be hermetically pressed on the end face of sleeve(6) and cut off the
return oil(12), the emergency oil flow through the oil opening (5) out of housing,
shoulders on rotor.
The obtain mentioned cases equally are: slide valve(7) divorced from sleeve(6).
Because of throttling function of throttle hole plate, at this time the oil
pressure in front of pilot valve is reducing rapidly, spring(8) push slide valve
to the end face of sleeve93), into emergency stop valve, the oil way is cut off ,
meanwhile emergency oil in front of sleeve(3), into emergency stop valve, the
oil way is cut off, meanwhile emergency oil in front of emergency stop valve
connected with the return oil, so as shut down emergency stop valve, halt the
turbine.
The emergency stop valve is mounted horizontally on the side of the turbine steam
chamber. One turbine may be equipped with one or two emergency stop valves based on
the steam flow admitted to it.
Fig.1 shows the emergency stop valve without independent valve casing used in the
turbine of model N. Its principle parts are a seam section and a hydraulic section. It is
usually used in most of the 3-series turbines. Fig.4 shows the emergency stop valve with
an independent valve case.
The steam section mainly consists of items 1 to 8 and item 18. The valve cover (5) is
used not only for sealing the end face of the admission chest but also as a connection of
the steam section with the hydraulic section.
Before the emergency stop valve opens, the live steam, after having passed the steam
strainer (3), arrives to the compartment before the valve cone (1). The valve cone is
pressed on the valve seat (18) under the steam force and the spring force (14), blocking
Hangzhou Steam Turbine Company Limited Page 1 of 5
Operating Instructions
Emergency Stop Valve (N) 1-2300-01-01
the live steam to the turbine. The relief cone (2) is provided in the valve cone, which
helps in reducing the actuating forces when the emergency stop valve is being opened,
because it tends to balance the pressure differential existing between the upstream and
downstream sides of the valve cone.
During the emergency stop valve being opened or after it closed (the isolation valve has
not been closed), a part of steam leaking out between the valve spindle (7) and the guide
sleeve (4) and labyrinth bush (6) will be drained off through connection K. As long as
the emergency stop valve is open, the valve cone contacts to the seal face of the guide
sleeve tightly, blocking the steam leaking along the valve spindle.
Most of the steam strainers used in the emergency stop valve are made of corrugated
stainless steel band through winding. But the welded steam strainer made of stainless
steel band with holes is also used in some of the turbines.
The hydraulic section mainly consists of oil cylinder (10), piston (13), spring (14),
piston disc (16) and sealing element. The oil cylinder is bolted on the valve cover (5).
On the end face of the oil cylinder three extension bolts are fitted for safety in mount
and dismount. The boltholes on the oil cylinder are fitted with thread bushes. Caution:
the bolt (8) and the nut (9) must be used in mounting and dismounting the oil
cylinder; otherwise the human injury can result.
The hydraulic section is the active element of the emergency stop valve. When opening
the emergency stop valve with the starting control (1-1840- ), the starting oil F flows to
the right of the piston (13), the oil pressure against the spring (14) force presses the
piston to the piston disc (16), making the sealing faces of the piston and the piston disc
contact each other. After that the trip oil E flows to the left of the piston disc. The
staring oil begin to drain under control with the trip oil pressure behind the piston disc is
building up. Thus, the piston disc and the piston, as an integral part, move rightwards
under the pressure difference at both sides until limited by the test piston (12). The right
end of the valve spindle is connected with the piston disc, the emergency stop valve will
opens with the movement of the piston disc.
The close of the emergency stop valve is actuated by the protection system. Once any of
the loops in the protection system acts, the trip-oil pressure will be lost. The piston will
separate from the piston disc under the action of the spring force, the trip oil at the left
of the piston disc drains through connection T1, the piston disc, together with the valve
spindle and the valve cone, is pushed to the close position.
As showed in Fig.2, a test piston (12) is equipped in the hydraulic section. It, together
with the test valve and the pressure gauge, forms a test device of the emergency stop
valve for checking the proper function of the emergency stop valve during turbine
operation.
If the emergency stop valve functions properly, P2<P1. Here, P1 is the permissible test
pressure; P2 is the actual test pressure at which the test piston begins to move.
The permissible test pressure can be calculated with the following formula:
P1≤A+B(P4-1)
Where:
A, B The characteristic value related with the size of the emergency stop valve,
see Technical data 0-0300-T.Nr-00
P4 Trip-oil pressure when turbine operation
The emergency stop valve can be equipped with the position switcher, as required, for
sending out a corresponding signal when the valve is at full-opened or full-closed
position.
The emergency stop valve is divided into 6 sizes based on the diameter of the live-steam
inlet, they are 100, 125, 150, 200, 250 and 320. All of them have the same structure
except for 320.
The emergency stop valve 320 has a larger valve cone, in order to reduce the lifting
force in opening the valve cone and avoid valve spindle bended, the valve cone, valve
cover and valve seat shown in Fig.3 are used. The remaining parts is the same as that
showed in Fig.1.
Fig.4shows the emergency stop valve with an independent casing. Its structure and
working mode is the same as described above except for the valve casing.
Function
The oil pump provides pressure oil to the turbine units, so as to use for
bearing’s lubrication and rotor axle diameter’s cooling and as control oil for
hydraulic regulation and safety. When the oil pump fails and turbine stop, and then
Structure
The oil pump consists mainly from guide wheel(1), antivortes baffle(3), raction
turbine rotor and radial positioned by key, sleeve is axial positioned. Guide wheel
is one casting with radial absorb oil inlet, on antivertex is installed guide blade,
the oil of traction wheel outlet flow through guide blade of antivortex, its flow
veloctity is reducing and generates the expansion pressure function. The oil pump
Principle
The working speed of oil pump is the turbine speed, pump absorbs the needed oil
mass from tank and generates the pressure correspond to traction wheel speed and
pipeline characteristics, the pressure oil with one way lead to hydraulic, another
way through throttle, after reaching of definite pressure through oil cooler and
Lube-oil Throttle
The throttle is used in lube-oil line for control the oil flow. Its structure is shown in the
picture.
There are two forms of casing (4) available; one for connecting to the piping with the
welding connection (5) as showed in the picture, the other is connected to the piping
with flanges. The casing is made of carbon steel or stainless steel as required.
The oil flow to the bearing is adjusted through varying the stroke of the throttle screw
(6), keeping the temperature rise of the bearing within the permitted range during
turbine operation. To adjust, remove the cover screw (1), after loosing the cap nut (2),
turn the throttle screw counterclockwise with a screwdriver or inner-hexagon spanner to
make it move upwards. This will increase the opening of the throttle and decrease the
differential pressure before and after the throttle, resulting in oil flow increased. The
opening of the throttle is restricted by its structure. It cannot be opened fully even if the
throttle screw is at its maximum stroke, because the excessive oil will fill up the bearing
housing. Turning the throttle screw clockwise will reduce the oil flow. In order to avoid
blocking the oil due to misoperation, the minimum flow about 0.5m3/h is permitted in
its lowest position.
1. Cover screw
2. Cap nut
3. Seal ring
4. Casing
5. Welding connection
6. Throttle screw
7. Seal ring
After adjusted, the cap nut must again be firmly tightened and the cover screw must be
screwed in again.
1. Adjustable sleeve
2. Spring seat
3. One-way valve
5. Retaining ring
6. Retaining ring
7. Spring
8. Valve casing
9. O-ring
The secondary oil enters into the valve casing (8) from the end B. The one-way valve (3)
is pressed against the valve seat under the action of the spring force (7) and oil pressure,
the secondary oil flows to the end A through bypass holes on the one-way valve and the
throttling passage between the valve casing and the adjustable sleeve (1). If the pressure
at end A is higher than that at the end B by 0.05 MPa, the one-way valve is opened. The
oil flows in the opposite direction without throttling, so as to unload the turbine quickly.
Turn the adjustable sleeve to change the area of the throttling passage infinitely. Turning
the sleeve clockwise (looking from B to A) will decrease the area of the passage, while
turning it in the opposite direction will increase the area. There are a scale ring on the
conical surface of the sleeve (1) in proximity of the end A and reference scale and
indicating ring on the end A of the valve casing, which indicate the working position of
the one-way throttling valve.
When adjusting, if pressure gauges are fitted at both ends of the valve, turn the sleeve
and observe the readings on the gauges. When the pressure after the valve decreases
modestly and the differential pressure between two ends reached 0 <△P<0.01MPa, turn
bake the sleeve by 1 to 2 scales. If there is no pressure gauge after the valve, it is
recommended to set the one-way throttling valve during static adjusting of the control
system before turbine start-up. In this case, turn the sleeve counterclockwise to fully
open the valve, and then change the secondary-oil pressure from the amplifier (or
electro-hydraulic converter) to bring the oil-relay stroke corresponding to the
secondary-oil pressure 0.15 to 0.45MPa in correspondence with the requirement defined
on the Characteristics Line (No.0-2500-T.Nr-00). After that, set the secondary-oil
pressure at 0.15MPa and the oil-relay stroke at 0, turn the sleeve clockwise until the
reset bar of the oil relay separates from the rolling bearing. Turn back the sleeve by 1 to
Turbine Oil
Usually, turbine oil of the type L-TSA46 or L-TSA32 is selected for lubricating and
control system of the turbine, except for the electric-hydraulic control system with
fire-resistant oil.
The type of the turbine oil that is used for your turbine is specified in the Technical Data
(0-0300-T.Nr.-00).
The fresh oil quality should be in compliance with the specification given in the
standard GB11120.
The inspection items and period, the quality standard that should be reached for the oil
during turbine operation are listed in the table 2.
Visual
1 Appearance Transparence
inspection
Visual
4 Mechanical impurities Nonexistence
inspection
GB/T7600 or
8 Water content mg/L ≤200
GB/T7601
The inspection items listed in the table 2 are the routine inspection items, all of them are
required to be carried out before the newly mounted turbine put into operation or after
the turbine overhaul. After the turbine has been operated, the inspections should be
carried out at least once a time for every year. The item 1 and 4 should be made at least
once a time for every week. The period of the inspection may be prolonged properly if
the turbine runs normally. However, if the oil is found with water, the inspections
should be increased and the proper treatment should be made in time.
The item 4 “Mechanical impurities” in the table 2 is checked with eyes. If the solid
pollutant is not visible in the oil sample, it is assumed that there is no impurity
(Nonexistence) in the oil. Since the human eyes can not see the particle smaller than
40μm. The “nonexistence” only indicates that there is no solid pollutant larger than
40μm in the oil. The visual inspection is a quick and ease method but with a rough
result. The user is recommended to inspect the mechanical impurities contained in the
oil quantitatively with proper instrument.
For the inspection items and range for flush of the oil system after the turbine overhaul,
please refer to this instruction.
For the turbine using the electric-hydraulic control system with fire-resistant oil, the
flush for the fire-resistant oil system should be carried out according with the relative
procedure.
It is recommended that the oil system is flushed with the same type and performance of
oil that is employed for normal turbine operation.
1. Preparations
1.1 Oil tank
Before filling up with the scavenging oil, the strainer must be cleaned first. Clean the
inside of the oil tank with the new cloth and then clean out the residues with paste.
1.4 Bearings
For the turbine below size 40 (including size 40), remove the radial and thrust bearings.
the turbine rotor is supported on the gland bush temporary during oil flushing.
1.14 For the turbine with its own main oil pump, block the inlets and outlets of the main
oil pump and injector. Remove the regulating valve of the injector. connect the inlet and
outlet piping of the main oil pump to the cycle piping for flushing with oil.
1.15 Instruments
The instruments in the oil system should be blocked off, except for the instruments at
the necessary monitoring points of pressure and temperature.
The containers for storing the oil should be clear and not confused with the containers
for other oil during transportation and storage.
2.4 In order to increase the flushing efficiency and shorten the flushing time, besides
increasing the scavenging oil flow, alternate the oil temperature between 25 ℃ and
75℃ as showed in picture. One cycle period will last 8 hours. It should be noticed
when heating oil the temperature must not exceed 80℃ so as to avoid the oil
deteriorated. During heating
the oil, all of the piping, in temperature ℃
which the oil flows, should be
warmed up. If some of them
are still cold, find out the
reason and eliminate it. In the
course of flushing, beat the
piping, with wood or copper
hammer, especially for the
welded junctions, making the time
impurities fall off and be flushed out.
2.5 The strainer in the oil tank should be washed at least once a time for every cycle
period. After the element has been mounted in the filter, it should be cleaned
regularly. Once the differential pressure between inlet and outlet approached to the
permitted up limit, switch over and wash the filter immediately, regardless of the
2.6 Flushing the control and protection system as following procedures respectively
according with the different arrangements:
2.6.1 For the turbine with hydraulic or mechanic-hydraulic governor, at the beginning
of the second cycle period, put the trip solenoid valve into the normal operation
position, place and lock the handle of the emergency trip gear at the engaged
position. After the second cycle period, return the oil inlet piping of the governor
to normal connection. From the third cycle period, operate the starting control to
switch it between two positions, the starting position and the operating position
to flush the trip-oil piping and starting-oil piping to the emergency stop valve.
Operate the test valve of the emergency stop valve regularly so that the test-oil
piping can be washed.
2.6.2 For the turbine with trip block, place and lock the emergency trip gear at the
engaged position (it is not required for the turbine without trip block) at the
beginning of the second cycle period. From the third cycle period, return the
inlet piping of pressure oil for the trip block to normal connection and place the
manual and remote controlled trip valve in the block to the normal operation
position. Regularly operate the control valves (manual and electric) for the
starting oil and trip oil, so that the starting- and trip-oil piping to the emergency
stop valve can be flushed. Place the test valve of the emergency stop valve to
test position timely for flushing the test-oil piping.
There are several evaluation methods due to the different implement standards and
inspection methods. Some typical methods are given below. It is suggested to use one of
them in evaluating the cleanliness for the oil system.
>0.25 Without
0.13~0.25 ≤5
2 ≤3.91 20
3 ≤5.49 45
4 ≤6.02 80
6 ≤7.11 180
Clean the insides of the oil cylinder of the emergency stop valve and pilot-valve housing,
wash the removed parts and components, including the bearings, restore the bearings,
Hangzhou Steam Turbine Company Limited Page 5 of 6
Operation Instructions
Scavenging with Oil 3-0340-01-01
turbine rotor, emergency stop valve, oil cylinder and emergency trip gear to the original
states.
For the turbine bringing its own main oil pump, connect the inlet and outlet piping of
the oil pump and mount the regulating valve of the oil injector.
For the turbine with the electric-hydraulic converter mounted on the trip block, the
attention should be taken that the blank plate between the converter and the trip block is
just used in oil flushing, is must be removed after flushing.
Steam Quality
The turbine is a rotary thermal power machine with steam as its working medium, the
quality of the steam entering into the turbine will not only has an effect on economical
operation but also be related with safety operation and service lift of the turbine. The
deposits that occur in the steam path of a turbine due to impure steam can lead to a
reduced section area of the steam path, decreased turbine output and an inefficiency,
also to increased axial thrust. The deposits that occur on the blades will increase the
stress of the blade, resulting in blade breakages. Furthermore, the deposits can lead to
seizure of the spindles of the emergency stop valve and /or control valve. Therefore, in
order to operate the turbine safely and economically in a long term, the qualities of the
steam and boiler feed water should be in line with the standard listed in the tables below.
The standard value is the limit value, while the expected value is much favorable for the
safe operation of the turbine.
Parkering ≤10 -
Sodium,μg/kg ≤15 ≤10 ≤5
Volatilizing ≤10 ≤5
Parkering - -
- ≤0.30
Conductivity(after Volatilizing ≤0.30
hydrion exchanged, Neutral-water
at 25℃) treatment and
- - ≤0.20 ≤0.15
μs/cm combined-water
treatment
Silicon dioxide μg/kg ≤20 ≤20 ≤20
In order to prevent the metal oxide deposited inside the turbine, the content of the
iron and copper in the steam should be in accordance with the valve given in the table 2.
One-
boiler
steam Mg/kg
Boiler PH Hydrazine Oil
pressure
type (25℃) mg/L mg/L
of boiler Standard Expected
MPa
boiler
The quality of the make-up water and the turbine condensate should also be
controlled according to the standard “The water and steam quality for thermal generator
set and steam power equipment” GB/T12145-1999.
During manufacturing, welding and installing the steam piping, not only the dirt will
enter into the piping but also the oxide and welding spatter will be attached on the inner
wall of the piping. Therefore, the solid impurities with the size less than the hole of the
strainer will enter into the steam path at high speed through the strainer, colliding with
and damaging the blade and gland bush. In order to eliminate this hidden risk, the steam
inlet piping should be purged with steam prior to first commissioning after turbine
installed.
To purge the steam inlet piping with steam, the emergency stop valve must be removed
in advance, mount the “Purging tool”(2-8535-xxxx-xx) supplied with the turbine for
blocking the passage through which the steam enters into the steam path.
A temporary exhaust pipe is required for purging, the inner diameter of the exhaust pipe
should be equal to or larger than that of the purged piping with a length as short as
possible for reducing the exhaust resistance. The outlet of the exhaust pipe should be
tilted up (by approx. 30°) to the air. The exhaust pipe should be fixed by the firm
support to bearing the reaction force of the exhaust. In order to reduce the noise level
produced by exhaust, a muffler may be mounted in the temporary exhaust pipe. But the
muffler mounted will increase the exhaust resistance.
To get the efficient purging, the scouring force against the piping wall during purging
should be larger than that during normal operation. Therefore, the purging-steam
parameters is determined and controlled by a momentum coefficient K, which is the
ratio of the steam momentum m1c1 under purging condition to the steam momentum
m0v0 under rated condition, i.e.:
m ⋅v
2
mc
K = 1 1 = 12 1 K should be ≥1.2~1.5
mo c o m o ⋅ v o
Where:
m1—Purging-seam flow
m0—Steam flow under rated condition
v1—Special volume of purging-steam
v0—Special volume of steam under rated condition
Before purging, the piping should be warmed up and all of the joint bolts for flanges
should be tightened under hot state. The purging is carried out in several times, which is
based on the clean condition of the piping. Each time of purging will last for 10 minutes.
The interval time between two purges is determined by the time required for the piping
temperature to drop below 100℃. When the temperature of the piping wall dropped
In order to examine and evaluate the purging result, a checkerboard may be fitted in the
exhaust pipe (Fig.1) or at the outlet of the exhaust pipe (Fig.2). It consists of a support
and target plate made of new aluminum plate with thickness of 1mm and width of
30mm, the length of the checkerboard is decided by the diameter of the exhaust pipe.
the target plate should be replaced and examined after each purging. On the premise that
the scouring force of the steam does not decrease, when the impacting blemishes on the
target plate in two adjacent purges has been ≤ 0.8mm and number of the blemishes is
less than 8, the purging is considered to be qualified.
Following the purging, remove the temporary exhaust pipe when the piping temperature
dropped to room temperature. Carefully clean the emergency stop valve housing and
remove the purging tool. Make sure that there is no impurity in the steam inlet
compartment and mount the emergency stop valve.
1. Level
2. Packing plate
3. Layer of mortar
4. Foundation
The packing plates are supplied by user, for the dimension of the cross section, see
Layout Drawing. The surface roughness of the packing plate topping should be .
The deviation of the flatness should be less than 0.1.
1. Pedestal (soleplate)
2. Trimming screw
3. Bearing plate for trimming screw
4. Foundation
Fig.3
3. Anchor-bolt holes
The anchor-bole holes should be cleaned of sundries.
Check the contact condition between the bottom plate of the anchor bolt and the
foundation surface around the hole. Under normal condition, the pre-tightened force of
the anchor bole acts on the concrete foundation via whole bearing face of the bottom
plate. If the protruding edge-angles and stones are existed around the anchor-bolt hole,
the load on the foundation becomes unevenly distributed. This will cause part of the
foundation cracked and damaged in a short time, resulting in the tightened force of the
anchor bole lost and then endangering the normal operation of the turbine. Therefore, an
approx. 5mm thick layer of high viscosity and stagnation cement mortar is to be applied
1. Asphalt tape
2. Anchor bolt
3. Anchor-bolt hole
4. Foundation
5. Filled cement
6. Bottom plate of anchor bolt
7. Nut
Fig. 4
After the turbine installed, the anchor bolt should be secured by spot welding and the
exposed thread should be coated with thick grease for corrosion prevention.
The material and formulation of the mortar is independent of turbine type and size, it is
selected by user and construction company. But we recommend:
When the thickness of the grouting layer ≤60mm, either the cement mortar mixed with
cement, sand and water in a given proportion or the epoxy mortar prepared with epoxy,
curing agent and quartz sand can be used.
When the thickness of the grouting layer is 60 to 100 mm, either the concrete with
pebble in the specified granularity or the cement mortar can be used.
1. Compression strength
≥40N/mm2, after 24 hours
≥60N/mm2, after 72 hours
≥70N/mm2, final strength
2. Volumetric change
The contraction is not allowed. The grouting material should expands slightly within 24
hours after grouting so as to ensure that there is enough cohesion between the
foundation and pedestal, but the further expansion is not allowed after 24 hours.
3. Expansion coefficient
The coefficient of the linear expansion for the mortar after solidified should be in
conform with that of the foundation.
Mounting or dismounting heavy component on the pedestal only can be done after back
grouting finished at least for 24 hours.
The anchor bolt only can be retightened after back grouting finished at least for 72
hours.
The preparation for the foundation before grouting and the maintenance should be done
according with the construction procedure.
Preserving the turbine casing with heat-insulating lagging reduces not only the turbine
thermal lose and but also the temperature difference at the same cross-section of the
casing and consequently the heat deformation caused by the temperature difference. At
the meantime, it lowers the ambient temperature around the turbine, enhancing the
working condition for operator.
After the piping that are connected to the casing and the instruments installed, the oil
system and steam piping scavenged, the installation of the heat-insulating lagging can
be carried out.
Attention: The unused blankets should be stored properly. Dragging the blanket
on the ground, standing or placing the heavy subjects on the blanket are not
allowed.
Flammable substance must not be infiltrated into the blanket. The blankets
infiltrated with turbine oil or adhered with grease must not be used.
The installation personnel should dress the tight work-clothes and rubber glove
when mounting the heat-insulating lagging.
Operating Supervision
This section describes the monitoring requirements of the main operation parameters for
the turbine. For the instrument configuration and function (including monitoring limit)
of individual turbine, please refer to “Bill of Material” 0-2020-T.Nr-00.
When the admission pressure of the turbine has exceeded the normal value and tends
toward the upper limit, the turbine operator should inform the boiler operator to reduce
the pressure at once. When necessary, turn down the isolated valve in the live steam line
for reducing the pressure; decrease the turbine load through reducing the opening of the
control valve.
When the admission pressure of the turbine has exceeded the normal value and tends
toward the lower limit, the turbine operator should reduce the turbine load and inform
the boiler operator to raise the pressure.
When the admission temperature of the turbine has exceeded the normal value and tends
toward the upper limit, the turbine operator should inform the boiler operator to reduce
the temperature. When necessary, decrease the turbine load through reducing the
opening of the control valve.
When the admission temperature of the turbine has exceeded the normal value and tends
toward the lower limit, the turbine operator should inform the boiler operator to raise
the temperature. When necessary, open the drain valve in the live steam line; decrease
the turbine load through reducing the opening of the control valve.
The continuous operation under the upper limits of both pressure and temperature for
the admission cannot exceed 15 to 20 minutes. The cumulated time in a year should not
exceed 20 hours.
The pressure and the temperature are monitored with pressure switch and thermal
coupling. When the admission pressure and/or temperature reached the reset limit, the
alarm and shutdown signal will be sent out.
Under the special conditions, such as start-up and commissioning, the admission
pressure and temperature of the turbine can differ to the normal values mentioned
above.
The chamber pressure has a coincidence relation with the steam flow. Under normal
condition, the chamber pressure changes with the change of the live-steam flow, please
see the attached documents No. 0-2505-T.Nr-00 “Characteristic Line of Control Valve”.
The maximum steam flow can be restricted through monitoring the chamber pressure,
so as to avoid over loading. Chamber pressure also reflects the deposition of the
steam-path section, which is related with the steam quality. The deposit on the blade
surface not only increases the blade stress, but also decreases the section area of the
steam-path, resulting in turbine output and efficiency reduced and the axial thrust
increased. If the steam-path is deposited, the chamber pressure will rise under the same
steam parameters and flow. With this characteristics, the measured relation of the
chamber pressure to the steam flow during operation can be compared with that
measured (the live-steam pressure and temperature under different operating conditions
should be kept constant) under the clean condition for the steam-path after the turbine
has been put into normal operation against “Characteristic Line of Control Valve”
0-2502-T.Nr-00. The relative increment Δ P is calculated with the formula
PR − PRO
ΔP = × 100% , here PRO is the chamber pressure corresponding to the
PRO
operation with the same steam parameters and flow. ΔP should not exceed 10%,
otherwise the immediate flushing is required (see 4-0600-).
Exhaust pressure
The exhaust pressure deviation from the normal value for the backpressure turbine will
have effect on the turbine output and the safety as well. The excessive high exhaust
pressure is going not only against the casing strength, nut also to increase the axial
thrust, while the excessive low exhaust pressure will endanger the blade safety.
Therefore, the exhaust pressure during turbine operation is not allowed to exceed the
permitted range.
The exhaust pressure of the turbine is monitored with the pressure switch. When the
exhaust pressure reached the preset limit, the alarm or shutdown signal will be sent.
Vacuum in condenser
During condensing turbine operation, the vacuum in the condenser will drop and the
exhaust pressure rise due to excessively high temperature of the recycling water, lack of
the cooling water flow, deposit of the cooling pipe in the condenser, leakage of the
vacuum system or bad work of the air ejector.
During turbine operation, the exhaust temperature under load should not exceed 70℃,
and 120℃ under no-load.
Extraction pressure
For the turbine with controlled extraction, the extraction pressure is either the exhaust
pressure of the first expansion section or the admitting steam pressure for the second
expansion section, so that it should be controlled within a permitted range.
Bearing temperature
The journal and thrust bearings used in turbine and gearbox are hydrodynamic bearings,
their normal working is lied on the oil film that can build-up loading capacity. The
viscosity of the lubricating oil, which is related with the bearing temperature, plays an
important role in influencing the loading capacity in the case that other factors have
been decided. Therefore, the bearing temperature must be strictly limited. When the
bearing temperature exceeded the specified stop value, the strength of the bearing babbit
may be reduced obviously. In order to insure the reliable operation of the bearing, the
bearing temperature should be kept within the normal range during turbine operation.
The rise of the bearing temperature during turbine operation is caused by friction power
of the bearing and the heat produced in heat exchange. When the heat the lubricating oil
takes out is equal to the heat the produce, the temperature tends to be stable. The
bearing temperature: t = t o + Δt . Here, t o is the lubricating inlet temperature, which
t o +20℃.
The temperature rise of the journal bearing is related with the speed and load.
Measuring the babbit temperature with the thermal resistance or thermocouple at the
minimum oil film at the lower half of the bearing can make a quick reflection of the
temperature change for the bearing pad. Where two temperature sensors are equipped
for one journal bearing as required by user, the temperature readings on each measuring
point are bound to be different. In this case, the journal-bearing temperature monitored
should subject to the reading on the measuring point at the minimum oil film related
with the rotating direction.
For the monitoring of the temperatures of the journal and thrust bearings, not only the
absolute value ( t o + Δt ) should be observed, but also the change of the bearing
temperature rise should be noticed. Compared with the highest temperature under same
working condition in the operation record before, if the temperature rise of the bearing
increased suddenly, it cannot be treated lightly even the bearing temperature has not
reached the alarm value yet. Should the bearing temperature rose instantaneously and
lasted for a very short period, and then it retune to the temperature in normal operation,
the partial damage of the bearing is often indicated. In this case, the continuous
operation of the turbine may cause the severe damage of the bearing.
For the alarm and stop limits of the bearing temperature, see 0-2020-T.Nr-00.
Oil pressure
For the turbine with the oil system using turbine oil as its working medium and the main
pump driven by the turbine shaft, the pressure of the pressure-oil is between 0.6~
1.3Mpa, which is related with the turbine speed. It will be ~0.8Mpa at rated speed. For
the turbine with an external oil pump, the pressure of the pressure-oil is >0.8Mpa. The
Where the pressure gauge is fitted in the oil inlet piping of the bearing, when adjusting
the oil flow to the bearing with the throttle valve based on the bearing temperature, the
oil pressure is only taken as the reference. The oil pressure behind the throttle valve is
not stipulated.
In general, the throttle valve is not required to readjust after adjusted in turbine
commissioning.
For the supervision of the high-pressure fire-resistant oil system, please refer to the
related instructions.
Shaft vibration
Usually, the shaft vibration of the turbine is continuously monitored with the
two-channel vibroscope.
The turbine has passed the high-speed balance and no-load test run in the workshop
before delivering. The value of the shaft vibration recorded in the Product Certificate is
the p-p value. The non-vibration deviation of the rotor resulted from the electric and
mechanical deviation in the workshop is limited within 6μm.
It is bound to produce slight vibration during turbine operates at the given speed and
within the given load range. The amplitude will increase in the process of the start of
stop, especially when turbine speed passes through the forbidden- to-stay-zone. As long
as it does not exceed the permitted range, such a vibration is still normal.
Under the good installation condition, there are many factors that will aggravate the
vibration during turbine operation, such as the uneven expansion of the turbine due to
the over-fast rate of loading or unloading, the change of the damping characteristic due
to the worsen bearing working status, the change of the original balancing state, water
hammer, compressor surging and etc. The abnormal sound is often companied with the
aggravating vibration. Therefore, listening the operation sound may be taken as the
auxiliary method for monitoring the shaft vibration.
When judging whether the vibration is normal or not, the absolute value of the
amplitude cannot be taken as the only reference. For example, the measured amplitude
is increased from 25μm to 30μm under a certain working condition, while under other
working condition it is increased from 5μm to 25μm. The former condition does not
always indicate the existence of some disturbances, while the latter may foreshow the
appearance of the fault, which must be put on alter. The cause resulting in the abnormal
vibration should be found out even it does not reach the alarm value, the corresponding
Most of the turbines are equipped with key-phase sensor, as required, to measure the
frequency and phase of the shaft vibration for analyzing the vibration characteristic with
the frequency spectrograph.
At present, the larger one of two P-P values measured in two orthogonal directions is
usually taken as the estimating index for the shaft vibration. The alarm and stop values
given in 0-2020-T.Nr-00 is not unique but for suggestion. User can reset them based on
his experience in operation and the standard adopted.
Axial displacement
There are to kinds of axial-displacement protective devices, mechanical and electrical.
In some of turbines both of them are used, for the others, only one of them is used.
The limit value of the axial displacement for the mechanical protective device is about
±1.0mm. When the thrust bearing damaged in operation and the axial displacement of
the rotor exceeded the clearance between the tripping lever and the cam on the rotor,
which has been adjusted in installation, the emergency trip gear acts and trips the
turbine, so as to prevent the rotor from colliding with the stationary parts in axial
direction and accident from going worse.
The electric axial displacement protective device continuously monitor the axial
position of the rotor with respect to the thrust bearing through the approximant sensor
and the position detector. It can send an early warning for the thrust bearing damage to
avoid the severe damage of the turbine. For the alarm and stop limits of the axial
displacement for the rotor, see 0-2020-T.Nr-00. When adjusting the sensor in
installation, The middle value of the total clearance between the thrust collars of the
rotor and the primary, secondary thrust pads is take as the zero position.
The axial displacement of the rotor is caused by the change of the axial thrust, which is
related with the turbine working condition and statues. The axial thrust in backpressure
or condensing turbine is approximately proportional to the live steam flow. The
maximum axial thrust will appear at maximum power. For the extraction turbine, it does
not appear under the rated working condition but under a certain middle working
condition, such as zero extraction condition. During normal operation, the axial thrust
will be within the permitted range when the load is changed within the given range, so
that the thrust bearing is safety. But under abnormal condition, such as overload, worn
inner gland seal, deposit of steam path, over-low live steam temperature and water
hammer, the axial thrust will be increased additionally.
Speed
Usually, tachometers are mounted on the local instrumentation panel and in the center
control room for monitoring the turbine speed in operation. Where the electric-hydraulic
control system is adopted, the digital governor also has the monitoring function for
speed. Additionally, some of turbines are equipped with the overspeed protective system
using two-out-of –three logic. They will continuously indicate the actual speed of the
turbine in operation. When the speed exceeded the rated speed or the maximum
continuous speed rose to the reset acting value, the alarm or stop signal is sent.
For the turbine with continuous barring gear, the barring speed should not be lower than
the specified minimum barring speed.
If there is any forbidden-to-stay zone (including the forbidden-to-stay zones for turbine
and driven machine) in the process of the turbine starting and stopping, make the
turbine speed pass through this zone quickly and continuously in operating.
With the governing system the turbine runs stably within the specified speed and load.
For the turbo-generator, after load rejection of the generator, the speed will rise
instantaneously and then stabilize at the up governor speed under normal condition.
During turbine operation, If the turbine speed is out of the control and rise to the stop
value reset but the protective device has not acted yet, manually trip the turbine at once
with the manual stop valve, emergency trip gear or the stop solenoid valve that receive
the stop command from the control room.
The thermal expansion of the casing in the axial direction is usually monitored with the
expansion indicator mounted on the front pedestal. The casing expands forwards when
heated and constricts when stopping, taking the dead point as the reference. The
expansion of the casing when heated should be continuous. The appearance of the step
change in expansion indicates the expansion obstructed. It is required, at any moment,
to check the clearances of the bolt washers on the front and rear supporting brackets of
Race time
The soundness of the turbine can be judged through measuring the race time during
normal stopping and comparing it with the race time measured in commissioning under
the same operation condition. If the race time measured currently is shorted obviously,
the rotor may be contacted with the stationary parts or bearing defect existed. While the
prolonging race time indicates that the steam leaked into the casing because of the
untight close of the emergency valve and control valve.
As the requirement in the order, the turbine may be equipped with casing-temperature
detector, absolute casing-expansion detector, differential expansion detector, rotor
eccentricity detector and etc. for monitoring the temperature deference between the top
and bottom casings, the thermal expansion of the casing in axial direction, the relative
expansion of the casing and the rotor and the flexural deformation of the rotor.
Abnormal Vibration
The turbine is a rotary machine in high speed, so vibration in different amplitude and
direction will occur in its operation. Any of the vibration that is within the limited
range is permitted and has no harmful to the machine. But some times the abnormal
vibration will occur during turbine operation for various reasons, especially during
commissioning. According to the statistics of the vibration troubles, most of the
abnormal vibrations are caused by improper installation or misconduct in operation
and maintenance. Since the turbine rotor has been balanced and passed the no-load
running test before delivery, it usually is not required to rebalance, except for the rotor
that has been repaired, bended permanently or which parts have been replaced. If the
abnormal vibration occurred during turbine-set starting and operating, carry out the
test and analysis by means of the frequency spectrograph or other real-time analyzer
for finding out the reason and resolving it based on the vibration characteristics.
1.2 Piping
1.2.1 Steam piping
Due to forced connection of the mis-positioned flanges or unreasonable piping layout,
the force and torque acting on the turbine exceed the permitted values. The abnormal
vibration is marked by: the vibration is related with the turbine hot state, the
amplitude will increase obviously at a certain load (temperature), the vibration
frequency is in step with the turbine speed, the vibration signal contains the
low-frequency component. Measure the vibration of the shaft and the bearing housing
at the front and rear sections of the turbine, if the larger vibration appears at the front
section, the steam inlet piping is likely to be with the problem. If the larger vibration
is at the rear section, it is mostly caused by exhaust piping.
Measure: Reconnect the piping according to the requirement or adjust the piping
supports.
1.4.3 Alignment under cold state is conformed with the requirement, but the center is
deviated during operation
In addition to the same characteristics mentioned in 1.4.2, the vibration characteristic
is related with hot state of the turbine set. For the backpressure turbine, the vibration
at its driving end will increase obviously when the load or the exhaust temperature
reached to a certain value. For the condensing turbine, the temperature of its exhaust
nozzle during operation is high than the ambient temperature when installation. If the
pre-pulling amount is too small when installing, the expansion of the exhaust nozzle
during operation will raise the center of the turbine rear bearing. Meanwhile, the
inside of the exhaust casing is under vacuum during operation, the exhaust casing
1.4.4 For the turbine coupled with the driven machine via a gearbox, if the offset of
the gear shaft when aligning the rotor is not conformed with the actual condition, the
vibration and noise of the turbine will increase obviously when the load reached to a
certain value. The vibration waveform contains high frequency harmonics. The high
frequency is synchronous with the working frequency.
Measure: Stop the turbine and check the aligning valve of the turbine rotor with the
gear shaft. Correct the aligning value according to the direction of the gear engaging
force.
1.5 Bearing
The carrying capacity of the multi-wedge bearing is related with the arrangement of
the oil wedge. The split of the four-wedge bearing should be angled of 45 °to the
split of bearing housing, this makes the load just be supported on the center of the
oil-wedge during operation. If the four-wedge bearing does not be turned by 45°
when installing on site, the carrying capacity of the bearing will decrease. Therefore,
during turbine operation the vibration will be increased in a sudden once the load
reached to a certain value. The vibration signal contains eddy signal at a frequency
lower than the working frequency.
Measure: Reassemble the bearing according with the requirement.
1.6 The axial positioning between the turbine and the driven machine is not
conformed to the requirement, especially for turbine that is directly coupled with the
generator. During operation, the expansion of the turbine rotor will push the generator
rotor to move axially. If the axial clearance between the moving and stationary parts
of the generator is less than the axial expansion of the turbine rotor, the moving part
will collided with the stationary one, resulting in turbine to vibrate violently with a
loud noise, finally damaging the equipment.
Measure: The turbine must be positioned correctly when installation. The amount of
the axial expansion for the turbine rotor is given in the attached document
0-0341-T.Nr-00.
2. Operation
2.1 Poor behavior of bearing
Insufficient lubricating oil, disqualified oil quality (emulsification, a lot of bubbles,
2.2 The water contained in the steam causes the temperature of the admitted steam to
drop suddenly, forming a water hammer. The turbine set vibrates intensively
companied by toneless roar.
Measure: Stop the turbine immediately, drain the inlet steam and exhaust piping
thoroughly, reinforce the monitoring of the boiler operation.
2.3 The deposit and corrosion of the steam path section due to the poor steam quality
will destroy the rotor dynamic balance, resulting in turbine vibration. In this case, the
vibration is increased gradually with prolong of the operation duration. Usually, it
does not occur suddenly, except for blade breakage. The vibration frequency is in step
with the speed.
Measure: The deposit content on the blade can be evaluated from the temperature of
the thrust bearing and the pressure change after the control stage. Clean the deposit in
time when necessary or during overhaul.
2.4 The drop of the vacuum for the condensing turbine will raise the exhaust
temperature and consequently change the rotor alignment under hot state, resulting in
turbine vibration. In this case, the vibration at the rear end of the turbine often
increases obviously. The vibration frequency is in step with the speed.
Measure: decrease the load and raise vacuum. Return the turbine to original operating
condition after the vibration reached to the normal value.
2.5 For the turbine that has been put into operation, most of the abnormal vibrations
occurring during starting or changing load are caused by improper operating, such as
improper barring after last stopping and insufficient warming-up during staring. If the
abnormal vibration occurs during raising speed and the noise of the metal friction at
the front and rear gland bushes can be heard, it indicates that the rotor has been
warped (where the eccentric monitor is provided, it can be used in measuring the
warping amplitude for the rotor. At this moment, the turbine speed should be lowered
and maintained at a stable value after the vibration returned to normal for warming-up
for about 15 minutes (the speed can not stay in the prohibition range), and then raise
the speed again. If the abnormal vibration still cannot be eliminated after 3 repeats,
the turbine must be stopped, check and repair the rotor.
Fast load changing also causes the vibration due to deformation of the uneven
expanded components. If the vibration occurs in loading, unload or lower the turbine
speed immediately. After stabilized, load the turbine (or raise speed) according to the
change rate given by the staring curve. If the vibration occurs in unloading, operate
2.6 For the turbine driving compressor, if the abnormal vibration only appears under a
certain load, it is mostly caused by the compressor and the characteristics of the pipe
network.
Measure: When changing load to near this load, slow down the changing rate
properly.
2.7 For the turbine diving compressor, the imprudent operation when reducing the
compressor flow or the improper set of the surge-proof system will cause the turbine
set running in the surging zone, resulting in sharp fluctuation of outlet pressure of the
compressor and consequently intensive vibration of the turbine and the compressor
outlet piping companied with a loud noise.
Measure: Trip the turbine set. Operate the turbine set according with the related
operating procedure to prevent the compressor running in the surging zone.
3. Defect of equipment
3.1 Toothed coupling
The eccentric load produced by the floating parts of the coupling under the centrifugal
force due to the existed backlash will cause vibration. Under the normal condition, the
vibration of the turbine will increase with the raising speed after the turbine started,
but the amplitude is within the permitted range. Additionally, under the action of self-
centering the eccentric load will decrease with the increase of the torque the coupling
is transferring, stabilizing the operation. But the excessive backlash resulted from
machining error or wearing may cause the amplitude to exceed the up limit with the
increase of the turbine speed.
Measure: Check the coupling during overhaul, improve the lubrication and replace the
coupling when necessary.
3.2 Generator
The vibration occurs when raising the generator voltage, but it disappears after the
excitation of the generator released. This indicates that the vibration is caused by the
unbalance magnetic field, which is arose from short-circuit of the generator winding
or the uneven air gap between the generator rotor and stator.
Measure: Inquire the electric technician.
The measures that should be taken under some of the common conditions:
If the plant requires the turbine to operate under overload, it only can run
occasionally in a short time. When the operating condition of the plant has been
changed and the turbine cannot be suitable for this new requirement, the proper and
reasonable solution is to innovate on the turbine for increasing its output.
2. For the turbo-generator paralleled in the network, the automatic increase of the
opening for the control valve when the frequency of the network lowered may result
in the turbine overloaded. Therefore, the attention must be paid in monitoring the
operation when the frequency of the network lowered. Decrease turbine load when
necessary.
3. When the inlet steam pressure and temperature decreased or the exhaust pressure
rose, the steam flow must be increased to maintain the original power output for the
turbo-generator. The excessive steam flow may increase the axial thrust force on the
turbine rotor even the turbine is not overloaded. For the Compressor driven turbine
4. When loading a controlled extraction turbine under “zero” or small extraction flow
condition, the axial thrust may exceed the permitted value, although the admitted
steam flow and the output of the turbine are far from the rated values. Therefore, the
extraction turbine must be strictly operated according to the limited condition given
on the extraction flow vs. power curve (Working condition chart).
Water hammer
Water hammer is one of turbine major accident. During turbine operation, if the steam
Most of the water hammer occurred in the turbine are caused by improper operation, but
some of them caused by the water flowing back into the turbine from the piping due to
the check valve in the extraction piping is not tightly closed. If the boiler is overflowed
or the azeotropy of the steam and water occurs, the steam entered into the turbine will
contain water. Since the water drops flow in a low speed, they will produce a braking
action when colliding on the blade convex, making the turbine output decreased
obviously. The steam containing water will significantly increase the blade stress,
resulting in blade broken and abnormal vibration of the turbine set. It also reduces the
steam path area, causing the thrust increased rapidly and endangering the thrust bearing.
In order to avoid the water hammer occurring, the change of the steam temperature must
be noticed when paralleling boilers for preventing it to be too low. For the turbine with
different steam sources, the thorough drain must be carried out when switching steam
source. During boiler operation the attention should be noticed in keeping the steam
pressure and temperature within the specified range.
Should the drain of the steam inlet piping be not complete in turbine starting, the water
hammer will occur due to the water accumulated in the piping. The piping and the
turbine set will vibrate intensively, companied with a loud tedious noise. In this case,
the turbine must be stopped at once.
Under the normal circumstances, owing to the layer of compact and stable oxide-proof
film formed on the surface the blade made of heat-resisting stainless steel, the blade has
a good corrosion resistance. The protective film of the blade surface will be erode when
the steam contains the Co2, and So2, especially the chloridion. Furthermore, the
corrosion will develop towards the depth quickly and corrode the blade, resulting in
rapid drop of the blade strength. Take the stainless steel 2Cr13 as the example, its
endurance bending strength in the air at normal temperature is 390 N/mm2 (a
un-notched teat piece under a number of stress cycles n=5×107, the same below), it
will still be 275 to 315 N/mm2 in the clear condensate. But it rapidly reduces to 115 to
135 N/mm2 in the chloride solution containing NaCl under a content ≥1%. The
reduction denotes shorten of the blade life. The corrosion can be found when check the
blade in overhaul. Most of the blade corrosion occurs on the stages in the wet steam
zone. Usually, the corrosion begins on the blade surface under the deposit layer and then
develops to crack. If continuing to operate, the blade will break due to corrosion fatigue.
The examination and analysis of the broken blade show that the deposit on the fracture
contains chlorides.
The corrosion of the turbine blade will occur not only during operation, but also during
shutdown, it is so-called as stand-by corrosion. After the turbine shutdown, the steam
left or leaked in the casing will condensed with cooling down of the turbine to dissolve
the deposited salt on the blade, producing a corrosion action to the blade. In this case,
the corrosion damage will occur on all of the blades other than the blades working in the
wet steam zone.
In order to reduce and avoid the corrosion damage of the blade, the boiler feed water
treatment should be perfected so as to ensure the steam quality. Additionally, much
attention should be paid in shutdown maintenance (see 4-0300-xx-xx for details).
If the crack on the blade is found during overhaul, the cracked blade should be replaced.
Blade breakage seldom occurs during turbine operation, but once occurring, it can cause
the severe accident in damaging the equipment and injuring the person. The blade
breakage during turbine operation will have following phenomena:
The turbine vibration increases suddenly, especially for the blade breakage on the
low-pressure stage, companied with an obvious increase in amplitude.
If the phenomena mentioned above occur during turbine operation, stop the turbine
immediately. After shutdown, open the casing for inspecting. Contact us as soon as
possible on affirmed the blade breakage for repairing. Send the rotor and damaged
component to our company for replacing the blade and rebalancing the rotor, when
necessary. The blade breakage of the middle stage will often damage the adjacent
stationary and moving blade. If the barring cannot be carried out caused by the broken
blade, the rotor should be checked whether it is bent.
1.1.2 For the oil system using positive displacement oil pump, the drop of oil
pressure may be caused by excessive bleed-off flow due to improper set of the
releasing valve at the outlet of the pump.
1.1.3 For the turbine equipped with elevated oil tank, the excessive overflow
throughput of the oil tank due to improper governing of the oil inlet valve will
reduce the oil pressure.
1.1.4 For the vertical oil pump mounted in the oil tank, the leakage of the
connecting flange in the discharging piping causes a part of the oil discharged
from the oil pump to inject into the tank.
1.3 The level in the oil tank is too low. It will cause not only the pressure drop but
also the pressure fluctuation.
1.5 The normal oil consumption of the turbine set is larger than the rated flow of the
oil pump, causing a drop in oil pressure. The oil pressure is too low after the main
oil pump put into operation in test running. If it has been verified through
1.5.2 Where the main oil pump is driven by the turbine shaft, raise the running
speed of the oil pump through changing the gear ratio of the driving element.
2.1 The oil tank position lower than the elevation specified on the layout drawing
increased the suction height of the oil pump or the inlet pressure is reduced due to
the increase in the length of the inlet piping and in the number of the elbows. This
will make the main oil pump suck with difficult and cannot work normally. In the
event that the increase in the oil flow of the oil injector cannot improve the
situation, it is better to modify the suction piping of the main oil pump.
2.2 The bottom valve of the oil injector cannot be opened to the required opening. The
increase in suction loss of the injector causes the main oil pump to suck with
difficulty. Check and repair the bottom valve. Re-filtrate the oil in the tank with a
filter, when necessary.
3. Oil leakage
3.1 Poor sealing caused by the improper assembling of the components or the
improper connection of the oil piping, or sealing surface damage will result in oil
leakage, which will be unveiled in test running. The corresponding treatment
should be carried out according to the examination for the leakage part to
eliminate the oil leakage.
3.2 The oil leakage caused by the worn sealing element during turbine operation can
be handled accordingly based on the component feature. For the devices that can
be repaired in the operation, such as the stop valve and gate valve, if the oil
leakage at the valve spindle occurs, press the seal packing properly. The further
treatment can be carried out when overhaul. When the oil leakage at the shaft seal
of the electric oil pump, which can be switched over in operation, start the spare
oil pump and stop the fault pump for repairing or replacing the damaged shaft seal.
For the component that only can be repaired after the turbine shutdown, such as
the oil relay, should be carefully inspected in regular examination. The oil
penetrating at the piston rod must be taken in account and recorded. If it is
4. Oil-piping vibration
The oil-piping vibration that is caused by the improper connection and will result in
turbine vibration is usually eliminated through taking the corresponding measure
when test running. But the other oil-piping vibrations are ignored. For some of the
turbines, the high-frequency vibration of the secondary-oil piping will occur during
operation. For the others, the protective-oil piping vibration will occur when tripping
the turbine. The oil-piping vibration will produce a dynamic load on the piping and at
the connection and welding seam. This will probably cause the restraining force of the
connection reduced and welding seam broken, resulting in oil leakage. Therefore, the
piping vibration must be eliminated in time. The oil-piping vibration is related with
the initial stress of the piping when connected, the velocity and the state of oil flow in
the piping. It can be eliminated through installing proper piping supports in most
cases.
1.2 The inner leakage of the oil cylinder will cause that the emergency stop valve
cannot be opened normally. This is because the excessive radial clearance between
the oil cylinder and the piston causes leakage of the starting oil in a large quantity;
the staring-oil pressure is not able to push the piston to the piston disk. In this case,
the trip-oil pressure cannot be built-up and emergency stop valve cannot be opened.
This fault can be removed through repairing, for example, Fitting sealing element
between the oil cylinder and the piston or using a specially mated piston.
1.3 The deposit and bend of the valve spindle will also cause that the emergency stop
valve cannot be opened normally. Therefore, the functional test of the emergency
stop valve should be carried out regularly (see 1-2300- and 1-1400- for details). If
the test-oil pressure rose, the probability is that the deposit of the valve spindle or
oil cylinder or the bend of the spindle exist. In this case, the repairing should be
arranged in time for finding the reason and eliminating it.
In order to avoid the valve spindle being bended, the spare spindle should be stored in
hanging instead of in lying.
2. Oil leakage of oil cylinder for emergency stop valve (leaking out)
2.1 This is caused by the improper assembling of the seal ring. In this case, the sealing
element should be re-assembled and the seal ring pressed tightly. If the wrong size
of the seal ring is used, it must be replaced with the right size one.
2.2 The disalignment of the valve spindle with the bush of the seal element or the
contact of the valve spindle to the sleeve caused by the bended valve spindle can
rough the spindle and damage the seal ring, resulting in the leakage of the oil
cylinder. In this case, repair and replace the valve spindle or sleeve, replace the seal
ring, and reassemble them carefully.
Measure: Stop the turbine in time and replace the slide valve. The replaced slide valve
can be stuck again user himself. Before sticking, clean the solidified adhesive on the
jointing surface with knife and sand cloth. The single-component anaerobic adhesive
with shear strength higher than 14.7 Mpa at room temperature can be chosen as the
adhesive. The sticking operation should be carried out according to the requirement for
the adhesive.
4.2.1 The play of the fork of the amplifier caused by the excessive axial clearance at
the joint of the fork and comparison lever can disturb the normal work of the
following-up piston, resulting in ripple of the secondary-oil pressure and
consequently the fluctuation of the load or speed.
Measure: Make-up the washer again in overhaul. The axial clearance at the joint
should be within 0.02 to 0.03 mm, making the fork swing flexibly without play
4.2.2 For the turbine using PG-PL governor, the unsuitable opening of the
compensating needle valve in the governor to the turbine performance can cause
the control system unstabilized. The needle valve can be adjusted during turbine
operation. The low fluctuating velocity indicates the opening of the needle valve
is too small, turn the needle valve counterclockwise to increase its opening.
While the fluctuating period is very short, the valve should be turn down. The
needle valve should be adjusted slowly and the turbine operation should be
observed when adjusting until the system stabilized. The adjustment of the
needle valve is considered to be in conformed to the requirement, when
changing the setpoint of the governor, the system can react immediately and
after a trifle overshoot it will return to the stable state. Usually, once the needle
valve adjusted, readjusting is not required.
Measure: After the normal stopping, clean the oil strainer and verify the relationship
between the electric signal and the oil pressure. If the relationship returns normal, it can
be put in operation. And meanwhile, the maintenance of the oil system should be
strengthened for improving the cleanness. If it is still abnormal, try to reset the initial
valve and range of the converter.
When the electric-hydraulic converter fault caused by inner reason occurred during
operation, it is better to stop the turbine and replace the converter with spare one.
Contact to the converter supplier for repairing.
The shortage of the cooling-water flow is usually resulted from the block of a part of the
cooling pipe in the condenser or abnormal operation of the cycling-water pump. If it is
caused by the former, an increase in differential pressure between the inlet and outlet of
the cycling water must be companied with.
3.1 Condensate pump fault: Pump or motor fault causes that the condensate cannot be
drawn out. Whether the pump fault or the motor fault can be judged from the change
of the pump discharge pressure of the motor current.
3.2 The cycling water leaks into the steam side of the condenser, caused by the broken
cooling-water pipe or the loose joint of the pipe to the pipe plate. This can be judged
3.4 The check valve at the output of the spare condensate pump is not closed tightly,
resulting in the condensate flowing back to the condenser.
If the vacuum drops when the load decreased, while it returns to normal when the load
increased, the drop of the vacuum is usually caused by the leakage at the joint of the
connecting piping for the low-pressure casing.
The leakage of the vacuum system may occur at the following parts: the flange between
the exhaust casing and the exhaust nozzle, the welded junction, the exhaust relief valve,
the drainer, the valve and the joint. To find the leakage requires not only being familiar
with the vacuum system but also being careful and patient. Once the leakage is detected,
handle it immediately.
6.1 The working steam parameter of the air ejector is deviated from the normal value
significantly, decreasing the ejector efficiency.
6.2 The shortage of the cooling-water flow to the cooler caused that the steam in the
drawn mixture of steam and air cannot be condensed completely and a good deal of
steam emerged from the exhaust pipe of the air ejector.
6.3 The cooler was full with water due to the obstructed draining or broken water pipe.
6.4 The drainer fault or loose close of the drain valve caused the air to leak into the air
ejector.
6.5 The improper distance between the ejector nozzle and the diffuser decreased the
capacity of air bleeding. Usually, this will be found and eliminated in test running.
6.6 The steam strainer or nozzle of the air ejector was blocked. It is because that the
steam inlet piping of the air ejector does not blown thoroughly, the impurities enters
into the ejector with the steam to block or even damage the steam strainer, making
the nozzle blocked. This will occur during test running and normal operation as
well.
When the strainer or nozzle blocked, the vacuum of the air ejector drops and the cooler
temperature decreases obviously and the ejector operates with an abnormal sound (the
steam jetting sound lowers and even disappears. When the second stage air ejector is
blocked, a sniffing sound can be heard in the exhaust pipe).
Should the vacuum drop during operation, start the spare air ejector when necessary. If
it is caused by the abnormal operation of the main ejector and cannot be eliminated
under operation, stop the faulty ejector for repairing.
Load Rejection
The electric load may drop to zero suddenly during the turbo-generator operating, this
is called as load rejection. The load rejection of the turbo-generator should be handled
according to the feature and reason.
In this case, set the speed setpoint of the governor to the rated speed and adjust the
gland steam, immediately. Cut off the extraction for the extraction turbine and adjust
the recycling flow of the condensate for the condensing turbine. Should the
turbo-generator operate normally, it can be incorporated in power network and loaded
again after the electric fault eliminated.
In this case, in addition to take the measures mentioned in item 1, check whether the
oil supply system operates normally. If there is no other fault, reset the overspeed
protection system and the emergency trip gear. After the control system adjusted,
restart the turbine, raise turbine speed, synchronize and load on.
For the extraction turbine using hydraulic control system, the hydraulic
reference-value relay (see 1-1114-01-xx for details) will act when load rejection. The
improper adjustment of the hydraulic reference-value relay will cause the momentary
oil flow of the working oil to the oil relay too large. Thus the trip-oil pressure is
dropped, making the emergency stop valve and the control valve closed.
In this case, the measure mentioned in item 2 may be taken. At the same time, the
In This case, the turbo-generator runs in motor mode must not exceed 3 minutes. The
fault should be eliminated immediately, then reopen the emergency stop valve and the
control valve and load the turbo-generator again. If the fault cannot be eliminated in 3
minutes, inform the control room for decoupling and stop the turbine. After the fault
eliminated, restart the turbine.
The maintenance of the turbine includes the maintenance when operation and the
protection during shutdown.
The operation maintenance is a regular job for the operator. He should strive for the
turbine operating under optimal state through proper operating with the help of the
monitoring instruments during turbine starting, operating and stopping. In case the
abnormal condition occurs, the operator should make a judgment for fault trend calmly
and rapidly. For the defect that does not endanger safety but can not be eliminated
temporarily, adjust or limit the operating condition of the turbine-set in time and make a
record in details and truth at the same time, which will be taken as the basis for
determining the repairing time and program. For the serious fault under which the
turbine must be stopped immediately, stop the turbine decidedly to avoid the fault
expanding further. In general, the reason causing fault can be divided into two kinds.
One is not influenced by the operation duration, such as the construction quality, the
design and manufacture level, the improper assembling and adjusting in installation and
overhaul, the false operation and etc. The other is related with the operation duration,
such as the normal wear, corrosion, deformation, material ageing, the expiring of the
service life, the deposition and consequent damages, the abnormal disturbance in
operation and etc. Most of problems caused by the first kind of reason (except for the
false operation) will come in light in the test running after installation and overhaul.
Typically, this kind of problems can be handled through “defect eliminating”. From the
second kind of reason and practical experience, it is known that the proper operation and
the careful maintenance will not only enhance the turbine usability, but also prolong the
service life within the expected lifetime. To ensure economic and reliable operation of
the turbine, must pay sufficient regards to the canonical operation during starting and
stopping, the avoidance of the intensive change of the steam parameter deviated from
the normal value, the limitation of the load change-rate, the monitor of the steam quality
and maintenance of the oiliness, scheduled overhaul and etc.
The turbine maintenance also includes the test carried out during operation. Before
testing, the operator must know fairly well about which parameters will change in the
process of the test, so as to avoid mishandling.
Protective care is required during turbine shutdown, so the necessity of protection and
the related measures that may be taken during shutdown are explained here.
Overhaul is to examine and repair the turbine (including the auxiliaries) during
shutdown. A reasonable overhaul schedule is based on the operation supervision and the
fault diagnosis. The operation statue of the turbine-set can be improved and the turbine
The necessity and essentiality of the preventative examination in the process of the
overhaul is cognized now days. The examining items and methods during overhaul will
be explained in the following sections to aid to the examinations.
Of cause, to overhaul the turbine-set must be shutdown and the production of the plant
must be stopped. Therefore, the examining items and the schedule should be made out
based on the operation state of the turbine-set and the production schedule in
consideration of the spare-parts reserve, the personnel and the cost, carrying out the
overhaul duly.
After the overhaul, the result should be estimated and the necessary preparation for next
overhaul should be made. When necessary, amend the operation procedure according to
the overhaul result. The overhaul effect must be verified through re-commissioning after
the turbine overhauled.
h: Hourly
d: Daily
w: Weekly
m: Monthly
y: Yearly
The combination of the digit and letter is used, such as 3m, that means every 3 months.
State codes:
A: On start up
B: On shutdown
R: In normal operation
S: After stopped or overhauled
The items listed in the table are not the unique, user can add or omit some items
according to the requirement on his turbine. The condition and the result of the checking
and the testing should be recorded.
component name
Leakage of front and d R Under the approximately similar operating condition, the
real gland seals increase of the steam leakage from the gland seal usually
indicates the increase of the radial clearance of the gland
seal. The clearance of the inner gland seal (including the
gland seal of the dummy piston) will change with the
change of the clearance of the outer one. The clearance
increase of the gland seal will increase not only the loss of
the steam leakage but the axial thrust as well. Therefore, the
checking and handling should be made.
Temperature of h R The bearing temperature is continuously recorded or
journal and thrust observed regularly by operator based on the configuration of
bearings the monitoring instrument. If the temperature rises, pay
attention to its change. When the it has approached or
reached to the alarm value, the load must be reduced. When
it reached the stop value, stop the turbine at once and find
out the cause.
Control valve
1.Check freedom of w A/R Change the valve opening through controlling a step change
movement of the actuating command of the oil relay and observe
whether the control valve reacts quickly. For the non-electric
system, briefly operate the accelerator lever on the speed
governor to carry out the test. Any deposit on the valve stem
will be cleaned at the same time.
2.Check tightness B Judge the valve tightness based on the race time.
3.Vlave-stem leakage R If the leakage at the position where the valve stem
penetrates through the valve bonnet, retighten the seal nut of
the valve stem. This should be done under the condition that
the admitted steam pressure has been reduced. The
replacement of the seal ring, if necessary, only can be done
after shutdown and cooled down.
component name
4.Check setpoint and ≥3m S For the turbine operated above 3 months, check the relation
sluggishness between the actuating command (secondary-oil pressure for
non-high-pressure-fire-resistant-oil system) of and the oil
relay travel, the control valve lift after shutdown. Determine
the sluggishness and readjust when necessary.
d R During operation, Check whether the valve opening, the
power (speed), steam flow and the wheel-chamber pressure
change smoothly with the change of the secondary-oil
pressure.
Hydraulic governor S The following examinations should be made after the
governor repaired or turbine overhauled:
1.Check static Check the static characteristic of the control system against
characteristic 0-2500-T.Nr-00, following the method described in 1-1840-.
2.Check the speed Connect the coupling to the driven machine, check the up
regulating range and and low limits of the speed regulating range, and reset them
droop when necessary. Determine the speed droop when the
condition is permitted.
3.Check stability Produce a step disturbance with the accelerator lever and
observe the transition. Under normal condition, the speed
will swing instantaneously and stabilize at the value before
disturbed.
Mechanical-hydraulic s The following examinations should be made after the
governor governor repaired or turbine overhauled:
1.Check static Check the static characteristic of the control system against
characteristic 0-2500-T.Nr-00, following the method described in 1-1840-.
2.Check the speed Connect the coupling to the driven machine, check the up
regulating range and and low limits of the speed regulating range, and reset them
droop when necessary. Determine the speed droop when the
condition is permitted.
3.Check stability Produce a step disturbance with the accelerator lever and
observe the transition. Under normal condition, the speed
will swing instantaneously and stabilize at the value before
disturbed.
component name
Speed transmitter Y R/S The filter of the breather should be cleaned at least once
every year.
Digital governor According to the Instructions of the governor.
Electric-hydraulic Y S Clean the filter after shutdown, as required.
converter Determine the characteristic once every year, mainly for the
relation between the electric signal and the secondary-oil
pressure.
Adjust the initial value and the range of the secondary-oil
pressure, when necessary. In case of fault, it is better to
replace it with the spare one, and then contact with the
supplier of the converter for repairing.
Oil relay D R Check for leakage.
Breather of pilot valve 6m R/S Clean the filter of breather.
Test valve of 3m R The test must be done periodically, no matter where the test
emergency stop valve valve is mounted, in the trip block or the piping. Compare
the measured test pressure P2 (see 1-2300-) with that
recorded in commissioning, if P2 increases, the
corresponding handling should be made during overhaul.
Teat valve of 3m A/R During start-up or operation, check for proper functioning
emergency governor of the emergency governor using the test valve (see
1-2810-).
Functional test for trip S/A/B Before turbine start or during starting or stopping, check for
components proper functioning of the trip action through operating the
trip device manually (such as manual stop valve,
remote-controlled stop solenoid valve, emergency trip gear
and etc.).
Extraction stop valve S After shutdown, check whether the open and close of the
controlled and non-controlled extraction stop valves are in
normal when the oil system is still running. Before testing,
it must be ensured that the isolated valve in the live steam
line has been closed.
component name
component name
Monitor and verify of d A/R/B The continuous monitoring of the rotor axial position may
monitor for rotor axial indicate:
position The thrust direction of the turbine rotor;
The displacement caused by the worn thrust bearing;
The elastic deformation of the thrust bearing and the
pedestal.
Under normal condition, the rotor position should be the
same under same operating condition.
The axial displacement monitor can be calibrated with the
same calibrator at the time when the vibration sensor
calibrated.
Oil system See 4-0400-
Grounding brush d R Check for the wear of the brush through view window,
replace it following the instructions in 1-7650, when
required.
component name
Overspeed trip test of 3m* B/S The reliability of the overspeed trip for the emergency
emergency governor governor is dependant on the flexibility of the eccentric bolt,
(For turbine without which may be locked by following causes:
test valve) Scraped sliding surface of the eccentric bolt;
The oil contains water or other causticity substance;
The oil contains foreign impurities;
The part is damaged by the shaft current caused by invalid
brush or without mounting the brush;
Improper operation in supplementing oil, the oil mud
separated out the oil is deposited in the emergency governor.
To ensure the reliability of the emergency governor, the trip
test of the emergency governor should be made under
following conditions:
After turbine overhaul;
After the emergency governor dismounted and adjusted;
Restarting after shutdown for a month;
* After the turbine operated for 3 months.
* After the turbo-generator operated for 3 months, the
overspeed trip test should be made when the turbine-set is
connected from the net.
For the turbine driving compressor or pump, when it
operated continuously above 3 months, disconnect the
coupling between the turbine and the driven machine and
carry out the overspeed trip test of the emergency governor
after shutdown.
For the test method and requirement, see 3-1400-.
The turbine-set cannot be put into operation when the
emergency is abnormal.
The corrosion of turbine interior can occur in a few days after the turbine has cooled.
For example, the blade can be corroded because of the presence of salt deposit in
conjunction with moisture. Such shutdown corrosion will not only produce chemical
corrosion on the scatheless blade but also cause secondary corrosive damage of the
corroded parts, resulting in an obvious decrease in the endurance limit of the blade.
Therefore, the protective measure must be taken even for short shutdown.
For the condensing turbine that will not be restart immediately after shutdown, make the
turbine interior as dry as possible through proper operation in stopping. This is one of
the protective measures in common use.
For long-term shutdown (for turbine overhaul or seasonal shutdown), one of the
necessary protective measures, without opening the casing, is to block the steam inlet
and outlet of the turbine for separating the turbine from the steam and condensing
system and avoiding the steam and vapor entering into the turbine. However, This can
not remove the possibility of the corrosion inside the turbine, because the temperature
of the parts inside the turbine will change with the ambient temperature in the workshop
(see Fig 1). The volume of the air contained inside the casing will change with the
change of the temperature. The interchange will occur between the airs inside the casing
and the exterior through shaft gland and other openings. Fig.1shows that the casing
(including the rotor) temperature is always lower than the temperature of the external air
entering into the casing within a larger range. It will transfer the heat to the turbine parts,
so that the air temperature will drop below the dew point forming water drops under
corresponding relative humidity, which supplies a prerequisite for corrosion. The test
also indicates: when the relative humidity is less than 60%, the corrosion rate for steel
decreases rapidly (see Fig.2). When the relative humidity is less than 35%, the corrosion
rate becomes zero soon. The polished surface of steel will not be rusted for a long time
at a relative humidity less than 35%. Therefore, to avoid corrosion of the turbine interior
during shutdown, the air inside the casing must be kept at a relative humidity less than
50%.
Nitrogen method
Fill the casing with inert gas, such as nitrogen, for protecting corrosion..
Before filling nitrogen, dry the turbine interior first and then close the steam and drain
connections tightly and seal off the lead-throughs of the shaft gland and valve stem with
airproof tape carefully. The nitrogen may be injected into the casing from the exhaust
casing or a drain port. The nitrogen pressure inside the casing should be kept at 0.5 to 1
Mbar.
Before restarting the turbine protected with nitrogen, the nitrogen inside the casing must
be vented thoroughly.
The nitrogen content in the air under normal condition is 78%. When it is higher than
84%, it will be harmful to human. So the measure must be taken in using the nitrogen
method for preventing accident
Protective coatings
For the turbine stopped not for overhaul, the application of the protective coatings only
can be used if the casings are opened.
Coat the surfaces of the parts inside the casing with antirust oil according to the
instructions for antirust oil.
Should the rotor coated with antirust oil still rest on the bearings, the oil film at the
journals will break or be squeezed out under the action of the rotor weight and outside
force (e.g. the foundation vibration), resulting in journal rusted. So it is better to lift out
the rotor from the casing and rest it on the special pedestal after coated with antirust oil.
The protection effect can be inspected regularly, because of the opened casings.
For the turbine that its oil system cannot run after shutdown, when the expected
If the shutdown duration is less than 3 days, the cycling water for the cooler, such as
condenser, oil cooler and etc, may not be interrupted, otherwise, it should be cut off.
Drain away the water in the water chamber, make the walls of the water chamber and
piping as dry as possible. The accumulated water inside the equipments and piping must
be drained away to avoid the damage of equipment caused by freezing during shutdown
in winter.
Where the temperature of the cooling water changes with the change of the ambient
temperature, the cooling water flow to the oil cooler is small, at a slow velocity of flow in the
cooling piping. In order to avoid and reduce the settlement of the feculence in the piping,
further open the inlet valve at least once a time every day for about 10 minutes to flush out the
4. Check for operation of the oil pump during regular inspection. Start the auxiliary and
emergency oil pumps periodically for functional examination.
6. For the system with the ventilator, check the vacuum in the oil tank periodically. The
vacuum in the oil tank and the return-oil header should be kept at 5 to 10 mm WS. A too
high vacuum will cause a large amount of dust and water vapor to be imbibed into the oil
system.
7. Oil quality
The reliable operation of the turbine is closely related with the usability of the oil system,
which is mainly affected by the oil quality.
The reasons that will cause the oil quality dropped and deteriorated are: gaseous, solid, and
liquid pollutions.
Gaseous pollution:
The main and frequent gaseous pollution is the oxidizing action. During using, the turbine oil
will contact with the air ceaselessly and make oxidizing reaction continuously. The water or
the metal particulates, if there is any contained in the oil, will has a catalysis on the oxidizing
reaction. The oxidizing action will translate the hydrocarbon molecule into acid, raising the
acid number of the oil, which will increase the corrosion action. The oxide will form jelly or
solid leavings to increase the viscidity, to block the oil passage, baffling the normal operation
of the hydraulic elements. Along with the increase in the oxidizing degree, the oil color will
become dark and turbid, the transparence of the oil drops. In addition, for the turbine driving
the compressor, the leakage of the process gas (such as ammonia, sulfureted hydrogen and
etc.) of the compressor under failure also will pollute the oil and deteriorate the oil quality.
In order to improve the antioxygenic property of the turbine oil, antioxidant, such as butylated
hydroxytoluene (T501) is added in the oil, which will restrain the oxidizing action, reducing
the oxidizing rate of the oil and prolong the oil service life. The T501 content in the new or
regenerated oil should not be lower than 0.3 ~ 0.5% (mass ratio), while the T501 content in
the operating oil should not be lower than 0.15%. When it is lower than 0.15%, the oil with a
PH number above 5.0 should be supplemented.
Solid pollution:
The solid impurities in the oil will speed the ware and make the oil thick, blocking the filter
and oil passage. Furthermore, the solid contaminations will reduce the air separation ability of
the oil, resulting in the oil being oxidized easily.
During operation, the solid contaminations are mainly cleaned off with the oil filter. Under
normal condition, the filter element must be cleaned in time when the oil pressure difference
between the inlet and outlet of the oil filter approached its up limit. For the newly installed
turbine, it is better to clean the filter once a week at least in the initial stage of operation.
Liquid pollution:
The moisture pollution is a main liquid pollution. The moisture makes the acid out of the oil
and become chemical soap that has strongly corrosive action. In this case, the oil is emulsified
to greasy stain, blocking the oil passage. In addition, the mixture of the other brand of oil in
the turbine oil will also worsen the oil quality.
Usually, the water will enter into the oil mainly under the following condition: the leaking
steam from the turbine shaft gland enters into the oil system through the bearing house; for
the oil system with a higher pressure at the water side than that at the oil side in the oil cooler,
the cooling water will enter into the oil system through the oil cooler when the water piping
broken of the expansion joint loosen; for the turbine using filling air structure at the seal ring
of the bearing house, the water will enter into the oil system when the filling air without
depurating contains water; the water vapor is inhaled into the oil system with the air.
Under normal condition, the water entered into the oil will be separated soon and settled at the
bottom. Find out from whence the water comes through assaying the water drained from the
oil tank and take the measure based the assaying result.
For the turbine with oil containing water, the antirust additive T746 may be added in the
turbine oil with an amount of 0.02 ~0.03% of the oil amount (mass ratio).
The oil quality will be changed during turbine operation, so that examination of the oil must
be made periodically. For standard on turbine oil quality, see 3-0320-xx-xx. When necessary,
purify and regenerate the oil. If it cannot reach the requirement after that, the oil should be
changed.
The main cause to affect the oil service life is oxidizing action. The oil should be changed
every 2 or 3 years at an operation temperature about 50℃. The period of oil change should be
shortened at a higher temperature.
The increase of the steam quality may prolong the efficient operation duration of the
turbine. However, the in the turbine is unavoidable. The extent of deposition of the
steam-path section can be judged though monitoring the chamber pressure (see 3-2010-
for details). When the chamber pressure exceeds the permitted value, the cleaning
should be carried out in time.
Based on the deposit components, which are related with the feed water quality and
treatment equipment and technics, various methods may be adopted in leaning the
steam-path section. In the most cases, the deposition includes salt and silicon deposits.
The salt deposit mainly contains NaCl, Na2So4, silicate and etc, which are soluble in
water, while the silicate deposit contains insoluble SiO2,SiO2 with different crystal
structures and very strong depositing potency. Its deposited layer is very hard.
Usually, the method of manual cleaning, flushing with wet steam or chemical flushing is
used in cleaning the deposition.
When the manual cleaning method is used during turbine overhaul, lift out the rotor and
place it on the supports prepared. Firstly, flush the rotor with high-pressure water or
solvent, and then remove the deposit manually with scraper and sand paper. It should be
careful so as not to damage the blade when doing so.
Flushing with wet steam is one of the common cleaning methods. The saturated steam
In some cases when the flushing with wet steam cannot clean the silicon deposit
efficiently, the chemical flushing should be used. With this method, the chemical, such
as NaOH solution, is added in the flushing steam. Owing to the generation of Na2Si2O5
resulted from the reaction of the NaOH and SiO2, the silicon deposit can be removed.
Since the chemical will corrodes the turbine components, the concentration of the
additive and flushing temperature should be strictly controlled. Furthermore, the turbine
should be flushed with pure wet steam again after chemical flushing to avoid the
residual additive corroding the blade.
In order to prevent the deformation of the casing, the casing temperature should be
reduced to the temperature of the flushing steam before flushing. If the operation
condition permitted, reduced the inlet steam parameters gradually in the process of
unloading and stopping to decrease the casing temperature. This may shorten the
cooling time of the casing before flushing.
In order to reach the good effect n flushing, the saturated steam admitted into the turbine
should not be throttled, namely the nozzle controlling valves should be fully opened
(the valves 1st to 4th are nozzle controlling valves for most of the turbines).
The turbine speed when flushing is decided based on the actual condition. It may be any
speed between the rated and governor lower limit speeds.
During flushing, regularly sample the condensate for chemist analysis, sampling at the
drain port of the exhaust piping for backpressure turbine and the discharge of the
condensate pump for condensing turbine.
In order to keep the validity of the flushing, it is required to adjust the parameter of the
flushing steam continually. This is because when the temperature in the steam-path
section reached the temperature of the saturated steam, the steam cannot be condensed
to generate the condensate on the blade surface so that the flushing action is weakened.
Therefore the temperature and pressure of the flushing steam should be adjusted in time
during flushing based on the analysis result of the condensate.
The draining in the process of flushing must be thorough, closely monitor the turbine
speed, listen in the sound from the turbine, preventing water hammer.
After flushing, the turbine interior should be kept dry and start the turbine as early as
possible to prevent the corrosion during shutdown.
The flushing under load for the turbine driving the generator may be carried out
according to the “turbine operation procedure” prepared by ministry of electric power.
For the turbine driving the machine, it is recommended to flush the turbine after the
driven machine is separated from the process.
For the user lacking of the experience in turbine flushing, especially for the chemical
cleaning, it is better to flush the turbine together with the professional cleaning
company.
Types of Overhaul
Based on the range and work amount of inspection and maintenance involved in the
overhaul, the turbine overhaul can be divided into four types, i.e. minor overhaul,
intermediate overhaul, major overhaul and componenet overhaul. However, the
overhaul mentioned in this Operation Instructions does not including the repair after the
event (the overhaul after the forced outage).
Minor overhaul
The minor overhaul is an overhaul method, which will spend shorter time with smaller
amount of inspection and repair. It is not required to open the turbine case. The minor
overhaul is basically restricted to the inspection and repair of the individual item
external casing and determined in advance, such as the inspection of the bearing and
coupling, measurement of the alignment, the visual r examination of the gear, the reset
of the controlling and protective systems, the checkout of the operating instrument and
etc. It mainly involves the examination and treatment aimed to the defect that is
discovered in operation and does not require forced outage. The forced stop of the
turbine can be avoided through such minor overhaul.
Usually, the minor overhaul is carried out on schedule as necessary. In some cases, it
might be possible to make use of a shutdown caused by other device of the plant..
The inspection and test data and experience got in the minor overhaul can be used as the
reference for the intermediate and major overhauls.
Intermediate overhaul
The intermediate overhaul is carried out during a planned shutdown of the turbine. The
work is approximately the same as for the minor overhaul but the percentage of
involved item is greater, e.g. radial runout checks, axial displacement check with thrust
bearing removed, check and measurement of rotor alignment to casing without opening
the casing.
Usually, the casings are not opened this overhaul. However, should the intermediate
overhaul be combined with a componenet overhaul, opening of the casing may be
required.
The inspection and test data will provide detailed information for the next overhaul.
Major overhaul
The major overhaul requires a planned shutdown of the turbine. The duration of the
shutdown will depend on the size of the turbine, the amount of labor available and the
diathesis of the service personnel, the overhaul schedule, the local conditions and the
availability of spares.
Should the turbine be renovated during major overhaul, the overhaul only can be carried
out when the substitutions has been got, so as to carry out the overhaul on schedule.
Modular overhaul
The modular overhaul is mainly to check and repair the turbine components, such as
main oil pump, governor, controlling valve, emergency stop valve, steam chest,
guide-blade carrier, seal gland and etc.
The modular overhaul may be carried out together with the intermediate overhaul.
The modular overhaul may be considered as the staged overhaul. It is very useful for the
turbine that cannot be stopped long time for overhaul due to the production.
The detailed inspection in the process of overhaul, please refer to 4-1100- and 4-1200-.
The following are the principal methods for the inspection and testing of the turbine
parts (including the auxiliary components). Being convenient for illuminating, they are
identified by the various codes.
A. Function test
This is an inspection and testing method for the components such as governor,
emergency stop valve, pump control system and etc, in order to ascertain what checks
and adjustments are necessary.
B: Visual inspection
-- Appearance inspection by eye or optical device with good illumination.
-- Inspection with a microscope for determining the nature of damage.
-- Inspection with endoscope, together with the camera or vidicon, especially for
inaccessible part surface, such as control valve seat, inner wall of the piping in cooler.
-- Inspection of the surface roughness of the part.
D: Ultrasonic testing
E: X-ray testing
H: Sounding testing
Excitation by a blow from a tool and judgment of the defect from the sound produced.
P: Pressure testing
Pressure or leak testing with water or working medium for checking tightness.
The followings are required to consider in determining the method and range of
the testing.
1. Lift time of the equipment
2. Operation mode (stable or frequently changed operating condition)
3. The experience from a comparable machine
4. The data from the fault
5. Structure and type of the turbine
6. Operating parameters (steam, output and etc.)
7. The abnormal conditions occurred in operation by accident (quick drop of
temperature, overspeed and etc.)
The following table lists the item and method of testing for main components of the
turbine. Here, the testing item means the defect to be found out. The overhaul type is
identified with code:
1—Minor overhaul; 2—Intermediate overhaul;
2—Major overhaul; 4—Modular overhaul.
method type
cross section
Inner casing
distortion, cracks
distortion
method type
crack, distortion
sealing element
leak
damage
erosion, scrape
Crack B, C 3, 4 checks of
Corrosion B 3, 4
Dynamic balancing D 3, 4
rotor ends
displacement
method type
gear Crack B, C 3, 4
of root, blocking
screw of last
Backlash K 2, 3, 4
method type
supporter and
hanger, welding
Tube.
Attention to
fireproofing
requirement
method type
Deposit B 3,4
joint
piping wall
Cavitation B, C 3,4
Abrasion B, K 3,4
Corrosion B, C 3,4
Generally, the control-oil and lubricating oil piping are not required to dismantle so as
to avoid readjustment of the throttle valve, entering of the dirt into the system and
leakage when restarting up after the overhaul.
When lifting the top half of the casing it is essential to check that all of the split bolts
have been removed and that the guide bolts have been fitted. During dismantling, all
important components should be marked or documented (including sketches or
photographs) so that a subsequent reassembling in every details in always possible.
When opening up the machine take particular notice of any wear and deposit. If there
is any visible sign of leak on sealing surface found, it is necessary to check the
flatness and opening of the mating surfaces by means of blueing, taking leads or using
feeler gauges.
Very accurate records must be taken of any deposit on the blade and its position in the
turbine. Sample should be taken and analyzed to determine under which state
(running or shutdown) and with which method (steam flushing or chemical cleaning)
in cleaning deposit.
For the damage caused by solid foreign matter, it is necessary to specify the
cleanliness of the steam system besides checking of the steam strainer and etc.
Bearings, journals and oil seal rings should be inspected visually for damage.
A close check for the grooves in the gland bush or the shrouding can provide
important clues to the running state of the rotor during startup and operation. It also
indicates the presence of any distortion of the rotor and casing. The required clearance
and alignment can be gained through analyzing.
Worn or corroded sealing strips will indicate the maloperation during stopping and
The admission section, beginning with the steam strainer, must be inspected very
carefully for damage. The working reliability of the emergency stop valve and the
operating performance of the control valves must also be checked closely.
The moving and fixed blades should be examined thoroughly, cleaning the deposit on
the blade surface if there is any. The cleaning process is also an essential preparation
for crack testing (magnetic or dye-penetration testing).
The adjusting elements of the guide-blade carriers should be inspected closely. From
the measurements of the relative position of the supporting surface and casing split to
the guide-blade carrier the clearance and adjusting value can be obtained. The guide
elements of the bearing housings, casing and carrier should also be checked. An
assessment of their condition can be made through clearance measuring.
The checks described above provide the findings from which the decisions on the
repairs, modifications and spares required can be taken.
After all the checks and necessary corrective work have been carried out, the
reassembly can begin. Special care must be taken with the lifting or the rotor, the
measurement of the clearances and the reassembly of the bearings.
Another important aspect of the work is the measurement of the relative position
between the individual sections of the plant:
Turbine to turbine
or turbine to gearbox
or turbine to driven machine
or gearbox to driven machine
In calculating the alignment valve and correcting, the relative movement between the
sections of the plant during operation must be considered. Checking firstly the radial
and axial runouts is an important method for correct adjustment.
In the process of reassembly, measure the actual values against the reference values,
which are given in the Product Certificate, steam-path drawing and initial installation
record, and log the measured results.
The next work is to mount and connect the supervisory system. Thorough check and
testing of all instruments, protection and safety systems are essential.
The oil supply system should also be checked. The cleaning of the oil system, the
Reset the control system and check all of the steam piping.
NO.
Scope of overhaul 1 2 3+4
7 measure bearing clearance. Check thrust bearing bracket and adjusting *** *** ***
Check casing and bearing-housing guides for dirt and jamming, dismantle,
10 ** *** ***
repair and readjust them when necessary
Check emergency stop valve, control valve and etc, replace any worn part at
11 - ** ***
both hydraulic and steam sides
Check connections and joint bolts of initial steam and extraction steam
17 - * ***
lines
18 Examine internal components of casing for rust, deposit and wear - * ***
19 inner casing (steam chest) and guide-blade carries, replace when - * ***
necessary
Test bolts in high temperature zone for looseness and crack, check
20 - * ***
thread
22 guide-blade carries with feeler gauge or taking leads under bolts loosen - * ***
Check shaft glands and labyrinth seals for wearing, corrosion, warping
23 - * ***
and breakage, replace when necessary
Check the fixed and moving blades for deposit and corrosion, cleaning
blades
27 Check the earthing brush and clean up the contact surface ** ** ***
28 Inspect the main and auxiliary oil pumps (including coupling) ** *** ***
Dismantle the oil pump for checking bearings, seal rings, shaft,
29 * ** ***
impeller and etc.
replaced
Inspect the level gauge and drain the oil tank, examine and purify the
31 - * ***
oil, check the tank and clean the strainer
Check the oil filter, remove the elements, clean and examine, test for
32 * ** ***
leaks
33 Check the oil cooler, withdraw the tubes, clean and examine * ** ***
Examine the pressure oil and return oil piping, eliminate any leak,
Inspect the steam piping of the turbine body for crack, distortion and
35 - - ***
rust
36 Check the pipe supports and hangers, record positioning data *** *** ***
Inspect tubes and waterbox of condenser for deposit, damage and leaks,
37 * *** ***
check the air ejector
Overhaul Example
This section, taking a condensing turbine as the example, introduces the steps of the
check and repair for turbine body in overhaul.
When establishing the overhaul schedule, the user should draw up the complete
overhaul items and timetable based on the turbine structure, operation condition and
local condition (field, staff, equipment and etc.).
1. Preparation
1.1 Preparation and check of the necessary tools and equipments for overhaul.
1.2 Vibration measurements with frequency analysis (shaft vibration, bearing housing,
foundation).
1.3 Final operating data logging, including the records of various operating condition
stopping and coastdown time, the barring gear put into operation until to turbine
cooled.
1.4 Check of spare parts.
1.5 Functional test of oil cylinder.
1.6 Leak check by sight and touch.
1.7 Test of shafting system earthing.
2. Dismantling turbine
2.1 Removal of encloser.
2.2 Removal of lagging.
2.3 Disconnection of initial-steam and extraction-steam piping, blanking off the
openings.
2.4 Removal of control-oil and lubricating-oil piping.
2.5 Disconnect of the couplings between the turbine and driven machine, turbine and
main oil pump.
2.6 Opening of the bearing housings, checking of differential expansion indicator and
lifting of bearing upper halves.
2.7 Measurement positioning dimension of rotor relative to casing and bearing housings,
inspection of alignment value.
2.8 Measurement of radial and axial runout of the rotor at coupling end.
2.9 Removal of casing split bolts and supporting bracket bolts.
2.10 Raising of casing top half with jacking bolts after fitting the guide bars, lift-off of
top half.
2.11 Release of the jointing blots of inner casing (two-half inner casing), guide blade
carriers and shaft glands, lift-off of top halves.
2.12 Radial runout check along full length of rotor, measurements of static and dynamic
clearances of each stage.
2.13 Lift-out of rotor.
2.14 Removal of bottom halves of inner casing, guide blade carriers and shaft glands.
2.15 Dismantling of emergency stop valve, control valves and main oil pump (see, 3.9,
3.6 Rotor
3.6.1 Remove and inspect emergency governor.
3.6.2 Check journals and thrust faces, smooth when necessary.
3.6.3 Smooth bearing seal ring section.
3.6.4 Smooth earthing brusher section.
3.6.5 Check gland strips, repair or replace conditionally.
3.6.6 Check moving blades (straight blade), shrouding, twist blades and tie wire, inspect
the blades for deposit, corrosion and crack.
3.6.7 Crack-test shaft.
3.6.8 Clean and finish half coupling.
3.6.9 Reassemble emergency governor, overspeed-test before test running again.
3.6.10 Rebalancing of rotor.
4. Others
4.1 Check and maintenance of the digital controller and electro hydraulic converter
should be carried out according to the relevant product manuals.
4.2 Check and verify of the operation supervision instruments.
4.3 Check and overhaul of the oil system (e.g. oil tank, auxiliary oil pump, oil cooler, oil
filter, accumulator and etc.), condensing system (e.g. condenser, condensate pump,
level controller, air ejector, gland steam pressure controller, exhaust safety valve and
etc.), steam line (piping, supports and hangers, extraction stop valve and actuator,
safety valve, exhaust nozzle and etc.), oil line (piping, expansion joint, tube, fittings
and etc.) should be carried out according to the overhaul schedule and procedure.
5. Reassembly of turbine
7. Overhaul report
The overhaul items, personnel, schedule, problems discovered and measures taken,
measurement records of reassembly, the results of the functional testing for components
should be reported in written, the chart and photos can attached when necessary (see
4-1400- for details).